Parcel No: 0323049029 Permit Number: D16-0281
Address: 11060 TUKWILA INTERNATIONAL Issue Date: 1/8/2018
BLVD BLDG Permit Expires On: 7/7/2018
Project Name: SEBCO DEMOLITION
Owner:
Name: SSEBCO INC
Address: 720 RAINIER AVE S, RENTON, WA,
98057
Contact Person:
Name: DAVID KEHLE
Address: 1913 BONAIR DR SW, SEATTLE, WA,
98116
Contractor:
Name: POE CONSTRUCTION INC
Address: PO BOX 1838, AUBURN, WA, 98071-
1838
License No: POECOI*247QZ
Lender:
Name: SEBCOINC
Address: 4020 E MADISON - SUITE 320,
SEATTLE, WA, 98112
Phone: (206) 433-8997
Phone: (253) 833-2400
Expiration Date: 5/1/2019
DESCRIPTION OF WORK:
DEMOLISH EXISTING 21,206 SQ FT OFFICE AND REPAIR GARAGE, ANCILLARY STRUCTURES AND ALL EXISTING SITE
IMPROVEMENTS
PW ACTIVITIES INCLUDE WATER CAPPING AT THE WATER MAIN, EROSION CONTROL.
SANITARY SEWER CAPPING UNDER VALLEY VIEW PERMIT #7443.
Project Valuation: $318,000.00
Type of Fire Protection: Sprinklers: YES
Fire Alarm:
Type of Construction: VB
Electrical Service Provided by:
Fees Collected: $5,830.44
Occupancy per IBC: B
Water District:
Sewer District:
ICurrent Codes adopted by the City of Tukwila: I
International Building Code Edition:
International Residential Code Edition:
International Mechanical Code Edition
Uniform Plumbing Code Edition:
International Fuel Gas Code:
Public Works Activities:
Channelization/Striping:
Curb Cut/Access/Sidewalk:
Fire Loop Hydrant:
Flood Control Zone:
Hauling/Oversize Load:
Land Altering:
Landscape Irrigation:
Sanitary Side Sewer:
Sewer Main Extension:
2015 National Electrical Code: 2017
2015 WA Cities Electrical Code: 2017
2015 WAC 296-4613: 2017
2015 WA State Energy Code: 2015
2015
Volumes: Cut: 0 Fill: 0
Number: 0
Storm Drainage:
Street Use:
Water Main Extension:
Water Meter: No
Permit Center Authorized Signature: Date: 014
I hearby certify that I have read and examined this permit and know the same to be true and correct. All
provisions of law and ordinances governing this work will be complied with, whether specified herein or not.
The granting of this permit does not presume to give authority to violate or cancel the provisions of any other
state or local laws regulating construction or the performance of work. I am authorized to sign and obtain this
development per nd agr--e to the conditions attached to this permit.
Signature:
DatA\�Ob�kb-
Print Name--nhw On&�
This permit shall become null and void if the work is not commenced within 180 days for the date of issuance, or if
the work is suspended or abandoned for a period of 180 days from the last inspection.
PERMIT CONDITIONS:
1: 'BUILDING PERMIT CONDITIONS'
2: All permits, inspection record card and approved construction documents shall be kept at the site of work
and shall be open to inspection by the Building Inspector until final inspection approval is granted.
3: Remove all demolition rubble and loose miscellaneous material from lot or parcel of ground, properly cap
the sanitary sewer connections, and properly fill or otherwise protect all basements, cellars, septic tanks,
wells, and other excavations. Final inspection approval will be determined by the building inspector based
on satisfactory completion of this requirement.
4: All plumbing and gas piping work shall be inspected and approved under a separate permit issued by the
City of Tukwila Building Department (206-431-3670).
5: All electrical work shall be inspected and approved under a separate permit issued by the City of Tukwila
Permit Center.
VALIDITY OF PERMIT: The issuance or granting of a permit shall not be construed to be a permit for, or an
approval of, any violation of any of the provisions of the building code or of any other ordinances of the City
of Tukwila. Permits presuming to give authority to violate or cancel the provisions of the code or other
ordinances of the City of Tukwila shall not be valid. The issuance of a permit based on construction
documents and other data shall not prevent the Building Official from requiring the correction of errors in
the construction documents and other data.
CONSTRUCTION CONTRACTOR'S RESPONSIBILITY (i)
Before bidding or starting any construction work, you are required to obtain a written asbestos report from
the building owner or owner's agent. The report must be based on a survey by an accredited AHERA
building inspector unless the building owner assumes materials in the structure are asbestos or has other
convincing documents showing asbestos is not present in the work area. A building owner may know
asbestos has been removed during prior work or that a new building has been constructed using materials
certified to be asbestos free.
If you discover suspect asbestos materials, you must report them to the building owner within 24 hours.
Asbestos materials may be found in enclosed structures or between other materials, where they are not
accessible before work.
State law specifies a minimum $250 per day fine for failure to obtain the asbestos report. This fine can be
applied to both the contractor and building owner. Additional fines may be applied if workers are exposed
to airborne asbestos.
(i) Washington State Department of Labor & Industries regulations & policies with regards to asbestos
removal.
A Copy of the asbestos report must be made available to the building inspector prior to the first inspection.
In addition, if asbestos has been found, confirmation of the completed abatement work must be provided
to the building inspector. Inspection scheduling will not be accepted until this documentation is received by
the building inspector.
9: Accumulation of combustible waste material is prohibited during the demolition phase of this project.
Remove and properly dispose of all waste material prior to the close of the working day and as often
throughout the day as needed.
10: All interior demo debris must be removed prior to demo of the automatic sprinkler system. Contact the
Tukwila Fire Prevention Bureau at 206/575-4407 for an inspection of the building prior to shut down of the
automatic sprinkler system.
11: Fire Department access and existing hydrants shall be constantly maintained during demolition and
construction.
8: Contact The Tukwila Fire Prevention Bureau to witness all required inspections and tests. (City Ordinances
#2436 and #2437)
12: Any overlooked hazardous condition and/or violation of the adopted Fire or Building Codes does not imply
approval of such condition or violation.
13: These plans were reviewed by Inspector 511. If you have any questions, please call Tukwila Fire Prevention
Bureau at (206)575-4407.
14: 'PUBLIC WORKS PERMIT CONDITIONS'
15: Call to schedule mandatory pre -construction meeting with Dave Stuckle, Public Works Inspector, (206) 433-
0179.
16: The applicant or contractor must notify the Public Works Inspector at (206) 433-0179 upon commencement
and completion of work at least 24 hours in advance. All inspection requests for utility work must also be
made 24 hours in advance.
27: Water service shall be capped at the water main and removal of the existing 2" WIVI shall be coordinated
with Tukwila Water Dept.
Fuel tank removal and contaminated dirt removal are not part of this demo permit.
28: Per Sound Transit all vehicles should enter the property via 112th Street or Tukwila International Blvd, and
NOT EAST MARGINAL WAY to minimize impact to Sound Transit Easement Areas. Refer to Sound Transit
December 1, 2017 Review and Assessment of Demolition letter, which is part of this permit approval.
17: Prior to construction, all utilities in the vicinity shall be field located. NOTE: For City of Tukwila utility
locates, call 811 or 1-800-424-5555.
18: Permit is valid between the weekday hours of 7:00 a.m. and 5:00 p.m. only. Coordinate with the Public
Works Inspector for any work after 5:00 p.m. and weekends.
19: No work under this permit during weekend hours without prior approval by Public Works. Coordinate with
the Public Works Inspector.
20: Any material spilled onto any street shall be cleaned up immediately.
21: Hauling 6 loaded vehicles per hour/8 hours a day for 2 or more consecutive days or hauling hazardous
waste shall require application for a Hauling Permit prior to any associated activity.
22: Temporary erosion control measures shall be implemented as the first order of business to prevent
sedimentation off-site or into existing drainage facilities.
23: The site shall have permanent erosion control measures in place as soon as possible after final grading has
been completed and prior to the Final Inspection.
24: From October 1 through April 30, cover any slopes and stockpiles that are 3H:1V or steeper and have a
vertical rise of 10 feet or more and will be unworked for greater than 12 hours. During this time period,
cover or mulch other disturbed areas, if they will be unworked more than 2 days. Covered material must
be stockpiled on site at the beginning of this period. Inspect and maintain this stabilization weekly and
immediately before, during and following storms.
25: From May 1 through September 30, inspect and maintain temporary erosion prevention and sediment at
least monthly. All disturbed areas of the site shall be permanently stabilized prior to final construction
approval.
26: Maintain emergency, pedestrian, and vehicular access to buildings, trails and transit at all times.
PERMIT INSPECTIONS REQUIRED
Permit Inspection Line: (206) 438-9350
1700
BUILDING FINAL"
5210
EROSION MEASURES FNL
1400
FIRE FINAL
5040
LAND ALTERING
0101
PRE -CONSTRUCTION
1600
PUBLIC WORKS FINAL
5160
PUBLIC WORKS PRE -CON
5090
STORM DRAINAGE
5130
WATER METER - PERM
CITY OF TUKWILA
Community Development Department
Public Works Department
Permit Center
6300 Southcenter Blvd., Suite 100
Tukwila, WA 98188
Nv..TUk\N'J IaWA.gov
SITE LOCATION
Site Adi
Tenant
Building Permit No. (P — OA I
Project No.
Date Application Accepted:
IDate Application Expires:
(For offlce use only)
CONSTRUCTION PERMIT APPLICATION
Applications and plans must be complete in order to be accepted for plan review.
Applications will not be accepted through the mail or by fax.
"Please Print"
PROPERTY OWNER
Name: fty IV,,
Address:4w (At �740
City: %--ku Staw: 1h f-lPW71
CONTACT PERSON - person receiving all project
conununication I
Name: �64LV
Address: 11 UP
City:eall*, State% Zipftilp
Phone:% 4?7,
_� _,%-pFax.J&.
