HomeMy WebLinkAboutCOW 2011-11-28 Item 4M - Contract Supplement #13 - Tukwila Urban Center Transit Center with IBI Group for $429,000COUNCIL AGENDA SYNOPSIS
CAS NUMBER:
AGENDA ITEM TITLE
Initials
Meeting Date I Prepared by Mayors review
11/28/11 1 BGIV C
12/05/11 B
ITEM INFORMATION
STAFF SPONSOR: BOB GIBERSON
Couni'l review
i
ITEM NO.
4.M.
ORIGINAL AGENDA DATE 11/28/11
Tukwila Urban Center Transit Center
Consultant Supplemental Agreement No. 13 with IBI Group
CATEGORY Discussion Motion Resolution Ordinance .Bid Aivard Public Hearing ❑Other
,A/It Dale 11/28/11 Mtg Date 12/05/11 Mtg Date Mtt Date Mtg Date Mtg Date Mtg Date
SPONSOR Council Mayor Adm Svcs DCD Finance .Fire Legal P &R Police PWI
SPONSOR'S This supplemental agreement will complete the final design of the Transit Center and
SUMMARY prepare the bid documents. With the WSDOT Regional Mobility grant of $4.7 million, the
Transit Center is funded and scheduled to begin construction in 2012. This supplement is
one of two being presented with the Andover Park W street improvements. Council is being
asked to approve Supplemental Agreement No. 13 in the amount $429,000.00.
RI- VIEWED BY COW Mtg. CA &P Cmte F &S Cmte Transportation Cmte
Utilities Cmte Arts Comm. Parks Comm. Planning Comm.
DATE: 1 1/21/11 COMMITTEE CHAIR: JOAN HERNANDEZ
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works
Commi'ITT -i- Unanimous Approval; Forward to Committee of the Whole
COST IMPACT FUND SOURCE
EYPEND1'1'URI3 RI QUIRI�-'D AMOUNT BUDGETED APPROPRIATION REQUIRED
$429,000.00 $738,000.00 $0.00
Fund Source: 104 ARTERIAL STREETS (NEW PAGE 16, PROPOSED 2012 CIP)
Comments:
MTG. DATE I
11/28/11
12/05/11
MTG. DATE
11/28/11
12/05/11
RECORD OF COUNCIL ACTION
ATTACHMENTS
Informational Memorandum dated 11/18/11
New page 16, Proposed 2012 CIP
Supplemental Agreement No. 13 with IBI Group
Minutes from the Transportation Committee meeting of 11/21/11
379
:1
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
TO: Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
DATE: November 18, 2011
SUBJECT: Tukwila Transit Center
Project No. 90610402, Contract 06 -019
Supplemental Agreement No. 13
ISSUE
Supplement to the IBI Group on the combined Tukwila Urban Center Transit Center and
Andover Park W design contract in the amount of $429,000.00.
BACKGROUND
In February 2006, IBI Group was retained by the City to begin the design of the Tukwila Urban
Center Transit Center on Andover Park W. The Transit Center's Concept Plan was completed in
December 2006. Due to the overlapping design needs of Transit Center and the Andover Park
W widening project (98810404), the two projects were combined under the IBI Group contract.
The design of the Tukwila Transit Center is at 30% and is coordinated with the design work on
Andover Park W.
DISCUSSION
With the Regional Mobility grant award earlier in 2011, completion of the design and ultimately
construction of the Transit Center is estimated to be fully funded. This supplemental agreement
is to complete the design work through the final design and PS &E documents. Another
supplemental agreement (No. 14) to complete the design effort on Andover Park W, including
design of the water main replacement, is being presented to the Transportation Committee at
the same time. The supplemental agreements are presented separately to aid in the ease of
billing and tracking expenditures by project
Fiscal Impact: A new CIP page is attached to represent the additional funds needed for design,
with the right -of -way costs reduced (page 16, Proposed 2012 CIP).
RECOMMENDATION
Approve Supplement No. 13 to Contract No. 06 -019 with the IBI Group in the amount of
$429,000.00 and consider this item at the November 28, 2011 Committee of the Whole and
subsequent December 5, 2011 Regular meetings.
Attachments: New Page 16, Proposed 2012 CIP
Supplemental Agreement #13
WAPW Eng \PROJECTSW- RW RS Projects \06RW02 Transit Center \INFO MEMO Supp #13 IBI Transit Center Design 11- 18- 11.docx 381
*6
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2012 to 2017
PROJECT: Tukwila Urban Center Transit Center Project No. 90610402
DESCRIPTION: Design and construct a Transit Center for the Tukwila Urban Center (TUC)
FUND SOURCES
Awarded TOD Grant
High transit ridership and bus operations warrant conversion of the existing bus stops on Andover Park West
40 428
468
to a Transit Center. The current facilities are inadequate in size and location to serve Metro operations and
JUSTIFICATION:
transit riders. City policy encourages the use of transit, and mitigation dollars and parking supply decisions
Mitigation Actual
500
have been made based upon the expected improvements to the transit center.
