HomeMy WebLinkAboutReg 2020-08-03 Item 8C - Reports - City Administrator / Public Safety Plan Monthly Construction and Budget ReportCity of Tukwila Allan Ekberg, Mayor Mayor's Office - David Cline, City Administrator The City of opportunity, the community of choice TO: Mayor Ekberg Councilmembers FROM: David Cline, City Administrator DATE: J u ly 29, 2020 SUBJECT: City Administrator's Report The City Administrator Report is meant to provide the Council, staff, and community an update on the activities of the City and on issues that concern Tukwila. Please let me know if you have any questions or need additional information about any of the following items. 1. Intergovernmental Update Meetings with State Legislative Representatives: Mayor Ekberg, City Administrator David Cline , Deputy City Administrator Rachel Bianchi and Lobbyist David Foster are meeting with State Legislative representatives to discuss the City's response to the coronavirus and associated budget reductions, as well as the 42nd Ave. bridge and the upcoming legislative session. Meetings with Representatives Bergquist and Hudgins took place on July 15 and a meeting with Senator Hasegawa was held on July 22. Additional meetings with other state representatives are scheduled for early August. Prioritizing and Budgeting for Racial Equity: Mayor Ekberg and several City staff members participated in a webinar on Prioritizing and Budgeting for Racial Equity presented by Governing for Racial Equity and Inclusion on July 17. Urban Growth Committee Technical Committee: Community Development staff attended the monthly meeting of the Urban Growth Committee Technical Committee on July 17 where an overview of the King County Growth Targets Methodology was provided. Growth targets are a policy statement about the amount of housing and employment growth a city is planning for within a 20-year comprehensive planning period. Targets are under development for the planning period 2019-2044 in support of the 2024 update of comprehensive plans. Coronavirus Coordination Briefing with Governor Inslee: On July 20 Mayor Ekberg and City Administrator David Cline participated in a Coronavirus Briefing with Governor Inslee, Secretary of Health Wiesman, and State Health Officer/Chief Science Officer Lofy about the COVID-19 pandemic response and how local governments can work together with the state for continued public health and safety. South King County Mayors Meeting: Mayor Ekberg participated in a South King County Mayors meeting on July 21. Tukwila City Hail • 6200 Southcenter Boulevard • Tukwila, WA 98188 • 206-433-1800 • Website: Tukwila WA.gov 35 City Administrator's Report July 29, 2020 Page 2 Meeting with Tukwila School District Superintendent: Mayor Ekberg and City Administrator David Cline had a virtual meeting with Tukwila School District Superintendent Dr. Flip Herndon on July 22. King County Metro Regional Transit Committee: Community Development staff attended the monthly meeting of the King County Metro Regional Transit Committee (RTC) and associated Sound Cities Association caucus prior to the meeting. Metro provided an overview of a proposed update to the Strategic Plan for Public Transportation. The intent of the update is to revise policies in Metro's Strategic Plan to (1) help implement the Metro Connects Long Range Transportation Plan, and (2) to incorporate recommendations of the Mobility Framework to help address equity in the context of changing mobility options and impacts from climate change. As part of the update to the Strategic Plan, Metro plans to streamline