Email*A64,,hl, , &X�WA rdA. &W t
GENERAL CONTRACTOR INFORMATION
Company Name:
Address:
city: State: Zip:
Phone: Fax:
Contr Reg No.: Exp Date:
Tukwila Business License No.:
Co Assessor's Tax No.: V-1 !t!2!fL - L/1'T i -14 -API
,YV Suite Number: - Floor: 1
New Tenant: E) ..... Yes Eff..No
ARCHITECT OF RECORD
Name: W
Company Name: ua-vo wa+w,
Address:
Architect Name"vtr) �e*o,
Address: 1UP two- 910�
City: "te Statol
Zip:61�11(.O,
Phone*� . 4-34 - mog Fax:ft.k,.!,�
Email: 4�"e Q 4Whkcw�,
601K
ENGINEER OF RECORD
Company Name:
Engineer Name:
Address:
City: State: Zip:
Phone: Fax:
Email:
LENDER/BOND ISSUED (required for projects $5,000 or
greater per RCW 19.27.095) 1 1
Name: W
RWOEV
Address:
rE� State: Zip:
H:\Appiieeliom\Forms-Applicelions On Line\2011 ApplicationsTerntit Application Revised -8-9-1l.docK
Revised: August 2011 Page 1 of 4
bh
BUILDING PERMIT INFORMATION — 206-431-3670
Valuation of Project (contractor's bid price): $ �1 b I Xr, CV Existing Building Valuation: $1,1 UIUACA
Describe the scope of work (please provide detailed information):
k-" NsT&4
4AJP 1AA, N6-tlQq
Will there be new rack storage? ..... Yes No If yes, a separate permit and plan'submittal will be required.
IProvide AD Building Arew in Square Footage Below
PLANNING DIVISION:
Single fianily building footprint (area of the foundation of all structum, plus any dec�s over 18 inches and overhangs greater than 18 inches)
*For an Accessory dwelling, provide the following:
Lot Area (sq fl)1g&.Qt Floor am of principal dwelling: Floor area of accessory dwelling- J4 A --
*Provide docurnentati6n that shows that the principal owner lives in one of the dwellings as his or her primary residence.
Number of Paricing Stalls Provided: Standard: 4 — Compact: Handicap:
Will them be a change in use? 14 ...... Yes El ....... No If "yes", explain: &1XS; B(I,—
A
k4
FIRE PROTECTIONA11AZARDOUS MATERIALS:
10 ....... Sprinlders 0 ....... Automatic Fire Alarm D ....... None 0 ....... Other (specify)_
Will there be storage or use of flammable, combustible or hazardous materials in the building? El ....... Yes [3 ....... No
If '5ws', attach list ofmaterials and storage locations on a separate 8-112 " x I I - paper including quantities and Material Safety Data Sheets.
SEPTIC SYSTEM
Ug y —Tb
61 -
Existing
Interior Remodel
Addition to
Existing
Structure
New
Type of
Construction per
IBC
Type of
Occupancy per
I" Floor
2 nd Floor $
3rd Floor
Floors thru
Basement
Accessory Structur,*
Attached Garage
Detached Garage
Attached Carport
Detached Carport
Covered Deck
Uncovered Deck
PLANNING DIVISION:
Single fianily building footprint (area of the foundation of all structum, plus any dec�s over 18 inches and overhangs greater than 18 inches)
*For an Accessory dwelling, provide the following:
Lot Area (sq fl)1g&.Qt Floor am of principal dwelling: Floor area of accessory dwelling- J4 A --
*Provide docurnentati6n that shows that the principal owner lives in one of the dwellings as his or her primary residence.
Number of Paricing Stalls Provided: Standard: 4 — Compact: Handicap:
Will them be a change in use? 14 ...... Yes El ....... No If "yes", explain: &1XS; B(I,—
A
k4
FIRE PROTECTIONA11AZARDOUS MATERIALS:
10 ....... Sprinlders 0 ....... Automatic Fire Alarm D ....... None 0 ....... Other (specify)_
Will there be storage or use of flammable, combustible or hazardous materials in the building? El ....... Yes [3 ....... No
If '5ws', attach list ofmaterials and storage locations on a separate 8-112 " x I I - paper including quantities and Material Safety Data Sheets.
SEPTIC SYSTEM
Ug y —Tb
61 -
PERMrr APPUCATION WITS —
Value of Construction — In all cases, a value of construction amount should be entered by the applicant This figure will be reviewed and is subject
to possible revision by the Permit Center to comply with current fee schedules.
Expiration of Plan Review — Applications for which no permit is issuedwithin 180 days following the date of application shall expire by limitation.
The Building Official may grant one or more extensions of time for additional periods not exceeding 90 days each. The extension shall be
requested in writing and justifiable cause demonstrated. Section 105.3.2 International Building Code (cunent edition).
I HEREBY CERTEFY THAT I HAVE READ AND EXAMINED THIS APPLICATION AND KNOW THE SAME TO BE TRUE UNDER
PENALTY OF PERJURY BY THE LAWS OF THE STATE OF WASHINGTON, AND I AM AUTHORIZED TO APPLY FOR THIS PERMIT.
BUILDING OWNER OR AIM10AUZED AGENT:
Date: tb�oLp
Print Name: Day Telephone: 4X&
Mailing Address:. �11.Le 4mlc-' Wb I) LP
City stft zip
MAWficatiMMOMIS.-AWlication; On LineWl I Wcationewnit Application Revised - 9-9-1 I.dDCX
Revised: August 2011
bb
Page 4 of 4
DESCRIPTIONS
ACCOUNT
QUANTITY
PAID
PermitTRAK
$3,643.45
D16-0281 Address: 11060 TUKWILA INTERNATIONAL BLVD BLDG
Apn:0323049029
$3,643.45
Credit Card Fee
$106.12
Credit Card Fee
ROOO.369.908.00.00
0.00
$106.12
DEVELOPMENT
$3,369.10
PERMITFEE
ROOO.322.100.00.00
0.00
$3,364.60
WASHINGTON STATE SURCHARGE
B640.237.114
0.00
$4.50
TECHNOLOGY FEE
$168.23
TECHNOLOGY FEE
TOTAL FEES PAID BY RECEIPT: R13240
ROOO.322.900.04.00
0.00 7---$168.23
$3,643.45
Date Paid: Monday, January 08, 2018
Paid By: DAVID E KEHLE
Pay Method: CREDIT CARD 06356D
Printed: Monday, January 08, 2018 2:02 PM I of 1 CIRWYSTEMS
Date Paid: Thursday, October 13, 2016
Paid By: DAVID KEHLE
Pay Method: CREDIT CARD 08082D
Printed: Thursday, October 13, 2016 1:42 PM 1 of 1 WYSTEMS
INSPECTION RECOIRD. I'D16-0281
INSPECTION NO. I Retain a copy with permit PERMIT NO.
CITY OF TUKWILA BUILDING DIVISION
6300 Southcenter Blvd., #100, Tukwila. WA 98188 (206) 431-3670
Permit Inspection Request Line (206) 438-9350
Project-
Type - of Inspection:
C> Pi yya L
->%A, inq
Address:
I y C) (0-o �-I' —14W X111lik-K"
Date Called:
r)"'L
Special Instructions: 13 Lj&
ys+
Date Wanted: a.m.
-3-H-20e p.m.
Requester: 50-6
Phone N
( --55 1 - 15 S/ —
nApproved per applicable codes. 1-1 Corrections required prior to approval.
REINSPECTION FEE REQUIRED. Prior to next inspection, fee must be
paid at 6300 Southcenter Blvd.. Suite 100. Call to schedute reinspection.
INSPECTION RECORD.
Retain a copy with permit
INSPECTION NO. PERMIT NO.
CITY OF TUKWILA BUILDING DIVISION
6300 Southcenter Blvd., #100, Tukwila. WA 98188 (206) 431-3670
Permit Inspection Request Line (206) 438-9350
Project:
-!!�5r8CO
Type of Inspection:
R')tLJ)1N& FINAL -
Address:
//low 71-11
Date Called:
Special Instructions:
Date Wanted: a. rn.
Requester:
go L?
Phone No:
C -
Approved per applicable codes. IffCorrections required prior to approval.
COMMENTS:
ALL PUJ3"C WOAK5 -?z-11qA
/741),ST d1C
Inspector: 11-1:2 4-1 Date:
REINSPECTION FEE REQUIRED. Prior to next inspection, fee must be
paid at 6300 Southcenter Blvd., Suite 100. Catl. to schedule reinspection.
INSPECTION RECORD. -f
Retain a copy with permit D I to J'?—
INSPECTION NO. PERMIT NO.
CITY OFTUKWILA BUILDING DIVISION
6300 Southcenter Blvd., #100, Tukwila. WA 98188 (206) 431-3670
Permit Inspection Request Line (206) 438-9350
Project:
77OW
Type of Ins ection:
PgE Z!0A/5T-R0C'rJCNW
Address:
A& 6 6 77 /1 B.,
Date Called:
Special Instructions:
Date Wanted*
P.M.
Requester:
905
AyV\
Phone No:
2-61e—
I I
Inspector: Date:
REINSPECTION FEE REQUIRED. Prior to next inspection, fee must be
paid at 6300 Southcenter Blvd., Suite 100. Call. to schedule reinspection.
INSPECTION RECORD 6-2,(�
Retain a copy wit��pl- eimit
INSPECTION NUMBER PERMIT NUMBERS
CITY OF TUKWILA FIRE DEPARTMENT
206-575-4407
Project:
Type of Inspection:
Address:
1(0670 77b
Contact Person:
Suite #:
Pre -Fire:
Special Instructions:
Phone No.:
ZApproved per applicable codes. FICorrections required prior to approval.
COMMENTS:
Needs Shift Inspection:
Sprinklers:
Fire Alarm:
Hood & Duct:
Monitor:
Pre -Fire:
Permits:
Occupancy Type:
I Hrs.:
Inspector: f Jtj 4�;� Date:
$100.00 REINSPECTION FEE REQUIRED. You will receive an invoice from
the City of Tukwila Finance Department. Call to schedule a reinspection.
Billina Address
Attn: I Company Name:
Address:
City: EStat
Word/Inspection Record Form.Doc 3/14/14 T.F.D. Form F.P. 113
EV—SouNDTRANsIT 1
RECEIVED
December 1, 2017
DEL 0 1 2017
Peter von Reichbauer
King Catairy Comic
David Kehle Architect
CHAIR
1916 Bondair Dr. SW TUKWILA
Dave Somers
Seattle, WA 98116 PUBLIC WORKS
Snohomah Countv Erecative
Property Management Manager
VICE CHAIRS
RE: Review and Assessment of Demolition of Existing Structure(s) at
John Marchione
Rechnotul AlaYar
11060 Tukwila International Blvd., Tukwila, WA
Marilyn Strickland
Tacoma Alamr
Dear Mr. Kehle:
BOARD MEMBERS
Thank you for taking the time to meet with us to discuss the Sebco
Nancy Backus
Development Project — 11000 Building (the "Project") on November 15, 2017.
