HomeMy WebLinkAboutCOW 2020-06-22 Item 3A - Public Hearing - Resolution Adopting 2021-2026 Transportation Improvement ProgramCOUNCIL AGENDA SYNOPSIS
---------------------------------- Initials
Meeting Date
Prepared b
Mayor's review
Council review
06/22/20
GL
07/06/20
GL
ITEM INFORMATION
ITEMNO.
3.A. & 4.A.
STAFF SPONSOR: CYNDY KNIGHTON
ORIGINAL AGENDA DATE: 06/22/20
AGENDA ITEM TITLE Resolution for Six -Year Transportation Improvement Program (2021-2026)
"To provide public hearing comments, please email citycouncil(&tukwilawa.gov, provide your first
and last name, and reference the public hearing topic in the subject line, by 5:00 p.m. on June 22,
2020. Once you have signed up by email, your name will be called upon during the meeting to
speak for up to five minutes. Call 1-253-292-9750, ACCESS CODE 670077847# at 7:00 p.m. on
June 22 2020 to access the meetin ."
CATEGORY ® Discussion
❑ Motion
® Resolution
❑ Ordinance
❑ Bid Award
® Public Hearing
❑Other
Mtg Date 06122120
Mtg Date
Mtg Date 07106120
Mtg Date
Mtg Date
Mtg Date 06122120
Mtg Date
SPONSOR ❑Council ❑Mayor ❑HR ❑DCD ❑Finance ❑Fire ❑TS ❑P&R ❑Police ®P1V ❑Court
SPONSOR'S The Transportation Improvement Program (TIP) is updated annually as required by the
SUMMARY Revised Code of Washington (RCW). The TIP is adopted by Resoultion after a Public
Hearing at the local agency level and incorporated into regional and state TIPs. Council is
being asked to approve the Resolution for the 2021-2026 Six -Year Transportation
Improvement Program and consider this item at the June 22, 2020 Committee of the Whole
with a Public Hearing and subsequent July 6, 2020 Regular Meeting.
REVIEWED BY ® Trans&Infrastructure ❑ CommunitySvs/Safety ❑ Finance Comm. ❑ Planning/Economic Dev.
❑ LTAC ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 06/01/20 COMMITTEE CHAIR: DELOSTRINOS JOHNSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works Department
COMMITTEE Unanimous Approval; Forward to Committee of the Whole
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0 $0 $0
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
06/22/20
07/06/20
MTG. DATE
ATTACHMENTS
6/22/20
Informational Memorandum dated 05/29/20
Draft Resolution
Draft 2021-2026 TIP Summaryr
2021-2026 "Draft" Transportation Improvement Program
Current Adopted 2020-2025 TIP
Minutes from the Transportation and Infrastructure Committee meeting of 06/01/20
07/06/20
Resolution in final form
2
TO:
FROM:
BY:
CC:
DATE:
SUBJECT
City of Tukwila Allan Ekberg, Mayor
Public Works Department - Henry Hersh, Director
INFORMATION MEMORANDUM
Transportation and Infrastructure Committee
Henry Hash, Public Works Director
Cyndy Knighton, Senior Program Manager
Mayor Ekberg
May 29, 2020
Resolution for Six -Year Transportation Improvement Program (2021 — 2026)
ISSUE
Approve a Resolution adopting the annual update of the Six -Year Transportation Improvement Program for
2021 —2026.
BACKGROUND
The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of
Washington (RCW). The TIP is adopted by Resolution after a public hearing at the local agency level and
incorporated into regional and state TIPS. The TIP is primarily a financial planning document for projects
competing for grants. Any project submitted for federal grant funding must be included in the local, regional,
and state adopted TIPS. The TIP is a rolling plan showing various funding sources: grants, developer, and
local funds. Projects "roll" as funds or stages occur (design report, final design, and construction).
Tukwila's TIP and Capital Improvement Program (CIP) list many of the same transportation -related projects.
The TIP generally lists only those transportation -related projects planned within the next six years that are
deemed regionally significant or that have grant funding awarded or expected. The TIP is scheduled for
adoption on July 6, 2020.
/_1►/_1W&I[.*I
The attached spreadsheet is the "Draft" 2021 — 2026 TIP and was created by modifying the 2020 — 2025 TIP
to add or remove projects and adjust project costs. No prioritization was assigned, and the list of projects is
presented in alphabetical order. Prioritization of projects is reflected in the current CIP. One new project was
added, and two projects were removed because they have either been completed or moved beyond the six -
year time frame of the TIP. The South King County Regional TDM for Centers & Corridors was added to the
State's TIP earlier this year as required when state or federal grant monies are awarded. It is being added to
the City's TIP for this adoption cycle. The Boeing Access Road over Airport Way Bridge Seismic Retrofit has
been removed as it is expected to be completed in 2020. The Strander Boulevard/SW 27th Street Phase III
was included in the 2020 TIP as the TIP was adopted about the same time the City decided to cancel the
project, therefore it is being removed from the 2021 — 2026 TIP.
