HomeMy WebLinkAboutCOW 2020-09-14 Item 4 - Report - Public Safety Plan Monthly Construction and Budget ReportTukwila Public Safety Plan – Fire Station 51 - Monthly Report
1
TUKWILA PUBLIC SAFETY PROJECTS
Fire Station 51
SOJ
Construction Management Monthly Report
August 2020
Report Reviewed by: Justine Kim
Owner’s Representative: Shiels Obletz Johnsen (SOJ)
Architect: Weinstein A + U
GCCM: Lydig
Construction Progress:
Casework installation complete.
Landscaping install complete.
DAS installation complete and inspected.
Mechanical, Plumbing, Low Voltage, Electrical, Fire Alarm, Fire Suppression, Public Works, Planning
Inspections signed off.
Fire Final pending.
Upcoming Activities:
Architect back-punch scheduled for September 1st.
Substantial Completion/Certificate of Occupancy scheduled September 1st.
FFE items to begin to arrive September 2nd.
Wetlands landscaping to be installed late October per permit requirements.
Budget Status:
See overall TPSP budget summary updated monthly and included in monthly report package.
Change Order Status:
Change Order #12 issued in August - $149,895
Total Change Orders to date - $838,911
Schedule Status:
See TPSP master project schedule updated monthly and included in monthly report package.
Critical Issues:
The COVID-19 pandemic and associated health/safety requirements has impacted jobsite labor
productivity and materials procurement. The project team is working closely with the GC/CM to
mitigate potential cost and schedule impacts.
193
Tukwila Public Safety Plan – Fire Station 51 - Monthly Report
2
View of Building from SW Corner
View of Building from NW Corner at Rear Apron
194
Tukwila Public Safety Plan – Fire Station 51 - Monthly Report
3
View of Building from Entry Walkway
195
196
Tukwila Public Safety Plan – Fire Station 52 - Monthly Report
1
TUKWILA PUBLIC SAFETY PROJECTS
Fire Station 52
SOJ
Construction Management Monthly Report
August 2020
Report Reviewed by: Justine Kim
Owner’s Representative: Shiels Obletz Johnsen (SOJ)
Architect: Weinstein A + U
GCCM: Lydig
Construction Progress:
Fiberglass windows arrived onsite.
Irrigation installation continues.
Most aluminum windows have been installed.
Wood ceiling grid being installed.
Floor polishing ongoing.
Landscaping ongoing.
Upcoming Activities:
Driveway placement on 65th mid-September.
Overhead doors to be installed mid-September.
Casework delivery expected mid-September.
Budget Status:
See overall TPSP budget summary updated monthly and included in monthly report package.
Change Order Status:
Change Order #11 issued in August - $123,921
Change Order #12 (COVID) issued in August - $63,918
Total Change Orders to date - $711,134
Schedule Status:
See TPSP master project schedule updated monthly and included in monthly report package.
Critical Issues:
The COVID-19 pandemic and associated health/safety requirements has impacted jobsite labor
productivity and materials procurement. The project team is working closely with the GC/CM to
mitigate potential cost and schedule impacts.
197
Tukwila Public Safety Plan – Fire Station 52 - Monthly Report
2
View of Entry Plaza and Concrete Seat Walls
Guardrail and Light Post Bases Along South Side of Property
198
Tukwila Public Safety Plan – Fire Station 52 - Monthly Report
3
Soffit in Progress at South Side of App Bay
199
200
Tukwila Public Safety Plan – Justice Center - Monthly Report
1
TUKWILA PUBLIC SAFETY PROJECTS
Justice Center
SOJ
Construction Management Monthly Report
August 2020
Report Prepared by: Ethan Bernau
Report Reviewed by: Justine Kim
Owner’s Representative: Shiels Obletz Johnsen (SOJ)
Architect: DLR Group
GCCM: BNBuilders
Construction Progress:
Passed final inspections by Fire Marshal and Building Official on August 20.
Received Certificate of Occupancy from DCD on August 28.
Continued commissioning of building systems.
Continued completion of punchlist work.
Continued building systems training for City staff.
Started furniture move-in and installation.
Upcoming Activities:
Complete furniture move-in and installation.
Complete permanent fencing and gates installation at site perimeter.
Complete punchlist work.
Complete commissioning of building systems.