500
STATUS:
Design began in 2006. Construction schedule is linked to milestones identified in the State Mobility grant.
MAINT. IMPACT:
Minimal to moderate, depends on final maintenance agreement with King County Metro.
(229)
0 1,376 329 0 0 0
TOD grant of $468k with mitigation from Westfield SIC Mall of $500k for parking variance. WSDOT Regional
TOTAL SOURCES
COMMENT:
Mobility Grant of $4.7m with $3.9m in 2011 -2013 and $835k in 2013 -2015 with a required match of 20% that
0 0 7,522
can include past expenditures, other grants, and ROW value of land dedicated by Westfield.
FINANCIAL
Through Estimated
(in $000's)
2010 2011 2012 2013 2014 2015 2016 2017 BEYOND TOTAL
EXPENSES
Design
271 40 738
1,049
Land(R/W)
343 916
1,259
Const. Mgmt.
250 300
550
Construction
2,300 2,364
4,664
TOTAL EXPENSES
614 40 4,204 2,664 0 0 0 0 0
7,522
FUND SOURCES
Awarded TOD Grant
40 428
468
Awarded Mob Grant
2,400 2,335
4,735
Mitigation Actual
500
500
ROW Donation
343
343
City Oper. Revenue
(229)
0 1,376 329 0 0 0
0 0 1,476
TOTAL SOURCES
614
40 4,204 2,664 0 0 0
0 0 7,522
Project Location
2012 2017 Capital Improvement Program
16
F
o
i
e
e
i
GIs
383
ME
SUPPLEMENTAL AGREEMENT NUMBER 13
TO
CONSULTANT AGREEMENT NUMBER 06 -019
THIS SUPPLEMENTAL AGREEMENT is entered into between the City of Tukwila,
Washington, herein -after referred to as "the City and IBI Groun, hereinafter referred to as "the
Consultant in consideration of the mutual benefits, terms, and conditions hereinafter specified.
The City desires to supplement the agreement entered into with the Consultant and executed on,
February 23, 2006 and identified as Agreement No. 06 -019. All provisions in the basic
agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Scope of Services, is hereby changed to include work described in Attachment A for
additional design work on the Tukwila Transit Center Project.
2. Payment, shall be amended as follows:
A. Payment for the work provided by the Consultant shall be made as provided on
Exhibit "C" attached hereto, provided that the total amount of payment to the Consultant
shall not exceed $429,000 without express written modification of the Agreement signed
by the City. The maximum amount payable under this agreement as supplemented
inclusive of all fees and other costs is now $1,221,815.
3. Time for Performance, shall be amended as follows:
The Consultant shall perform all services and provide all work product required pursuant
to this Agreement by December 31, 2012, unless an extension of such time is granted in
writing by the City.
DATED this day of 20
CITY OF TUKWILA
Jim Haggerton, Mayor
CONSULTANT
By:
Printed Name:
Title:
385
x
k
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
NOVEMBER 11TH, 2011
IBI
GROUP
387
/a/oxoup
SCOPE opWORK
PHASE 3: FINAL DESIGN ADDITIONAL SERVICES 1
TaskD: ROW ACquisiUoO.. 1
PHASE4: CONSTRUCTION DOCUMENTS
5
Task Project Management
o
Task 6: Stakeholder Coordination 7
Task 7: Design Documents 0O% and 1U0%i B
Task 8:Cost Estimates K0% and 1UU%L--
11
Task 9:Assistance with Building Permit
11
PHASE S: BID AND CONSTRUCTION SUPPORT (OPT|ONAL)
12
Task10: Bid Support.
12
Task11: Construction Support
12
SCHEDULEAND FEE
13
November I/th,on1
Page
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
PHASE 3: FINAL DESIGN ADDITIONAL SERVICES
The following additional task has been added to support the Phase 3, Task 3 Right of Way
Acquisition work.
The objective of this task is to assist the City in ROW acquisition. Work to be performed includes
preparation of legal documents detailing the ROW acquisition necessary along Andover Park West
to accommodate the new Transit Center, assist with purchase offers, and negotiate final
agreements. The general approach will be as follows:
Obtain a Right of Entry for no compensation. The area would be from the right of way
line to the front of the Firestone building. The purpose would be to obtain information
needed to finalize the plan for demolition and remediation of the site after demolition is
complete. A request for right to do environmental tests to determine if there are any
hazardous materials on site should also be included. Activities for this effort would include
detailed topographical survey work, soil testing for hazardous materials and the right to
have project personnel enter the property to complete the survey and soil testing. This
should be completed as soon as possible.
