HomeMy WebLinkAboutTIC 2020-06-01 Item 2F - Discussion - 2020 Overlay and Repair OptionsCityiif
Tukwila Akan Ekberg, Mayor
Public Forks Uepadment - Henry Nosh, Director
INFORMATIONAL MEMORANDUM
TO:
Transportation and Infrastructure Committee
FROM:
Henry Hash, Public Works Director
Vicky Carlsen, Finance Director
BY:
Cyndy Knighton, Senior Program Manager
Scott Bates, Program Manager
CC:
Mayor Ekberg
DATE:
May 29, 2020
SUBJECT:
2020 Annual Overlay and Repair Program
Project No. 92010401 - Options for Partial Funding
ISSUE
Discussion on potential overlay options for 2020.
BACKGROUND
Every year road segments are identified for possible inclusion in the City's annual Overlay Program.
Tukwila uses a pavement management system (PMS) to rate the condition of the pavement, which is
the first step in identifying street segments for overlay. Using the pavement scores created in the PMS,
staff considers the pavement condition and preliminary cost to overlay, and frequency of ongoing
maintenance needs to develop a "long list" of potential projects for the next overlay cycle. Design of
the "long list" of selected projects is brought to 50% and, at that point, selection of the final list is
generally made based on funding availability for the highest priority segments. This year was no
exception to the standard process. Ten locations were fully designed, and the attached Engineer's
Estimate was developed.
The COVID-19 Pandemic has impacted the City's finances and many programs and projects are being
reduced or eliminated in 2020 to mitigate the City's revenue losses. Construction of the 2020 Annual
Overlay and Repair Program has currently been suspended. At the May 18, 2020 Transportation and
Infrastructure Committee (TIC) meeting, members requested staff develop options in the event that
partial funding became available.
DISCUSSION AND FINANCIAL IMPACT
Potential project savings identified in the table below could be reallocated for use in a truncated 2020
Overlay and Repair Program. Sites F and G on the Engineer's Estimate attachment are recommended
by staff for construction, should funds be allocated. Both 54th Avenue S and S 158th Street are in
immediate need of overlay restoration and service a high amount of traffic. The work would include
asphalt repair, fixing drainage runoff issues, upgraded ADA compliant ramps, and additional guardrail
to a portion of 54th Avenue S.
CIP Reallocation
First Priority Overlay Locations
1_5............_..._Bridge
Inspections 2020
18
.......
..........................................._..._$..........._20,000
ADA Improvements
....... .....P. ..............................................................................................
...
50,000
Site F: 54th Avenue S
19
Annual Traffic Signal
..........................................................................
62,500
_..........................................................................................................................................................................................................................................................................................
(S 166th St to Slade Way) $
165,814
22
...............................:.......................................................................................................................................................................................................................................
Walk & Roll
75,000
23
TIB Channelization Study................
25,000
Site G: S 158th St
..............
Use of Existing fund balance
80,000
(39th PI S to 42nd Ave S)
136,213
Savings
$ 312,500
Overlay Cost $
302,027
Contingency $
10,473
The second priority for Overlay is Site A: S 200th Street (Southcenter Parkway to Green River Bridge)
is estimated to cost $368,229. Sites B, C and D are not high -volume streets, or a high maintenance
demand compared to other sites.
https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 06-01-2020/f. 2020 Overlay & Repair Options/INFO MEMO - 2020 Overlay Oplions.docx
69
INFORMATIONAL MEMO
Page 2
Reducing the budget for the projects listed in the table on the previous page will not cancel the projects,
only delay them until a later date, when funding is available.
Decision points for other capital projects
At the May 18, 2020 Transportation and Infrastructure Committee meeting, the status of capital
projects in the residential street, arterial street, and general government improvement funds were
reviewed. The analysis provided status updates on the projects listed in the table above as well as a
few others, including 42nd Ave S Bridge design, S 119th St Pedestrian Bridge painting, siding repair at
TCC, and the facilities study.
4211 Ave S Bridge: Council authorized funding of up to $1 million ($320k general fund, $680k solid
waste utility tax) for 30% design. There is a possibility that a federal infrastructure bill could include
funding for "shovel ready" projects. In order for this project to have the best chance of receiving
funding, the project would need to be at least 30% designed. The City expects to select a design
consultant later this summer to get to 30% design. Since funding for the highest priority areas for
overlay have been identified, staff is recommending that a decision on whether to fund this project or
redirect funds elsewhere, be delayed until the true cost of design is understood.
S 1191" St Ped Bridge painting: Not funding this project will only delay the project, not cancel it. There
is a window of opportunity to paint the bridge due to weather and fish cycles. Removing funding for
this project will delay the project until at least 2021.