Complete building systems training for City staff.
Complete City move-in.
Install groundwater monitoring wells.
Budget Status:
See overall TPSP budget summary updated monthly and included in monthly report package.
Change Order Status:
Change Orders #13 for $133,403 and #14(COVID) for $86,636 issued in July.
Total Change Orders issued to date = $2,496,525.
Schedule Status:
See TPSP master project schedule updated monthly and included in monthly report package.
Critical Issues:
None.
201
Tukwila Public Safety Plan – Justice Center - Monthly Report
2
Public Plaza along TIB
Exterior Area for Staff
202
Tukwila Public Safety Plan – Justice Center - Monthly Report
3
Duwamish Feature Wall in Lobby
PD Records Office Area
203
Tukwila Public Safety Plan – Justice Center - Monthly Report
4
PD Locker Rooms
Courtroom
204
Tukwila Public Safety Plan – Fire Station 52 - Monthly Report
1
TUKWILA PUBLIC SAFETY PROJECTS
Public Works
SOJ
Construction Management Monthly Report
August 2020
Report Reviewed by: Justine Kim
Owner’s Representative: Shiels Obletz Johnsen (SOJ)
Architect: SHKS Architects
Development Progress:
Architects are competing the documents and awaiting permit comments from DCD on the Tenant
Improvement project.
Property fence installation contract has been issued
PW and DCD to work together in the vesting process for future development of the Master Plan.
Upcoming Construction Activities:
Fence installation to occur before end of 2020 – SHKS to coordinate with fence scope and timing.
Budget Status:
See overall TPSP budget summary updated monthly and included in monthly report package.
Change Order Status:
None
Schedule Status:
Project schedule to be included in the next month’s report
Critical Issues:
Heiser Tenant Improvement project is in its final phase to complete the Construction Documents
and will be ready for bid in late September / October, pending council approval.
205
9,943,234.95$
Updated 6.26.20 2,312,584.00$
City of
Seattle Self-
Certification
OMWBE State
Certification
OMWBE
Federal
Certification
SCS
Axiom Division 7 SCS 217,945$
Caliber Concrete Const WBE 394,500$
Masonry Cascade Construction SCS 310,097$
Fencing Secure-A-Site WBE 299,000$
Steel Erection CHG Building Systems SCS 168,922$
Overhead Doors Crawford Door Company SB, VOSB 102,261$
Emerald Fire LLC WBE 49,750$
Bituminous Waterproofing Inland Waterproofing WBE 10,850$
Striping Stanley Patrick Striping SCS 4,834$
Plumbing Adept Mechanical MBE MBE / DBE SCS 659,596$
Concrete Sawing Salinas Sawing & Sealing MBE 1,347$
Trucking SilverStreak Inc WBE T/M
Site Services Construction Site Services MBE WBE T/M
Office Supplies Keeney Office Supply WBE T/M
RC Building Specialties MBE 880$
Interior/Exterior Signage Shine On Signs and Graphics SCS 22,139$
KT Painting MBE 70,463$
2,312,584$
23%
Do you
anticipate
using a SCS
Is this a
Spread the
Work SCS
Can only a
Sole Source
do the
work?
Approximate
Subcontract $ Amount
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
Lydig Construction, Inc Fire Station #51
Roofing
Percentage of Contract Amount:
Site Concrete
City of Tukwila
Approximate
Subcontract $ Amount Sub/Supplier Name
WMBE Participation
Certification
GC Contract Value
Fire Protection Specialties
Fire Protection
Award Amount:
Painting
Total Amount Not Yet Committed to a Sub/Supplier:
Scopes of Work that you Intend to
Award to WMBEs
Total Amount Intended to be Performed by DBE to Date:
Scopes where the sub/supplier is not yet
determined or committed When do you anticipate making a selection?
