HomeMy WebLinkAboutSpecial 2020-12-14 Item 2E - Contract - 2021 Overlay and Repair Program Design with KPG Inc for $149,912ITEM INFORMATION
STAFF SPONSOR: SCOTT BATES ORIGINAL AGENDA DATE: 12/14/20
AGENDA ITEM TITLE 2021 Overlay and Repair Program
Design Consultant Selection and Agreement
CATEGORY Discussion Motion Resolution Ordinance Bid Award Public Hearing Other
Mtg Date Mtg Date 12/14/20 Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date
SPONSOR Council Mayor HR DCD Finance Fire TS P&R Police PW Court
SPONSOR’S
SUMMARY
Three engineering firms were evaluated from the MRSC Consultant Roster to provide
design services for the 2021 Overlay and Repair Program. KPG has performed well
regarding design and construction management services and also demonstrates the
knowledge and understanding that matches the City's expectations. Council is being asked
to approve the design contract with KPG, Inc. for the 2021 Overlay and Repair Program in
the amount of $149,912.00.
REVIEWED BY Trans&Infrastructure CommunitySvs/Safety Finance Comm. Planning/Economic Dev.
LTAC Arts Comm. Parks Comm. Planning Comm.
DATE: 12/07/2020 COMMITTEE CHAIR: C. DELOSTRINOS JOHNSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works Department
COMMITTEE Unanimous Approval; Forward to Special Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$149,912.00 $150,000.00 $0.00
Fund Source: 104 ARTERIAL STREETS
Comments: Page 12, 2021 - 2026 CIP
MTG. DATE RECORD OF COUNCIL ACTION
12/14/20
MTG. DATE ATTACHMENTS
12/14/20 Informational Memorandum dated 12/04/2020
2021 - 2026 CIP, page 12
Consultant Selection Scoring Matrix
Vicinity/Candidate Map
Consultant Agreement, Scope of Work and Fee Estimate
Minutes from Transportation and Infrastructure Committee meeting of 12/07/2020
COUNCIL AGENDA SYNOPSIS
----------------------------------Initials --------------------------------- ITEM NO.
Meeting Date Prepared by Mayor’s review Council review
12/14/20 JR Spec 2.E.
165165
166166
https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/2020 Agenda Items/TIC 12 -07-2020 Last/2021 Overlay Design/InfoMemo Overlay 2021 Design 113020.docx
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Hari Ponnekanti, Interim Public Works Director
BY: Scott Bates, Traffic Engineering Project Manager
CC: Mayor Ekberg
DATE: December 4, 2020
SUBJECT: 2021 Overlay and Repair Program
Project No. 92110401
Design Consultant Selection and Agreement
ISSUE
Execute a contract with KPG, Inc. (KPG) to provide design services for the 2021 Overlay and Repair
Program.
BACKGROUND
Three engineering firms were evaluated from the MRSC Consultant Roster to provide design services
for the 2021 Overlay and Repair Program (see attached scoring & selection matrix). All of the firms
offer baseline qualifications, however KPG provides a unique blend of knowledge and understanding
of the City’s overlay program that provides efficiency and benefits which cannot be matched at this
time by any other firm. KPG has also performed very well in providing construction management
services.
DISCUSSION
KPG has provided a contract, scope of work, and fee estimate to complete the design of the 2021
Overlay and Repair Program and advertise for construction bids. Preliminary locations for 2021
Overlay are shown on the attached vicinity map. This year’s design will include the locations that
were not completed in 2020 and four additional locations from the Pavement Management Survey
priority list. The final selections will be made after the design cost estimates have been completed.
FISCAL IMPACT
KPG Contract 2021 Budget
2021 Design Contract $ 149,912.00 $ 150,000.00
RECOMMENDATION
Council is being asked to approve the design contract with KPG, Inc. for the 2021 Overlay and Repair
Program in the amount of $149,912.00 and consider this item on the Consent Agenda at the
December 14, 2020 Special Meeting.