New: South King County Regional TDM for Centers & Corridors
Deleted: Completed: Boeing Access Road over Airport Way Bridge Seismic Retrofit. Moved to Beyond:
Strander Boulevard/SW 27th Street Phase III
FINANCIAL IMPACT
None.
RECOMMENDATION
Council is being asked to approve the Resolution for the 2021 — 2026 Six -Year Transportation Improvement
Program and consider this item at the June 22, 2020 Committee of the Whole with a Public Hearing and
subsequent July 6, 2020 Regular Meeting.
Attachments: Resolution
Draft 2021-2026 TIP Summary
2021 — 2026 "Draft" Transportation Improvement Program
Current Adopted 2020 — 2025 TIP
https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 06-01-2020/e. 2021-2026 Six Year TIP/1. Info Memo TIP 2021.docx
11
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2021-
2026), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26, the
City Council of the City of Tukwila has previously adopted a Transportation Improvement
Program and thereafter periodically modified said Transportation Improvement Program
by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six -Year Transportation Improvement Program for the
ensuing six calendar years (2021-2026); and
WHEREAS, on June 22, 2020, a public hearing was held regarding the City's Six -
Year Transportation Improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six -Year Transportation Improvement Program
for the calendar years 2021 to 2026, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the Secretary
of Transportation and the Transportation Improvement Board of the State of Washington.
W:\Legislative Development\TIP 2021-2026 5-20-20
CK:bjs Review and analysis by Barbara Saxton Page 1 of 2
5
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Regular Meeting thereof this day of , 2020.
ATTEST/AUTHENTICATED:
Christy O'Flaherty, MMC, City Clerk
APPROVED AS TO FORM BY:
Office of the City Attorney
De'Sean Quinn, Council President
Filed with the City Clerk:
Passed by the City Council:
Resolution Number:
Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2021 to 2026
W:\Legislative Development\TIP 2021-2026 5-20-20
CK:bjs Review and analysis by Barbara Saxton
0
Page 2 of 2
2019-2024
CIP Sheet
DRAFT 2021 - 2026 TIP SUMMARY
,xr
PROJECT TITLE
15
42nd Avenue S Bridge Replacement
4
46th Avenue Safe Routes to School
18
ADA Improvements
26
APE/Minkler Blvd Intersection
17
Annual Bridge Inspections and Repairs
16
Annual Overlay and Repair Program
-
BNSF Regional Center Access
25
Green River Trail
5
Macadam Road S Complete Streets Project
20
S 140th St Intersection Improvements
14
S 144th St Bridge Sidewalks
6
S 152nd Street Safe Routes to School
-
S. King Co. Regional TDM for Centers & Corridors
12
West Valley Highway
TOTAL
May 20, 2020
Project Costs in
Thousands of Dollars
FUNDING SOURCES
2021
2022
2023
2024
2025
2026
TOTAL
Federal
State/TIB
Developer
Unsecuredl
City
500
1,734
280
9,460
9,459
0
21,433
17,000
17,000
4,433
0
526
2,070
0
0
0
2,596
2,277
2,277
319
200
200
200
200
200
200
1,200
-
1,200
0
144
1,570
0
0
0
1,714
-
1,714
335
335
405
405
450
450
2,380
-
2,380
1,850
1,850
1,950
2,050
2,050
2,050
11,800
-
11,800
0
0
0
0
0
100
100
-
100
74
1,200
0
0
0
1,274
1,146
1,146
128
0
0
500
3,100
0
0
3,600
3,250
3,250
350
0
0
200
1,200
0
0
1,400
-
1,400
0
0
443
0
0
0
443
400
400
43
369
2,600
0
0
0
0
2,969
2,340
2,600
629
352
312
447
357
125
37
1,630
450
1,165
15
1,030
0
3,195
0
0
0
0
0
3,195
2,179
-
1,016 il
6,875 8,901 8,065 16,772 12,284 2,837 55,734 20,190 10,017 15 1 27,703
PROJECTS REVISED FROM 2020-2025 TIP
New Deleted/Completed: Deleted/Moved to Beyond:
South King County Regional TDM for Centers & Corridors BAR over Airport Wy Bridge Seismic Retrofit* Strander Blvd/SW 27th St Phase III
M
MAMIL ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
-
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
B
Z
C. Project Title
=
y
3
1e
°—
n
c
3
D. Road Name or Number
o
0
3
0
°o
m
w
S.