Auburn Afa.vot
Claudia Balducci
Sound Transit has reviewed the drawings and plans prepared by Barghausen
King Counti, Coundimember
Consulting Engineers, Inc. dated 09/19/2016 and has determined that the
Fred Butler
demolition of the existing structures located at 11060 International Blvd.
Iv,%aquah MaVor
Tukwila, WA, will not impact Sound Transit's Traction Power Substation
Dow Constantine
Easement Area nor Sound Transit's Light Rail Guideway Easement Area. This
King Countv r-%ec ittive
letter will serve as our written confirmation of no impact for demolition
Bruce Darnmeler
activities Dgly.
Pierre Comm E%ecutive
Dave Earling
When performing the demolition of the existing structures, all vehicles should
Edinntulv Mayor
enter the property via I I 2h Street or Tukwila International Blvd. and not East
Rob Johnson
Seattle Counc dinember
Marginal Way to minimize impact to Sound Transit's Easement Areas. No
equipment such as mobile cranes, scissor lifts, scaffolding or other lifting
Kent Keel
Univervin Place Mayor Pre) Tent
devices shall be higher than Sound Transit's top of rail and have the potential
Joe McDermott
to fall and foul the light rail tracks or enter or swing over the Traction Power
King Ciawtv Onvit il Chah
Substation Easement Area. If the proposed demolition plan changes and there
Roger Millar
could be a potential impact to Sound Transit's Easements, please notify us
Wa %hington State Sec retan-
immediately so we can provide additional comments.
(if Tiampartation
Mary Mass
Sound Transit is currently reviewing the plans for the proposed construction of
Lukewcvxf Couric ilmember
the new building at this location and will provide comments via an additional
Paul Roberts
letter. Thank you for your assistance. Please contact me at 206.398.5201 or
Evererr Caumilmember
Angie House at 206.398.5430 if you have any questions.
Dave Upthegrove
King Otuntv Countilinember
c
Si erely,
Peter von Reichbauer
King Catairy Comic
go
dinernher
CHIEF EXECUME OFFICER
Nancy Ben et
Peter M. Ragoff
Property Management Manager
nancy.bennett@soundtransit.org
Central Puget Sound Regional Transit Authority - Union Station
401 S. Jackson St., Seattle, WA 98104-2826 - Reception: (206) 398-5000 - FAX: (206) 398-5499
www.soundtransit.org D
City of Tukwila
Department of Community Development
6300 Southcenter Boulevard, Suite 100
Tukwila, WA 98118
Attn: Ms Joanna Spencer
Re: Sebco Demo Permit D16-0332
11060 Tukwila International Blvd
DearJoanna,
I have finally had direct meetings with both City Light and Sound Transit. I also met with Valley
View Sewer district and obtained the Capping permit which is attached.
Per your correction letter #2 of February 8th, 2017 (attached), I have the following comments to
resolve those issues:
1. Valley View Sewer Capping Permit see attached. I had previously submitted the site
plan with the capping info as given to Valley View.
2. 1 met with City Light and have attached their meeting notes stating to just show the 14'
clearance from the transmission line to my building. I have done that on sheets El and
E2 which I showed to them and they want it submitted with the service application. I
have also attached those to this response for your info.
3. 1 met with Sound Transit and they have no issue with the demo permit being issued
because there is no adjacency to their easements. I have not received the letter yet, but
you can talk with Angela House (206-398-5430) to confirm.
4. NO[ is a part of the Public Works permit PW1600161.
I really need to get the Demo permit now as the tenant has been able to vacate the end of the
month and the first step is the building demo and clean up.
Please expedite your review and I trust we can obtain the Demo permit ASAP if you have any
other concerns or comments, please let me know.
DSincerel ,
a
David Kehle
Cc: Jay Ayers
'�ORRECTIGN
J R #
IR E C E 1 V EEED
C, ITY 0 F T U K VV ii!.- A
kUV' 2 0 239
PERMITGENTER
(206) 433-8997
1916 Bonair Drive S.W. fax (206) 246-8369
Seattle, WA 98116 t)l(e-- 0 n- I
email: dkehle@dkehlearch.com
Below, please find the minutes of the meeting at 11060 Tukwila International Blvd.
In attendance,
Ryan Tham, David Kehle, Alan Peterson, Abdu Issa, Percy Schlimm
The first item discussed was the customer requesting a letter from Seattle City Light(SCL) for City of
Tukwila verifying/approving the location of the building. Abdu explained that SCL will not give any
letter saying the building is good to go. SCL can provide the standard showing our clearance
requirement, then the appropriate authority can check if the clearance is met before issuing the permit.
Abdu then discussed the purpose of the meeting; which is to assist the customer to provide a complete
application for the service request so the project can be sent to SCL Engineering. We also explained the
time frame- 5 to 6 months until it will be assigned to an engineer after a complete application is
received. The materials requested are: site plan with details of where the electrical service will be
located(cletailing the way the building meets SCL requirements maintaining the clearance from SCL
infrastructure) — including how the customer wishes to be served (pad mount, underground vault or in -
building vault transformer), a detailed riser diagram showing the type, size and number of customer
cables coming to the SCL transformer, the size of switch gear, and Load Calcs — even though the cust
does not have a tenant, we stated SCL Engineering needs the perspective tenant loads that may be
needed — looking at the maximum potential cust.
We need a clearly demarcated site plan, elevation plans and a surveyed plan showing that there is a
minimum of 14' clearance between the edge of the building to the closest high voltage primary line
along the customer's property.
We then had a detailed discussion regarding the transformer. The cust suggested a padmount
transformer. Abdu detailed what is required with a padmount transformer — (There is a requirement for
an oil containment system, which the customer has to get designed, signed and stamped by a
PE). Abdu also explained the other options; Padmount transformer, below grade transformer vault and
in -building transformer vault for the customer to decide. The actual design and size to be decided by
the project engineer).
It was stated that SCL will need to know with the final submittal for the project all the details on the
"hard copies" of the drawings. Abdu added that the load calcs can be changed (customer can ask for a
revision of the service) if finalized numbers changed but that there be a cost for changing the loads due
to engineering work completed.
The customer would like to have power by next summer.
Percy L Schlimm CORRECTION
Electrical Service Representative, Senior
Seattle City Light LTR#
206-386-1735
NUV 2 0 2017
E R 1`0 i T YE
SIDE SEWER PERMIT APPLICATION
ALLOW 24148 HOURS FOR ISSUANCE
OWNER INFORMATION I PLEASE COMPLETE
SERVICE ADDRESS:
BILLING ADDRI
For Office Use (Pre-Pennit Coinpkltion)
PERMIT# -7L+4'2
RECEIPT #
ACCOUNT#
ICISS ACCOUNT #
PACER CREDIT CHECK: YES NO
DELINQUENT CHARGES. - 0 &
METRO BILLING START DATE:
DATE OF CONNECTION:
Cirde: RESIDENTIAL / 4XV9EMW / AADU I DADU
OWNER COMMENTS / LEGAL:
PHONE NUMB
.EMAIL ADDRESS: 4N hk a 40111cavvn.&PA
TAX LOT NUMBER2M
For Officd,USe
CHARGES: COMMENTS I LEGAL:
CHARGE IN LIEU OF ASSESSMENT $
GENERAL FACILITY CHARGE $
SYSTEM FACILITY CHARGE $
SWSSD / MIDWAY CHARGE $
UNIT CHARGE $
DEVELOPER EXTENSION PAYBACK $
METRO FORM: YESINO
-PERMITS:
$139.00
SIDE SEWER
$100.00
SIDE SEWER (PRIVATE PUMP)
$150.00
REPAIR (SPOT)
$15.00
REPAIR (TRENCH)
$100.00
CERT. OF FUTURE CONNECTION
$70.00 y"
RIGHT O� WAY PERMIT
ITOTAL CHARGES
RECORDING FEES
IC CONTRACT + LIEN
$139.00
SS CONTRACT + LIEN
$140.00
IC + SS + LIEN
$142.00
TEMP SVC AGREEMENT
$112.00
EASEMENTS (2 PAGES)
$74.00
CERT. OF FUTURE CONNECTION
$73.00
• ULID 41 / $3856.00/5.5%
ITOTAL CHARGES
• ULID 45 / $6400.00/6.0%
1$ -70
CONTRACTPAYMENT
RECORDING FEE
PERMIT FEE
OTHER
• ULID 20 / $875.50
.-III Y UF 1 U AVII
K
• ULID 24 / $3387.00
• ULID 34 / $4335.90
Noy 2 0 2017
• ULID 33 / $7803.00
• CDS / $4875.00
. ERMIT CENTEk
• ULID 43 / $8286.00/5.5%
(2006)
• ULID 41 / $3856.00/5.5%
(2007)
• ULID 45 / $6400.00/6.0%
(2007)
• CDBG (1) / $2000.0012.0% (2012)
• W OF 33 / $3176.0013.0% (2014)
*If residence was billed in ULID prior to UUD 18 (RVSD) or ULID20 (VVSD) no GFC Is collected unlessoutof bilring fbr5 years
Inside ULID boundary or abutting property. Not complete list Check connection charge layer.
C 0 R BE C T 10 N
L T R # —1---
4r
DAVID KEHLE ARCHITECT
1916 SONAIR DR SW
SFATnE WA 98116-1821
PAY
TO THE
ORDER OF
20575
19-2/1250 WA
31107
$
�6v Q --.,POLLARS
Ban f America I-Sor"O"
125000024
FOR 61epx, 0
0020575,12 412SO000241: 000073&BS01131"
City of Tukwila
Department of Community Development.
February 08, 2017
DAVID KEHLE
1913 BONAIR DR SW
SEATTLE, WA 98116
RE: Correction Letter # 2
DEVELOPMENT Permit Application Number D 16-0281
SEBCO DEMOLITION - 11060 TUKWILA INTERNATIONAL BLVD
Dear DAVID KEHLE,
Allan Ekberg, Mayor
Jack Pace, Director
This letter is to inform you of corrections that must be addressed before your development permit can be approved. All
correction requests from each department must be addressed at the same time and reflected on your drawings. I have
enclosed comments from the following departments:
PW - DEPARTMENT: Joanna Spencer at 206-431-2440 if you have questions regarding these comments.