Attachments: Page 12, Proposed 2021 CIP
Consultant Selection Scoring Matrix
Vicinity/Candidate Map
Consultant Agreement, Scope of Work and Fee Estimate
167167
168168
&,7<2)78.:,/$&$3,7$/352-(&76800$5<
WR
352-(&7 $QQXDO2YHUOD\DQG5HSDLU3URJUDP
3URMHFW1R [[
'(6&5,37,21
-867,),&$7,21
67$786
0$,17,03$&7
&200(17
),1$1&,$/ 7KURXJK (VWLPDWHG
LQ
V %(<21' 727$/
(;3(16(6
'HVLJQ
/DQG5:
&RQVW0JPW
&RQVWUXFWLRQ
727$/(;3(16(6
)81'6285&(6
$ZDUGHG*UDQW
3URSRVHG*UDQW
0LWLJDWLRQ$FWXDO
0LWLJDWLRQ([SHFWHG
&LW\2SHU5HYHQXH
727$/6285&(6
2QJRLQJSURMHFW2QO\RQH\HDUDFWXDOVVKRZQLQILUVWFROXPQ
(DFK\HDUYDULRXVVHFWLRQVRIURDGZD\WKURXJKRXWWKH&LW\DUHGHVLJQHGDQGFRQVWUXFWHGIRUDVSKDOW
RYHUOD\
5HGXFHVDQQXDOPDLQWHQDQFH
6HOHFWGHVLJQDQGFRQVWUXFWDVSKDOWDQGFRQFUHWHSDYHPHQWRYHUOD\VRIDUWHULDODQGUHVLGHQWLDOVWUHHWV
3UHVHUYHDQGPDLQWDLQWKHVWUHHWVWUXFWXUHLQDVDIHDQGXVHDEOHVWDWHE\UHVXUIDFLQJEHIRUHIDLOXUHZKLFK
DOVR
PLQLPL]HVFRVWV6RPHLQGLYLGXDOVLWHVPD\EHFRRUGLQDWHGZLWKZDWHUVHZHUDQGVXUIDFHZDWHUSURMHFWV
2021 - 2026 Capital Improvement Program 169169
170170
2021 Overlay Program
Contract for Design Services
Pa
r
a
m
e
t
r
i
x
KP
F
F
KP
G
,
I
n
c
.
Paving Project Design and Construction Management Experience with the City.0 3 5
Knowledge of FHWA, State, and Tukwila Standards and Procedures 5 4 5
Environmental Experience 5 5 5
Experience with Similar Projects.3 4 5
Traffic Control Design Expertise.4 4 4
Experienced Design Project Manager. 4 4 5
Small Scale Project Experience.2 3 5
Utilities Coordination Experience.5 4 5
Storm water, Drainage, and Detention Design.4 4 5
Public Outreach Experience.3 3 4
Survey Crew In-House.4 4 5
TOTALS 39 42 53
For each category, highest score is 5 (with the lowest or worst score 1)
Consultant with the highest score is ranked the best.
Staff: Scott Bates
Selection Date: 11/30/20
Selected Consultant: KPG, Inc.
Selection Justification: The selected firm has demonstrated relevant pavement
overlay design experience on multiple past federal and locally funded paving projects
including the City overlay program. KPG has provided excellent design construction
management results on City drainage projects as well. They have exceptional
familiarity with City Public Works systems, WSDOT and FHWA standards. Based on
overall score KPG prevailed. Consultants percieved ablility to perform CM services
was also reviewed since the design contract could be extended to include those
services as well.
1
7
1
1
7
1
2021 Overlay Vicinity Map
172172
173173
174174
175175
176176
177177
178178
City of Tukwila KPG, Inc.
2021 Overlay Program Page 1 of 4 November 2020
EXHIBIT A
City of Tukwila
2021 Overlay Program
Scope of Work
November 24, 2020
The Consultant shall prepare final Plans, Specifications and Estimates for the 2021
Overlay Program. Specific projects will be determined from the following list of
candidate streets:
S 200th St Southcenter Pkwy to Green River Bridge
S 126th St East Marginal Way to 37th Ave S
44th Avenue S S 140th St to end
48th Avenue S S 109th S, North to Dead End
S 109th St 47th Avenue S to 48th Avenue S
S 150th St 46th Avenue S, East to Dead End
53rd Ave S S 137th St to 52nd Ave S & Vicinity
S 188th St Orillia Rd & Bow Lake Station
Southcenter Pkwy Strander Blvd to Minkler Blvd
Minkler Blvd Andover Pk E to Industry Dr
S 141st St 37th Ave S to TIB
The 2021 Overlay Program will be bid as a single bid package as budget allows.
Projects may be re-prioritized or deferred to a future overlay program based on
available budget and other considerations. Detailed estimates will be prepared at the
50% design to verify the final project list to be included in the 2021 Overlay Program.