m o
d
E. Begin & End Termini
t
Z
-
y
F. Project Description G. Structure ID
a
P
m
y
s
m
a
05
TUK-62
06/22/20
11
0.100
DCE
Yes
42nd Ave S Bridge Replacement
42nd Ave S over he Duwamish River at the intersection with Interurban Ave S
Interurban Ave S to Northern end of bridge
Replace the existing 42nd Ave S steel truss bridge. The replacement would require
preliminary engineer design, right-of-way, and construction phases. The new
structure would meet current road and bridge design standards. The replacement
structure configuration would be two through lanes, possibly a turn pocket, and
include sidewalks.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2021
0
0
500,000
500,000
P
PE
2022
STP
1,500,000
0
234,000
1,734,000
P
RW
2023
0
0
30,000
30,000
P
CN
2023
0
0
250,000
250,000
P
CN
2024
STP
3,000,000
01
468,2001
3,468,200
P
CN
2024
BR
12,500,000
0
2,950,800
15,450,800
Totals
17,000,000
10
4,433,000
21,433,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
500,000
1,734,000
0
0
0
RW
0
0
30,000
0
0
CN
0
0
250,000
9,460,000
9,459,000
Totals
500,000
1,734,000
280,000
9,460,000
9,459,000
Repoli Date: May 19, 2020
Page 1
IN
O
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwasof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
�o
C. Project Title
m
m
m
3
A
c
D. Road Name or Number
m
a
a
o
0
r'
m
m c
3
E. Begin & End Termini
t
9
z
-
°o
S.
y 'm_
F. Project Description G. Structure ID
(o
a
p
m
y
s
m
a
19
WA-11113
06/22/20
05
0.370
Yes
46th Avenue Safe Routes to School
46th Avenue S
i<+100
S 150th Street to S 144th Street
co
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
ONP
crosswalk across S 144th Street with RRFB.
r 1
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
SRTS
180,000
90,000
270,000
P
RW
2022
0
SRTS
232,000
24,000
256,000
P
CN
2023
0
SRTS
1,865,000
205,000
2,070,000
Totals
0
2,277,000
319,000
2,596,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
270,000
0
0
0
RW
0
256,000
0
0
0
CN
0
0
2,070,000
0
0
Totals
0
526,000
2,070,000
0
0
Repoli Date: May 19, 2020 Page 2
MAML ►I MhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
y
3
1e
°—
n
c
3
D. Road Name or Number
o0
0
0
3
cf
°o
m
S.
m o
d
E. Begin & End Termini
t
Z
-
y
F. Project Description G. Structure ID
co
a
P
m
y
s
m
a
00
WA-05405
06/22/20
06
No
Americans with Disabilities Act (ADA) Improvements
Various locations
i<+100
to
co
Design and construct ADA compliant upgrades to City infrastructure in conjunction
:0
with a City developed plan.
OW416,
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2021
0
0
1,200,000
1,200,000
Totals
0
0
1,200,000
1,200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
Sth & 6th
ALL
200,000
200,000
2QQ,000
200,000
400,000
Totals
200,000
200,000
200,000
200,000
400,000
Report Date: May 19, 2020
Page 3
N
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwa:of Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
y
3
1e
°—
n
c
D. Road Name or Number
0
0
3
0
m
m o
3
E. Begin & End Termini
o0
s
Z
-
°o
S.
y d
F. Project Description G. Structure ID
(o
a
P
m
uD
s
m
a
16
WA-07746
06/22/20
03
C G O P S
No
so
TW
Andover Park E/Minkler Blvd Intersection
i<+100
Andover Park E
co
Minkler Blvd to
D
Construct left turn lanes on Andover Park East and reconstruct traffic signal
I
Is
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
0
134,000
134,000
P
RW
2022
0
0
10,000
10,000
P
CN
2023
0
0
1,570,000
1,570,000
Totals
0
0
1,714,000
1,714,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
134,000
0
0
0
RW
0
10,000
0
0
0
CN
0
0
1,570,000
0
0
Totals
0
144,000
1,570,000
0
0
Repoli Date: May 19, 2020 Page 4
MAMIL ► MhingtanState Six Year Transportation Improvement Program
AP Della►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
�o
C. Project Title
m
m
m
3
m
A
m c
c
3
D. Road Name or Number
m
t
a
9
a
o
0
°o
r,
S.
'm_
E. Begin & End Termini
z
-
y
F. Project Description G. Structure ID
(o
a
P
m
y
s
m
a
14
WA-03731
06/22/20
06
No
Annual Bridge Inspections and Repairs
Various City Street
i<+100
to
co
Perform load ratings and bi-annual inspections as well as construct necessary
0
repairs and maintenance
OW41h,
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2021
0
0
2,380,000
2,380,000
Totals
0
0
2,380,000
2,380,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
Sth & 6th
ALL
335,000
335,000
Q5,000
405,000
900,000
Totals
335,000
335,000
405,000
405,000
900,000
Repoli Date: May 19, 2020
QM
Page 5
W
MAML ►I MhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
y
3
1e
°—
n
c
3
D. Road Name or Number
o0
0
0
3
ct
°o
m
S.