Obtain a Temporary Construction Easement (TCE). Compensation to be determined
during an appraisal of the property. The area would be from the existing right of way line to
the front of the Firestone building as wide as is needed to allow project personnel and
equipment access to demolish the existing canopy, as well as to remediate any damage
done to the property during demolition. Remediation should include input from the property
owners regarding their wishes for what the site would look like after the canopy is removed
and would likely include work such as paving, parking striping, landscaping, irrigation, and
lighting. This TCE should show on the right of way plans.
Obtain a Permanent Easement. This type of restrictive easement will likely cost the same
as a fee simple acquisition if the City were paying for the entire easement.
CERTIFIED Land Services (CLS) will also sub contract with an appraisal firm to perform the initial
appraisals needed. CLS recommends obtaining at least two bids from qualified WSDOT- approved
appraisers that will include costs and delivery schedule. CLS will make a recommendation for the
hiring of the appraiser that the City can review and make a final decision on.
Assumptions
This work will be performed by Certified Land Services, as sub consultant to IBI
Group.
All forms and conveyance documents will be based on WSDOT templates.
CLS will hire and manage a WSDOT- approved Appraiser for both the Southbound stop
permanent easement and the Northbound stop right of way assessments. Note that in the
Phase 3 scope it was assumed that the City would hire a WSDOT- approved Appraiser.
This has been added to Phase 4 scope to move forward with the acquisitions /easements
November 11 th, 2011
IBI
GROUP
9-1
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
with the Phase 3 WSDOT- approved appraiser assumed to be hired by the City representing
appraisal of the completed project.
There are no relocations for this project.
Sign relocations will be considered cost to cure items addressed in appraisals and
negotiations.
All utilities easements, permits and clearing will be handled by the City.
Transactions will be closed in escrow. Agents will prepare escrow agreements for each
parcel to clear all encumbrances and parties in interest from each parcel.
Commercial parcels typically have multiple parties in interest. All parties in interest will be
addressed in clearing title.
The City will record all documents and will pay property owners and /or lien
holders /encumbrances for any property or property rights acquired for this project.
CERTIFED will provide certification prep and review.
Acquisition documents for one parcel will be prepared.
The acquisition of the parcel assumes that parking will not be impacted. Additional fees will
be negotiated for the preparation of a Parking Impact Study.
The City of Tukwila will provide title reports for parcels if additional reports are necessary.
The task does not include resolving boundary issues should the title reports have conflicting
information.
Work Activities
3.3. Permanent Easement Firestone
The project involves one parcel which is known as the Firestone property (KC Tax ID NO. 92 -247-
0070) which is a commercially zoned property. We anticipate the acquisition of a right of entry for
design and environmental assessment of the parcel. Upon completion of final design and right of
way plans, the project may require the acquisition of a strip of land in fee simple and improvements
located in that strip of land.
State and /or federal funds are involved in this project requiring strict adherence to Federal
Highways Administration policies and procedures as well as all applicable federal, state and local
laws including, but not limited to the Uniform Relocation Assistance and Real Property Acquisition
Policies Act of 1970 and its amendments, 49CFR Part 24, and state Revised Statutes. Work will be
in accordance with the WSDOT Local Agencies Guidelines and by reference the WSDOT Right of
Way Manual.
3.3.1. CERTIFIED staff will review all documents, files, maps, legal descriptions and other
information provided. Errors, questions and clarifications will be reviewed and
discussed.
3.3.2. Appraisal
Assumptions
It is assumed that the Rights of Entry will be obtained for no compensation.
390
November 11 th, 2011
Page 2.
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
In accordance with funding source requirements and the Agency's approved
right of way procedures, CERTIFIED will advise if the acquisition may be
acquired with appraisal waiver or if a full narrative appraisal is required.
Appraisal tasks include the following:
3.3.2.1. CERTIFIED will prepare a preliminary funding estimate (PFE) for the one (1)
fee take parcel describing the parcel, its ownership, the estimated cost of
acquisition, labor, escrow, condemnation, and summary of total right of way
project costs.
3.3.2.2. An Administrative Offer Summary (appraisal waiver) will be written if the
acquisition is valued under $25,000 in the PFE.
3.3.2.3. CERTIFIED will hire and manage the appraiser.
3.3.3. Appraisal Review
Assumptions
Appraisal Reviews are not necessary for acquisitions valued under $25,000
according to state and federal funding source requirements, and the Agency's
approved right of way procedures.