performance measures and develop a public -facing dashboard to show the agency's progress towards meeting performance measures. The RTC will revisit recommended changes to the Strategic Plan in January 2021, with transmittal to the King County Council planned for July 2021. South Kin County ounty Housing and Homeless Partnership: Community Development staff attended a South King County Housing and Homeless Partnership (SKHHP) staff working group meeting and Executive Board meeting. The SKHHP Interlocal Agreement calls for the creation of a SKHHP Advisory Board to provide advice and recommendations to the Executive Board. To help foster community buy -in and will help to ensure that SKHHP Executive Board decisions are equitable and grounded by community interests each jurisdiction was asked to provide 3-4 names of community members for initial outreach. II. Community Events • Parks & Recreation Regional Coordination: Parks & Recreation Director Rick Still has been attending weekly meetings with Parks and Recreation directors across the state to keep current on activities and program that can be offered during Safe Start phases. • Community Center Availability by Phone: Beginning July 27 staff will be available by phone at the Community Center to answer inquiries via phone on Mondays & Tuesdays, from 9:00am to 1:00pm. • Residential Collection Event: The annual Residential Collection Event of difficult to recycle items typically held in April at Foster HS has been rescheduled to August 22 at the Tukwila Community Center. Notices will be mailed to city residents and posted on City's website. III. Staff Updates Public Safety • Valley Independent Investigation Team Non -Law Enforcement Interviews: Chief Linton, Deputy Chief Drever and Council President De'Sean Quinn continue to interview volunteer applicants interested in serving as the Non -Law Enforcement representative to the Valley Independent Investigation Team. Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov 36 City Administrator's Report July 29, 2020 Page 3 • Police Regional Coordination: Chief Linton continues to meet weekly with Valley Chiefs in the COVID-19 coordination efforts. • Fire Regional Coordination: Chief Wittwer continues to coordinate with regional partners regarding the COVID-19 issues affecting the region. • Regional Law Safety and Justice Committee: Chief Linton attended the Regional Law Safety and Justice Committee meeting on July 23. Project Updates • Boeing Access Rd over Airport Way Bridge: Estimated Completion: December 2020 The construction contract has been signed by the Mayor and the Notice to Proceed was issued to Razz Construction. The pre -construction conference will be scheduled by early August 2020, and then construction on Boeing Access Road can commence. The estimated timeframe for construction is six weeks. • 42nd Ave S Bridge Design: Public Works staff are working with the selected consultant to receive the scope of work and cost for the 30% design and is planned to be brought to the City Council Transportation and Infrastructure Committee in late August.. • 42nd Ave S Bridge In-depth Inspection: The bridge was closed to vehicle and pedestrian traffic July 22 through July 24 from 8 AM to 6 PM. During the closure, the inspection team used specialized equipment to measure the internal composition and check for cracks of the critical steel members. A briefing on this is planned for a Transportation and Infrastructure Committee. • Riverton Creek Flapgate Removal Project: Construction began on July 13. To date, trees have been cleared, many