1) Subn-dt copy of Valley View Sewer Capping permit.
2) Applicant shall submit approval from SCL for work under high voltage power lines.
3) Submit approval from ST for work near their guideway.
4) If more than I acre of land is going to be disturbed as result of proposed construction, please obtain (NOI) Notice of
Intent- Construction Storm Water Permit from the Dept. of Ecology.
Please note that this demo permit shall not be issued without the erosion /sediment control permit PW16-0161 which is still
pending. Please contact Barghausen Engineers, PW16-0161 permit applicant to avoid duplication in obtaining approvals
from other agencies.
A hauling permit shall be required for hauling contaminated dirt from the site. The hauling contractor shall submit a haul
route map to Public Works.
Please address the comments above in an itemized format with applicable revised plans, specifications, and/or other
documentation. The City requires that two (2) sets of revised pl4n pages, specifications and/or other documentation be
resubmitted with the appropriate revision block. ' I
In order to better expedite your resubmittal, a'Revision Submittal Sheet'must accompany every resubmittal. I have
enclosed one for your convenience. Corrections/revisions must be made in person and will not be accepted throulih the mail
or by a messenizer service.
If you have any questions, I can be reached at (206)433-7165.
Sincerely,
Rachelle Ripley
Permit Technician
File No. DI 6-0281
6300 Southcenter Boulevard Suite #100 * Tukwila Washington 98188 * Phone 206-431-3670 * Fax 206-431-3665
C 0
*1-tv of Tukwila
Department of Community Development - Jack Pace, Director
October 9, 2017
David Kehle
1916 Bonair Dr. SW
Seattle, WA 98116
RE: Request for Application Extension #2
Permit Number D16-0281
Dear Mr. Kehle,
Allan Ekberg, Mayor
This letter is in response to your written request for an extension to Application Number D 16-028 1. The
Building Official, Jerry Hight, has reviewed your letter and considered your request to extend the above
referenced permit. It has been determined that the City of Tukwila Building Division will be granting an
extension to the permit through April 13, 2018.
If you should have any questions, please contact our office at (206) 431-3670.
Sincerely,
--I
Bill Rambo
Permit Technician
File: Perrr�t No. D 16-0281
Tukwila City Hall - 6200 Southcenter Boulevard - Tukwila, WA 98188 # 206-433-1800 & Website: TukwilaWA.gov
AP "— aq
A
d w..m d
ffdfile
September 20, 2017
City of Tukwila
Request for Ex—nsion # 2 -
Current Expiration Date: 17
Extension Request:
YApproved for days
El Denied (provide explanation)
Ili,naturellnitials
Department of Community Development
6300 Southcenter Boulevard, Suite 100
Tukwila, WA 98118
Attn: Bill Rambo
Re: Sebco Demolition Permit D16-0281
11060 Tukwila International Blvd
Dear Bill,
Thank you for your notification of the permit expiring soon. Back in March, we extended the
permit because of the same reasons as below. I would like to extend that permit again, for
several reasons:
1. The existing tenant is not able to relocate until after their lease is up in November 2017,
and so we cannot do the demolition until they are gone.
2. 1 �m still working with the several other agencies adjacent to the property. I have
submitted the capping application and did receive approval subject to a contractor,
Sound Transit has the full civil package for the new curb cut work and has a couple of
additional questions being answered; city light has given me some info on the wires and
clearances and I am working on the sections for that.
Thus, the reason for the extension. The primary reason is the tenant move out date is still
November.
Thank you for your review and I trust we can obtain the permit extension for the demo permit.
If you have any other concerns or comments, please let me know.
Sincerely,
David Kehle
Cc: Jay Ayers, Jason Hubble
1916 Bonair Drive S.W
Seattle, WA 98116
RECEIVED
CITY OF TUKWILA
OCT 0 5 2017
PERMIT CENTER
(206) 433-8997
fox (206) 246-8369
email: dkehle@dkehlearch.com
8/31/2017
City of Tukwila
Allan Ekberz Mavor
Department of Community Development Jack Pace, Director
DAVID KEHLE
1913 BONAIR DR SW
SEATTLE, WA 98116
RE: Permit Application No. D16-0281
SEBCO DEMOLITION
11060 TUKWILA INTERNATIONAL BLVD
Dear DAVID KEHLE,
In reviewing our current application files, it appears that your permit applied for on 10/13/2016, has not been issued by the City of
Tukwila Permit Center. Per the International Building Code, International Mechanical Code, Uniform Plumbing Code and/or
National Electrical Code every permit application not issued within 180 days from the date of application shall expire and become
null and void. Currently your application has a status of COMMENTS OUT and is due to expire on 10/13/2017.
If you still plan to pursue your project, you are hereby advised to do one of the following:
1) If the plan review is complete for the project and your application is approved, you may pick up the application before
the date of expiration. At the time of permit issuance the expiration date will automatically be extended 180 days.
-or-
2) If the plan review is not completed submit a written request for application extension (7) seven days in advance of the
expiration date. Address your extension request to the Building Official and state your reason(s) for the need to extend your
application.
The Building Code does allow the Building Official to approve one extension of up to 90 days. If it is determined that your extension
request is granted, you will be notified by mail.
In the event that we do not receive your written request for extension or request is denied, your permit application will expire and
your project will require a new permit application, plans and specifications, and associated fees.
Thank you for your cooperation in this matter.
Sincerely,
—&--V —��6j
Bill Rambo
Permit Technician
File No: D 16-0281
6300 Southcenter Boulevard Suite #100 o Tukwila Washington 98188 * Phone 206-431-3670 e Fax 206-431-3665
C 0
itv of Tukwila
Department of Community Development - Jack Pace, Director
April 14, 2017
David Kehle, Architect
1916 Bonair Dr SW
Seattle, WA 98116
RE: Request for Extension #1
Permit Application Number D16-0281
Dear Mr. Kehle,
Allan Ekberg, Mayor
This letter is in response to your written request for an extension to Permit Application 1) 16-028 1. The
Building Official, Jerry Hight, has reviewed your letter and considered your request to extend the above
referenced permit application. It has been determined. that the City of Tukwila Building Division will be
granting an extension to the permit through October 13, 2017.
If you should have any questions, please contact our office at (206) 431-3670.
Sincerely,
V)
Rachellejip
Permit Technician
File: Permit No. D 16-0281
Tukwila City Hall - 6200 Southcenter Boulevard - Tukwila, WA 98188 - 206-433-1800 - Website: TukwilaWA.gov
P—M qLe sk
d d
krhie
March 28, 2017
City of Tukwila
Department of Community Development
6300 Southcenter Boulevard, Suite 100
Tukwila, WA 98118
Attn: Rachell Ripley
Re: Sebco Demolition Permit D16-0281
11060 Tukwila International Blvd
Dear Rachel,
REC'EIVEO
WY OF TUKWILA
APR P, 5 2017
PERMIT CENTER
Thank you for your notification of the permit expiring soon. I would like to extend that permit
for several reasons:
1. The existing tenant is not able to relocate until after their lease is up in Novemeber
2017, and so we cannot do the demolition until they are gone.
2. 1 am still working with the several other agencies adjacent to the property. I have
submitted the capping application and plan to Valley View but no formal answer; Sound
transit now wants the full civil package for the new curb.cut work; city light has given
me some info on the wires and clearances and I am working on the sections for that.
These seem to be on a slow track for reviews. Thus, the reason for the extension.
Thank you for your review and I trust we can obtain the permit extension for both the demo
and the new building. If you have any other concerns or comments, please let me know.
Sincerely,
Request for Extension #
Current Expiration Date:
David Kehle
Extension Request:
Cc: Jay Ayers, Jason Hubb '. le Approved for days
Denied (provide explanation)
Signature/Initials
(206) 433-8997
1916 Bonair Drive S.W fox (206) 246-8369
Seattle, WA 98116 email: dkehle@dkehlearch.com
(0
3/1/2017
City of Tukwila Allan Ekberg, Mayor
Department of Community Development Jack Pace, Director
DAVID KEHLE
1913 BONAIR DR SW
SEATTLE, WA 98116
RE: Permit Application No. D 16-0281
SEBCO DEMOLITION
11060 TUKWILA INTERNATIONAL BLVD
Dear DAVID KEHLE, .
In reviewing our current application files, it appears that your permit applied for on 10/13/2016, has not been issued by the City of
Tukwila Permit Center. Per the International Building Code, International Mechanical Code, Uniform Plumbing Code and/or
National Electrical Code every permit application not issued within 180 days from the date of application shall expire and become
null and void. Currently your application has a status of COMMENTS OUT and is due to expire on 4/13/2017.
If you still plan to pursue your project, you are hereby advised to do one of the following:
1) If the plan review is complete for the project and your application is approved, you may pick up the application before
the date of expiration. At the time of permit issuance the expiration date will automatically be extended 180 days.
-or-
2) If the plan review is not completed submit a written request for application extension (7) seven days in advance of the
expiration date. Address your extension request to the Building Official and state your reason(s) for the need to extend your
application.
The Building Code does allow the Building Official to approve one extension of up to 90 days. If it is determined that your extension
request is granted, you will be notified by mail,
In the event that we do not receive your written request for extension or request is denied, your permit application will expire and
your project will require a new permit application, plans and specifications, and associated fees.
Thank you for your cooperation in this matter.
Sincerely,
Bill Rambo
Permit Technician
File No: DI 6-0281
6300 Southcenter Boulevard Suite #100 9 Tuk,�vila Washington 98188 0 Phone " I
266431-3670 e Fax206-431-3665
"_ P
A ki
d d
O'gle
kec
1_4'06K
November 29, 2016
City of Tukwila
Department of Community Development
6300 Southcenter Blvd, Suite 100
Tukwila, WA 98188
Attn: Mr. Bill Rambo
RE: 11000 Building
11060 Tukwila International Blvd
Development Permit D16-0281
Dear Bill,
I am in receipt of your correction letter 1, dated 11-02-16. Sorry for the delay. The following reflect my
answers to your comments:
Planning:
I have e-mailed directly to Max his questions of 11-08 and have attached a copy to this response.
Public Works:
1. 1 have added the location of both underground and above ground storage tanks for removal. I will
obtain a fire permit for the removal.
2. 1 have added the area of petroleum contamination based on the phase 2 report.