m o
d
E. Begin & End Termini
t
Z
-
y
F. Project Description G. Structure ID
(o
a
P
m
uD
s
m
a
16
WA-03733
06/22/20
06
C G O P S
No
so
TW
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2021
0
0
11,800,000
11,800,000
Totals
0
0
11,800,000
11,800,000
Expenditure Schedule
Phase
1st
2nd
rd`,
4th
Sth & 6th
ALL
1,850,000
1,850,000
,9W,000
2,050,000
4,100,000
Totals
1,850,000
1,850,000
1,950,000
2,050,000
4,100,000
�C "
Report Date: May 19, 2020 Page 6
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
B
Z
C. Project Title
=
y
3
1e
°—
n
c
3
D. Road Name or Number
o
0
3
0
°o
m
w
S.
m o
d
E. Begin & End Termini
t
Z
-
y
F. Project Description G. Structure ID
a
P
m
y
s
m
a
00
WA05409
06/22/20
08
EIS
No
BNSF Regional Center Access
New Facility
to
Construct a new access to the BNSF Regional Distribution Center, relocating the
900+daily truck trips from residential streets in Allentown.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2026
0
0
100,000
100,000
Totals
0
0
100,000
100,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
Sth & 6th
PE
0
0
0
0
100,000
Totals
0
0
0
0
100,000
QM
Repoli Date: May 19, 2020
Page 7
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
y
3
1e
°—
c1
c
D. Road Name or Number
0
0
3
cf
m
0
3
E. Begin & End Termini
o0
t
Z
-
°o
S.
y d
F. Project Description G. Structure ID
(o
a
P
m
y
s
m
a
00
WA-11115
06/22/20
28
0.140
DCE
No
Green River Trail
so
Green River Trail
i<+100
Christensen Road to Green River
co
Replace the existing 8-foot wide Green River Trail with 12-foot wide concrete paved
trail with 2-foot gravel shoulders, including illumination, CCTV, wayfinding, and
ONP
pedestrian plaza.
r 2
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2022
0
Ped/Bike Program
1,146,000
128,000
1,274,000
Totals
0
1,146,000
128,000
1,274,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
74,000
1,200,000
0
0
0
Totals
74,000
1,200,000
0
0
0
0
Repoli Date: May 19, 2020 Page 8
MAML ► aishingtanState Six Year Transportation Improvement Program
AP Delsa►tinwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
y
3
1e
°—
n
c
D. Road Name or Number
0
0
3
0
m
m
0
3
E. Begin & End Termini
o0
t
Z
-
°o
S.
y d
F. Project Description G. Structure ID
(o
a
P
m
y
s
m
a
17
WA-11110
06/22/20
04
0.350
DCE
No
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
9
and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
r 2
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
Ped/Bike Program
360,000
40,000
400,000
P
RW
2022
0
Ped/Bike Program
90,000
10,000
100,000
P
CN
2023
0
Ped/Bike Program
2,800,000
300,000
3,100,000
Totals
0
3,250,000
350,000
3,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
400,000
0
0
RW
0
0
100,000
0
0
CN
0
0
0
3,100,000
0
Totals
0
0
500,000
3,100,000
0
Report Date: May 19, 2020
Page 9
MAMIL ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
�o
C. Project Title
m
m
m
3
A
c
D. Road Name or Number
m
a
a
o
0
r,
m
m c
3
E. Begin & End Termini
t
9
z
-
°o
S.
y 'm_
F. Project Description G. Structure ID
(o
a
P
m
uD
s
m
a
14
WA-09873
06/22/20
04
C G P S T
0.100
DCE
Yes
so
W
S 140th St Intersection Improvements
S 140th Street
Tukwila International Blvd to
Design and construct a new traffic signal at the S 140th Street/Tukwila International
Blvd intersection
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2023
0
0
150,000
150,000
P
RW
2023
0
0
50,000
50,000
P
CN
2024
0
0
1,200,000
1,200,000
Totals
0
0
1,400,000
1,400,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
150,000
0
0
RW
0
0
50,000
0
0
CN
0
0
0
1,200,000
0
Totals
0
0
200,000
1,200,000
0
Report Date: May 19, 2020 Page 10
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
0
m
Z
C. Project Title
=
y
3
1e
°—
n
c
D. Road Name or Number
0
0
m
m o
3
E. Begin & End Termini
o0
t
Z
-
°o
S.
y d
F. Project Description G. Structure ID
(o
a
P
m
y
s
m
a
17
WA03782
06/22/20
28
0.250
No
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
01
Widen existing sidewalks on bridge over 1-5 between 51 st Ave S and 53rd Ave S
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2023
SRTS
400,000
0
43,000
443,000
Totals
400,000
0
43,000
443,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
443,000'
0
0
Totals
0
0
443,000
0
0
Repoli Date: May 19, 2020
Page 11
N
O
MAMIL ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
-
o<<
A. PIN/Project No. B. STIP ID
3
0
3
c
_
0
'
B
z
�o
C. Project Title
m
'o
m
m
3
A
c
D. Road Name or Number
m
CL
o
0m
M
m c
3
E. Begin & End Termini
t
z
-
°o
S.