Page 2/3206
Journey
Labor Hours
Apprentice
Labor Hours
Total Labor
Hours for
Project
Apprentice
Percentage
Number of
Apprentices
1,245 0 1,245 0.00%0
1,483 0 1,483 0.00%0
73 0 73 0.00%0
646 258 903 28.52%1
1,453 198 1,651 11.96%3
1,087 0 1,087 0.00%0
313 154 467 32.98%2
229 0 229 0.00%0
1,386 117 1,502 7.77%1
2,828 1,170 3,998 29.27%7
91 0 91 0.00%0
2 0 2 0.00%0
546 0 546 0.00%0
136 0 136 0.00%0
5,919 215 6,134 3.51%5
4,020 2,328 6,348 36.67%4
83 0 83 0.00%0
19 0 19 0.00%0
1,344 810 2,154 37.60%1
12 0 12 0.00%0
30 0 30 0.00%0
4,686 101 4,787 2.11%0
25 0 25 0.00%0
498 0 498 0.00%1
70 40 110 36.36%4
28,221 5,389 33,611 16.03%29
15%
KT Painting
PBS Supply
Ralph's Concrete Pumping
Surgent
West Wind Reinforcing
SCI Infrastucture
Secure A Site
TOTALS:
Apprenticeship Utilization Requirement:
CHG
Emerald Fire
ESM Consulting Engineers
Façade Tech
GK Knutson
K Fox Insulation
LaRusso Concrete
Lydig Construction
Mckinstry
Miles Sand & Gravel
Multiwire
Northshore
Cascade
Inland Waterproofing
Caliber
Cadman
List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and
apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours.
Estimated information
Prime Contractor and all Subcontractors
Adept Mechanical
Axiom Division 7
Apprentice Utilization Plan - Updated 7.28.2020
Page 3/3207
16,519,792.50$
Updated 6.23.2020 4,498,795.28$
City of
Seattle Self-
Certification
OMWBE State
Certification
OMWBE
Federal
Certification
SCS
Corona Steel MBE 284,775$
Inland Waterproofing WBE 32,534$
Masonry R&D Masonry VOB 441,959$
Fencing Secure-A-Site WBE 194,150$
Roofing Axiom Division 7 SCS 277,950$
Metal Siding Axiom SCS 342,371$
Pellco SCS 2,450,369$
Structural Steel Supply B&B Fabricators WBE 474,688$
***Note: Not all contracts are bought out yet, and Mini-MACC does not include all scopes.
4,498,795$
27%
Do you
anticipate
using a SCS
Is this a
Spread the
Work SCS
Can only a
Sole Source
do the
work?
Approximate
Subcontract $ Amount
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
Lydig Construction, Inc Fire Station #52
Damp & Waterproofing
City of Tukwila
GC Contract Value
Award Amount:
WMBE Participation
Scopes of Work that you Intend to
Award to WMBEs Sub/Supplier Name
Certification
Approximate
Subcontract $ Amount
Structural Steel Erection
Earthwork
Total Amount Intended to be Performed by DBE to Date:
Percentage of Contract Amount:
Scopes where the sub/supplier is not yet
determined or committed When do you anticipate making a selection?
Total Amount Not Yet Committed to a Sub/Supplier:
Page 2/3208
Journey
Labor Hours
Apprentice
Labor Hours
Total Labor
Hours for
Project
Apprentice
Percentage
Number of
Apprentices
301 108 409 26.44%2
1,219 0 1,219 0.00%0
12 0 12 0.00%0
6 0 6 0.00%0
48 0 48 0.00%0
198 0 198 0.00%2
138 26 163 15.64%0
1,390 0 1,390 0.00%1
5 0 5 0.00%0
57 0 57 0.00%7
99 0 99 0.00%0
58 0 58 0.00%0
483 0 483 0.00%5
168 34 202 16.63%2
5,649 3,496 9,145 38.23%0
16 0 16 0.00%8
471 222 693 32.03%3
4,766 688 5,454 12.61%0
165 0 165 0.00%0
9 0 9 0.00%0
4 0 4 0.00%0
45 0 45 0.00%6
3,284 193 3,477 5.55%
18,288 4,658 22,946 20.30%34
15%
List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and
apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours.
Apprentice Utilization Plan - Updated 7/24/2020
Estimated information
Prime Contractor and all Subcontractors
Axiom Div 7
Brundage Bone
Axiom CC
Innovative Vacuum Services
Kulchin Foundation Drilling Co
LaRusso
Lydig Construction
Apprenticeship Utilization Requirement:
TOTALS:
Vanderlip & Co.