of which will be reused in the stream as habitat features; access pads have been graded for large equipment to construct the soldier pile wall and install the roadway tie -back anchors; 12 steel pipe piles have been installed for the trail bridge; and the segment of existing retaining wall along the trail has been demolished as required. Boards, Commissions and Committees Arts Commission: The next meeting is scheduled for August 12 as a joint meeting with Park Commission for a presentation on the Riverton Creek Restoration Project by Artist in Residence Sarah Kavage who has been working on implementing "restoration art" as part of the project managed by Public Works. 3 Resident positions terms expire December 31, 2020. No vacancies. • Civil Service Commission: The next meeting is scheduled for August 10, 2020. No terms set to expire in 2020. VACANT:1 Community Representative. One application received. COPCAB: The next meeting is scheduled for August 13, 2020. No terms set to expire in 2020. VACANT: Student Representative. Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov 37 City Administrator's Report July 29, 2020 Page 4 • Equity & Social Justice Commission: The next meeting is scheduled for August 6, 2020. 1 Education position term expires December 31, 2020. 1 City Employee position term expires December 31, 2020. 2 Community Representative positions terms expire December 31, 2020. VACANT: 1 Education Representative and Student Representative. • Human Services Advisory Board: The next meeting is scheduled for July 29, 2020. 1 Resident position term expires December 31, 2020. 1 Business Community Representative position term expires December 31, 2020. No vacancies. • Library Advisory Board: The next scheduled meeting is yet to be determined. 1 Resident position terms expire December 31, 2020. VACANT: Student Representative. • Lodging Tax Advisory Committee: The next meeting is scheduled for August 14, 2020. All positions are 1-year terms. VACANT: 1 Business Collecting Tax Representative and 1 Funded by Tax Representative. • Park Commission: The next meeting will be a joint meeting with the Arts Commission on August 12, 2020. 1 Community position terms expire December 31, 2020. VACANT:1 Community Representative and Student Representative. One application received for Community Representative position. • Planning Commission: The next meeting is scheduled for August 27, 2020. No terms set to expire in 2020. No vacancies. Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov MR TUKWILA PUBLIC SAFETY PROJECTS Fire Station 51 SOJ Construction Management Monthly Report J u ly 2020 ReiDort Reviewed bv: Justine Kim Owner's Representative: Shiels Obletz Johnsen (SOJ) Architect: Weinstein A+ U GCCM: Lydig Construction Progress: • Casework installation ongoing. • Landscaping install underway. • Water and irrigation meters installed. • Rear Apron pavi n g co m p lete. • Final Inspections underway. • Interior and exterior painttouch-up underway. • Air Barrier Test passed. • Architect Punch Walks underway. Upcoming Activities: • Day Wireless DAS installation to complete late July/early August. • Final Inspections to complete in August. • Achieve Substantial Completion/Certificate of Occupancy. Budget Status: • See overall TPSP budget summary updated monthly and included in monthly report package. Change Order Status: • Change Order#10 issued in July- $55,935 • Change Order #11 (COVID) issued in July- $103,680 • Total Change Orders to date - $689,016 Schedule Status: • See TPSP master project schedule updated monthly and included in