3. 1 have e-mailed the report of phase 2 to Max already. I will forward that to you in an e-mail (very
large report). Phase I will not attach to an e-mail )1500 pages).
4. 1 have shown the location of the sanitary sewer connection needing to be capped and will forward to
Dana at Valley View.
5. 1 am working with City Light on whom to copy the plans to.
6. 1 will submit plans to Sound Transit for work near their guide rail.
I trust these will answer your questions and as I receive approvals from City Light and Sound Transit, I
will forward those to you. Those can remain as conditions of approval. RECEIVED
CITY OF TUKWILA
CORRE TION HOV 30 2016
LTR#!f
David Kehle PLRHIT CENTER
1b [&"W (206) 433-8997
1916 Bonair Drive S.W. fox (206) 246-8369
Seattle, WA 98116 email: dkehle@dkehlearch.com
City of Tukwila
Allan Ekberg, Mayor
Department of Community Development Jack Pace, Director
February 08, 2017
DAVID KEHLE
1913 BONAIR DR SW
SEATTLE, WA 98116
RE: Correction Letter # 2
DEVELOPMENT Permit Application Number D 16-0281
SEBCO DEMOLITION - 11060 TUKWILA INTERNATIONAL BLVD
Dear DAVID KEHLE,
This letter is to inform you of corrections that must be addressed before your development permit can be approved. All
correction requests from each department must be addressed at the same time and reflected on your drawings. I have
enclosed comments from the following departments:
PW - DEPARTMENT: Joanna Spencer at 206-431-2440 if you have questions regarding these comments
1) Submit copy of Valley View Sewer Capping permit.
2) Applicant shall submit approval from SCL for work under high voltage power lines.
3) Submit approval from ST for work near their guideway.
4) If more than I acre of land is going to be disturbed as result of proposed construction, please obtain (NOI) Notice of
Intent- Construction Storm Water Permit from the Dept. of Ecology.
Please note that this demo permit shall not be'issued without the erosion /sediment control permit PW16-0161'which is still
pending. Please contact Barghausen Engineers, PW16-0161 permit applicant to avoid duplication in obtaining approvals
from other agencies.
A hauling permit shall be required for hauling contaminated dirt from the site. The hauling contractor shall submit a haul
route map to Public Works.
Please address the comments above in an itemized format with applicable revised plans, specifications, and/or other
documentation. The City requires that two (2) sets of revised plan pages, specifications and/or other documentation be
resubmitted with the appropriate revision block.
In order to better expedite your resubmittal, a'Revision Submittal Sheet' must accompany every resubmittal. I have
enclosed one for your convenience. Corrections/revisions must be made in person and will not be accepted through the mail
or by a messenger service.
If you have any questions, I can be reached at (206)433-7165.
Sincerely,
Rachelle ipley
Permit Technician
File No. D 16-0281
6300 Southcenter Boulevard Suite #100 * Tukwila Washington 98188 * Phone 206-431-3670 *,-)Fax 206-431-3665
November 29, 2016
City of Tukwila
Department of community Development
6300 Southcenter Blvd, Suite 100
Tukwila, WA 98188
Attn: Mr. Maxwell Baker
RE: 11000 Building
11060 Tukwila International Blvd
SEPA Development Permit D16-0281
Dear Max,
I am in receipt of your e-mail of Nov. 8 requesting additional items relative to the demolition permit and
SEPA. The following reflect my answers to your comments:
1. Need a completed Traffic Concurrency Certificate: This is now attached. How does the existing
traffic get credited back to the new project?
2. The project will comply with the geotechnical report which will accompany the permit submittal and
will be noted on the structural notes.
3. The level one and two environmental reports will be sent via e-mail to both you and to Joanna
Spencer in Public Works as they are extremely long.
4. The correction to the item #9, page 14 of the Environmental check list is attached listing the
additional government approvals being required.
Fire has asked for the transmission lines locations to be on the site plan along the southerly property
line which I will try and show accurately.
Building has commented that the building permit will not be issued until the demolition permit has final
inspections.
I agree to the above and can be conditions of the MDNS.
M
David Kehle
1916 Bonair Drive S.W
Seattle, WA 98116
CORREC ION
RECFIVED
CITY OF TUMILA
NOV 30 2016
PaRMST CENTER
0 *1 91 (206) 433-8997
fax (206) 246-8369
email: dkiahle@dkehlearch.com
City of Tukwila
Allan Ekberg, Mayor
Department of Community Development Jack Pace, Director
November 02, 2016
DAVID KEHLE
1913 BONAIR DR SW
SEATTLE, WA 98116
R I,: Correction Letter # I
DEVELOPMENT Permit Application Number D16-0281
SEBCO DEMOLITION - 11060 TUKWILA INTERNATIONAL BLVD
Dear DAVID KEHLE,
This letter is to inform you of corrections that must be addressed before your development permit can be approved. All
correction requests from each department must be addressed at the same time and reflected on your drawings. I have
enclosed comments from the following departments:
PLANNING DEPARTMENT: MAX BAKER at (206)-431-3683 if you have questions regarding these comments.
SEPA Planned Action will need to be completed before demolition can begjn.
http://www.tukwilawa.gov/wp-content/uploads/DCD-Apps-SEPA-Planned-Action.pdf
PW DEPARTMENT: Joanna Spencer at 206-431-2440 if you have questions regarding these comments.
1) Show location of any above ground or underground storage tank on your site plan. Obtain storage tank(s)
removal permit from Tukwila Fire Dept. @ 206 971-8718.and submit copy to Public Works.
2) Show area of petroleum contamination.
3) Submit copy of Environmental Site Assessment reports mentioned in your SEPA application.
4) Show location of sanitary side sewer capping on your site plan. Submit the demo plan to Mr. Dana Dick, Valley
View Sewer District at 206 433-1864 for sewer capping permit approval.
3) Submit Seattle City Light approval for working under or in the immediate vicinity of high voltage power lines.
4) Submit copy of Sound Transit permit for working under or in the vicinity of the Sound Transit guideway.
Contact Nancy Clark at (206) 689-4936 or Angie Marmion at (206) 398-5430 to start the process.
Please address the comments above in an itemized format with applicable revised plans, specifications, and/or other
documentation. The City requires that two -(2) sets of revised plan pages, specifications and/or other documentation be
resubmitted with the appropriate revision block.
In order to better expedite your resubmittal, a'Revision Submittal Sheet'must accompany every resubmittal. I have
enclosed one for your convenience. Corrections/revisions must be made in person and will not be accepted through the mail
or by a messen-ger service.
If you have any questions, I can be reached at 206-431-3655.
Sincerely,
Bill Rambo
Permit Technician
File No. D 16-0281
6300 Southcenter Boulevard Suite #100 o Tukwila Washington 98188 9 Phone 206-431-3670 9 Fax 206-431-3665
PERMIT COORD COPY
PLAN REVIEW/ROUTING SLIP
PERMIT NUMBER: D16-0281
DATE: 10/22/17
PROJECT NAME: SEBCO DEMOLITION
SITEADDRESS:- 11060 TUKWILA INTERNATIONAL BLVD
Original Plan Submittal Revision # before Permit Issued
x Response to Correction Letter # 2 Revision # after Permit Issued
DEPARTMENTS:
Building Division El Fire Prevention Planning Division E]
Pul5lic Works Structural El Permit Coordinator
PRELIMINARY REVIEW: DATE: 10/28/17
Not Applicable El Structural Review Required
(no approvallreview required)
REVIEWERc6 INITIALS: DATE:
APPROVALS OR CORRECTIONS: DUE DATE: 12/26/17
Approved
0
Corrections Required El
(corrections entered in Reviews)
Notation:
Approved with Conditions
Denied
(ie: Zoning Issues)
REVIEWERc6 INITIALS: DATE:
Permit Center Use Only
CORRECTION LETTER MAILED:
Departments issued corrections: Bldg El Fire El PIng E] PW Staff Initials:
12/18/2013
PERMIT COORD CON
PLAN REVIEW/ROUTING SLIP
PERMIT NUMBER: D16-0281
DATE: 11/30/16
PROJECT NAME: SEBCO DEMOLITION
SITE ADDRESS: 11060 TUKWILA INTERNATIONAL BLVD
Original Plan Submittal Revision # before Permit Issued
X Response to Correction Letter # I Revision # after Permitlssued
DEPARTMENTS:
Ran oDivisi?�l
Building Division F-1
Fire Prevention
P ing
jj� MW 'i
Public Works
Structural
Permit Coordinator
PRIELIMINARY RIEVIEW:
DATE: 12/01/16
Not Applicable F-1
Structural
Review Required
(no approvallreview required)
REVIEWER'S INITIALS:
DATE:
APPROVALS OR CORRECTIONS:
DUE DATE: 12/29/16
Approved F1
Approved with Conditions
F-1
Corrections Required F]
Denied
0
(corrections entered in Reviews)
(ie: Zon ing Issues)
Notation:
REVIEWER'S INITIALS: DATE:
Perinit Center Use Only
CORRECTION LETTER MAILED:
Departments issued corrections: Bldg 0 Fire El Ping El PW ld Staff Initials:
12/18/2013
rIERMIT COORD COR
PLAN REVIEW/ROUTING SLIP
PERMIT NUMBER: D16-0281 DATE: 10/13/16
PROJECT NAME: SEBCO DEMOLITION
SITE ADDRESS: 11060 TUKWILA INTERNATIONAL BLVD
X Original Plan Submittal Revision # before Permit Issued
Response to Correction Letter # Revision # after Permit Issued
DEPARTMENTS:
ki I to�j� W � pu mp�,
Builc MingDivisioh 10 Fire Prm Im Planning Division
'z cowp— W—)jmp
Public Works 0 Structural El Permit Coordinator
PRELIMINARY REVIEW: DATE: 10/18/16
Not Applicable F]
(no approvallreview required)
REVIEWER'S INITIALS:
Structural Review Required 1:1
DATE:
APPROVALS OR CORRECTIONS: DUE DATE: 11/15/16
Approved Approved with Conditions F-1
Corrections Required N7
(corrections entered in Reviews)
REVIEWER'S INITIALS:
Denied F-1
(ie: Zoning Issues)
DATE:
Permit Center Use Only
CORRECTION LETTER MAILED:
Departments issued corrections: Bldg E] Fire E] Plng74V PW�5 Staff Initials:
12/18/2013
City of Tukwila
Department of Community Devel
6300 Southcenter Boulevard, Suite #100
Tukwila, Washington 98188
Phone: 206-431-3670
Web site: http://www.TukwilaWA.gov
REVISION
SUBMITTAL
Revision submittals must be submitted in person at the Permit Center.
