HomeMy WebLinkAboutReg 2021-05-03 Item 5F - Final Acceptance - Water Fund: Andover Park East Water Main Pavement Repair with ICON Materials for $114,158.43COUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Mayor's review
Council review
05/03/21
JR
ITEM INFORMATION
ITEM No.
5.F.
51
STAFF SPONSOR: SCOTT BATES
ORIGINAL AGENDA DATE: 05/03/21
AGENDA ITEM TITLE Water
Completion
Fund - Andover Park East Water Main Pavement Repair Project
and Acceptance
CATEGORY ❑ Discussion
Mtg Date
Motion
Date 05/03/21
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
1
M
SPONSOR ❑Council Mayor HR ❑DCD Finance Fire TS P&R Police PIV ❑Court
SPONSOR'S The Notice to Proceed for Contract No. 20-123 with ICON Materials of Pacific, Washington
SUMMARY was issued on December 14, 2020 for the Andover Park East Water Main Pavement Repair
Project. This project provided permanent repairs to the roadway and driveways due to the
10" diameter water main failure on June 17, 2020. Construction was physically completed
on February 4, 2021. Council is being asked to accept and finalize the contract with ICON
Materials for $114,158.43.
REVIEWED BY
Trans&Infrastructure
❑ CommunitySvs/Safety ❑ Finance Comm. ❑ Planning/Economic Dev.
❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
COMMITTEE CHAIR: VERNA SEAL
❑ LTAC
DATE: 04/26/2021
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITTEE
Public Works Department
Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$114,158.43 $141,546.00 $0.00
Fund Source: 401 WATER FUND
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/03/21
MTG. DATE
ATTACHMENTS
05/03/21
Informational Memorandum dated 04/23/21
Notice of Completion Contract No. 20-123
Minutes from Transportation and Infrastructure Committee meeting of 04/26/21
51
52
City of Tukwila
Allan Ekberg, Mayor
Pit be Works Deportment - Barr Portae Intl, Director/City Engineer
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Services Committee
FROM: Hari Ponnekanti, Public Works Director
BY: Scott Bates, Project Manager
CC: Mayor Allan Ekberg
DATE: April 23, 2021
SUBJECT: Water Fund - Andover Park East Water Main Pavement Repair Project
Project No. 92040102, Contract No 20-123
Contract Completion and Acceptance
ISSUE
Accept contract as complete and authorize release of performance bond.
BACKGROUND
The Notice to Proceed for Contract No. 20-123 with ICON Materials of Pacific, Washington was issued
on December 14, 2020 for the Andover Park East Water Main Pavement Repair Project. This project
provided permanent repairs to the roadway and driveways due to the 10" diameter water main failure
on June 17, 2020.
ANALYSIS
Construction was physically completed on February 4, 2021. The project budget for the Water
Departments' construction was $141,546.00 and included a 5% contingency, which was not utilized.
Under -runs were primarily due to fewer quantities needed during the roadway excavation, haul, and
repair phase of the project.
Construction Contract Amount $ 141,546.00
Additions/Change Orders 0.00
Under -runs (27,387.57)
Total Amount Paid $ 114,158.43
RECOMMENDATION
Council is being asked to formally accept and authorize the release of the performance bond, subject to
standard claim and lien release procedures, for the Andover Park East Water Main Pavement Repair
Project construction contract with ICON Materials in the final amount of $114,158.43 and consider this
item on the Consent Agenda at the May 3, 2021 Regular Meeting.
Attachment: Dept of Revenue Notice of Completion
https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/2021 Agenda Items/TIC 04-26-21/b. APE Water Main ICON Closeout - Scott Bates/Info Memo APE Water Main Pavement repairs
Closeout.docx
53
54
NOTICE OF COMPLETION OF
PUBLIC WORKS CONTRACT
Department Use Only
Assigned to:
Date Assigned:
Date 02/9/2021
Form Version Original
Revision Reason
Awarding Agency Information
Prime Contractor Information
Name TUKWILA, CITY OF
UBI 916001519
Name ICON MATERIALS
UBI 601006854
Address 6200 S CENTER BLVD TUKWILA,WA-98188
Address 1508 Valentine Ave SE Pacific, WA 98047
Email Address scott.bates@tukwilawa.gov
Email Address mark.eichelberger@iconmaterials.com
Contact Name Scott Bates
Phone 206-431-2193
Contact Name Mark
Eichlberger
Phone 206-574-3902
Project Information
Project Name 2020 Andover Park East Water Main Pavement Repair
Contract # 20-123
Affidavit ID 1106904
Jobsite Address
Date Awarded
11/11/2020
Date Work Commenced
01/4/2021
Date Work Completed
02/4/2021
Date Work Accepted
02/4/2021
Federally Funded Transportation Project If yes, attach Contract Bond Statement. ❑
Bond Waived? 9358588
Retainage Waived?