monthly report package. Critical Issues: • The COVID-19 pandemic and associated health/safety requirements has impacted jobsite labor productivity and materials procurement. The project team is working closely with the GC/CM to mitigate potential cost and schedule impacts. Tukwila Public Safety Plan - Fire Station 51- Monthly Report 1 39 Trees in place at east facade with irrigation Trees installed at entry planters log Tukwila Public Safety Plan - Fire Station 51- Monthly Report 2 4� Shop casework and pegboard shelving 0 Tukwila Public Safety Plan - Fire Station 51- Monthly Report 41 42 TUKWILA PUBLIC SAFETY PROJECTS Fire Station 52 SOJ Construction Management Monthly Report J u ly 2020 ReiDort Reviewed bv: Justine Kim Owner's Representative: Shiels Obletz Johnsen (SOJ) Architect: Weinstein A+ U GCCM: Lydig Construction Progress: • Second modularwetland installed. • Irrigation installation underway. • Aluminum storefront arriving onsite. • Tile installation started. • Landscaping soil preparation ongoing. • Ceiling grid being installed. • PSE Gas conduit being installed. Upcoming Activities: • Metal panel installation to start in August. • Driveway grading and paving to start late August. • Cascadia windows arriving onsite in August. Budget Status: • See overall TPSP budget summary updated monthly and included in monthly report package. Change Order Status: • Change Order#10 issued in July- $32,764 • Total Change Orders to date - $523,296 Schedule Status: • See TPSP master project schedule updated monthly and included in monthly report package. Critical Issues: • The COVID-19 pandemic and associated health/safety requirements has impacted jobsite labor productivity and materials procurement. The project team is working closely with the GC/CM to mitigate potential cost and schedule impacts. Tukwila Public Safety Plan - Fire Station 52 - Monthly Report 1 43 VI Overhang at east Apparatus Bay Tukwila Public Safety Plan - Fire Station 52 - Monthly Report --% _ _ Av. Tukwila Public Safety Plan - Fire Station 52 - Monthly Report 45 m TUKWILA PUBLIC SAFETY PROJECTS Justice Center SOJ Construction Management Monthly Report J u ly 2020 Report Prepared by: Ethan Bernau Report Reviewed bv: Justine Kim Owner's Representative: Shiels Obletz Johnsen (SOJ) Architect: DLR Group GCCM: BNBuilders Construction Progress: • Completed Seattle City Light vault adjustment on 1501n • Completed Comcast CATV connection to building. • Continued interior casework and finishes. • Continued fencing and gates, irrigation and landscaping. • Continued building systems training for City staff. • Started functional testing and commissioning of HVAC equipment and building systems. • Started Architect and Engineer punchlist inspections. Upcoming Activities: • Final inspections by Authorities Having Jurisdiction. • Demobilize construction trailers on North Parking Lot. • Certificate of Occupancy and Substantial Completion targeted for mid -August. • Seattle City Light cutover from overhead to underground power on Military. Budget Status: • See overall TPSP budget summary updated monthly and included in monthly report package. Change Order Status: • Change Orders #11 for $277,690 and #12 (COVID) for $116374 issued in June. • Total Change Orders issued to date = $2,276,486. Schedule Status: • See TPSP master project schedule updated monthly and included in monthly report package. Critical Issues: • COVID-19 health/safety requirements impactjobsite labor productivity and materials procurement. The project team is working closely with the GC/CM to mitigate cost and