If required, the City will hire a WSDOT- approved appraisal reviewer who will
provide appraisal review services.
Appraisal Review tasks include the following:
3.3.3.1. CERTIFIED will manage the appraisal reviewer hired by the City, and the City
will set just compensation from which the offer will be made.
3.3.4. Administrative
Assumptions
The City will provide a preliminary title commitment for each parcel with
Schedule B showing exceptions listed; copies of vesting deeds and supporting
documents for all liens and encumbrances of record will be included.
PACE will provide all legal descriptions.
PACE will provide an exhibit map for the fee acquisition the rights of entry on the
project.
CERTIFIED staff will maintain all records, files, documents, and reports in
accordance with statutory and WSDOT guidelines and regulations.
Administrative tasks include the following:
3.3.4.1. CERTIFIED will provide signature ready legal documents that will be used to
convey fee or temporary construction easement rights for all parcels.
3.3.4.2. CERTIFIED will provide written status reports on a weekly basis, or as agreed
upon, and will provide verbal status reports on demand, as requested.
3.3.5. Negotiation
Assumptions
CERTIFIED agents will act in good faith at all times.
November 11 th, 2011
Page 3.
391
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
CERTIFIED staff will never coerce owners in an attempt to settle parcels.
CERTIFIED will provide the City with an Administrative Settlement letter for all
requested administrative settlements.
CERTIFIED staff will work whatever hours are necessary, including evenings
and weekends, to make themselves available to owners and their
representatives.
Negotiation tasks will include the following:
3.3.5.1. CERTIFIED will prepare an offer letter for the parcel.
3.3.5.2. CERTIFIED agents will make at least three (3) personal contacts with the
owner with the intent of reaching settlement for the conveyance of property
needed. As many contacts as needed to reach settlement will be made, until it
is mutually agreed between the City and CERTIFIED that negotiations should
be suspended or given to the City Attorney to pursue eminent domain actions.
3.3.5.3. CERTIFIED staff will explain the City's offer verbally and in writing.
3.3.5.4. CERTIFIED staff will provided detailed written diaries for each parcel.
3.3.5.5. CERTIFIED staff will transmit organized parcel files containing all pertinent
information, documents, forms, diaries, and Disclaimer Statements.
3.3.5.6. CERTIFIED staff will prepare a condemnation summary memo if the City
deems it is necessary to acquire the property through the exercising of its
power of eminent domain.
3.3.6. Closing and Conveyance
Closing and Conveyance tasks include the following:
3.3.6.1. CERTIFIED staff will review title for each parcel.
3.3.6.2. CERTIFIED will clear all encumbrances on title that are in conflict with the
acquisition areas of the partial taking parcel.
3.3.6.3. CERTIFIED will prepare any documents needed for clearing any liens or
encumbrances as noted above.
3.3.6.4. CERTIFIED will provide the City with complete files at the close of negotiations
for each parcel. Included in our transmittal packages will be conveyance
documents ready for the City to record and all documents related to lien and
encumbrance removal.
Deliverables
Updated Right of Way Acquisition Table
Legal documents for property acquisition
Weekly status reports
Detailed written diary for the parcel
Documents required to clear any liens or encumbrances
A complete record including all files will be provided at the close of negotiations
392
November 11 th, 2011
Page 4.
IBI GROUP
SCOPE OF WORK
PHASE 4: CONSTRUCTION DOCUMENTS
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
The Transit Network Plan for the Tukwila Urban Center (TUC) Subarea' includes as one of its
key recommendations the construction of a new transit center in the immediate vicinity of the
existing focal point of bus service on Andover Park West and Baker Avenue. A new transit
center in this location is expected to act not only as a replacement for the existing bus
stop(s); it will also serve the new King County Metro RapidRide F Line that will begin service
in 2013. In addition, the new transit center is an important step in the redevelopment of the
area, building from current initiatives to redevelop the Southcenter Mall and future plans to
redevelop the Tukwila Urban Center.
The objective of this Phase of the project is to develop a construction documents package
(60% and 100 for the Tukwila Transit Center that provides design documentation, cost
information and environmental and geotechnical information to the City that allows for future
bidding of the project. This phase will begin from the work completed during Phase 3
described in the Tukwila Transit Center Final Design scope of work dated June 15, 2011 and
continue the design process and stakeholder coordination in preparation of bid documents
that will include the ability to meet the Regional Mobility grant requirements.
A work breakdown structure of five primary tasks has been developed for this Phase of the
work, recognizing an overall design timeline of six months. This includes a two -week City
Design Review period after both the 60% and Draft 100% submittals. Primary tasks, in
general, include the following:
Review and assembly of relevant information, including geotechnical and
environmental appropriate to completing the design phase of the project including the
Firestone Property, Northbound and Baker transit stops.