Barnhart Crane
Miles Sand & Gravel
Pellco
RL Clearing
Stoneway Concrete
Sky High Tree Removal
Conco
ESM Consulting Engineers
Evergreen Concrete Cutting
Grady Excavating
General Storefronts
Ground Up Road Construction
Inland Waterproofing Services
Ralph's Concrete Pumping
Morse Steel Reinforcing
Page 3/3209
BNB - Justice Center 29,098,053.00$
8/20/2019 4,645,946$
City of
Seattle Self-
Certification
OMWBE State
Certification
OMWBE
Federal
Certification
SCS
Contract Hardware Inc.
SBE
310,362$
Caliber Concrete WBE 520,550$
Sign Wizards SDBE/WSB
E 36,236$
SnapTex SBE/WBE/
MBE 33,875$
Workpointe SBE 454,003$
Redline Mechanical X 809,002$
C&C Solutions VOSBE 235,700$
Skyline Marble WBE 88,000$
Zombie Base WSBE 4,758$
Axiom #1027 583,020$
Halili WBE 219,450$
Fire Protection Columbia Fire #1599 287,890$
RE Sides Landscaping #1054 1,020,000$
Construction Site Services 22,000$
Waterproofing Inland Waterproofing WBE 21,100$
Darling Nava Consulting M4F0026198
4,645,946$
16%
Do you anticipate
using a SCS
Is this a
Spread the
Work SCS
Can only a
Sole Source
do the
work?
Approximate
Subcontract $
Amount
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
Outreach Coordinator
Total Amount Not Yet Committed to a Sub/Supplier:
Scopes of Work that you Intend to
Award to WMBEs
In Progress Participation:
Scopes where the sub/supplier is not
yet determined or committed
When do you anticipate making a
selection?
Temp Sanitation (NSS)
Roofing Systems
City of Tukwila
Approximate
Subcontract $
Amount
Sub/Supplier Name
WMBE Participation
Certification
GC Contract Value
Painting and Coatings
Irigation and Landscaping
Award Amount:
Supplier of Hardware, Doors and Frames
Site Concrete
Signage
Supplier
Shelving
Plumbing
Controls
Marble Supply
Rubber Base Install
Percentage of Award Amount:
Page 2/3210
This Month
Journey Labor
Hours
This Month
Apprentice
Labor Hours
Total Labor
Hours for
Project
Total
Apprentice
Percentage
Number of
Apprentices
Acoustical Design 28 0 962 10.71%0
Apex Steel 0 0 9,985 11.26%0
Apex Steel ( Magnum Crane)0 0 293 0.00%0
Apex Steel (Corona Stud & Deck)0 0 22 0.00%0
Ascendent, LLC 0 0 8,262 2.51%0
Axiom (Northshore Exteriors)144 0 144 0.00%0
Axiom Division 7 1,522 0 2,460 0.00%0
Barclay Dean Architectural 0 0 24 33.33%0
BNBuilders 1,059 0 31,098 17.18%0
Caliber Concrete 529 146 2,190 24.50%0
Caliber Concrete (Evergreen Concrete)24 24 59 0.00%2
Caliber Concrete (Stoneway)0 0 125 0.00%0
Caliber Const (Miles Sand & Gravel)0 0 3 0.00%0
CML Security 0 0 1,158 21.42%0
Columbia Fire 372 264 1,601 45.67%2
Commercial Fence (Evergreen Concrete Cutting)3 0 3 0.00%0
Commercial Fence Corp 59 0 210 0.00%0
Floor Solutions 71 68 1,303 30.89%1
General Storefronts 57 136 3,155 32.84%4
Gonsalves & Santucci DBA Conco 8 0 744 5.04%0
Harris Rebar (Central Steel)0 0 6,343 6.02%0
Iliad (Bravo Enviromental)0 0 4 0.00%0
Iliad (City Transfer)0 0 40 0.00%0
Iliad, Inc 0 0 20,562 0.76%0
Inland Waterproofing 0 0 247 0.00%0
Iris Window Coverings 35 0 35 0.00%0
Johansen (Multiwire)238 114 351 32.34%1
Johansen Mechanical 824 155 11,982 28.40%3
Johansen Mechanical (C&C Solutions)266 0 266 0.00%0
