HomeMy WebLinkAboutTIC 2020-07-20 Item 2D - Bid Award - Riverton Creek Flap Gate Removal with AtWork Comercial EnterprisesCity of Tukwila Allan Ekberg, Mayor Public Works Department - Henry Hash, Director INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Committee FROM: Henry Hash, Public Works Director BY: Mike Perfetti, Habitat Project Manager CC: Mayor Ekberg DATE: July 17, 2020 SUBJECT: Surface Water Fund - Riverton Creek Flap Gate Removal Project Restoration Phase Project No. 99830103 Bid Award ISSUE Award a contract to AtWork Commercial Enterprises, LLC for construction of the Riverton Creek Flap Gate Removal Project Restoration Phase. BACKGROUND This project is the second and final contract to construct the Riverton Creek Flap Gate Removal Project. This phase will restore 1.48 acres of native riparian vegetation along Riverton Creek and 0.45 acres along the Duwamish River. DISCUSSION The Riverton Creek Flap Gate Removal Project Restoration Phase call for bids was sent on June 24, 2020 to organizations on the MRSC small works roster that provide restoration services. Three bids were received via e-mail by the due date of July 13, 2020. The bids were checked and tabulated. The apparent low bidder is At Work! with a bid of $106,090.60. The Engineer's Estimate was $112,290.75. FISCAL IMPACT (All amounts include sales tax) The Riverton Creek Flap Gate Removal Project construction, including both phases, was initially budgeted at $918,000. The low bid for the first phase, which was recently awarded, exceeded the budget and is utilizing all CIP funds dedicated for this project. Staff proposes to transfer budget from the 205 Levee Certification Project, which is not currently needed since the City has petitioned the King County Flood Control District to fund the rebuilding of the 205 Levee. Bid Results Estimate Budget Bid Amount 106,090.60 112,290.75 Contingency (10%) 10,609.06 Funding from 205 Levee Certification CIP 66,699.66 WRIA 9/CWM grant 50,000.00 Total $116,699.66 $112,290.75 $116,699.66 RECOMMENDATION Council is being asked to award the construction contract for the Riverton Creek Flap Gate Removal Project to AtWork Commercial Enterprises, LLC in the amount of $106,090.60 and consider this item on the Consent Agenda at the August 3, 2020 Regular Meeting. Attachments: CIP Page 93 CIP Page 94 Bid Tabulation https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/Agenda Items/TIC 07-20-2020/4. Riverton Creek Flapgate Removal PH 2 Bid Award/Info Memo Bid Award —Riverton Creek Restoration_20200720.docx 33 CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2019 to 2024 PROJECT: Riverton Creek Flap Gate Removal Project No. 99830103 Remove two culverts and flap gates at Duwamish River; install pipe arch, create open channel DESCRIPTION: confluence, install trail bridge over new channel, restore/revegetate 200 feet of creek channel and 450 ft. of pond shoreline. JUSTIFICATION: Increase available salmonid rearing habitat and increase flood refuge in lower Duwamish River. Improve fish access to Riverton Creek and enhance salmon rearing and resting area. STATUS: Design underway in 2018. Construction grant of $846k from WA State RCO. MAINT. IMPACT: Expected to increase maintenance. COMMENT: Project used as mitigation for East Marginal Way Pipe Replacement Project and HPA Control #133763-1 requires work to be