The Consultant shall utilize the data collection and analysis provided by Infrastructure
Management Service (IMS) to identify additional roadway segments to be included in
the design and construction of the 2021 Overlay Program.
The City of Tukwila may require other services of the consultant. These services could
include additional design, right of way, environmental documentation, construction phase
services, or other work tasks not included in the scope of work. At the time these services
are required, the Consultant will provide the City with a detailed scope of work and an
hour and fee estimate. The Consultant will not proceed with the work until the City has
authorized the work and issued a Notice to Proceed.
179179
City of Tukwila KPG, Inc.
2021 Overlay Program Page 2 of 4 November 2020
Assumptions for the 2021 Overlay Program Bid Package
Roadway and utility casting mapping will be based on aerial photography, GIS,
and field reviews by the Consultant. Topographic field survey may be required
for ADA ramp improvements and will be performed by the Consultant as
required.
Typically, only surface utilities requiring adjustment to grade will be shown.
No utility upgrades are anticipated in the project design.
It is assumed there will be approximately thirty (30) plan sheets at 1”=20’ scale
full size (22” X 34”), 1”=40’ at reduced scale (11” X 17”).
Drainage & Water Quality Reports will not be required.
Environmental Documentation will not be required.
Consultant shall not be responsible for printing and supplying City or Contractor
with hard copies of plans and specifications at interim submittals or contract
award.
Deliverables
50% review submittal with Plans and Estimate (electronic copies)
90% review submittal with Plans, Specifications, and Estimate (electronic
copies)
Routing of 50% and 90% Plans to utilities for review and comment.
Bid Documents and Engineer’s Estimate for 2021 Overlay Program.
Coordinate upload of Plans and Specifications to Builders Exchange.
Bid Analysis and recommendation for award.
Preconstruction Meeting Attendance.
SCOPE OF WORK
TASK 1 – 2020 Remaining Final Design
1.1 The Consultant shall provide continuous project management and administration for
the duration of the Project. (Estimate 6 months).
Hold project coordination meetings with the City to update progress and
review submittals. Assume (4) meetings.
The Consultant shall provide monthly status reports and billings.
The Consultant shall provide independent QA/QC reviews by senior in-
house staff of all deliverables prior to submittal to the City.
180180
City of Tukwila KPG, Inc.
2021 Overlay Program Page 3 of 4 November 2020
1.2 The Consultant shall update and prepare Final Plans for the proposed improvements
that were excluded from the construction in the 2020 Overlay Program. Sites are
limited to the following:
S 200th St Southcenter Pkwy to Green River Bridge
S 126th St East Marginal Way to 37th Ave S
44th Avenue S S 140th St to end
48th Avenue S S 109th S, North to Dead End
S 109th St 47th Avenue S to 48th Avenue S
S 150th St 46th Avenue S, East to Dead End
53rd Ave S S 137th St to 52nd Ave S & Vicinity
S 188th St Orillia Rd & Bow Lake Station
1.3 The Consultant shall recalculate quantities and prepare a Final Engineers Estimate of
Probable Construction Cost for the Bid Documents. Projects will be prioritized in
collaboration with the City following the 50% Submittal of Task 2 to determine final
project segments.
1.4 The Consultant shall update the Contract Specifications per 2021 WSDOT Standard
Specifications for the Bid Documents.
TASK 2 – 2021 New Final Design
2.1 The Consultant shall prepare base maps for all project locations, identified below,
using field measurements, available record drawings, and/or ortho-photography.
Topographic survey will be utilized only at ADA ramp locations where field conditions
require it to meet ADA compliance
Sites include, but not limited to:
Southcenter Pkwy Strander Blvd to Minkler Blvd
Minkler Blvd Andover Pk E to Industry Dr
S 141st St 37th Ave S to TIB
2.2 The Consultant shall prepare 50%, 90%, and final Plans for the proposed
improvements including the following:
Plans shall be prepared with such provisions in such detail as to permit field
layout and construction within a degree of accuracy acceptable to the City and
per industry standards.
Typical sections and details will be prepared for items not available as standard
details from the City, State, or WSDOT standard drawings.