Siding repair at TCC: Siding repair for TCC has been listed as a project as early as 2018. When the
2019-2020 budget was drafted, the expectation was that $200k in siding and roofing repairs at TCC
would occur. Budget for this project is $120k and funding currently exists in the general government
improvement fund. Continuing to delay this project will only result in higher costs when the repair is
finally completed. Staff is recommending that TCC siding repair occur this year utilizing the existing
budget.
Facilities Study: This project is also funded out of the general government improvement fund and there
is currently adequate funding to complete Phases 1 and 2 for approximately $190k, as currently
proposed. The original request for this project was $300k, however, the final phase could be done at
a later date. By completing Phases 1 and 2 now, the City will have updated seismic information on
City Hall, 6300 building, TCC, and Fire Stations 53 and 54. These phases will also provide a facility
condition assessment and space planning at City Hall. The completion of the Justice Center will occur
in the next few months and many staff members who are currently located at City Hall and the 6300
building will be moving to the new facility, resulting in significant unused space in both buildings. By
completing Phases 1 and 2 now, it will position the City to make informed decisions on the best next
steps for the next phase of facility planning. Staff is recommending that phases 1 and 2 move forward
as planned.
RECOMMENDATION
Discussion only or possible recommendation for full Council for review for June 8 Committee of the
Whole meeting.
Attachments: Engineer's Estimate
2020 Overlay Cover
Active 2020 Projects
hftps:/Itukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 06-01-2020/f. 2020 Overlay & Repair Options/INFO MEMO - 2020 Overlay Options.docx 70
OVERLAY FUNDS NEIGHBORHOOD TRAFFIC CALMING PROGRAM
2020 OVERLAY PROGRAM
PROJECT N0.92010401
MARCH 2O20
MAYOR CITY COUNCIL
ALLAN EKBERG DE'SEAN QUINN, PRESIDENT
DIRECTOR OF PUBLIC WORKS VERNA SEAL
KATHY HOUGARDY
HENRY HASH KATE KRULLER
CITY ENGINEER THOMAS MCLEOD
HARI PONNEKANTI, P.E. ZAK IDAN
CYNTHIA DELOSTRINOS JOHNSON
SCHEDULE OF DRAWINGS
SHEET NO.
SHEET TITLE
SCHEDULE A
1
COVER
2 - 4
DETAILS
LEGEND
5
44TH AVE S
EXISTING:
PROPOSED:
tw
WATER VALVE
THICKENED EDGE
6
S 109TH ST & 48TH AVE S
m
GAS VALVE
7
S 126TH ST
FIRE HYDRANT
PAVEMENT REPAIR
O
TELEPHONE MANHOLE
8
S 126TH ST RAMPS
®
FIBER OPTIC MANHOLE
0
HMA OVERLAY
9
S 150TH ST
�
POWER POLE
HMA PAVEMENT SECTION
10
S 150TH ST & 46TH AVE S IMPROVEMENTS
®
MONUMENT0
SANITARY SEWER
0
CRUSHED GRAVEL
11 — 12
RRFB AND LUMINAIRE PLANS & DETAILS
®
WATER METER
14
S 158TH ST
CATCH BASIN
0
CEMENT CONC. PAVEMEN-
15
S 158TH ST RAMPS
0
TREE
BUTT JOINT OR EDGE PLI
CRUSHED GRAVEL
16 — 17
54TH AVE S
— — — — — — —
SAWCUT
CEMENT CONC. PAVEMENT
18 — 19
S 200TH ST
INLET PROTECTION PER N
20
S 200TH ST RAMPS
VEGETATION
STD PLAN 1-40.20-00
—••—
FENCELINE
21
S 148TH ST CURB RAMP (3438 S 148TH ST)
_ _ _ _
ROW LIMITS
SCHEDULE B
PROPERTY LINE
22 — 23
53RD AVE S RE—ROUTE IMPROVEMENTS
24
CURB RAMP DETAILS
25
DRIVEWAY DETAILS
26
53RD AVE S & VICINITY DETAILS
ITH AVE S
S & S 137TH ST
EDULE B)
;LAY & 46TH AVE S
DVEMENTS
?�F 0
�l VAL
Q
3
F
IL
m
}
F
N
wlLa by I date
designed BMC 03/2020
PUBLIC WORKS DEFT_ KPGr Bap 2020 OVERLAY PROGRAM
o s drawn MKE 03/2020 Interdisciplinary Design
*ENGINEERING *STREETS *WATER*SEWER* checked NdD o3/2020 3131EIIiouAve 2502deifersanAve 24
a. y Suite 400 Tacoma, WA 98402
"'sue 903 ,��° o dii� Seattle, WA98121 (253) 627-0720 ��������� file no 19168COV.DWG
field irno Seau aslsao www.kpg.com27-072 COVER scale 1"=,IG
no date revisions J72 03/2020
Project
Fund No.
