Loading...
HomeMy WebLinkAboutTIC 2020-06-15 Item 2B - Discussion - Fleet and Facilities Building Improvements Update and 60% Design ReviewCity of Tukwila Allan Ekberg, Mayor Public Works Department - Henry Hash, Director INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Committee FROM: Henry Hash, Public Works Director BY: Hari Ponnekanti, Deputy PW Director CC: Mayor Allan Ekberg DATE: June 12, 2020 SUBJECT: Public Works Fleet & Facilities Building Tenant Improvements Project No. 91630601 Project Update and 60% Design Review ISSUE Provide an update on the PW Fleet and Facilities Tenant Improvements at 60% design, schedule, and cost estimate. BACKGROUND On 12/02/19, Council approved the PW Fleet and Facilities tenant improvements project budget in the amount of $9.5 million dollars with funding split 50/50 with the General Fund and Water/Sewer/Surface Water Utilities. DISCUSSION SHKS Architect has reached the 60% design milestone. Please see the attached design drawing, project timeline schedule, and cost estimates. 60% design cost estimates are within the range of the estimated budgets. The following are some of the highlights of the design progress. • Geo-technical explorations have been completed and seismic bracing design is advancing forward. • Plumbing, HVAC, vehicle exhaust connection, lighting, tire storage facility, office and kitchen area design is advanced in this design period. Project specifications and bid documents are created. More detailed cost estimates are prepared as part of the 60% design. Paint booth removal contract is signed, and permit application is submitted to DCD. PHASE 1 FINANCIAL IMPACT Expenditures 2019/2020 Budget SHKS Design Am No. 2 570,768.00 Misc Consultant Services 105,460.00 Estimate - Soft Costs 2,108, 772.00 Estimate - Construction 6,715,000.00 Funding - General Fund $ 4,750,000.00 Funding - Utilities 4,750,000.00 Total $ 9,500,000.00 $ 9,500,000.00 DISCUSSION ONLY Committee discussion only Attachments: Cost estimates Tentative Schedule https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 06-15-2020/FRF 60%/Info Memo for PW F F Update 051820.docx 5 Public Works Fleet and Facilities Building - Phase 1 Cost Estimates Expenditures to Estimates at 30% Estimates at 60% Budget date 12/31/19 Design Design Land Purchases $ 24,706,348.00 SHKS Master Plan 1,398,437.09 Design SHKS Design Fee Geo-Tech Design Fee Hazard Study Fee Mayes Testing Soft Costs Demolition of Out Buildings Construction Phase 1 Building Renovation Remoal of Paint Booths Fence and Security Gates Outside Structural Repair and Paint Covered Storage - Outside Civil Site Work Trench Drains (Alternate) Emergency Generator (Alternate) Grand Total $ 26,105,000.00 $ 26,104,785.09 $ 17,547.68 $ 553,220.32 80,000.00 3,450.00 $ 553,220.32 80,000.00 11,160.00 14,300.00 $ 2,880,000.00 $ 636,670.32 $ 658,680.32 $ 81,077.70 $ 81,077.70 $ 4,524,329.00 $ 5,237,611.00 106, 615.54 168, 000.00 300,000.00 212,560.72 280,000.00 750,000.00 750,000.00 750,000.00 750,000.00 35,885.00 35,885.00 382,852.00 382,852.00 $ 6,715,000.00 $ 404,163.22 $ 6,992,143.70 $ 7,449,986.42 $ 35,700,000.00 $ 26,122,332.77 $ 7,628,814.02 $ 8,108,666.74 $ 34,031,146.79 $ 34,230,999.51 https://tukwiIawa.share point. cam/sites/puhlicworks/engineering/PWDrop Box/01 TIC Agenda/Agend a Item s/TIC06-15-2020/F&F60%/Cost Estimates04142020 6 Page 1 DCW Cost Management 60% Design Cost Plan April 17, 2020 Tukwila Public Works Fleets & Facilities Buildina Fleets and Facilities Renovation Alternate 1: Emergency generator 43,200 114.08 4,928,268 368,277 7 DCW Cost Management Tukwila Public Works Fleets & Facilities Building A10 Foundations Substructure Desigr Superstructure B20 Exterior Enclosure B30 Roofing C10 Interior Construction C20 Stairways C30 Interior Finishes D20 Plumbing Systems D30 Heating, Ventilation & Air Conditioning D40 Fire Protection D50 Electrical Lighting, Power & Communications E10 Equipment E20 Furnishings Equipment F20 Selective Demolition 60% Design Cost Plan April 17, 2020 8 Gross Area: 40,255 SF 6% 7.88 7% 9.10 1 % 1.67 0% 0.29 3% 1% 4% 7% 15% 2% 14% 9 3% 1% 4% 3.74 0.68 4.42 8.59 17.88 2.53 17.44 3.16 1.21 4.76 317,358 366,210 67,160 11,568 150,569 27,475 178,050 345,678 719,616 101,758 702,132 127,040 48,528 191,580 Z10 Contingency 15.00% 10% 12.50 503,208 BUILDING ELEMENTAL COST INCLUDING CONTINGENCIES 78% 95.84 3,857,930 Z20 General Requirements 6.50% 5% 6.23 250,765 Z21 General Conditions 9.88% 8% 10.08 405,939 Z22 Office Overhead & Profit 5.00% 5% 5.61 225,732 Z23 Bonds and insurance 1.50% 1 % 1.44 57,869 Z24 Permit by owner 0.00% 0% 0.00 0 BUILDING CONSTRUCTION COST BEFORE ESCALATION 97% 119.20 4,798,236 Z30 Escalation to Midpoint (Jan 2021) 2.71 % 3% 3.23 130,032 A 10