Subcontractors Used? If yes, complete
Addendum A. /1
Amount Disbursed
Detailed Description of Work Completed Hot mix asphalt full depth reconstruction of Andover Park East to include
sidewalks and driveways.
DOR Tax Information
"Right -click on the total field and select Update Field to auto -calculate.
Contract Amount
$141,546.00
Liquidated Damages
$ 0.00
Additions (+)
$ 0.00
Amount Disbursed
$114,158.43
Reductions (-)
$27,387.57
Amount Retained
$ 0.00
Sub -Total*
$114,158.43
Other
$ 0.00
Sales Tax Amount
$ 0.00
Sales Tax Rate If multiple rates, attach a list.
0.00%
TOTAL*
$114,158.43
TOTAL*
$114,158.43
These two totals must be equal.
Apprentice Utilization Information
Was Apprentice Utilization Required? If yes, complete this entire section. ❑
Engineer's Estimate $ 0.00
Utilization %
Was a Good Faith Effort approved?
Comments
The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM THE RETAINED FUNDS until receipt of all release certificates and affidavits.
Submitting Form: Submit the completed form by email to all three agencies below.
rtiaDepartment of Revenue
Public Works Section
(360) 704-5650
PWC cx dor.wa.gov
Washington State Department of
"Labor & Industries
Contract Release
(855) 545-8163, option # 4
Contra ctRelease@ LN I. WA. GOV
Employment Security Department
Registration, Inquiry, Standards &
Coordination Unit
(360) 890-3499
publicworks@esd.wa.gov
55
Addendum A: Please List all Subcontractors and Sub-tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&l release will be granted until all affidavits are listed.
Subcontractor's Name:
UBI Number: (Required)
Affidavit ID*
GROUND UP ROAD CONST INC
602790246
1109311
NORTHWEST CONCRETE
603572428
1109118
NORTHWEST TRAFFIC INC
602140049
1110769
O'BUNCO ENGINEERING INTL. INC.
602045762
1109117
TRANSPORTATION SYSTEMS INC
602726209
1109568
56
City of Tukwila
City Council Transportation & Infrastructure Services Committee
Meeting Minutes
April26, 2021- 5:30 p.m. - Electronic Meeting due to COVID-19 Emergency
Councilmembers Present:Verna Seal, Chair, De'Sean Quinn, Thomas McLeod
Staff Present: Henry Ancira, Hari Ponnekanti, Scott Bates, Cody Lee Gray, Cyndy
Knighton, Adib Altallal, Brittany Robinson, Gail Labanara, Bryan Still,
Laurel Humphrey
Chair Seal called the meeting to order at 5:30 p.m.
I. BUSINESS AGENDA
A. Contract Completion: TCC Siding Repairs Phase III
Staff is seeking Council approval of contract completion and release of retainage in the
amount of $116, 589.00 with Lake Washington Construction LLC for the Tukwila Community
Center Siding Repairs Phase III Project.
Committee Recommendation
Unanimous approval. Forward to May 3, 2021 Regular Consent Agenda
B. Contract Completion: Andover Park East Water Main Pavement Repair
Staff is seeking Council approval of contract completion and release of retainage in the
* amount of $114,158.43 for the Andover Park East Water Main Pavement Repair Project.
Committee Recommendation
Unanimous approval. Forward to May 3, 2021 Regular Consent Agenda
C. Neighborhood Traffic Calming Program
Staff updated the Committee on the status of the Program, which is collecting submissions but
unfunded in the current budget. One request has been received in 2021 and there are 28 issues
identified as waiting for action, funding, or recurring complaints to be tracked. A resident
addressed the Committee in favor of increasing speed cameras and reducing speed limits
citywide.
Items needing follow-up:
• Provide prioritized list of items.
• Include in Finance & Governance Committee review of service restoration.
Committee Recommendation
Discussion only.
57