y 'm_
F. Project Description G. Structure ID
c4e
P
m
y
s
m
a
19
WA-11112
06/22/20
06/17/19
1961
05
0.300
No
S 152nd Street Safe Routes to School
"<+100
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Design and construct curb, gutter and sidewalks on both sides including widening
pavement width by 3 feet to construct on -street parking lane on north side of street.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2021
0
0
369,000
369,000
P
CN
2022
0
SRTS
2,340,000
260,000
2,600,000
Totals
0
2,340,000
629,000
2,969,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
369,000
0
0
0
0
CN
0
2,600,000
0
0
0
Totals
369,000
2,600,000
0
0
0
Repoli Date: May 19, 2020 Page 12
MAML ► MhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
0
m
`2
Z
C. Project Title
=
y
3
0�
1e
°—
c1
c
3
D. Road Name or Number
o0
0
0
0
0
00
m
S.
0
d
E. Begin & End Termini
t
Z
-
y
F. Project Description G. Structure ID
co
a
p
m
y
s
m
0.
00
TUK-63
06/22/20
24
0.000
No
South King County Regional TDM for Centers and Corridors
South King County
i<+100
Various to Various
The project will focus on providing TDM services at selected activity centers (e.g.
business parks, commercial and residential multi -tenant buildings, educational
institutions) and/or congested corridors in Tukwila, Renton, SeaTac, and Kent to
reduce drive alone travel and traffic congestion in south King County. A key strategy
will include the development of partnerships with embedded organizations in the
communities we are serving to facilitate more effective outreach and improve long-
term program outcomes.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2021
0
OTHER
132,750
15,000
147,750
P
ALL
2021
CMAQ
450,000
OTHER
1,029,860
0
1,479,860
Totals
450,000
1,162,610
15,000
1,627,610
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
352,100
312,100
444,600
357,100
161,700
Totals
352,100
312,100
444,600
357,100
161,700
Repoli Date: May 19, 2020
N
Page 13
N
N
MAMIL ►emhingtanStarte Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2021 to 2026
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
M
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
�o
C. Project Title
m
m
m
3
m
A
m c
c
3
D. Road Name or Number
m
t
a
9
a
o
0
°o
r'
S.
'm_
E. Begin & End Termini
z
-
y
F. Project Description G. Structure ID
(o
a
p
m
y
s
m
a
14
TUK-60
06/22/20
28
0.170
DCE
No
West Valley Highway/Longacres Way Shared Use Pathways
SR 181 & Longacres Way
i<+100
W end of planned Green River Bridge to Longacres Way
rw
Improvements will be completed on SR 181 from the west end of the planned Green
River non -motorized Bridge to Longacres Way, including a 12-14 ft. separated
shared use path with a 5 ft. landscaped buffer strip on the west side of the highway.
Design -only will be completed for future improvements on Longacres Way between
SR 181 to the Tukwila Sound Transit Link Station.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2021
0
TIB
2,179,000
1,016,000
3,195,000
Totals
0
2,179,000
1,016,000
3,195,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
3,195,000
0
0
0
0
Totals
3,195,000
0
0
0
0
Federal Funds State Funds Local Funds Total Funds
Grand Totals for Tukwila 17,850,000 112,354,610 25,527,000 55,731,610
Repoli Date: May 19, 2020 Page 14
MAMIL ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
-
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
0
B
Z
C. Project Title
=
y
3
M
m
n
c
3
D. Road Name or Number
o
0
3
0
w
S.
m o
d
E. Begin & End Termini
s
1D
Z
$
y
F. Project Description G. Structure ID
(o
p
y
s
m1
a
05
TUK-62
V
11
0.100
DCE
Yes
42nd Ave S Bridge Replacement
OOOF
42nd Ave S over he Duwamish River at the intersection with Interurban Ave S
Interurban Ave S to Northern end of bridge
Replace the existing 42nd Ave S steel truss bridge. The replacement would require
preliminary engineer design, right-of-way, and construction phases. The new
structure would meet current road and bridge design standards. The replacement
structure configuration would be two through lanes, possibly a turn pocket, and
include sidewalks.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2020
0
0
1,600,000
1,600,000
Totals
0
0
1,600,000
1,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
1,600,000
0
0
0
0
Totals
1,600,000
0
0
0
0
Repoli Date: May 20, 2020
N
W
Page 1
N
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwasof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
C. Project Title
m
'o.
m
m
3
A
M
,any
c
D. Road Name or Number
m
0
o
0r'
m
m c
3
E. Begin &End Termini
t
a
3z
-<
°o,
.<
S.
y 'm_
F. Project Description G. Structure ID
(o
a
p
m
y
s
m
a
19
WA-11113
06/10/19
06/17/19.