2. Preparation of stakeholder presentation materials and meeting summaries and
participation at meetings.
3. Preparation of construction documents (60% and 100% Draft and Final) plans and
specifications.
4. Construction cost estimates for the Transit Center (60% and 100
5. Assistance to the City in preparation of a building permit for the shelters.
The following scope describes the work to be conducted, and assumptions and deliverables
to be provided.
Task 5: Project Management
This task includes the day -to -day activities to be performed by the Consultant to manage and
administer the work to deliver quality work products that meet the needs of the City.
Final Transit Network Plan, Tukwila Urban Center Subarea, Perteet, Inc., December 2004.
November 11 th, 2011
Page 5.
393
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
ASSUMPTIONS
Primary project management coordination will be through the Consultant Project
Manager and City Project Manager.
All Consultant requests for meetings with City staff shall come from the Consultant
Project Manager. Such requests will be issued to the City Project Manager.
All sub consultant requests for meetings will be coordinated through the Consultant
Project Manager or Consultant Design Coordinator (the latter if a design related
issue).
Steps will be taken to schedule meetings as far ahead as reasonable to secure
participation of invitees, City assistance may be requested from time -to -time to
expedite design or information collection related meetings.
The City will be responsible for providing meeting space and issuing invites to City
staff and other stakeholders for all stakeholder and city council meetings and
presentations.
The City will be responsible for providing base information such as existing plans,
previous studies, land surveys, GIS data, etc. The Consultant will coordinate with the
City to make sure that information requests are reasonable and do not overly burden
City staff.
The Consultant will be responsible for all work products delivered, and commits to
providing staff and resources to complete the work in a timely manner.
WORK ACTIVITIES
5.1. Contract Administration
This activity covers basic administration of the work including:
5.1.1. Preparation of a Project Schedule in MS Project, ongoing tracking of that
schedule, and reporting of any variances on a monthly basis. Issues identified
during the course of the work that have the potential to affect schedule will be
promptly identified for the City Project Manager (this is in addition to regular
monthly reporting).
5.1.2. Cost and project team time control.
5.1.3. Monthly invoicing and project progress reporting (report to be included with
invoice).
5.1.4. Sub consultant administration.
5.2. Meetings and Coordination
This includes general coordination and project management meetings; stakeholder
meetings are covered in Task 6. Meeting and coordination are expected to include the
following:
5.2.1. Design Review meetings with City staff (3) (At the start of 60% design, during
60% design and during 100% design tasks).
5.2.2. Internal design team coordination meetings
5.2.3. Client coordination calls and ad -hoc coordination (Up to 6).
394
November 11 th, 2011
Page 6.
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
5.3. Quality Control
5.3.1.All work products will be subject to internal quality review before issuance per
IBI Group quality control procedures.
DELIVERABLES
Project schedule
Invoices and monthly progress reports
Meeting agendas
Meeting notes
This task will continue the stakeholder coordination efforts from the work completed earlier
during schematic and final design phases through the construction document phase by
assisting the City with communication with key stakeholders. Key stakeholders include the
City project team, King County Metro, adjacent property owners and businesses, council
committees, review boards and commissions. The Consultant will prepare presentation
materials as defined below.
ASSUMPTIONS
The City will be responsible for publicizing stakeholder meetings and for arranging
meeting logistics.
The Consultant will be responsible for the preparation one set of presentation
materials for the City's use at stakeholder meetings.
IBI will lead one (1) presentation for the Adjacent Property Owners and Tenants.
Meeting notes will be prepared for the meeting.
WORK ACTIVITIES
6.1. Preparation for Stakeholder Workshops
6.1.1. Stakeholder meeting agendas will be developed through collaborative planning
sessions involving the City Project Manager, Consultant Project Manager, and
other key staff.
6.1.2. The Consultant will prepare one set of graphics and a rendering that will be used
at all of the stakeholder meetings listed above. Presentation material will be
focused on the transit stations, urban design and landscape features. The
graphics prepared will reflect the reviewed and approved design plans.
6.2. Documentation of Stakeholder Workshops
6.2.1. The Consultant will provide the City with copies of meeting materials and
meeting notes for stakeholder events (paper and electronic).
November 11th, 2011
Page 7.
395
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
6.3. Public Art Program Identification and Coordination
6.3.1. The Consultant will work with the City to incorporate public art into the project.
The Consultant will coordinate the location of the art into the project site. The
Consultants effort is limited to coordination of the art piece and is limited to 16
hours as identified in the fee proposal. The work does not include any additional
design services or design modifications of the art to accommodate the piece into
the project. Additional design and coordination services if required will be
negotiated with the City prior to providing the services.