schedule impacts. Tukwila Public Safety Plan -Justice Center - Monthly Report 1 47 Main Entrance along TIB Duwamish Feature Wall in Lobby Tukwila Public Safety Plan -Justice Center - Monthly Report 2 HUB Break Room and Kitchen Vol PD Evidence, Area A Tukwila Public Safety Plan - Justice Center- Monthly Report i • City of Tukwila Lydig Construction, Inc Fire Station #51 GC Contract Value $ 9,943,234.95 Up da ted 6.2 6.2 0 Award Amount: $ 2,312,584.00 WMBE Participation Scopes of Work that you Intend to Award to WMBEs Sub/Supplier Name Certification Approximate Subcontract $ Amount City of Seattle Self- Certification OMWBE State Certification OMWBE Federal Certification SCS Roofing Axiom Division 7 SCS $ 217,945 Site Concrete Caliber Concrete Const WBE $ 394,500 Masonry Cascade Construction SCS $ 310,097 Fencing Secure -A -Site WBE $ 299,000 Steel Erection CHG Building Systems SCS $ 168,922 Overhead Doors Crawford Door Company SB, VOSB $ 102,261 Fire Protection Emerald Fire LLC WBE $ 49,750 Bituminous Waterproofing Inland Waterproofing WBE $ 10,850 Striping Stanley Patrick Striping SCS $ 4,834 Plumbing Adept Mechanical MBE MBE / DBE SCS $ 659,596 Concrete Sawing Salinas Sawing & Sealing MBE $ 1,347 Trucking SilverStreak Inc WBE T/M Site Services Construction Site Services MBE WBE T/M Office Supplies Keeney Office Supply WBE T/M Fire Protection Specialties RC Building Specialties MBE $ 880 Interior/Exterior Signage Shine On Signs and Graphics SCS $ 22,139 Painting KT Painting MBE $ 70,463 Total Amount Intended to be Performed by DBE to Date: $ 2,312,584 Percentage of Contract Amount: 23% Scopes where the sub/supplier is not yet determined or committed When do you anticipate making a selection? Do you anticipate using a SCS Is this a Spread the Work SCS Can only a Sole Source do the worke Approximate Subcontract $ Amount $ $ $ Total Amount Not Yet Committed to a Sub/Supplier: $ Page 2/3 51 52 Apprentice Utilization Plan - Updated 6.26.2020 List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours. Estimated information Prime Contractor and all Subcontractors Journey Labor Hours Apprentice Labor Hours Total LaborApprentice Hours for Project Percentage Number of Apprentices Adept Mechanical 1,245 0 1,245 0.00% 0 Axiom Division 7 1,483 0 1,483 0.00% 0 Cadman 73 0 73 0.00% 0 Caliber 646 258 903 28.52% 1 Cascade 1,449 198 1,646 12.00% 3 CHG 1,087 0 1,087 0.00% 0 Emerald Fire 313 154 467 32.98% 2 ESM Consulting Engineers 229 0 229 0.00% 0 Fagade Tech 1,386 117 1,502 7.77% 1 1 GK Knutson 2,784 1,162 3,946 29.45% 7 Inland Waterproofing 49 0 49 0.00% 0 K Fox Insulation 2 0 2 0.00% 0 KT Painting 546 0 546 0.00% 0 LaRusso Concrete 136 0 136 0.00% 0 Lydig Construction 5,492 215 5,707 3.77% 5 Mckinstry 3,900 2,320 6,220 37.29% 4 Miles Sand & Gravel 83 0 83 0.00% 0 Multiv,ire 19 0 19 0.00% 0 Northshore 1,283 764 2,047 37.32% 1 Ralph's Concrete Pumping 30 0 30 0.00% 0 SCllnfrastucture 4,623 73 4,696 1.55% 0 Secure A Site 25 0 25 0.00% 0 Surgent 452 0 452 0.00% 1 West Wind Reinforcing 70 40 110 36.36% 4 TOTALS: 27,402 5,299 32,701 16.21% 29 Apprenticeship Utilization Requirement: 15% Cal W Page 3/3 54 City of Tukwila Lydig Construction, Inc Fire Station #52. GC Contract Value $ 16,519,792.50 Updated6.23.2020 Award Amount: $ 4,498,795.28 WMBE Participation Scopes of Work that you Intend to Award to WMBEs Sub/Supplier Name Certification Approximate Subcontract $ Amount City of Seattle Self- Certification OMWBE State Certification OMWBE Federal Certification SCS Structural Steel Erection Corona Steel MBE $ 284,775 Damp & Waterproofing Inland Waterproofing