completed by June 11, 2019, which will need to be extended. FINANCIAL Through Estimated (in $000'sl 2017 2018 2019 2020 2021 2022 2023 2024 BEYOND TOTAL EXPENSES Design 204 100 40 344 Land (R/W) 0 Monitoring 15 15 15 15 15 15 90 Const. Mgmt. 184 184 Construction 918 918 TOTAL EXPENSES 204 1 100 1 1,142 1 15 15 1 15 15 15 15 1,536 FUND SOURCES Awarded Grant 72 847 919 Proposed Grant 0 Mitigation Actual 0 Mitigation Expected 0 Utility Revenue 132 100 295 15 15 15 15 15 15 617 TOTAL SOURCES 204 100 1,142 15 15 15 15 15 15 1,536 y Project Locat►on 5 N r - w+i: St s •y S 1 8t 9 w C� 611 t yc � w s 1 s N L S1LEIF A s $ 128 ' '0 S 3� St � ■ 2019 - 2024 Capital Improvement Program 93 34 CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2019 to 2024 PROJECT: Tukwila 205 Levee Certification Project No. 91341203 DESCRIPTION: Obtain levee certification for the Tukwila 205 Levee. The US Army Corps of Engineers no longer provides levee certification services to federally authorized JUSTIFICATION: levees. The existing certification expired in August of 2013. Certification is required for the Federal Emergency Management Agency to accreditate the levee system as providing a 100-year level of flood protection. STATUS: Phase I was a overview of entire levee system and Phase II includes identification of levee deficiencies. MAINT. IMPACT: Certification process is expected to lead to additional levee repair projects that are required to meet the certification criteria. Certification is valid for a 10-year period. Costs listed in 2019 through 2022 are estimates for potential repairs that would be grant dependent. King COMMENT: County Flood Control District's Opportunity Grant Program currently has $63k per year. The Army Corps of Engineers is currently designing a levee repair project near Mitchell Moving, GACO, and Segale Properties with construction in 2019. Overall costs for Corps/Flood District project is $55 million, with no City funding. FINANCIAL Through Estimated (in $000's) 2017 2018 2019 2020 2021 2022 2023 2024 BEYOND TOTAL EXPENSES Certification Phase 1 350 350 Certification Phase 11 93 220 250 563 Design 275 275 Const. Mgmt. 30 115 600 745 Construction 200 750 4,000 4,950 TOTAL EXPENSES 443 220 525 230 865 4,600 0 0 0 6,883 FUND SOURCES KC Flood Control 113 63 63 63 63 63 63 63 63 617 Proposed Grants 150 780 4,500 5,430 Mitigation Actual 0 Mitigation Expected 0 Utility Revenue 330 157 462 17 22 37 (63) (63) (63) 836 TOTAL SOURCES 443 220 525 230 1 865 1 4,600 1 01 01 01 6,883 Project Location: Entire System ' s 2019 - 2024 Capital Improvement Program 94 35 Riverton Creek Flapgate Removal Project - Phase 2: Restoration Certified Bid Tab ITEM NO. ITEM UNITS QUANTITY 1 Unexpected Site Changes FA 1 2 Site Preparation LS 1 3 Wattles LF 1,000 4 Bark and Wood Chip Mulch CY 105 5 PSIPE - Acer macrophyllum, BR EA 10 6 PSIPE - Alnus rubra, BR EA 30 7 PSIPE - Arbutus menzesii, 10" tube EA 10 8 PSIPE - Betula papyrifera, BR EA 125 9 PSIPE - Cornus nuttallii, #1 EA 10 10 PSIPE - Cornus sericia, BR EA 231 11 PSIPE - Corylus cornuta, BR EA 125 12 PSIPE - Fraxinus Iatifolia, BR EA 47 13 PSIPE - Holodiscus discolor, BR EA 416 14 PSIPE - Lonicera involucrata, BR EA 131 15 PSIPE - Malus fusca, BR EA 7 16 PSIPE - Physocarpus capitatus, BR EA 131 17 PSIPE - Picea sitchensis, #1 EA 47 18 PSIPE - Populus basamifera, BR EA 30 19 PSIPE - Populus