1961
05
0.370
Yes
46th Avenue Safe Routes to School
00
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
W
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
0
SRTS
180,000
0
180,000
P
RW
2021
0
SRTS
232,000
0
232,000
P
CN
2022
0
SRTS
2,125,000
0
2,125,000
Totals
0
2,537,000
0
2,537,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
180,000
0
0
0
RW
0
232,000
0
0
0
CN
0
0
2,125,000
0
0
Totals
0
412,000
2,125,000
0
0
Repoli Date: May 20, 2020 Page 2
MAML ►I MhingtanState Six Year Transportation Improvement Program
AP Della►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
D
3
m
n 0
c
D. Road Name or Number
m
t
o
0
3
0m
°o,
w
M
S.
m 3
c
E. Begin &End Termini
a
Z
-<
.<
y d
F. Project Description G. Structure ID
co
a
P
m
y
s
m
a
00
WA-05405
06/10/19
06/17/19.
1961
06
No
Americans with Disabilities Act (ADA) Improvements
00
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
r�'l
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2020
0
0
1,050,000
1,050,000
Totals
0
0
1,050,000
1,050,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
50,000
200,000
200,000
200,000
400,000
Totals
50,000
200,000
200,000
200,000
400,000
Report Date: May 20, 2020
N
Cn
�/
Page 3
N
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwa:of Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
D
3
m
w
n 0
c
D. Road Name or Number
m
o
0
3
0
M
m 3
c
E. Begin &End Termini
z
a
Z
-<
°o,
S.
y d
F. Project Description G. Structure ID
(o
a
P
m
N
s
m
a
16
WA-07746
06/10/19
06/17/19.
1961
03
C G O P S
No
TW
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
r�'l
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
0
134,000
134,000
P
RW
2022
0
0
10,000
10,000
P
CN
2023
0
0
1,570,000
1,570,000
Totals
0
0
1,714,000
1,714,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
134,000
0
0
0
0
RW
10,000
0
0
0
0
CN
0
1,570,000
0
0
0
Totals
144,000
1,570,000
0
0
0
Repoli Date: May 20, 2020 Page 4
MAMIL ► MhingtanState Six Year Transportation Improvement Program
AP Della►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
C. Project Title
m
'o.
m
m
3
m
A
M
,any
m c
c
3
D. Road Name or Number
m
t
0
o
3z
0
°o,
m
S.
'm_
E. Begin &End Termini
a
-<
.<
y
F. Project Description G. Structure ID
(o
a
P
m
y
s
m
a
14
WA-03731
06/10/19
06/17/19.
1961
06
No
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
r�'l
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2020
0
0
2,495,000
2,495,000
Totals
0
0
2,495,000
2,495,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
335,000
405,000
405,000
405,000
900,000
Totals
335,000
405,000
405,000
405,000
900,000
Repoli Date: May 20, 2020
N
4
�/
Page 5
MAML ►I MhingtanState Six Year Transportation Improvement Program
AP Della►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
D
3
m
n 0
c
D. Road Name or Number
m
t
o
0
3
0
°o,
m
w
M
S.
m 3
c
E. Begin &End Termini
a
Z
-<
.<
y d
F. Project Description G. Structure ID
(o
a
P
m
N
s
m
a
16
WA-03733
06/10/19
06/17/19
W
1961
06
C G O P S
No
TW
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
r�'l
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2020
0
0
8,400,000
8,400,000
Totals
0
0
8,400,000
8,400,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
1,400,000
1,400,000
1,400,000
1,400,000
2,800,000
Totals
1,400,000
1,400,000
1,400,000
1,400,000
2,800,000
�/
Report Date: May 20, 2020 Page 6
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Della►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
B
Z
C. Project Title
=
D
3
°—
n
c
D. Road Name or Number
m
t
o
0
3
0
°o,
w
S.
m 3
c
E. Begin &End Termini
aO
Z
-<
.<
y d
F. Project Description G. Structure ID
(o
a
P
y
s
m1
a
00
WA05409
06/10/19
6/17/19
V,
1961
08
EIS
No
BNSF Regional Center Access
00
New Facility
to
Construct a new access to the BNSF Regional Distribution Center, relocating the
900+daily truck trips from residential streets in Allentown.
r�'l
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2023
0
0
100,000
100,000
Totals
0
0
100,000
100,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
100,000
0
Totals
0
0
0
100,000
0
Repoli Date: May 20, 2020
N
�/
Page 7
W
O
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
D
3
m
n 0
c
D. Road Name or Number
m
o
0
3
0m
w
M
m 3
c
E. Begin &End Termini
t
a
Z
-<
°o,
.<
S.
y d
F. Project Description G. Structure ID
(o
a
P
m
y
s
m
a
00
WA-11115
06/10/19
06/17/19.
1961
28
0.140
DCE
No
Green River Trail
00
Green River Trail
Christensen Road to Green River
Replace the existing 8-foot wide Green River Trail with 12-foot wide concrete paved
trail with 2-foot gravel shoulders, including illumination, CCTV, wayfinding, and
pedestrian plaza.