Project
Status
2020 CIP Projects
103, 104, & 303 Funds
A B
City Funding
Funding 2020 Budget
C
D E
F
G H I
Grant/
2020
Phase 1 & II
103 Fund
Dedicated Rev
Expenditures Committed
Reductions
Balance Policy Decision Council
Funding
to Date for 2020
5/11/2020
Reduction Go / No Go? Decision
103 Fund - Residential Streets
1
103
99410303
42nd Ave S Phase III
Physically completed, final payments
City
$ 378,000
$ 24,102
$ 353,898
2
103
99110301
53rd Ave S
Utility undergrounding, Comcast next
Grant Funded
399,000
120,140
278,860
3
103
Various
(3) Safe Routes to School Projects
Not started, seeking grants, no $ to date
Grant Funded
$ 5,301,000
4
103
81910301
Traffic Calming
On hold due to negative fund balance
City
400,000
9,564
53,504
$ 350,000
5
103
Interfund Loan Repayment
Covers SCL expenditures for 42 & 53
City
1
1 336,932
Total 103 Fund $ 1,177,000
104 Fund - Arterial Streets
$ 153,806
$ 1,023,194
$ 350,000
6 104 104 Wages & Benefits Ongoing staff expenses City $ 485,383
$ 93,471 $ 391,912
7
104
98610403
Strander Blvd Extension
Closed, final 2020 grant reimbursement
City
147,362
$ 475,000
622,362
8
104
99310410
West Valley Hwy
Design funds only, underway
Grant Funded
600,000
60,237
539,763
9
104
91310407
BAR Bridge over Airport Way
Construction awarded 5/4/20
Grant Funded
-
2,614,000
17,861
2,596,139
10
104
91810404
42nd Ave S Bridge Replacement
In-depth bridge inspection
City
39,884
39,884
11
104
91810404
42nd Ave S Bridge Replacement
30% Design proposals due 5/19/20
City/WM tax
320,000
680,000
$ 1,000,000
12
104
9030404
S 144th St Bridge - Sidewalks
Not started, seeking grants, no $ to date
Grant Funded
-
227,000
13
104
92010401
Overlay & Repair 2020
Design underway, ready to bid, on hold
City
1,400,000
128,453
71,547
$ 1,200,000
14
104
82010403
Traffic Counts 2020
Ongoing, contract began 1/1/20
City
18,750
3,300
15,450
15
104
92010402
Bridge Inspections 2020
4 legally required bridge inspections
City
196,000
93,000
2,252
49,444
20,000
16
104
91710406
S 196th St/200th St Br Repair
Completed, retainage to be paid
City
1,304
16,000
17
104
91610407
S 119th St Pedestrian Bridge
Painting of pedestrian bridge on hold
City
200,000
18
104
91510405
ADA Improvements
ADA ramps at 53, 58, on hold w/ Overlay
City
50,000
50,000
19
104
82010404
Annual Traffic Signal
Ongoing, reduced by 50%, deferred maint.
City
125,000
2,549
59,951
62,500
20
104
11301302
Wetland & Envir Mitigation
Ongoing, required by permit
City
40,000
16,219
23,781
21
104
82010405
Transp Element of the Comp Plan
Not started, required by GMA, due by 2021
City
400,000
400,000
22
104
82010406
Walk & Roll
Update not started, on hold
City
75,000
75,000
23
104
81710404
TIB Channelization Study
Study completed, $25k balance remaining
City
25,000
25,000
24
104
Park Impact Fees Transfer to 301
Housekeeping transfer from 104 to 301
City
1,009,000
$ 325,646
1,009,000
$ 5,835,232
$ 1,200,000
$ 1,432,500
Total 104 Fund $ 4,331,379 $ 4,462,000
303 Fund - Facilities
25 Beginning Fund Balance Drawdown of fund balance $ 656,000
27
303
91930304
6300 Dry Fire Sprinkler System
Completed
City
30,000
$ 30,000
28
303
91630305
TCC Siding Repairs
Not started, 2 quotes received in 2019
City
200,000
$ 120,000
303
91630305
TCC Siding Repairs -Savings
Savings from bids
City
80,000
303
91630304
City Hall Siding Repairs
No started
City
100,000
$ 100,000
29
303
82030301
2020 Facilities Study/Seismic
RFPs in, not started
City
300,000
110,000
190,000
Total 303 Fund
$ 630,000
$ 30,000
$ -
$ 210,000
$ 390,000
Total 1 $ 1,822,500
Lines 3 & 12, not added in totals as completely grant funded and no grants to date.
Dedicated revenues include REET, Parking tax, & MVFT
Grant funded
Line 11, Solid Waste Utility tax revenue may be reduced due to COVID-19
hops://tukwilawa.sharepoint.com/sites/publicworks/engineering/Shared Documente/Actlw 2020 Projects.xlsx 73