Revisions will not be accepted through the mail, fax, etc.
Date: Plan Check/Permit Number: D16-0281
Response to Incomplete Letter #
Response to Correction Letter # — 2
Revision # after Permit is Issued
Revision requested by a City Building Inspector or Plans Examiner
Deferred Submittal #
Project Name: SEBCO DEMOLITION
Project Address: 11060 TUKWILA
Contact Person:
Summary of
ATIONAL BL
Phone Number: Im —43 -3 —
RECEIVED
CITY OF TUKWILA
NOV 2 0 210,167
PERMIT CENTER
SheetNumber(s): 2 - 6t A. 62- VAOS C-u-6(ae40007
"Cloud" or highlight all areas of revision
Received at the City of Tukwila Permit Cet
F� Entered in TRAKiT on
C:\Usci,s\Racholle-R\I)csktop\Revision Submittal Form - D]6-0305.doc
Revised: August 2015
n
City of Tukwila
Department of Community Development
6300 Southcenter Boulevard, Suite #100
Tukwila, Washington 98188
Phone: 206-431-3670
Fax: 206-431-3665
Web site: http://�ww.ci.tukwila.wa.us
REVISION SUBMITTAL
Revision submittals must be submitted in person at the Permit Center. Revisions will not be accepted through
the mail, fax, etc.
Date: �11V- IV Plan Check/Permit Number:
F� Response to Incomplete Letter #
F� Response to Correction Letter # I
F-1 Revision # after Permit is Issued
F-1 Revision requested by a City Building Inspector or Plans Examiner
Project Name: Sebco Demolition
Project Address: 11060 Tukwila Intemational Blvd
D16-0281
ZU -5 5 —
. 1 -4 -Mq4
Contact Person . VQ �OM Phone Number: IP6
Summary of Revision:
— 46 W?F-M-M-e
RECEIVED
CITY OF TUKWILA
NOV 3 0 2016
PERM CENTER
Sheet Number(s): T A — WIZI-Ille
"Cloud" or highlight all areas of revision including date of revisiop
Received at the City of Tukwila Permit Center by:
k—Entered in TRAKiT on
\applications\forms-applications on line\revision submittal
Created: 8-13-2004
Revised:
POE CONSTRUCTION INC
1-1 arn 0, F.Spahol, Contact
Safety & Health Claims & Insurance
Aft Washington State Department of
4L.j Labor & Industries
Page I of 3
ISearch L&I
A -Z Index I I ell) My L&I
Workplace Rights Trades & Licensing
I POE CONSTRUCTION INC I
Owner or tradesperson PO BOX 1838
AUBURN, WA 98071-1838
Principals 253-833-2400
WILLIAMS, WAYNE WALTER, PRESIDENT KING County
PETERSON, ALAN DONALD, VICE
PRESIDENT
POE, CHARLES EARL, SECRETARY
POE, FRED W
(End: 0 1 /0 1 /1980)
CLARK, DENNIS M, CHIEF OPERATING
OFFICER
(End: 01/16/2006)
FRY, KYLE R, TREASURER
(End: 02/18/2010)
POE, CHARLES E, PRESIDENT
(End: 04/10/2015)
WILLIAMS, WAYNE W, VICE PRESIDENT
(End: 04/10/2015)
PETERSON, ALAN DONALD, SECRETARY
(End: 04/10/2015)
REIFSCHNEIDER, CAROL M, SECRETARY
(End: 07/09/2003)
WELFRINGER, SUZANNE M, TREASURER
(End: 07/09/2003)
Doing business as
POE CONSTRUCTION INC
VVA UBI No. Business type
171 004362 Corporation
Governing persons
ALAN
PETERSON
CHARLES POE;
WAYNE WILLIAMS;
KYLE RAY FRY;
ILicense I
Verify the contractors active registration / license / certification (depending on trade) and any past violations.
Goln.sbructi,qn 9pri.1tractor. Active.
Meets current requirements.
License specialties
GENERAL
License no.
POECOI*247QZ
Help us improve
https:Hsecure.Ini.wa.gov/verify/Detail.aspx?UBI=171004362&LIC=POECOI*247QZ&SAW= 01/08/2018
VICINITY Mi
Asphalt Pavement
I
CAP EXISTING 5EWERAT MANHqLE AND
PROVIDE FOR FUTURE RE USE NEW
15UILDING I
C-) /"
61
'a- '�- �b
0
4�s Q3
Q
a A!�
PWR
VAULT
6 CS
z�
"
+
0
Ir t!
G
Cl)
V6
"Ox
00
6
!k
7 Z
Z�' -
? b1F I
A P H A L T A R E A
S
These plans have been reviewed by the Public
Works Department for conformance with current
City standards. Acceptance is subject to errors and
omissions which do not authorize violations of
adopted standards or ordinances. The responsibility
for the adequacy of the design rests totally with the
Se
APPROX. LOCATION OF LU5E OIL PLUME designer. Additions, deletions or revisions to these
APPROX. 5' DEEP TO 5F_ REMOVED AND drawings after this date will void this acceptance
REMEDIATEID. SEE LEVEL 2 A55ESMENT and will require a resubmittal of revised dmwings �_u
for subsequent approval.
Final acceptance i b ct to field inspection by WON=
S S ie
the Publi Works util ties inspector.
Date: By -
REMOVE EX15TING 5UILDINGS, STRUCTURES,
_R
FOUNDATIONS, ASPHALT, ETC. TO 5RING ANSIT GUIDEWAY EASEMENT
M
THE SITE TO A GRADED SU5 GRADE PER FOR CENTRAL PUGET SOUND REGIONA
ENGINEERING DRAWINGS WITH TRANSIT AUTHORITY. REC. NO. 20040
CIVIL E
TEMPORARY ER05ION CONTROL. 10' SANITARY SEWER EASEMENT
0
GRANTED TO ROBBLEE INVESTMENT CO.
a,
REC. NO. 8412210387 W
z
SERVICE AND PARTS DEPT SIGN
TRUCK SIGN A S P H A L T A R E A
YD'3 CB
RIM=15.6' RIM=15.9' - VALVE)
EXI NG GAS MAIN
sum
6 PARKING STALLS
ARKING SIGN Bom
STALLS
A S P H A L T A R E A
7,
,7 1^
Building
4e
conc. Pavement
COD
Water Line
_W—
—G—
Gas Line
Sanitary Sewer Line
—SS—
—SD—
Storm Drain
Underground Power
—P
—T—
Underground Telephone
—TV —
Underground Television
0
Ir t!
G
Cl)
V6
"Ox
00
6
!k
7 Z
Z�' -
? b1F I
A P H A L T A R E A
S
These plans have been reviewed by the Public
Works Department for conformance with current
City standards. Acceptance is subject to errors and
omissions which do not authorize violations of
adopted standards or ordinances. The responsibility
for the adequacy of the design rests totally with the
Se
APPROX. LOCATION OF LU5E OIL PLUME designer. Additions, deletions or revisions to these
APPROX. 5' DEEP TO 5F_ REMOVED AND drawings after this date will void this acceptance
REMEDIATEID. SEE LEVEL 2 A55ESMENT and will require a resubmittal of revised dmwings �_u
for subsequent approval.
Final acceptance i b ct to field inspection by WON=
S S ie
the Publi Works util ties inspector.
Date: By -
REMOVE EX15TING 5UILDINGS, STRUCTURES,
_R
FOUNDATIONS, ASPHALT, ETC. TO 5RING ANSIT GUIDEWAY EASEMENT
M
THE SITE TO A GRADED SU5 GRADE PER FOR CENTRAL PUGET SOUND REGIONA
ENGINEERING DRAWINGS WITH TRANSIT AUTHORITY. REC. NO. 20040
CIVIL E
TEMPORARY ER05ION CONTROL. 10' SANITARY SEWER EASEMENT
0
GRANTED TO ROBBLEE INVESTMENT CO.
a,
REC. NO. 8412210387 W
z
SERVICE AND PARTS DEPT SIGN
TRUCK SIGN A S P H A L T A R E A
YD'3 CB
RIM=15.6' RIM=15.9' - VALVE)
EXI NG GAS MAIN
sum
6 PARKING STALLS
ARKING SIGN Bom
STALLS
A S P H A L T A R E A
7,
,7 1^
6S,
'/WMH
RIM=15.2
ox
ASP H A L T A REA A S P H A L T A REA
CB
RIM=17.6'
CB
N 89*18'52" 646-64' EYJSnNG GAq MAIN EIRIM=17.4'
CURB
cam
'e -
T 7
A S P H A L T A R E A CRASH BARRIER \7MM BWW CRASH
"im
18 PARKING i4T L75 CB, SCO, HOLDING TANK,
A S P H A L T A R E A
AND SEM LINE PERx,,"*
SIDE SEWER INFO, PROVIDED BY
top Soo
VAL VUE SEWER DISTRICT, PERMIT NO. 03498
FOUND 'b -
'J A R E A EP
_gx HIGH Pyff)PW F CE W1 RAZOR CMCER71NA ON TOP G R A V EL
401 4�A L 9GX
G\ A\J P\ A\E A
N,
'A
ICB 4.- 780 GAL HOLDIN CT\
A
1-TTANK % % \
OIL WATER SEPARATO I TO BE REMOVED VATH kv C'
APPROXIMATE LOCATION FIRE DEPARTMENT PERMI�, _- i� -
CL I
9 PARIONG STALLS
I TO 5E REMOVED WTIH 1P.
xop
=RMIT
FIRE DEPARTMENT Pr 55' PERMANENT EASEMENT AREA
FOR ELECTRICAL TRACTION POWER
SUBSTATION TO CENTRAL PUGET
-- — --------- — - 4-A
------- SOUND REGIONAL TRANSIT AUTHORITY
T REC. NO. 200440517003078
W_LARDSJ(TyPV)
I
NO A S P H A L T A R
ASPHALT A'R E A
BOLLARql: a
YDP REMOVE OMMO ASPHALT �0
CO
R1IM-17.9 SEE CIVIL PLANS 1P
_0
REMOVE EXISTING ASPHALT A S P H A L T A R E A
n SEE cIVIL PLANS A S P H A L T A R E A V '�4rS
ASPHALT A R E A T
rx- T .--x
I I ,
x A S P H A L T A R E A
o�x- x -W S70 k—. I I A
INI IINSERTS
A S P H A L T A R E A p
RIM=16.7'
C3
CB Cap
--,,R I M 16.6'
PARIONG STALLS 10 TRUCK PARIONG STALLS
A S P H A L T A R E A
(_8" SAN. SEwER roRcE MAIN 170 9
_SS--QI _SS F, 69
1; - im "I ___l.