181181
182182
EXHIBIT B
PRIME CONSULTANT COST COMPUTATIONS
City of Tukwila
2021 Overlay Program
Decemeber 2020
Principal Survey Mgr Sr. Engineer
Construction
Mgr
Project
Surveyor
Project
Engineer
Design
Engineer
CAD
Technician Sr. Admin Engineering
Technician Survey Crew II Office Admin
252$ 226$ 187$ 166$ 142$ 140$ 116$ 103$ 103$ 96$ 219$ 88$ Hours Fee
1.1 Project Management and Administrative Services 12 12 8 8 40 6,232$
1.2 Prepare Final Plans 4 4 16 20 44 6,232$
1.3 Project Cost Estimates (Final)4 4 4 8 12 32 4,932$
1.4 Project Specifications 4 4 4 20 8 8 48 6,852$
24 0 8 12 0 56 40 0 8 0 0 16 164 24,248$
2.1 Prepare Project Base Maps 4 4 8 32 60 8 60 80 256 38,332$
2.2 Prepare 50%, 90%, and Final Plans 24 12 60 120 40 160 416 48,280$
2.3 Project Cost Estimates (50%, 90%, Final)4 16 4 40 24 12 100 14,200$
2.4 Project Specifications 4 24 12 40 16 8 104 15,648$
2.5 Utility Coordination 4 20 8 4 36 4,860$
8 4 72 28 8 192 228 48 0 236 80 8 912 121,320$
3.1 Bid Period Services 2 4 2 8 4 2 22 3,344$
2 0 4 2 0 8 4 0 0 0 0 2 22 3,344$
34 4 84 42 8 256 272 48 8 236 80 26 1,098 148,912.00$
Mileage at current IRS rate 1,000.00$
1,000.00$
149,912.00$
Labor Hour Estimate Total Hours and Labor Fee
Estimate by TaskTask
No.Task Description
Task 1 - 2020 Remaining Final Design
Task Total
Total Estimated Budget
Total Reimbursable Expense
Total Labor Hours and Fee
Reimbursable Direct Non-Salary Costs
Task 2 - 2021 New Final Design
Task Total
Task 3 - Bid Period Services
Task Total
FEE ESTIMATE 12/1/2020
1
8
3
1
8
3
1
8
4
1
8
4
City of Tukwila
City Council Transportation & Infrastructure Committee
Meeting Minutes
December 7, 2020 – 5:30 p.m. – Electronic Meeting due to COVID-19 Emergency
Councilmembers Present: Cynthia Delostrinos Johnson, Chair, Verna Seal, Kate Kruller
Staff Present: Rachel Bianchi, Hari Ponnekanti, Scott Bates, Cyndy Knighton, and
Gail Labanara
Guest: Emily Moon
Chair Delostrinos Johnson called the meeting to order at 5:30 p.m.
I.BUSINESS AGENDA
A.Project Completion: 2020 Overlay & Repair Project
Staff is seeking Council approval of project completion and release of retainage with Miles
Resources, in the amount of $277,220.01 for the 2020 Overlay & Repair Project.
Committee Recommendation
Unanimous approval. Forward to December 14, 2020 Special Consent agenda.
B.Consultant Agreement: 2021 Overlay and Repair Project
Staff is seeking Council approval of a contract with KPG, Inc. in the amount of $149,912.00 for
design of the 2021 Overlay & Repair Program, which will include locations not completed in
2020 and four additional from the Pavement Management Survey priority list. It includes
design of the 53rd Ave S traffic revisions (with sidewalks) and King County improvements near
the Bow Lake Transfer Station.
Committee Recommendation
Unanimous approval. Forward to December 14, 2020 Special Consent agenda.
II.Miscellaneous
a.53rd Ave S Street Improvements – Councilmembers and staff discussed a recent public
comment letter regarding the project.
Committee follow up: Chair Delostrinos Johnson would like staff to reach out to the
residents that met on site to give them an update on the signs. Additional outreach
requested on Tukwila Talk, Hazelnut, or our website to inform residents that more signs are
coming. Once design is finalized in Spring 2021, conduct outreach to entire neighborhood
on the new revisions that include sidewalks.
b.For the Metropolitan Water Pollution Abatement Advisory Committee (MWPAAC),
representation by City staff is needed. Hari will contact the appropriate Public Works staff.
c.TIB Bus stop video posted this morning, 12/7/20. Public Works staff responded with the
cleaning schedule of Mondays and Fridays. There are ongoing issues at bus stops being
used for permanent shelter.