W
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2022
STP(E)
896,000
0
140,000
1,036,000
Totals
896,000
0
140,000
1,036,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
74,000
62,000
0
0
Totals
0
74,000
962,000
0
0
,/
Repoli Date: May 20, 2020 Page 8
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
-
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
B
Z
C. Project Title
=
D
3
°—
n
c
D. Road Name or Number
m
o
0
3
0
w
m 3
c
E. Begin &End Termini
t
aO
Z
-<
°o,
.<
S.
y d
F. Project Description G. Structure ID
(o
a
p
y
s
m
1 a
17
WA-11110
06/10/19
06/17/19.
1961
04
0.350
DCE
No
Macadam Rd S Complete Streets Project
00
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
W
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
Ped/Bike Program
397,000
0
397,000
P
RW
2022
0
Ped/Bike Program
100,000
0
100,000
P
CN
2023
0
Ped/Bike Program
2,273,000
460,000
2,733,000
Totals
0
2,770,000
460,000
3,230,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
397,000
0
0
RW
0
0
100,000
0
0
CN
0
0
0
2,733,000
0
Totals
0
0
497,000
2,733,000
0
Report Date: May 20, 2020
W
Page 9
W
N
MAMIL ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwa:of Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
C. Project Title
m
'o.
m
m
3
A
M
,any
c
D. Road Name or Number
m
0
o
0
r,
m
m c
3
E. Begin &End Termini
t
a
3z
-<
°o,
.<
S.
y 'm_
F. Project Description G. Structure ID
(o
CLP
m
N
ma
14
WA-09873
06/10/19
06/17/19
W
1961
04
C G P S T
0.100
DCE
Yes
W
S 140th St Intersection Improvements
S 140th Street
Tukwila International Blvd to
Design and construct a new traffic signal at the S 140th Street/Tukwila International
Blvd intersection ,eN,
V, %
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
0
Ped/Bike Program
67,000
8,000
75,000
P
RW
2021
0
Ped/Bike Program
40,000
10,000
50,000
P
CN
2022
0
Ped/Bike Program
568,000
57,000
625,000
Totals
0
675,000
75,000
750,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
75,000
0
0
0
RW
0
50,000
0
0
0
CN
0
0
625,000
0
0
Totals
0
125,000
625,000
0
0
Report Date: May 20, 2020 Page 10
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
0
m
Z
C. Project Title
=
D
3
m
n 0
c
D. Road Name or Number
m
o
0
3
0
m
w
M
m 3
c
E. Begin &End Termini
t
a
Z
-<
°o,
.<
S.
y d
F. Project Description G. Structure ID
(o
a
P
m
y
s
m
a
17
WA03782
06/10/19
06/17/19
qV
1961
28
0.250
No
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1-5 between 51 st Ave S and 53rd Ave S
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
SRTS
443,000
0
0
443,000
Totals
443,000
0
0
443,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
216,000
227,000
0
Totals
0
0
216,000
227,000
0
Report Date: May 20, 2020
W
W
K*1
Page 11
W
MAMIL ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
'<
�
a
-
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
0
B
�o
C. Project Title
m
'o
m
°—
3
A
c
D. Road Name or Number
m
0
o
cf
m
m c
3
E. Begin & End Termini
t
a°
z
°o
--
S.
y 'm_
F. Project Description G. Structure ID
(o
a
P
y
s
m
a
19
WA-11112
06/10/19
06/17/19.
1961
05
0.300
No
S 152nd Street Safe Routes to School
00
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Design and construct curb, gutter and sidewalks on both sides including widening
pavement width by 3 feet to construct on -street parking lane on north side of street.
r�'l
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
SRTS
243,000
0
243,000
P
CN
2023
0
SRTS
2,584,000
0
2,584,000
Totals
0
2,827,000
0
2,8271000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
243,000
0
0
CN
0
0
0
2,584,000
0
Totals
0
0
243,000
2,584,000
0
Repoli Date: May 20, 2020 Page 12
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
�
c
o
A. PIN/Project No. B. STIP ID
3
0
<<
3
_
o
m
Z
C. Project Title
=
0.
3
1e
°—
n
c
3
D. Road Name or Number
o0
0
0
3
0
S.
