HomeMy WebLinkAboutPCD 2021-05-03 Item 1D - Discussion - Development Review Permitting Statusof Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Planning and Community Development Committee
FROM: Nora Gierloff, DCD Director
CC: Mayor Ekberg
DATE: April 27, 2021
SUBJECT: Development Permit Volumes, Review Status and Recommendations
ISSUE
Timelines for review and issuance of both construction and land use permits have increased over
the past year.
BACKGROUND
Permits related to construction include development (building), mechanical, plumbing, electrical,
land altering, public works, and fire permits and are the focus of this memo. The Planning Division
also processes land use permits, which include conditional use, design review, SEPA
environmental review, special permission, and critical areas approvals which are facing many of
the same processing challenges as described in this memo.
The graphic below shows that the number of mechanical and plumbing permits applied for was
quite stable from 2016 through 2020. Building and electrical permit applications were fairly
consistent, but then dipped in 2020. Building permit valuation showed a strong increasing trend
through 2019 before dropping back to 2017-18 levels in 2020. This volatility is often driven by the
timing of one or more large projects such as the Dermody Oxbow and Prologis warehouse
developments.
Permit Trend by Permit Type
2016 - 2021
$200,000,000
$180,000,000
$160,000,000
$140,000,000
$120,000,000
6100,003,000
$80,000,000
$60,004000
$40,000,000
$20,000,000
$o
2016 2017 2018 2019 2020 2021
- Value bldg $62,522,529 590,338,910 $107,177,700 5174,296,492 $98,709,745 $25,208,366
- Value meth $8,222,986 $8,570,133 $10,892,939 $19,197,011 $8,317,111 $1,812,801
- Value dumb $9,321,296 $2,925,137 $5,330,971 $10,651,064 $4,722,584 $436,413
ill Value elect $13,626,845 $20,412,867 $27,015,631 $35,826,473 $24,159,775 $5,014,219
- Issued bfdg 311 342 319 345 225 83
Issued meth 192 197 169 174 165 34
Issuedplumb 185 165 161 159 133 41
T Issued elect 1175 1046 1108 986 875 233
1400
1200
1000
800
600
400
200
0
PERMITS ISSUED
39
PG: 49
PLUMBING PERMITS
5:19
SIGN PERMITS
40
INFORMATIONAL MEMO
Page 2
The number of permits issued from January through April 2021 is similar to the pre -pandemic
numbers for that period in 2019 and 2020.
2019-2021 COMPARISON
JANUARY 1— APRIL 20
2021 ISSUED PERMITS • LAST UPDATED 9/2o/2021
Select Dara Range: '
PERMITS ISSUED
621
AVG DAYS TO ISSUE
42.3
DAYS TO ISSUE
AVG DAYS TO APPROVE
30.7
DAYS TO APPROVE
PERMIT JOB VALUE
$44,297,962
PERMIT FEES PAID
$1,006,141
D: 94
DEVELOPMENT PERMITS
PW: 37
PUBLIC WORKS PERMITS
EL: 287
ELECTRICAL PERMITS
PWF: 16
FRANCHISE PERMITS
M: 49
MECHANICALPERMITS
F. 67
FIRE PERMITS
2020 ISSUED PERMITS
Select Dare Range:
PERMITS ISSUED
548
AVG DAYS TO ISSUE
28.7
DAYS TO ISSUE
AVG DAYS TO APPROVE
21.5
DAYS TO APPROVE
PERMIT JOB VALUE
$39,590,743
PERMIT FEES PAID
$1,233,263
D: 68 EL: 262
DEVELOPMENT PERMITS ELECTRICAL PERMITS
PW: 33
PUBLIC WORKS PERMITS
M: 35
MECHANICAL PERMITS
PWF: 47
FRANCHISE PERMITS
F: 45
FIRE PERMITS
PG: 40
PLUMBING PERMITS
S. 17
SIGN PERMITS
2019 ISSUED PERMITS
Select Date Range:
'v a/gZ019
PERMITS ISSUED
659
AVG DAYS TO ISSUE
29.6
DAYS TO ISSUE
AVG DAYS TO APPROVE
16.6
DAYS TO APPROVE
PERMIT JOB VALUE
$80,560,819
PERMIT FEES PAID
$2,140,329
D: 107
:>EVELOPMENTPERMITt,
PW: 42
JBUC WORKS'
EL: 332
_ECTRICAL PERMITS
PWF: 46
RANCHISE PERMITS
M: 54
MECHANICAL PERMITS
F: 0
FIRE PERMITS
PG: 51
PLUMBING PERMITS
5: 25
SIGN PERMITS
The 2019 permit valuation and revenue numbers were outliers from Tukwila's trends. 2021
numbers are on track to be near the average levels seen in prior years.
2019-2021 COMPARISON
JANUARY 1 - DECEMBER 31 (`2021 UPDATED TO APRIL 20, 2021)
2021 ISSUED PERMITS LAST UPDATED 4/20/2021
Select Date Range.