WBE $ 32,534 Masonry R&D Masonry VOB $ 441,959 Fencing Secure -A -Site WBE $ 194,150 Roofing Axiom Division 7 SCS $ 277,950 Metal Siding Axiom SCS $ 342,371 Earthwork Pellco SCS $ 2,450,369 Structural Steel Supply B&B Fabricators WBE $ 474,688 ***Note: Not all contracts are bought out yet, and Mini-MACC does not include all scopes. Total Amount Intended to be Performed by DBE to Date: $ 4,498,795 Percentage of Contract Amount: 27% Scopes where the sub/supplier is not yet determined or committed When do you anticipate making a selection? you Do y anticipate using a SCS Is this a Spread the Work SCS Can only a Sole Source do thework? Approximate Subcontract $ Amount $ $ $ Total Amount Not Yet Committed to a Sub/Supplier: $ Page 2/3 55 56 Apprentice Utilization Plan - Updated 712412020 List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours. Estimated information Prime Contractor and all Subcontractors Journey Labor Hours Apprentice Labor Hours Total Labor Hours for Project Apprentice Percentage Number of Apprentices Axiom CC 35 10 44 21.59% 2 Axiom Div 7 1,188 0 1,188 0.00% 0 Brundage Bone 6 0 6 0.00% 0 Conco 48 0 48 0.00% 0 ESM Consulting Engineers 198 0 198 0.00% 0 Evergreen Concrete Cutting 138 26 163 15.64% 2 Grady Excavating 1,390 0 1,390 0.00% 0 General Storefronts 5 0 5 0.00% 1 Ground Up Road Construction 57 0 57 0.00% 0 Inland Waterproofing Services 99 0 99 0.00% 7 Innovative Vacuum Services 58 0 58 0.00% 0 Kulchin Foundation Drilling Co 483 0 483 0.00% 0 LaRusso 152 9 161 5.30% 5 Lydig Construction 5,341 3,344 8,685 38.50% 2 Miles Sand & Gravel 16 0 16 0.00% 0 Morse Steel Reinforcing 457 222 679 32.70% 8 Pellco 4,601 624 5,225 11.94% 3 Ralph's Concrete Pumping 165 0 165 0.00% 0 RL Clearing 9 0 9 0.00% 0 Stoneway Concrete 411 0 41 0.00% 1 0 Sky High Tree Removal 45 0 45 0.00% 0 Vanderlip & Co. 2,839 193 3,032 6.37% 6 TOTALS: 17,297 4,417 21,714 20.34% 34 Apprenticeship Utilization Requirement. 15% Cal 4 Page 3/3 w City of Tukwila BNB - Justice Center GC Contract Value $ 29,098,053.00 812012019 Award Amount:Fs 4,645,946 WMBE Participation Scopes of Work that you Intend to Award to WMBEs Sub/Supplier Name Certification Approximate Subcontract $ Amount City of y Seattle Self- Certification OMWBE State Certification OMWBE Federal Certification SCS Supplier of Hardware, Doors and Frames Contract Hardware Inc. SBE $ 310,362 Site Concrete Caliber Concrete WBE $ 520,550 Signage Sign Wizards SDBE/WSB E $ 36,236 Supplier SnapTex SBE/WBE/ MBE $ 33,875 Shelving Workpointe SBE $ 454,003 Plumbing Redline Mechanical X $ 809,002 Controls C&C Solutions VOSBE $ 235,700 Marble Supply Skyline Marble WBE $ 88,000 Rubber Base Install Zombie Base WSBE $ 4,758 Roofing Systems Axiom #1027 $ 583,020 Painting and Coatings Halili WBE $ 219,450 Fire Protection Columbia Fire #1599 $ 287,890 Iri ation and Landscaping RE Sides Landscaping #1054 $ 1,020,000 Temp Sanitation (NSS) Construction Site Services $ 22,000 Waterproofing Inland Waterproofing WBE I I $ 21,100 Outreach Coordinator Darling Nava Consulting M41=0026198 In Progress Participation: $ 4,645,946 Percentage of Award Amount: 16% Scopes where the sub/supplier is not yet determined or committed When do you anticipate making a selection? Do you anticipate using a SCS Is this a Spread the Work SCS Can only a Sole Source do the work? Approximate Subcontract $ Amount $ - Total Amount Not Yet Committed to a Sub/Supplier: $ - Page 2/3 59 Apprentice Utilization Plan - June 2020 List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours. Prime Contractor and all Subcontractors BNBuilders