�ob. 3' H16i SINGLE STRAND CAME Ssi�—�7-!41- W
b --�CONCRETE EXTRUDED CUR
r4l I'-- -W 48_:_WATER MAIN CONCRETE EXTRUDED CURB QN(
-70 -1-1 . I W —W
N8918' low 60' WIDE CONDEMNED BY THE CITY OF SEATTLE
=15.0' 4-�" - 0. fe,
Q FOR PIPE LINE RIGHT OF WAY UNDER KING COUNTY 10
SUPERIOR COURT CAUSE NO. 121648, PURSUANT
T6 CITY OF SEATTLE ORDINANCE NO. 37022. 4 3
4ATH
W
1p��
11C
.0-
A S P H A L T A R E A '90
A S P H A L T A R E A
ASPHALT A R E A Op %
3 TRUCK pARMG
ASPHALT AREA ENDS STALLS
7
T FENCE (TYP)
11 TRUCK PARION STALLS
-F SD MH W/ GRATE
RIM=19.9'
ed. 011-1
20289
—8
wbxr�ww� / I n —X
q�9?1
D11 —b- I
ITC
127 CO C PIP
CENTERLINE
OULU QURS
A'DUAI TR D D CURB
W ER QW -OF
SPEED LIMIT C8
SIGN 35 RIM=98.1'
PLANNING APPROVED
No changes can be made. to these
plans without approval from the
Planning Division of DCD
Approved f3y.-Ii-
L)n1tv
of Tultmia
BUILDIM Divisim
REVISIONS
No changes shall be made to the scope
of work without prior approval of
. Tukt!vila Building Division.
NOTE: Revisions W11 require a new plan submittal
and may include additional plan review fees.
F -REVIEWED FOR
CODE COMPLIANCE
APPROVED
DEC 0 6 2017
*'r W
city of Tukwila
"iANI
.e:
RECENED
DEC 0 1 2016
-WKWILA
PUBLIC WORKS CORRECTION
DEMO NOTE6: LTR
1. D15CONNECT ALL UTILITIES TO THE
EXISTING IBUILDING AND STRUCTURES,,
2. CAP ALL EXISTING UTILITIES I P ER RECEIVED
!.�:' �. I , CITY OF TUKWIL
GOVERNING AGENCY AT T
LINE NOV 30 2016
3. RECYCLE AS MUCH AS P9.SSIR�E
PERMIT CENTEI
ASPHALT, CONCRETE, ETC�,'-
SEE CIVIL ENGINEERING fz��,"AN FOR
TEMPORARY ERROSION C� P, GRADr=
AND FILL
FOR FUTRUE CREDIT ON PLUMP, Fl�
;I <TURES,
THIS IBUILDING HAS (o TOILET�," U INALS, (o SINKS,
3 FLOOR DRAINS, AND 4 HP�P, �I-P55.
lu
(L (L
LU
z
0 W
LL
\\VVKST-4\IDocurnents\CAD\2O15\.,J 5-03 SE.BC9 HOR!70N FORD\CD's 09-22-16\CD's 09-22-16\DEMO PLAN.dwg, DEMO
4e
COD
A S P H A L T A R E A
CY
N201 2'23"E
N56*11'53"W
16.1 �'
N89'18'52"E
28.68 NNRI�
W 0
A S P H A L T A R E A
6S,
'/WMH
RIM=15.2
ox
ASP H A L T A REA A S P H A L T A REA
CB
RIM=17.6'
CB
N 89*18'52" 646-64' EYJSnNG GAq MAIN EIRIM=17.4'
CURB
cam
'e -
T 7
A S P H A L T A R E A CRASH BARRIER \7MM BWW CRASH
"im
18 PARKING i4T L75 CB, SCO, HOLDING TANK,
A S P H A L T A R E A
AND SEM LINE PERx,,"*
SIDE SEWER INFO, PROVIDED BY
top Soo
VAL VUE SEWER DISTRICT, PERMIT NO. 03498
FOUND 'b -
'J A R E A EP
_gx HIGH Pyff)PW F CE W1 RAZOR CMCER71NA ON TOP G R A V EL
401 4�A L 9GX
G\ A\J P\ A\E A
N,
'A
ICB 4.- 780 GAL HOLDIN CT\
A
1-TTANK % % \
OIL WATER SEPARATO I TO BE REMOVED VATH kv C'
APPROXIMATE LOCATION FIRE DEPARTMENT PERMI�, _- i� -
CL I
9 PARIONG STALLS
I TO 5E REMOVED WTIH 1P.
xop
=RMIT
FIRE DEPARTMENT Pr 55' PERMANENT EASEMENT AREA
FOR ELECTRICAL TRACTION POWER
SUBSTATION TO CENTRAL PUGET
-- — --------- — - 4-A
------- SOUND REGIONAL TRANSIT AUTHORITY
T REC. NO. 200440517003078
W_LARDSJ(TyPV)
I
NO A S P H A L T A R
ASPHALT A'R E A
BOLLARql: a
YDP REMOVE OMMO ASPHALT �0
CO
R1IM-17.9 SEE CIVIL PLANS 1P
_0
REMOVE EXISTING ASPHALT A S P H A L T A R E A
n SEE cIVIL PLANS A S P H A L T A R E A V '�4rS
ASPHALT A R E A T
rx- T .--x
I I ,
x A S P H A L T A R E A
o�x- x -W S70 k—. I I A
INI IINSERTS
A S P H A L T A R E A p
RIM=16.7'
C3
CB Cap
--,,R I M 16.6'
PARIONG STALLS 10 TRUCK PARIONG STALLS
A S P H A L T A R E A
(_8" SAN. SEwER roRcE MAIN 170 9
_SS--QI _SS F, 69
1; - im "I ___l.
�ob. 3' H16i SINGLE STRAND CAME Ssi�—�7-!41- W
b --�CONCRETE EXTRUDED CUR
r4l I'-- -W 48_:_WATER MAIN CONCRETE EXTRUDED CURB QN(
-70 -1-1 . I W —W
N8918' low 60' WIDE CONDEMNED BY THE CITY OF SEATTLE
=15.0' 4-�" - 0. fe,
Q FOR PIPE LINE RIGHT OF WAY UNDER KING COUNTY 10
SUPERIOR COURT CAUSE NO. 121648, PURSUANT
T6 CITY OF SEATTLE ORDINANCE NO. 37022. 4 3
4ATH
W
1p��
11C
.0-
A S P H A L T A R E A '90
A S P H A L T A R E A
ASPHALT A R E A Op %
3 TRUCK pARMG
ASPHALT AREA ENDS STALLS
7
T FENCE (TYP)
11 TRUCK PARION STALLS
-F SD MH W/ GRATE
RIM=19.9'
ed. 011-1
20289
—8
wbxr�ww� / I n —X
q�9?1
D11 —b- I
ITC
127 CO C PIP
CENTERLINE
OULU QURS
A'DUAI TR D D CURB
W ER QW -OF
SPEED LIMIT C8
SIGN 35 RIM=98.1'
PLANNING APPROVED
No changes can be made. to these
plans without approval from the
Planning Division of DCD
Approved f3y.-Ii-
L)n1tv
of Tultmia
BUILDIM Divisim
REVISIONS
No changes shall be made to the scope
of work without prior approval of
. Tukt!vila Building Division.
NOTE: Revisions W11 require a new plan submittal
and may include additional plan review fees.
F -REVIEWED FOR
CODE COMPLIANCE
APPROVED
DEC 0 6 2017
*'r W
city of Tukwila
"iANI
.e:
RECENED
DEC 0 1 2016
-WKWILA
PUBLIC WORKS CORRECTION
DEMO NOTE6: LTR
1. D15CONNECT ALL UTILITIES TO THE
EXISTING IBUILDING AND STRUCTURES,,
2. CAP ALL EXISTING UTILITIES I P ER RECEIVED
!.�:' �. I , CITY OF TUKWIL
GOVERNING AGENCY AT T
LINE NOV 30 2016
3. RECYCLE AS MUCH AS P9.SSIR�E
PERMIT CENTEI
ASPHALT, CONCRETE, ETC�,'-
SEE CIVIL ENGINEERING fz��,"AN FOR
TEMPORARY ERROSION C� P, GRADr=
AND FILL
FOR FUTRUE CREDIT ON PLUMP, Fl�
;I <TURES,
THIS IBUILDING HAS (o TOILET�," U INALS, (o SINKS,
3 FLOOR DRAINS, AND 4 HP�P, �I-P55.
lu
(L (L
LU
z
0 W
LL
\\VVKST-4\IDocurnents\CAD\2O15\.,J 5-03 SE.BC9 HOR!70N FORD\CD's 09-22-16\CD's 09-22-16\DEMO PLAN.dwg, DEMO
POLE AT INTERNATION AL
NO IBUILDING
Lu
w
z
LL
-1
(L
1—
w
HIGH PC
z
14' RAE)
(Z
r;
III
n
POLE AT INTERNATION AL
NO IBUILDING
Lu
w
z
LL
-1
(L
1—
-1
HIGH PC
14' RAE)
(Z
r;
—O�
)WE L IN
lu
US LE NCE
NEXT HI
HIGH POWER LINE
WRADIU5 (fLE NGE
3H POW R LINE
'NEXT HIGH OW R LINE
14'RADIUS CLEARANCE
(p
61
NEXT HIGH POWER LINE
17�r
cq ct)
POLE AT INTERNATION AL
NO IBUILDING
FOLE/WIRE
SCALE: 1116" = V—Oil
6 TO 5IJ
tu
Lu
0
r2 Ile
CL
JII
FF 20JI
EX. AADEJ
MID POLE
kl�
IN
a
HIGH POWER INE
14'RAIDIU5 C EAS
J11 NEXT HIGH wrz�
LINE
lu
HIGH POWER NI
14' RAE) I US C A
901-2111 //1' NEXT HIGH P �E
V15
0
cq
(q
FF 2 0.5
W_ _'l_
EX. GRADEI i�'7
MID SPAN
Lu
Lu
w
z
z
-1
(L
1—
-1
w
(Z
(Y_
)WE L IN
lu
US LE NCE
HIGH POWE LIN
HIGH POWER LINE
WRADIU5 (fLE NGE
3H POW R LINE
'NEXT HIGH OW R LINE
14'RADIUS CLEARANCE
cl)
61
NEXT HIGH POWER LINE
17�r
cq ct)
FF 10
EX. GRADE
MID SPAN
NO POLE
FOLE/WIRE
SCALE: 1116" = V—Oil
6 TO 5IJ
tu
Lu
0
r2 Ile
CL
JII
FF 20JI
EX. AADEJ
MID POLE
kl�
IN
a
HIGH POWER INE
14'RAIDIU5 C EAS
J11 NEXT HIGH wrz�
LINE
lu
HIGH POWER NI
14' RAE) I US C A
901-2111 //1' NEXT HIGH P �E
V15
0
cq
(q
FF 2 0.5
W_ _'l_
EX. GRADEI i�'7
MID SPAN
Lu
rA� POLE AT 112tW
\1DI
It
RECEIVED
NOV 2 2 2017
TUKWILA
PUBLIC WORKS
RECEIVED
CORRECTION CITY OF TUKWILA
LTR# —2w— Nuv 2 0 2017
PERMIT CENI*ER
coop
C:\Docu-fteTts aTd Seti-fosk DAM-&
mz
0
F-1
F -i
Z
Iy
F -i
c)
c)
v_-1
Lu
z
-1
(L
1—
-1
(Z
(Y_
lu
HIGH POWER LINE
—INE
14'RADIUS CLEARANCE
61
NEXT HIGH POWER LINE
17�r
CA
m
FF 20.51
EX.GRADE
rA� POLE AT 112tW
\1DI
It
RECEIVED
NOV 2 2 2017
TUKWILA
PUBLIC WORKS
RECEIVED
CORRECTION CITY OF TUKWILA
LTR# —2w— Nuv 2 0 2017
PERMIT CENI*ER
coop
C:\Docu-fteTts aTd Seti-fosk DAM-&
mz
0
F-1
F -i
Z
Iy
F -i
c)
c)
v_-1
NEW CONCRETE 51 WALK AND CUR5
AND GIJTTER, sE y
51 W,
-UR5
ASPH ALT AREA A S P
TING GAS MAIN 2—GAS VALVES N 89018'52" W
G G
� POURED IN PLACE CUR5
ON PROPERTY LINE
.Z5 T
136a.51=110.51 11 -It 25 0
0 IV-
Pl\*
C'v
(o' 20'
'ot
%7//
& c: HI
'CIV 'v I
0'5UILDI
SET15AC Is 50, H.C. RAMPS AND 5IGNAGE
SEE 5P-3
Xz (P 50,
101*.< 5'LANDS A -00'
4,Z 7/ 0 1'51DEWALK
15 DOCK DOORS
LANDSCAP L
1 0 -
A
Fli
5.02 A(
0
A
C'V
C121
v CO
* co
co
A S P H A L T A R E A
jr
0
-7-t C4.)4
cid
*t 4z
ci NO,
PP
A S P H A L T A R E A
PP N201 2'23"E
c) N56*1 1'53"W N89*1 8'52"E
28.68'
W BO E A
Wv
Z;� 1�
is CO
CZ
Z'
'��RETE EXTRUDED CURB
WMH C)
R1M=1 5.2'9---� W
N89*18'52"W
CD
r10
LUMINAIRE
60' WIDE CONDEMNED BY THE CITY OF SEATTLE
FOR PIPE LINE RIGHT OF WAY UNDER KING COUNTY
SUPERIOR COURT CAUSE NO. 121648, PURSUANT
TO CITY OF SEATTLE ORDINANCE NO. 37022.
F\ C- U. IN U. L)t I Z- I U J 0
c
0
-50 1
DUMPSTER ENCLOSURE 5' ERMANENT EASEMENT AREA
SEE la/5�-3 F R LECTRICAL TRACTION POWER
STATION TO CENTRAL PUGET
tOUND EGIONAL TRANSIT AUTHORITY
A S P H A L T A R E A REC. NO. 200440517003078
in 0RIVE INAAMI
1 413'
3 HOUR FRE WALL
TA5LE 106.4
MAX 25% CF WALL CAN
5E RATED 3 HOUf;Z
OPENING (106-54116-511
OVEF
5ULc
4.13
OFF
&.41
ffvwEirm
MD141S)
70-59
-1 'A �))
646-64' EXISTING GAS MAIN
G G G
-�Q
TRUCK LOAD ING
130' MIN. 24'
6L
CN
18, (01 111 2
IJ -
Ln
N05E OF 65' TRACTER TRAILER HCqHC
t
H.C. RAMPS AND 5IGNAGE
SEE SD -3 401 0
51DEWAL
01
0. 00�
13 DOCK DOORS -Ir- 7-
4ND5CAPE 3� r
121 *-w-�
VO\A
0.
TENA�"WO -0�0
do
.130
MAX. 12,055 5F
SURVEY
r -Ir m W V) y
00 00
I I z
T-
ALL It 04 V)
0 e-1111-1% <
(c) (0 z
oo
01.
0 Ld
M -i
1-- 00
LLI
z
0 x
m < LLJ
80, co-) 0- LL- V) 0)
FIRE DEPARTMENT ACCESS
DOORS AT 100'O.C. 0
FIRE DEPARTMENT KNOX 5OX
(00 _M\4\
ff 0I
E�' LANID6CAPE -"��20' 5UILC)ING
ID FRONT 51FT5Ac<
i -n TRANer-ORME-R ----=77-:: ) . ........
j 2 j -Q�� 87*15 46 E PID x
IL
—W—N87*41'10"W W 110111.
W—
POWER POLE WITH SWITCH ATER BLOW—OF
SOY TH 11 2TH STREET M351418)- FOWER,POLE WITH WITCH
AND CONDUITS FO NPER
ADD CONDUIT FOR . 1. 1- k"" 1, m �4
PRELIM 511
NORTH SCALE: I" = -30'
08-05-16
013-22-1(o
AN 51X
R ExPANc) EXISTVG CURIB C)
CUT TO THE 50 H C)
Rr=MOVE RAMP E X.
CUR5 CU7��
RECEIVED
EP CITY OF TUKWILA
S 0 I'M 2 0 2017 E
PERMIT CENTER
CADocuments and Settings\All Users\Documents\CAD\2015\1 5-03 SEBCO HORIZON FORD\CD'S REV 08-14-17\SD-1,SD-3,Al-A7,El.dwg, poles plan, 11/20/2017 10:54:45 AM
TENANT
ONE
65.21ATA
2c343I,OFFr2.44v
25,all 8F
2 HOUR WALL
N'e
TA5LE 601
STA
-
16201
®r
OFF
5h5
A S P H A L T A R E A
STA
OFF
eft Ila C14
0
0
GA
c2-
48" WATER MAIN W
CONCRE 8
—
60' WIDE CONDEMNED BY THE CITY OF SEATTLE
FOR PIPE LINE RIGHT OF WAY UNDER KING COUNTY
SUPERIOR COURT CAUSE NO. 121648, PURSUANT
TO CITY OF SEATTLE ORDINANCE NO. 37022.
F\ C- U. IN U. L)t I Z- I U J 0
c
0
-50 1
DUMPSTER ENCLOSURE 5' ERMANENT EASEMENT AREA
SEE la/5�-3 F R LECTRICAL TRACTION POWER
STATION TO CENTRAL PUGET
tOUND EGIONAL TRANSIT AUTHORITY
A S P H A L T A R E A REC. NO. 200440517003078
in 0RIVE INAAMI
1 413'
3 HOUR FRE WALL
TA5LE 106.4
MAX 25% CF WALL CAN
5E RATED 3 HOUf;Z
OPENING (106-54116-511
OVEF
5ULc
4.13
OFF
&.41
ffvwEirm
MD141S)
70-59
-1 'A �))
646-64' EXISTING GAS MAIN
G G G
-�Q
TRUCK LOAD ING
130' MIN. 24'
6L
CN
18, (01 111 2
IJ -
Ln
N05E OF 65' TRACTER TRAILER HCqHC
t
H.C. RAMPS AND 5IGNAGE
SEE SD -3 401 0
51DEWAL
01
0. 00�
13 DOCK DOORS -Ir- 7-
4ND5CAPE 3� r
121 *-w-�
VO\A
0.
TENA�"WO -0�0
do
.130
MAX. 12,055 5F
SURVEY
r -Ir m W V) y
00 00
I I z
T-
ALL It 04 V)
0 e-1111-1% <
(c) (0 z
oo
01.
0 Ld
M -i
1-- 00
LLI
z
0 x
m < LLJ
80, co-) 0- LL- V) 0)
FIRE DEPARTMENT ACCESS
DOORS AT 100'O.C. 0
FIRE DEPARTMENT KNOX 5OX
(00 _M\4\
ff 0I
E�' LANID6CAPE -"��20' 5UILC)ING
ID FRONT 51FT5Ac<
i -n TRANer-ORME-R ----=77-:: ) . ........
j 2 j -Q�� 87*15 46 E PID x
IL
—W—N87*41'10"W W 110111.
W—
POWER POLE WITH SWITCH ATER BLOW—OF
SOY TH 11 2TH STREET M351418)- FOWER,POLE WITH WITCH
AND CONDUITS FO NPER
ADD CONDUIT FOR . 1. 1- k"" 1, m �4
PRELIM 511
NORTH SCALE: I" = -30'
08-05-16
013-22-1(o
AN 51X
R ExPANc) EXISTVG CURIB C)
CUT TO THE 50 H C)
Rr=MOVE RAMP E X.
CUR5 CU7��
RECEIVED
EP CITY OF TUKWILA
S 0 I'M 2 0 2017 E
PERMIT CENTER
CADocuments and Settings\All Users\Documents\CAD\2015\1 5-03 SEBCO HORIZON FORD\CD'S REV 08-14-17\SD-1,SD-3,Al-A7,El.dwg, poles plan, 11/20/2017 10:54:45 AM