PERMITS ISSUED
621
AVG
DAYS TO ISSUE
42.3
DAYS TO ISSUE
AVG
DAYS TO APPROVE
30.7
DAYS TO APPROVE
PERMIT JOB VALUE
$44,297,962
D:94 II EL:287
DEVELOPMENT PERMITS
IIPW: 37
PERMIT FEES PAID
$1,006,141
PUBLC.'.ORKSPERM'. S
ELECTRICAL PERMITS
PWF: 16
FRANCHISE PERMITS
M: 49
MECHANICAL PERMITS
F: 67
FIRE PERMITS
PG: 49
PLUMBING PERMITS
5:19
SIGN PERMITS
2020 ISSUED PERMITS
Select Date Range:
Inrm2o. 12n1/2(129 - =
PERMITS ISSUED
1,916
AVG
DAYS TO ISSUE
41.6
DAYS TO ISSUE
AVG
DAYS TO APPROVE
32.2
DAYS TO APPROVE
PERMIT JOB VALUE
$258,764,984
PERMIT FEES PAID
$4,208,085
D: 257
DEVELOPMENT PERMITS
PW: 117
EL: 861
ELECTRICAL PERMITS
PWF: 133
FRANCHISE PERMITS
M: 164
MECHANICAL PERMITS
F: 205
FIRE PERMITS
PG: 129
PLUMBING PERMITS
S: 42
SIGN PERMITS
2019 ISSUED PERMITS
Select Date Range:
PERMITS ISSUED
2,155
AVG
DAYS TO ISSUE
29.3
DAYS TO ISSUE
AVG
DAYS TO APPROVE
17.9
DAYS TO APPROVE
PERMIT JOB VALUE
$ 217,446,717
PERMIT FEES PAID
D: 372
DEVELOPMENT PERMITS
EL: 1,030
ELECTRICAL PERMITS
$7,380,632 PW: 153 PWF: 148
PUBLIC WORKS PERMITS FRANCHISE PERMITS
https://tukwilawa.sharepoint.com/sites/mayorsoffice/cc/Council Agenda Items/DCD/PCD InfoMemo Permits 5-3-21.docx
M: 192
V7 ECHANICAL PERMITS
F: 1
FIRE PERMITS
PG: 175
PLUMBING PERMITS
S: 80
SIGN PERMITS
INFORMATIONAL MEMO
Page 3
DISCUSSION
On February 29, 2020, Washington Governor Inslee declared a state of emergency in response to
the COVID-19 pandemic. On March 23, 2020, Governor Inslee issued a statewide "Stay Home,
Stay Healthy" order which resulted in the closure of City Hall to the public and temporarily paused
many construction projects.
One of the ways that the permitting departments (DCD, Fire and Public Works) responded to the
crisis was by accelerating the transition to online permit submittal and review so that we could
accept and issue permits remotely. While this was a long planned for improvement to customer
service, implementing it on an abbreviated timeline in the midst of the other disruptions of the
pandemic was a major effort that pulled staff away from permit processing. As shown in the data
above, permit volumes did not slow down significantly in 2020 and therefore this transition
contributed to a backlog of permits waiting for review.
Freezing the vacant Associate Planner position, staff furloughs, and letting go the extra labor
planning intern were some of the measures taken in 2020 to reduce DCD's budgetary expenditures
in response to the financial impacts of the pandemic. While these measures were prudent in light
of the uncertainty around the financial impact of the pandemic, they have also contributed to the
permit backlog and significantly impacted permit review times as anticipated in the 2021-2022 DCD
budget narrative.
f0
0
O
140
120
100
W00
80
40
20
0
2019-2021 Average Review Times
11 I
IR 1 1 1 i— , id
Development Electrical Mechancal Plumbing Fire PW Sgn
Axis Title
■ 2019 ■ 2020 ■ 2021
These numbers show the overall time from permit application to issuance. For permits that require
revisions in order to meet code requirements, some of that time is dependent on the applicant's
response time to the City's correction letter(s). Architects, developers, and contractors have faced
their own pandemic disruptions which in some cases has led to poor quality submittals or longer
turnaround times.
Another unexpected event was the departure of three of the five members of the DCD leadership
team during the early months of 2021, with a fourth now out on extended medical leave. We have
appointed two staff into acting roles as an interim measure but that leaves them trying to fulfill two
roles at once. Reduced staffing levels have resulted in a reduction of services due to the team's
reduced capacity.
https://tukwilawa.sharepoint.com/sites/mayorsoffice/cc/Council Agenda Items/DCD/PCD InfoMemo Permits 5-3-21.docx
41
42
INFORMATIONAL MEMO
Page 4
Proposed Solutions to Improve Customer Service
• Allow DCD to rehire the frozen Associate Planner position
• Retitle the Planning Supervisor position as Development Supervisor to reflect the transfer of
PW Development Review Engineers to the DCD permit team
• Recruit and hire for the vacant Deputy Director and Development Supervisor positions
• Send some development permits out for building code review by a consultant when review
times for that division exceed targets
• Begin recruiting when notified of an impending vacancy rather than waiting to hire until the
end of the vacation/sick leave cash out period, especially when we are "one deep" in that role
• Continue to cross train staff and document procedures to improve resiliency to unexpected
events
• Continue to pursue agreements with neighboring cities for inspection back up to handle
vacations and illnesses
• Continue working with TIS to improve the online permit submittal experience
• Improve the permit handouts and website to provide better direction to applicants
• Rehire the extra labor Planning Intern position if/when the frozen planner position is refilled
• Continue efforts to fill the vacant Building Division Plans Examiner and Inspector positions
If we are successful in recruiting appropriate candidates in this challenging hiring environment we
could have positions filled in approximately three months. Onboarding and training would take
another two to three months before new staff would reach full productivity. We could expect a
reduction in the permit backlog and an improvement in processing times within 5 to 6 months,
assuming no additional vacancies.
FINANCIAL IMPACT
The proposed unfreezing of the vacant Associate Planner position would require applicable salary
and employee related expenses to be added back to the DCD budget. Most of the other changes
could be accomplished within the existing 2021 budget.
RECOMMENDATION
Information only. The Finance and Governance Committee held a discussion of service restoration
priorities on April 26, 2021.
https://tukwilawa.sharepoint.com/sites/mayorsoffice/cc/Council Agenda Items/DCD/PCD InfoMemo Permits 5-3-21.docx