m o
d
E. Begin & End Termini
s
1D
Z
$
--
'0
y
F. Project Description G. Structure ID
(o
AL
P
m
y
s
a
03
/1380(004) TUK-61
06
0.050
CE
No
S Bar/Airport Way
OOOF
S Boeing Access Road over Airport Way S
Airport Way S to Airport Way S
Install seismic protection on the structure.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2020
STP(BR)
2,613,855
0
0
2,613,855
Totals
2,613,855
0
0
2,613,855
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
2,613,855
0
PP0
0
0
Totals
2,613,855
0
0
0
0
Repoli Date: May 20, 2020
W
E40
Page 13
W
MAML ►himhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
c
c1
m o
y d
o
Z
c
3
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
=
m
t
co
D
o
a
CLP
3
3
a
3
m
M
0
3
Z
3
a
<<
3
-
m
_
,�
0
°o
y
o
°—
s
m
'<
m
m
E
a
16
/ 1276(007) TUK-59
06/10/19
06/17/19
1961
01
0.300
DCE
Yes
Strander Blvd./SW 27th St Extension
00
Strander Blvd./SW 27th St Extension
West Valley Highway to Naches Ave
This project is Phase 3 of a multi -phase improvement that will connect Strander
r
Blvd./SW 27th St between West Valley Hwy in Tukwila and Oakesdale Ave in
Renton. This project will complete the design, right-of-way and construction phases
for the roadway segment between West Valley Hwy and Naches Ave. Project
components include a railroad bridge for the Union Pacific RR to provide grade
separation, a new 4/5 lane roadway segment east of West Valley Hwy, roadway
widening of two lanes for a portion of the project segment, a separated joint -use trail,
a new trail bridge for the Interurban Trail (including new trail connections to Strander
Blvd.), a new flyover bridge connection to the Tukwila Station, a new traffic signal
serving the Tukwila Station, and storm drainage facilities. Current funding will
complete the preliminary engineering and right of way phases. Construction will be
funded as part of a future phase.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2020
STP
1,730,000
0
270,000
2,000,000
S
RW
2020
STP(UL)
1,487,000
0
233,000
1,720,000
S
CN
2021
FMSIB
5,000,000
0
0
5,000,000
S
CN
2021
Discretionary
5,000,000
0
0
5,000,000
P
CN
2021
STP
4,760,000
TIB
112,000,0001
01
16,760,000
P
CN
2021
TIGER
25,000,000
WSDOT
24,518,000
0
49,518,000
Totals
42,977,000
136,518,000
503,000
79,998,000
Repoli Date: May 20, 2020 Page 14
MAML ►emhingtanState Six Year Transportation Improvement Program
AP Depairtnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
2,000,000
0
0
0
0
R W
1,720,000
0
0
0
0
CN
0
38,389,000
37,889,000
0
0
Totals
3,720,000
38,389,000
37,889,000
0
ff 0
Report Date: May 20, 2020
W
Page 15
MAMIL ►emhingtanState Six Year Transportation Improvement Program
AP Delsa►tnwakof Transportation From 2020 to 2025
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y nside N Outside
m
3
a
'<
-
oM
A. PIN/Project No. B. STIP ID
3
0
<<
3
c
_
o
'
B
z
�o
C. Project Title
m
'o
m
m
3
A
c
D. Road Name or Number
m
o-
o
0
m
m e
'm_
3
E. Begin & End Termini
t
z
-
°o
E
y
F. Project Description G. Structure ID
(o
c
p
m
y
s
m
a
14
TUK-60
06/10/19
06/17/19
1961
28
0.170
DCE
No
West Valley Highway/Longacres Way Shared Use Pathways
00
SR 181 & Longacres Way
W end of planned Green River Bridge to Longacres Way
Improvements will be completed on SR 181 from the west end of the planned Green
r
River non -motorized Bridge to Longacres Way, including a 12-14 ft. separated
shared use path with a 5 ft. landscaped buffer strip on the west side of the highway.
Design -only will be completed for future improvements on Longacres Way between
SR 181 to the Tukwila Sound Transit Link Station.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2020
0
TIB
50,000
50,000
100,000
S
CN
2020
CMAQ
441,000
TIB
2,276,000
728,000
3,445,000
Totals
441,000
2,326,000
778,000
3,545,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
100,000
0
0
0
0
CN
3,445,000
0
0
0
0
Totals
3,545,000
0
0
0
0
Federal Funds State Funds Local Funds Total Funds
Grand Totals for Tukwila 47,370,855 47,653,000 17,315,000 112,338,855
Repoli Date: May 20, 2020 Page 16
Transportation & Infrastructure Committee Minutes
June 1, 2020
E. Resolution: 2021-2026 Transportation Improvement Program
Staff is seeking approval of a Resolution adopting the Six -Year Transportation
Improvement Program for 2021-2026. The annual update is required by the state and lists
projects deemed regionally significant or that have grant funding awarded or expected.
Committee Recommendation
Unanimous approval. Forward to June 22, 2020 Committee of the Whole for Public Hearing.
F. 2020 Overlay & Repair Options
Staff returned with a funding proposal for two projects in the annual Overlay Program on
54th Avenue South and South 158th St. Councilmembers previously expressed a desire to
retain some of the Overlay Project, so staff identified $312,500 in reallocation from other
CIP projects or existing fund balance in order to complete these two high priority projects.
Committee members and staff discussed decision points for other capital projects in the
context of COVID-19 related budget cuts. The City Council may make further adjustments
to reduce the proposed use of contingency.
Committee Recommendation
Unanimous approval to proceed with both projects. Forward to June 8, 2020 Committee of the
Whole.
II. MISCELLANEOUS
The meeting adjourned at 6:24 p.m.
CDJ
Committee Chair Approval
Minutes by LH
39