DELIVERABLES
One set of stakeholder meeting graphic materials and renderings
Stakeholder meeting notes /documentation
This task will prepare construction documents (60% and 100 design plans and
specifications for landscape architecture, civil, architectural, urban design, structural,
ITS /communications and electrical systems for the Northbound, Southbound and Baker
Transit Stops.
ASSUMPTIONS
A Value Engineering Study is not included as part of this scope of work. If required,
additional scope and fee will be negotiated with the City.
A building permit will be required for the shelter only. The City will prepare all other
permits.
Information will be prepared in CSI format for Lump Sum bidding. The City will
provide Division 00 and 01 sections meeting federal and state funding requirements.
Detention and water quality is required for this project. The areas requiring water
quality treatment and pervious and impervious area changes will be documented in a
technical memo. The work required for this requirement will be combined with
proposed improvements within the Andover Park West improvement project.
Canopies and planter walls will be founded on conventional spread footings. The
design of pile foundations would be considered additional scope.
A single canopy design would be applied to all canopies at the Northbound and
Southbound transit stations. Baker Blvd. transit station will not include a shelter.
100% Draft Design Plans will be utilized for the Building Permit submittal no
additional plans will be prepared for the Building Permit
The City will provide comments for the 60% and Draft 100% Design submittals within
2 weeks of receiving the documents. The City will provide consolidated comments
that are non conflicting to the Consultant for incorporation into the next submittal.
November 11th, 2011
Page 8.
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
WORK ACTIVITIES
7.1. 60% Design
Plans and project specifications will be prepared to a 60% design level. One design
review meeting will be held during the 60% design task with key City staff. Progress
design drawings will be reviewed and key design issues and decisions discussed.
7.1.1. Civil The Consultant will develop 60% design documents covering drainage
facilities. The 60% design for utilities will include relocation; new utility services
that may be required for project. The plans will include the following: the final
grading of existing and installation of plans; pavement layout will include extent
of the new pavement for bus pullouts and /or plaza areas, and will include
pavement cross sections. The Consultant will also prepare 60% demolition
drawings for the Firestone canopy foundations.
7.1.2. Landscape Design 60% plans for landscape design documentation will be
developed for both the pedestrian plaza and transit center locations.
7.1.3. Urban Design The Consultant will develop 60% urban design project site plans
and details including Transit Center, Pedestrian Plaza and Crosswalk design.
7.1.4. Architecture Design 60% design architectural documentation of planters,
railing, signage, lighting, seating, plaza and shelter will be developed for the
transit center.
7.1.5. Structural The Consultant will develop 60% designs for structural elements
(planter walls, a single trellis, feature signs, unique light standards and a
standard canopy). The structural design for the transit center will include
foundation, planter wall, and framing plans and details for all sites.
7.1.6. Electrical The Consultant will develop 60% designs for site electrical power
service and distribution, and receptacle locations. The Consultant will coordinate
any required discussions between the City, service utility, and design team
members to determine power availability and access. The Consultant will
develop 60% design lighting plans and coordinate lighting system standards with
the City.
7.1.7. ITS The Consultant will develop 60% designs for video surveillance cameras
for the transit center. The cameras will be an expansion of the City's existing
system and will not include a new operating system. The Consultant will develop
60% designs for a conduit layout for a future VMS display and connection to the
Rapidride technology pylon.
November 11th, 2011
Page 9.
397
IBI GROUP
SCOPE OF WORK
7.2. 100% Design
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
Plans and project specifications will be prepared for a complete design. One design
review meeting will be held during the 100% design task with key City staff. Progress
design drawings will be reviewed and key design issues and decisions discussed. A
draft 100% design submittal will be prepared and submitted to the City for Review. The
draft 100% design documents will be utilized for the submittal of the Building Permit to
the City of Tukwila.
A final 100% bid ready set of plans and specifications will be prepared. This set will
incorporate the final comments from the City's review and the Building Permit Review.
7.2.1. Civil The Consultant will develop 100% design documents covering drainage
facilities. The 100% design for utilities will include relocation; new utility services
that may be required for project. The plans will include the following: the final
grading of existing and installation of plans; pavement layout will include extent
of the new pavement for bus pullouts and /or plaza areas, and will include
pavement cross sections. The Consultant will prepare 100% demolition drawings
for the Firestone canopy foundations.
7.2.2. Landscape Design —100% plans for landscape design documentation will be
developed for both the pedestrian plaza and transit center locations.
7.2.3. Urban Design The Consultant will develop 100% urban design project site
plans and details including Transit Center, Pedestrian Plaza and Crosswalk
design.