Apex Steel Ascendent, LLC Axiom Division 7 Caliber Concrete General Storefronts Gonsalves & Santucci DBA Conco Harris Rebar (Central Steel) Iliad, Inc Inland Waterproofing Johansen Mechanical Lakeside Industries Northshore Exteriors Northwest Partitions Performance Contracting Rhine Demolition Valley Electric Columbia Fire Johansen Mechanical (Redline Mach) NW Complete Contracting Northshore Exteriors (Pape) Northwest Partitions (InsulPro) Caliber Concrete (Evergreen Concrete) Caliber Concrete (Stoneway) CIVIL Security Lacey Glass NW Partitions (Sian Wizards) Iliad (Bravo Enviromental) Iliad (City Transfer) Valley Electric (Penhall) Valley Electric (Praetoria Power) Acoustical Design Barclay Dean Architectural Caliber Const (Miles Sand & Gravel) Commercial Fence Corp Floor Solutions Lakeside Industries (NW Traffic) Lakeside Industries (PacWest Grindi Valley Electric (EZ Interface) Apex Steel (Corona Stud & Deck) Apex Steel ( Magnum Crane) Insulpro (NW Partitions Johansen (Maple Valle,, Northshore Exteriors (V Vallev Electric (Stonew TOTALS: added this month This Month Journey Labor Hours This Month Apprentice Labor Hours Total Labor Hours for Project Total Apprentice Percentage Number of Apprentices 1,727 128 28,440 19.24% 1 2 0 0 9,985 11.26% 0 0 0 8,262 2.51 % 0 0 0 938 0.00% 0 0 0 3,013 19.14% 0 526 138 3,093 33.57% 2 16 0 2,616 8.53% 0 0 0 6,343 6.02% 0 381 80 20,261 1.17% 1 0 0 247 0.00% 0 0 0 11,004 29.51% 0 325 33 1,908 6.60% 1 102 93 9,213 39.24% 3 0 0 15,288 12.37% 0 0 0 164 4.89% 0 0 0 2,090 11.10% 0 1,103 877 16,184 40.23% 7 0 0 966 48.42% 0 0 0 3,024 16.60% 0 0 0 4,195 1.67% 0 0 0 22 0.00% 0 0 0 1,521 13.81% 0 0 0 22 0.00% 0 0 0 125 0.00% 0 0 0 1,748 19.22% 0 0 0 4 50.00% 0 0 0 30 0.00% 0 0 0 62 12.96% 0 0 0 4 0.00% 0 0 0 40 0.00% 0 0 0 10 50.00% 0 32 0 42 0.00% 0 148 0 934 11.03% 0 0 0 24 33.33% 0 0 0 3 0.00% 0 80 0 152 0.00% 0 0 0 1,164 28.73% 0 18 0 36 0.00% 0 0 0 15 0.00% 0 0 0 960 55.05% 0 11 16 27 58.49% 1 146 0 146 0.00% 0 16 0 16 0.00% 0 1,630 407 2,037 19.98% 8 821 0 821 0.00% 0 43 0 43 0.00% 0 36 01 1 36 0.00% 1 0 7,1621 1 1,7711 1 157,2721 1 17.74% 1 1 25 Apprenticeship Utilization Requirement: 10% Page 3/3 61 62 (1)City of Tukwila - Facilities Plan MONTHLY Budget Report TOTAL PROJECT (REVISED Budgets; D-20 Plan Adopted by Council) Life to Date Costs Original A/E Services (both Design & CA) $ 3,278,125 $ (3,125) $ 3,275,000 $ 3,210,300 $ 2,920,855 $ 289,445 $ 64,700 $ - Permits/Fees $ 700,000 $ 330,000 $ 1,030,000 $ 896,961 $ 896,961 $ - $ 133,039 $ - Construction (Pre -Con, Const & Tax) $ 38,738,678 $ 1,784,126 $ 40,522,804 $ 39,838,286 $ 36,450,833 $ 3,517,209 $ 0 $ - Construction Related Costs (met Bond) $ 2,112,639 $ 402,194 $ 2,514,833 $ 2,289,745 $ 1,014,366 $ 1,275,379 $ 225,088 $ - PM Services (met Other Professional Svcs) $ 1,815,875 $ 221,211 $ 2,037,086 $ 2,018,377 $ 1,650,118 $ 368,259 $ 18,709 $ - Contingency (incl Construction & Project) $ 6,507,731 $ (4,789,324) $ 1,718,407 $ - $ - $ - $ 2,268,407 $ - Contingency for Site Contamination (soils,hazmat) $ - $ 550,000 $ 550,000 $ 684,518 $ 554,762 $ - $ - $ Land Acquisition $ 14,133,295 $ (416,714) $ 13,716,581 $ 13,716,462 $ 13,692,508 $ 23,954 $ 119 $ - Contingency for Land Acquisition $ 1,250,000 $ 250,000 IS $ 1,500,000 $ 1,491,500 IS $ 1,491,500 $ $ 8,500 $ TOTAL I $ 68,536,343 (1,671,632) $ 66,864,711 64,146,150 IS 58,671,903 $ 5,474,246 $ 2,718,561 1 $ COUNCIL/ LifetoDateCusts Retuning Committed Renaming Budget A/E Services (both Design & CA) $ 1,070,000 $ 298,956 $ 1,368,956 $ 1,297,777 $ 1,246,526 $ 51,250 $ 71,179 $ - Land Acquisition $ - $ - $ - $ - $ - $ - $ - $ - Permits/Fees $ 234,000 $ 100,000 $ 334,000 $ 243,648 $ 227,861 $ 15,788 $ 90,352 $ - Construction (Pre -Con, Const & Tax) $ 9,396,000 $ 2,072,959 $ 11,468,958 $ 11,468,907 $ 10,621,642 $ 847,264 $ 52 $ - Construction Related Costs (met Bond) $ 931,000 $ (258,042) $ 672,958 $ 487,614 $ 313,136 $ 174,478 $ 185,344 $ - PM Services (incl Other Professional Svcs) $ 526,000 $ (133,000) $ 393,000 $ 365,550 $ 271,738 $ 93,812 $ 27,450 $ Contingency (incl Construction & Project) $ 1,116,000 $i (669,240) $ 446,760 $ $ $ $ 446,762 $ TOTAL $ 13,273,000 $ 1,411,633 $ 14,684,632 $ 13,863,495 $ 12,680,903 $ 1,182,592 $ 821,137 $ CO UNCIL REPOR FIRE STA I A/E Services (both Design & CA) S 1,415,000 $ 458,172 $ 1,873,172 $ 1,871,265 $ 1,671,879 $ 199,386 $ 1,907 $ Land Acquisition $ 16,000 $ 1,160 $ 17,160 $ 17,157 $ 17,157 $ - $ 3 $ - Permits/Fees $ 353,000 $ 50,000 $ 403,000 $ 360,079 $ 299,902 $ 60,177 $ 42,921 $ - Construction (Pre -Con, Const & Tax) $ 13,298,000 $ 5,047,271 $ 18,345,271 $ 18,344,870 $ 11,997,512 $ 6,347,358 $ 401 $ - Construction Related Costs (met Bond) $ 1,398,000 $ (132,660) $ 1,265,340 $ 829,978 $ 296,513 $ 533,465 $ 435,362 $ - PM Services (incl Other Professional Svcs) $ 787,000 $ (95,000) $ 692,000 $ 555,454 $ 409,582 $ 145,872 $ 136,546 $ - Contingency (incl Construction &Project) $ 1,343,000 $ (188,943) $i 1,114,057 $ $ $ $ 1,154,057 $ TOTAL $ 18,610,000 $ 5,140,000 $ 23,750,000 $ 21,978,803 $ 14,692,545 $ 7,286,258 $ 1,771,197 $ SUMMARY - I Original A/E Services (both Design & CA) $ 150,000 $ (15,505) $ 134,495 $ 134,495 $ 132,995 $ 1,500 $ (0) $ Land Acquisition $ 902,668 $ 31,206 $ 933,874 $ 933,875 $ 933,775 $ 100 $ (1) $ - Permits/Fees $ 20,000 $ (11,827) $ 8,173 $ 4,971 $ 4,971 $ - $ 3,202 $ - Construction (Pre -Con, Const & Tax) $ 230,000 $ (123,300) $ 106,700 $ 84,196 $ 84,196 $ - $ 22,504 $ - Construction Related Costs (met Bond) $ 50,000 $ (2,698) $ 47,302 $ 42,302 $ 29,145 $ 13,157 $ 5,000 $ - PM Services (incl Other Professional Svcs) $ 107,500 $ (835) $ 106,665 $ 106,665 $ 86,066 $ 20,599 $ - $ - Contingency (incl Construction & Project) $ 41,832 $ 122,959 $ 164:721 $ $ $ $ 164,791 $ TOTAL $ 1,502,00. $ $ 1,502,005 $ 1,306,505 $ 1,271,148 $ 35,357 $ 195,495 $i COUNCIL/' Original A/E Services (both Design & CA) $ 767,385 $ 15,000 $ 782,385 $ 335,382 $ 293,363 $ 42,019 $ 447,003 $ Land Acquisition $ 22,000,046 $ 3,374,913 $ 25,374,959 $ 25,373,239 $ 25,371,146 $ 2,093 $ 1,720 $ - Permits/Fees $ 110,000 $ (20,000) $ 90,000 $ 1,730 $ 1,730 $ - $ 88,270 $ - Construction (Pre -Con, Const & Tax) $ 4,950,000 $ (1,895,000) $ 3,055,000 $ 81,078 $ 81,078 $ - $ 2,973,922 $ - Construction Related Costs (met Bond) $ 529,036 $ (404,793) $ 124,243 $ 81,598 $ 66,558 $ 15,041 $ 42,645 $ - PM Services (met Other Professional Svcs) $ 668,426 $ (348,426) $ 320,000 $ 280,545 $ 177,282 $ 103,263 $ 39,455 $ - Contingency (incl Construction & Project) $ 975,107 $ (721,694) $ 253,413 $ $ $ $ 253,413 $ TOTAL $ 30,000,000 $ $ 30,000,000 $ 26,153,572 $ 25,991,156 $ 162,416 $ 3,846,428 1 $ e 2016 A/E PROCUREMENT PROGRAMMING DESIGN/PERMITTING BIDDING/CONSTRUCTION MOVE-IN/OCCUPANCY FIRE STATION 5 2 A/E PROCUREMENT PROGRAMMING DESIGN/PERMITTING BIDDING/CONSTRUCTION MOVE-IN/OCCUPANCY A/E PROCUREMENT PROGRAMMING DESIGN/PERMITTING BIDDING/CONSTRU;CTION MOVE-IN/OCCU'PANCY A/E PROCUREMENT MASTER SITS PLAN DESIGN PHASE 1 BIDDING/CONSTRUCTION PHASE 1 rn MOVE-IN/OCCUPANCY PHASE 1 2017 r � i 2019 2020 I 2021 PROJECT = A/E PROCUREMENT M PROGRAMMING M DESIGN/PERMITTING _ BIDDING/CONSTRUCTION MOVE-IN/OCCUPANCY