Johansen Mechanical (Maple Valley Energy)0 0 1,642 0.00%0
Johansen Mechanical (Redline Mech)0 0 3,024 16.60%0
Lacey Glass 0 0 4 50.00%0
Lakeside Industries 0 0 2,201 4.25%0
Lakeside Industries (NW Traffic)21 0 75 0.00%0
Lakeside Industries (PacWest Grinding)0 0 15 0.00%0
Northshore Exteriors 4 854 9,065 48.27%9
Northshore Exteriors (Pape)0 0 22 0.00%0
Northshore Exteriors (WA Waterproofing)0 0 86 0.00%0
Northwest Complete Contracting 0 0 4,195 1.67%0
NW Partitions 558 109 14,555 13.75%3
NW Partitions (Barclay Dean)0 0 28 0.00%0
NW Partitions (InsulPro)0 0 908 21.38%0
NW Partitions (Sign Wizards)0 0 30 0.00%0
Performance Contracting 0 0 164 4.89%0
Rhine Demolition 0 0 2,090 11.10%0
Valley Electric 1,071 670 15,910 38.95%4
Valley Electric (D&G Mechanical)87 0 87 0.00%0
Valley Electric (EZ Interface)428 328 1,716 49.93%3
Valley Electric (NessCampbell Crane)16 0 16 0.00%0
Valley Electric (Penhall)10 50.00%0
Valley Electric (Praetoria Power)74 0.00%0
Valley Electric (Stoneway Concrete)73 0.00%0
Zesbaugh 62 12.96%0
7,418 2,867 159,675 17.79%32
10%
Apprentice Utilization Plan - July 2020
*newly added this month Apprenticeship Utilization Requirement:
List the prime and all subcontractors scheduled to work on this project, and indicate the estimated number of hours to be performed by journey level and
apprentice workers for each. Apprentice utilization must equal or exceed 15% of the total labor hours.
Estimated information
Prime Contractor and all Subcontractors
TOTALS:
Page 3/3211
212
City of Tukwila - Facilities Plan MONTHLY Budget Report
TOTAL PROJECT (REVISED Budgets; D-20 Plan Adopted by Council)
Life to Date Costs
as of August 27, 2020 (reconciled w/acctg thru Aug 16, 2020 GL)
Original Budget Budget Transfers Current Budget Committed Budget Life to Date Costs Remain'g Committed Remaining Budget Cost at Completion
A/E Services (both Design & CA)3,278,125$ (3,125)$ 3,275,000$ 3,210,300$ 2,961,030$ 249,270$ 64,700$ -$
Permits/Fees 700,000$ 330,000$ 1,030,000$ 897,544$ 897,544$ -$ 132,456$ -$
Construction (Pre-Con, Const & Tax)38,738,678$ 2,026,169$ 40,764,847$ 40,080,329$ 38,212,523$ 1,997,562$ 0$ -$
Construction Related Costs (incl Bond)2,112,639$ 402,194$ 2,514,833$ 2,415,031$ 1,187,049$ 1,227,982$ 99,802$ -$
PM Services (incl Other Professional Svcs)1,815,875$ 221,211$ 2,037,086$ 2,018,377$ 1,695,514$ 322,863$ 18,709$ -$
Contingency (incl Construction & Project)6,507,731$ (5,031,367)$ 1,476,364$ -$ -$ -$ 2,026,364$ -$
Contingency for Site Contamination (soils,hazmat)-$ 550,000$ 550,000$ 684,518$ 554,762$ -$ -$ -$
Land Acquisition 14,133,295$ (416,714)$ 13,716,581$ 13,716,462$ 13,692,508$ 23,954$ 119$ -$
Contingency for Land Acquisition 1,250,000$ 250,000$ 1,500,000$ 1,492,320$ 1,492,320$ -$ 7,680$ -$
68,536,343$ (1,671,632)$ 66,864,711$ 64,514,881$ 60,693,250$ 3,821,631$ 2,349,830$ -$
Original Budget Budget Transfers Current Budget Committed Budget Life to Date Costs Remain'g Committed Remaining Budget Cost at Completion
A/E Services (both Design & CA)1,070,000$ 298,956$ 1,368,956$ 1,297,777$ 1,252,073$ 45,704$ 71,179$ -$
Land Acquisition -$ -$ -$ -$ -$ -$ -$ -$