7.2.4. Architectural Design 100% design architectural documentation of planters,
railing, signage, lighting, seating, plaza and shelter will be developed for the
transit center.
7.2.5. Structural The Consultant will develop 100% design plans for foundation,
planters, and shelter structure.
7.2.6. Electrical The Consultant will develop 100% design plans for site electrical
power service and distribution, and receptacle locations. The Consultant will
coordinate any required discussions between the City, service utility, and design
team members to determine power availability and access. The Consultant will
develop final design lighting plans and coordinate lighting system standards with
the City.
7.2.7. ITS The Consultant will develop 100% design plans for video surveillance
cameras for the transit center. The Consultant will develop final designs for a
conduit layout for a future VMS display and a connection to the RapidRide
technology pylon.
DELIVERABLES
60% Design Plans and Specifications submittal for all disciplines
Draft 100% Design Plans and Specifications submittal for all disciplines (will also be
used as the submittal for Building Permit)
Final 100% Design Plans and Specifications (Bid- ready) submittal for all disciplines
November 11th, 2011
Page 10.
Ml
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
Cost estimates will be developed for the 60% and 100% submittals with a level of accuracy
commensurate with the level of design. The cost estimates will include the cost of
construction for the design and include any potential risks that have been identified as a
result of the conceptual engineering and design tasks. The cost estimate will be subdivided
into costs for each of the disciplines listed below.
ASSUMPTION(S)
Information will be prepared in CSI format for Lump Sum bidding
WORK ACTIVITIES
8.1. 60% Cost Estimating
8.1.1. The Consultant will develop an 60% cost estimate based on the civil, landscape,
urban, architectural, structural, ITS /Communications, mechanical and electrical
design.
8.2. 100% Cost Estimating
8.2.1. The Consultant will develop a 100% cost estimate based on the civil, landscape,
urban, architectural, structural, ITS /Communications, mechanical and electrical
design.
DELIVERABLE(S)
Lump sum construction cost estimates for 60% and 100% documentation.
Task 9: Assistance with Building Permit
ASSUMPTIONS:
City staff has indicated that the only City permit required will be the building permit for
the station canopies.
The Consultant will communicate with the City on corrections or other issues that
arise during review, up to the level of effort identified in the Cost Estimate.
All permit fees will be paid by the City directly and are not included in the cost
estimate.
The City will lead the submittal and tracking of the building permit and coordinate with
the reviewers during the review and approval process.
The Consultant team effort for this task is limited to 20 hours as defined in the
attached fee proposal.
November 11th, 2011
Page 11.
IBI GROUP
SCOPE OF WORK
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
WORK ACTIVITIES
9.1. Building Permit
The Consultant team will assist the City in obtaining the building permit for the station
canopies by assembling the building permit application materials which include drawings
prepared for the 100% Draft Design plans and specifications. Additional drawings will not be
prepared for the permit submittal. The Consultant will prepare required forms and assemble a
draft application package for City review. The City will lead the submittal of the application
and track the progress of the permit package through the approval process and coordinate
with the Consultant Team on questions and revisions during the approval process. The
Consultant team effort for this task is limited to 20 hours as defined in the attached fee
proposal.
DELIVERABLES
Building permit application (draft, final)
PHASE 5: BID AND CONSTRUCTION SUPPORT (OPTIONAL)
ASSUMPTIONS
The City will be responsible for all aspects of the procurement not spelled out
specifically below.
No Conformed set of documents including addenda will be prepared.
DELIVERABLES
The Consultant will make a "camera ready" or digital record of the Final bid
documents available to the City for their use in the copying and dispersal of
documents to prospective bidders.
The Consultant will respond to bidder questions forwarded by the City with Addenda
information in the form of text and drawings necessary and appropriate to obtain
bids.
Task 11: Construction Support
ASSUMPTIONS
The City will retain personnel as required to manage the day -to -day administration of
the construction.
No budget is included for this work. Final Budget and Scope will be determined at a
later date.
DELIVERABLES
Review and comment on submittals
Review and comment on requests for information
November 11th, 2011
Page 12.
W1
IBI GROUP
SCOPE OF WORK
Review and respond to owner questions
City of Tukwila
TUKWILA TRANSIT CENTER
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
PHASES 3 AND 4
Issue clarifications, including supplemental drawings
Maintain a log of all submittals, requests for information, owner questions,
supplemental drawings and issued clarifications
The consultants will make site visits to review progress
SCHEDULE AND FEE
The Consultant team will conduct the work described in Phase 4 Construction Documents
in an overall timeline of six months with two additional 2 week periods for City review of the
design deliverables after 60% and 100% draft design. The additional services work for Phase
3 described in this document will be conducted simultaneously with the Phase 4 tasks and
will continue as described to completion of the acquisition tasks. A definitive timeline for this
work cannot be estimated; however, the work will be coordinated with the City and regular
status reports will be provided. CLS sub contracting of the WSDOT- approved appraiser has
been included at an estimated maximum cost of $5,000; however, this is going out to bid per
Task 3.3 so this cost is not exact.