tremuloides, BR EA 7 20 PSIPE - Prunus emarginata, BR EA 7 21 PSIPE - Pseudotsuga menzesii, #1 EA 145 22 PSIPE - Ribies sanguineum, BR EA 416 23 PSIPE - Rosa nutkana, BR EA 456 24 PSIPE - Rosa pisocarpa, BR EA 131 25 PSIPE - Rubus parvifolium, BR EA 416 26 PSIPE - Rubus spectabilis, BR EA 131 27 PSIPE - Salix hookeriana, LS EA 270 28 PSIPE - Salix Iucida (lasiandra), BR EA 47 29 PSIPE - Salix scouleriana, LS EA 265 30 PSIPE - Salix sitchensis, LS EA 265 31 PSIPE - Sambucus racemosa, BR EA 547 32 PSIPE - Spiraea douglasii, BR EA 40 33 PSIPE - Symphoricarpos alba, BR EA 150 34 PSIPE - Thuja plicata, #1 EA 147 35 PSIPE - Tsiga heterophylla, #1 EA 22 Subtotal: Sales Tax Total Construction Cost: Errors in Contractor Bid Proposals: 1 Amount on bid amount shown as $6,972.16 Engineer's Estimate Atwork Applied Ecology Daramola UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT 10,000.00 15,000.00 10,000.00 10,000.00 10,000.00 17,500.00 10,000.00 10,000.00 36,000.00 10,000.00 10,000.00 50,000.00 15,000.00 17,500.00 2.25 36,000.00 50,000.00 3.50 3,500.00 2,250.00 5.88 5,880.00 6.00 6,000.00 45.00 4,725.00 67.00 7,035.00 69.05 7,250.25 60.00 6,300.00 14.00 140.00 13.00 130.00 16.76 167.60 20.00 200.00 14.00 420.00 13.00 390.00 16.76 502.80 20.00 600.00 16.00 160.00 18.00 180.00 22.69 226.90 20.00 200.00 14.00 1,750.00 13.00 1,625.00 16.76 2,095.00 20.00 2,500.00 18.50 185.00 18.00 180.00 22.69 226.90 20.00 200.00 14.00 3,234.00 13.00 3,003.00 16.76 3,871.56 20.00 4,620.00 14.00 1,750.00 13.00 1,625.00 16.76 2,095.00 20.00 2,500.00 14.00 658.00 13.00 611.00 16.76 787.72 20.00 940.00 14.00 5,824.00 13.00 5,408.00 16.76 6,972.16 20.00 8,320.00 14.00 1,834.00 13.00 1,703.00 16.76 2,195.56 20.00 2,620.00 14.00 98.00 13.00 91.00 16.76 117.32 20.00 140.00 14.00 1,834.00 13.00 1,703.00 16.76 2,195.56 20.00 2,620.00 18.50 869.50 18.00 846.00 22.69 1,066.43 20.00 940.00 14.00 420.00 13.00 390.00 16.76 502.80 20.00 600.00 14.00 98.00 13.00 91.00 16.76 117.32 20.00 140.00 14.00 98.00 13.00 91.00 16.76 117.32 20.00 140.00 18.50 2,682.50 18.00 2,610.00 22.69 3,290.05 20.00 2,900.00 14.00 5,824.00 13.00 5,408.00 16.76 6,972.16 1 20.00 8,320.00 14.00 6,384.00 13.00 5,928.00 16.76 7,642.56 1 20.00 9,120.00 14.00 1,834.00 13.00 1,703.00 16.76 2,195.56 20.00 2,620.00 14.00 5,824.00 13.00 5,408.00 16.76 6,972.16 20.00 8,320.00 14.00 1,834.00 13.00 1,703.00 16.76 2,195.56 20.00 2,620.00 13.75 3,712.50 7.00 1,890.00 16.50 4,455.00 20.00 5,400.00 14.00 658.00 13.00 611.00 16.76 787.72 20.00 940.00 13.75 3,643.75 7.00 1,855.00 16.50 4,372.50 20.00 5,300.00 13.75 3,643.75 7.00 1,855.00 16.50 4,372.50 20.00 5,300.00 14.00 7,658.00 13.00 7,111.00 16.76 9,167.72 20.00 10,940.00 14.00 560.00 13.00 520.00 16.76 670.40 20.00 800.00 14.00 2,100.00 13.00 1,950.00 16.76 2,514.00 20.00 3,000.00 18.50 2,719.50 18.001 2,646.00 22.691 3,335.43 20.00 2,940.00 18.50 407.00 18.001 396.00 22.691 499.18 20.00 440.00 102, 082.50 10, 208.25 112,290.75 96,446.00 9,644.60 106,090.60 141,830.70 14,183.07 156,013.77 168, 540.00 16, 854.00 21 185,394.00 Corrected bid m Riverton Creek Flapgate Removal Project - Phase 2: Restoration Certified Bid Tab Engineer's Estimate Atwork Applied Ecology Daramola ITEM NO, ITEM UNITS QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT 2 Total bid proposal was $155,275.95 Certified by Date 5 Mike Perfetti, Habitat Project Manager 7/15/2020 37