HomeMy WebLinkAboutCSS 2021-02-01 Item 1D - Project - Teen and Senior Center UpdateCity of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Community Services and Safety Committee
CC: Mayor Ekberg
FROM: Rachel Bianchi, Deputy City Administrator
Nate Robinson, Teen Specialist
DATE: January 26, 2021
SUBJECT: Update on Combined Teen and Senior Center Project
ISSUE
Staff is providing the Committee an update on this project.
DISCUSSION
During the 2021/2022 budget process, the Council provided direction that staff should begin the
planning for a teen and senior center facility located in the Tukwila International Boulevard
neighborhood. Staff returned with a preliminary outline as to how such direction could be
achieved (see attached October 23, 2020 memo). Initial funding of $600 thousand for planning
and community outreach associated with the center was included in the 2021/2022 budget.
Since the passage of the biennial budget, staff has been working on initial project
implementation with our project management partner, SOJ, including drafting a Request for
Proposals (RFQ) for architectural services. Friday, January 29 is the deadline for the responses.
The RFQ process will allow the City to select an architecture firm that will assist with initial
planning, programming, site selection and cost estimates associated with the center. It is
anticipated that the project team will bring the recommended firm to the Council in early March.
In addition, the project team has been meeting with various outreach practitioners and
consultants to identify the best partner for community outreach associated with this project. As
mentioned in the initial project memo that went to the Council, the project team feels strongly
that robust community engagement be a cornerstone of this planning effort. The project team is
doing a limited RFQ call to determine whether an outside partner could boost the team's
outreach efforts.
The project team expects to begin outreach in February, which is expected to be intense for the
first three to four months to gather information from the community. The team will then
incorporate the feedback into the initial plans and go back out to the community in early fall to
ask whether feedback was appropriately included. The team continues to expect to bring the
project back to the Council during the fourth quarter of this year with programming, preliminary
site selection, cost estimate and funding plan.
RECOM MENDATION
Information only.
81
82
City of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: City Council
CC: Mayor Ekberg
FROM: Rachel Bianchi, Deputy City Administrator
DATE: October 23, 2020
SUBJECT: Planning for a Multigenerational Center in the TIB Neighborhood
ISSUE
Staff wishes to be responsive to the Council's direction to develop a process to plan and
construct a multigenerational center in the Tukwila International Boulevard neighborhood to
serve Tukwila's teen and senior communities.
DISCUSSION
At the October 20, 2020 budget workshop the City Council indicated that the Council's budget
priority for the 2021/2022 budget is the development of a multigenerational center to serve
teens, youth, families, and seniors in Tukwila. Further, the Council indicated that the center
should be located in the TIB neighborhood in proximity to Foster High School, Showalter Middle
School the senior community and existing multi -family neighborhoods in the area. Staff is
excited to propose a draft process, funding for the initial planning phase, share the short- and
medium-term bonding capacity of the City and the proposed City project team. Staff further
looks forward to the Council's thoughts and feedback on this proposal in order to ensure it
centers the Council's expectations and produces the best outcome for the City.
Planning — RFP Process
Staff suggests the development of a Request for Proposals (RFP) process to engage an
architectural firm for the initial planning of a multigenerational facility that includes programming
(identifying the key components needed in such a facility), site selection, estimating the cost for
the facility and providing "test to fits" on a chosen site to understand the orientation of such a
facility on the chosen site. Staff envisions this effort having a significant community
engagement effort to solicit input from a wide variety of teens, families, seniors, and service
providers to ensure the new facility is inclusive and meets the needs of the diverse community.
At the October 20 budget workshop, the Council consistently used the word "innovative" when
discussing this new facility, and staff believes this should start with the community engagement
and RFP process and continue through the entire project.
Proposed RFP Timeline:
• November — Research other similar centers across the country to gain a better
understanding of opportunities, lessons learned and key firms in this space
• December — Draft RFP, allow for opportunity for Council input on draft
• January 4, 2021 — Publish RFP
• January 29, 2021 — Close RFP
• Week February 1, 2021 — Panel, including Council participation, scores RFP
• February 8, 2021 — Panel, including Council participation, interviews three first with top
scores
• Early March — Contract Award
83
84
INFORMATIONAL MEMO
Page 2
Funding
Staff proposes funding the programming and initial planning process up to $600 thousand. This
funding is available from savings associated with the Justice Center project.
The Justice Center project team has been able to reserve $1.2 million from the owner's
contingency and will return it to the Public Safety Plan D.20 funding model. Staff proposes
using half of these savings to fund the programming and community engagement effort and
keeping the other half in the Public Safety Plan D.20 model in order to reduce the long-term
general fund contribution. (It is important to note that repurposing this $600 thousand for this
project is allowable because there are multiple funding sources for the Justice Center that are
not restricted for Public Safety Plan projects. The additional funding sources include land sales,
REET funds, investment earnings and Streamlined Sales Tax Mitigation payments. The $600
thousand transfer to the new multigenerational center will come from these funding sources and
not the voter -approved Public Safety Bond nor current councilmanic debt.)
As to the funding for the final design and construction of the facility, staff believes there are a
number of options that can be examined during the project planning phase. There are potential
partnerships that could be investigated, such as the YMCA/YWCA and Boys and Girls Club, as
examples. It is also possible that this center would be of interest to members of the
philanthropic and business community for financial support. In addition, the City's 2021
remaining debt capacity will be $49.7M, forecast to raise to $81M in 2024 and $146.6M in 2030
(this forecast assumes an annual 4.5% increase in assessed value, which is actually less of an
increase that what the City has experienced over the last several years). Staff is confident that
the City can identify a funding program for this new City facility.
City Team
The City has learned many recent lessons from the construction of two new fire stations and the
Tukwila Justice Center. It is staff's intention to take these lessons learned and build on them,
with a keen eye toward innovation, to make the new multigenerational center the newest
community asset in the City of Tukwila. As such, Rachel Bianchi, who has served as the City's
program manager for the Public Safety Plan will lead this effort on behalf of the City. While we
expect that staff members from across the City will be greatly interested in being a part of this
effort, we also recognize that we have key staff who work with the community that can take
other leadership roles in this effort, including:
• Nate Robinson — Teen Programming Lead & Project Management Support
• Sheri McConnaughey — Senior Programming Lead
• Darren Hawkins —Youth & Family Programming Lead
• Niesha Fort -Brooks — Community Engagement
Draft Timeline for a Stand -Alone Facility
2021 — First Quarter — RFP Process complete, architectural firm selected
2021 — Second Quarter — Programming, site selection review, community engagement,
partnership and philanthropic development, funding options vetted
2021 — Third Quarter — Programming, site selection review, community engagement,
partnership and philanthropic development, funding options vetted
2021 — Fourth Quarter — Recommendations to Council on final facility program, site selection,
partnerships and funding options
2022 — First Quarter — Schematic Design phase (30% design complete)
2022 — Second Quarter — Design Development (60% design complete)
2022 — Third Quarter — Contract Documents (90% design complete)
2022 — Fourth Quarter — Contract Documents (90% design complete)
2023 — First Quarter — Construction begins
INFORMATIONAL MEMO
Page 3
RECOM MENDATION
Staff is seeking the Council's input on this initial draft process and recommendation to move
forward to ensure alignment with the Council's expressed priority to plan, design and construct a
new multigenerational facility for the Tukwila community.
85