The estimated fee for the Phases 3 and 4 work is summarized below:
Phase 3 Additional Services and Phase 4: Construction Documents $429,000
Phase 5: Bid and Construction Support
TBD
Additional Services not included in this Scope of Work
Hazardous Materials
November 11th, 2011
$16,386
Page 13.
401
p
N
N M M
K w
00 0000 000 0� o00 oo oo° N a
w N R a
U
J
a
a a
3 N
op N o00 0 0000 000 00!��°,ry
b
N
o
n N
-.!o
0 0
0 00 0000 000 0 000o a a w oo�'�o o owo
M r
O
L
yy O
N.r wN
2
vN �o °N
V
N M
U
Y ILL
la
y
i
O D OOO 0 000 O o 0 00 000 0 p yi»N
Q
a
W
J N f N O M
w
O
n N
9
G
e
'm
LLz a
O
N L N
o a e
mM O "c 'oU_
x m° m j9a �`o= �`o da oaf° L°Eo a
F a ul O'vQ 2Ti $U' u od �u l w a
N��vA "°AVM 2g 3 w,
Q
N n N i0 b b m Qi m
EXHIBIT
O
LL
x
a�
k
m
N
KIM
Transportation Committee Minutes
November 21. 2011— Pape 2
Statewide Transportation Enhancement Program. This is Washington State Department of Transportation
Grant in the amount of $500,000. The City applied for the grant in July 2010, and was awarded funding in
2011. No matching funds are required. UNANIMOUS APPROVAL. FORWARD TO NOVEMBER 28
COW FOR DISCUSSION.
D. Tukwila Urban Center Pedestrian /Bicycle Bridge: Supplemental Agreement No. 9 with KPFF
Staff is seeking Council approval for Supplemental Agreement No. 9 of Contract No. 07 -123 with KPFF
Consulting Engineers in the amount of $1,367,580.11 to:
Complete design and environmental permitting for the Tukwila Urban Center
Pedestrian/Bicycle Bridge
Design of a new pedestrian signal across West Valley Highway
Trail design connecting bridge users to the Tukwila Longacres Sounder Station
Design along Baker Boulevard to add bike lanes and on- street parking
KPFF conducted the Type, Size and Location (TSL) study and resulting report for the Pedestrian /Bicycle
Bridge. Funding for the Supplemental Agreement will come from the grants described in Item C above,
including matching funds. UNANIMOUS APPROVAL. FORWARD TO NOVEMBER 28 COW FOR
DISCUSSION.
E. Tukwila Urban Center Transit Center Supplemental Agreement No. 13 with IBI Group
Staff is seeking Council approval for Supplemental Agreement No. 13 with the IBI Group for completion of
the final design and PS &E documents for the Tukwila Urban Center Transit Center in the amount of
$429,000.
Funding for this Supplemental Agreement will come from the TOD grant and the WSDOT Regional
Mobility grant. UNANIMOUS APPROVAL. FORWARD TO NOVEMBER 28 COW FOR
DISCUSSION.
F. Andover Park West Street Water Improvements Supplement No. 14 with IBI Group
Staff is seeking Council approval for Supplemental Agreement No. 14 with the IBI Group for completion of
the final design and PS &E documents for the Andover Park West widening and water main replacement in
the amount of $313,037 (widening $167,693 water main $145,344).
Funding for this Supplemental Agreement will come from mitigation and traffic impact fees. The City was
recently awarded $1,420.000 in grant funds for construction from the State Transportation Improvement
Board. UNANIMOUS APPROVAL. FORWARD TO NOVEMBER 28 COW FOR DISCUSSION.
G. Ordinance: Tukwila Urban Center Transit Center
Staff is seeking Council approval to acquire property /condemnation authority as required for right -of -way
and easements need for the Tukwila Urban Transit Center Project as follows:
One right -of -way dedication
Three temporary construction easements
One permanent easement
It is standard for City staff to request condemnation authority at the beginning of a property acquisition
process for public projects. Although it is highly unlikely that any parcel of land within this area will
require condemnation, establishing the ordinance prepares the City for condemnation proceedings, if
required. Four parcels with three separate owners are included in the project area. The agenda packet
provides specific details on ownership. UNANIMOUS APPROVAL. FORWARD TO NOVEMBER 28
COW FOR DISCUSSION.
403