Permits/Fees 234,000$ 100,000$ 334,000$ 244,428$ 228,641$ 15,788$ 89,572$ -$
Construction (Pre-Con, Const & Tax)9,396,000$ 2,237,843$ 11,633,843$ 11,633,791$ 11,070,785$ 563,006$ 52$ -$
Construction Related Costs (incl Bond)931,000$ (258,042)$ 672,958$ 487,814$ 330,179$ 157,635$ 185,144$ -$
PM Services (incl Other Professional Svcs)526,000$ (133,000)$ 393,000$ 365,550$ 280,076$ 85,474$ 27,450$ -$
Contingency (incl Construction & Project)1,116,000$ (834,124)$ 281,876$ -$ -$ -$ 281,876$ -$
13,273,000$ 1,411,633$ 14,684,632$ 14,029,360$ 13,161,754$ 867,606$ 655,273$ -$
Original Budget Budget Transfers Current Budget Committed Budget Life to Date Costs Remain'g Committed Remaining Budget Cost at Completion
A/E Services (both Design & CA)1,415,000$ 458,172$ 1,873,172$ 1,871,265$ 1,698,209$ 173,056$ 1,907$ -$
Land Acquisition 16,000$ 1,160$ 17,160$ 17,157$ 17,157$ -$ 3$ -$
Permits/Fees 353,000$ 50,000$ 403,000$ 360,711$ 300,534$ 60,177$ 42,289$ -$
Construction (Pre-Con, Const & Tax)13,298,000$ 5,253,893$ 18,551,893$ 18,551,492$ 12,782,414$ 5,769,078$ 401$ -$
Construction Related Costs (incl Bond)1,398,000$ (132,660)$ 1,265,340$ 829,978$ 375,067$ 454,911$ 435,362$ -$
PM Services (incl Other Professional Svcs)787,000$ (95,000)$ 692,000$ 555,454$ 421,785$ 133,669$ 136,546$ -$
Contingency (incl Construction & Project)1,343,000$ (395,565)$ 947,435$ -$ -$ -$ 947,435$ -$
18,610,000$ 5,140,000$ 23,750,000$ 22,186,057$ 15,595,166$ 6,590,891$ 1,563,943$ -$
Original Budget Budget Transfers Current Budget Committed Budget Life to Date Costs Remain'g Committed Remaining Budget Cost at Completion
A/E Services (both Design & CA)150,000$ (15,505)$ 134,495$ 134,495$ 132,995$ 1,500$ (0)$ -$
Land Acquisition 902,668$ 31,206$ 933,874$ 933,875$ 933,775$ 100$ (1)$ -$
Permits/Fees 20,000$ (11,827)$ 8,173$ 4,971$ 4,971$ -$ 3,202$ -$
Construction (Pre-Con, Const & Tax)230,000$ (123,300)$ 106,700$ 84,196$ 84,196$ -$ 22,504$ -$
Construction Related Costs (incl Bond)50,000$ (2,698)$ 47,302$ 42,302$ 29,145$ 13,157$ 5,000$ -$
PM Services (incl Other Professional Svcs)107,500$ (835)$ 106,665$ 106,665$ 86,066$ 20,599$ -$ -$
Contingency (incl Construction & Project)41,832$ 122,959$ 164,791$ -$ -$ -$ 164,791$ -$
1,502,000$ -$ 1,502,000$ 1,306,505$ 1,271,148$ 35,357$ 195,495$ -$
COUNCIL REPORTING SUMMARY -
FIRE STATION 52
COUNCIL REPORTING SUMMARY -
FIRE STATION 51
TOTAL
COUNCIL REPORTING SUMMARY -
JUSTICE CENTER
TOTAL
TOTAL
COUNCIL REPORTING SUMMARY -
FIRE STATION 54
TOTAL213
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
A/E PROCUREMENT
PROGRAMMING
PROJECT
2017 2018
TUKWILA PUBLIC SAFETY PLAN
DESIGN/PERMITTING
FIRE STATION 52
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
2016 2019 2020
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
JUSTICE CENTER
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
A/E PROCUREMENT
PROGRAMMING
DESIGN PHASE 1
PUBLIC WORKS
BIDDING/CONSTRUCTION PHASE 1
MOVE-IN/OCCUPANCY PHASE 1
A/E PROCUREMENT
MASTER SITE PLAN
DESIGN/PERMITTING
FIRE STATION 51
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
A/E PROCUREMENT
PROGRAMMING
2021214