INFORMATIONAL MEMORANDUM
Transportation & Infrastructure Services Committee
TO:
Hari Ponnekanti, Public Works Director/City Engineer
FROM:
MichaelRonda,Public WorksProjectManager
BY:
Mayor Allan Ekberg
CC:
June 11, 2021
DATE:
Public Works Shops-Minkler Restroom Remodel
SUBJECT:
Project No. 91930606,Contract No.20-048
Project Completion and Acceptance
ISSUE
Accept contract as complete and authorize release of retainage and performance bond.
BACKGROUND
Contract No. 20-048withSaybr Contractors, Incwas issued onJuly 1,2020for the bathroom
remodel at the Minkler Public WorksMaintenance Shop.This projectprovidedanADA
accessible bathroom, showerand lockerroomfacilities for members of the Public Works
Operation and Maintenance Staff.The contract was performed throughaJob Order Contract
(JOC)so paymentincluded a Job Order componentto Saybr and a Management Fee to The
Gordian Group for their supportof the contract.This closeout will apply to both portions of the
JobOrder.
DISCUSSION
Construction for this JOC component was physically completed onMay6,2021.Twochange
ordersfor a total of $4,198.77were executedto includea modification to thematerials used for the
bathroom partitions,different locker hardware,and some permit fees which were a direct
reimbursable item in the contract.
PROJECT PHOTOS
23
INFORMATIONAL MEMO
Page 2
FINANCIAL IMPACT
Theconstruction contractat awardwas$272,061.44,which included the costs for both the Saybr
contract and the Gordian fee.The total project budget was setat $308,000 to includein-house
construction support,project management and other soft costs.No explicit contingency was
dedicated tothe project. The final contract cost was within budget and the remaining $31,739.79
willbe used on security upgrades and lighting upgrades as approved by Council in March 2020.
ProjectCosts
Initial Construction Contract$272,061.44
Changes and Net Over/UnderQuantities 4,198.77
Final Construction ContractAmount$276,260.21
RECOMMENDATION
Councilisbeing asked toformally accepttheMinkler Restroom RemodelProjectwith Saybr
Contractors Incand The Gordian Group,in the amount of $276,260.21andauthorizerelease of
thebonds, subject to standard claim and lienreleaseprocedures, andconsider this item on the
Consent Agenda at the June 21, 2021Regular Council Meeting.
ATTACHMENTS:Notice of CompletionSaybr
Contract #20-048-Final Pay Estimate
24
x
306.98.594.480.62.00
BR
MIKE RONDA
WITHIN 10% OVERAGE ALLOTTED
25
INVOICE NO.
INVOICE
26645
3852 S 66th Street
Tacoma, WA 98409-2472
Phone: (253) 531-2144
Fax: (253) 536-2068
City of TukwilaCOT Minkler Bldg Restroom Reno
SHIP
SOLD
11210 Tukwila International Bl600 Minkler Bldvd
TO
TO
Tukwila, WA 968188Tukwila, WA 98188
ACCOUNT NOPO NUMBERJOB NUMBERTERMSINVOICE DATEPAGE
1
CITTUK919306062202087Net 305/12/2021
Contract No. 20-048
Project No. 91930606
Budget Item: 91930606.300.178 and 402.98.594.353.48.00
CLIN QUANTITYDESCRIPTIONUNIT PRICEEXTENDED
1Contract Billing No. 7422.91422.91
100% Complete
IT422.91
TEM OTAL
T42.71
AX
TA465.62
OTAL MOUNT
26
27
28
Department Use Only
NOTICE OF COMPLETION OF
Assigned to:Date Assigned:
PUBLIC WORKS CONTRACT
Date 05/19/2021 Form Version Original Revision Reason
Awarding Agency InformationPrime Contractor Information
Name TUKWILA, CITY OF UBI 179000208 Name SAYBR CONTRACTORS INC UBI 601795367
Address 6300 S CENTER BLVD #100 TUKWILA,WA-98188 Address 3852 S 66th St. Tacoma,WA-98409
Email Address Mike.Ronda@TukwilaWA.gov Email Address ggegax@saybr.com
Contact Name Michael Ronda Phone 206-433-7194 Contact Name SAYBR Phone 253-531-2144
x_____CONTRACTORS INC
Project Information
Project Name Minkler Restroom Contract # 20-048 Affidavit ID 1025089
Jobsite Address 600 Minkler Blvd
Tukwila, WA 98188
Date Awarded Date Work Commenced Date Work Completed Date Work Accepted
07/01/202012/14/202004/23/202105/06/2021
Federally Funded Transportation Project
If yes, attach Contract Bond Statement.
Bond Waived? Retainage Waived?Subcontractors Used?
If yes, complete Addendum A.
Detailed Description of Work Completed Provide new modular restroom
DOR Tax Information
*Right-click on the total field and select Update Field to auto-calculate.
Contract Amount$236,174.69Liquidated Damages$ 0.00
Additions (+)$3,644.93Amount Disbursed$263,838.18
Reductions (-)$ 0.00Amount Retained$ 0.00
Sub-Total*$239,819.62 Other$ 0.00
Sales Tax Amount$24,018.56Sales Tax Rate 10.10%
If multiple rates, attach a list.
TOTAL*$263,838.18TOTAL*$263,838.18
These two totals must be equal.
Apprentice Utilization Information
Was Apprentice Utilization Required? Engineer’s Estimate $ 0.00
If yes, complete this entire section.
Was a Good Faith Effort approved?
Utilization % 3.60%
Comments
First four payments of $203,214.86 were taxed at 10%. Total Tax was $20,321.48.
Final three payments of $36,604.76 were taxed at 10.1%. Total Tax was $3,697.08
The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM THE RETAINED FUNDS until receipt of all release certificates and affidavits.
Submitting Form: Submit the completed form by email to all three agencies below.
Employment Security Department
Registration, Inquiry, Standards &
Coordination Unit
Contract Release
(360) 890-3499
(855) 545-8163, option # 4
publicworks@esd.wa.gov
ContractRelease@LNI.WA.GOV
29
Addendum A: Please List all Subcontractors and Sub-tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor’s Name:UBI Number: (Required)Affidavit ID*
ADEPT 601443349 996643
ASPHALT PATCH SYSTEMS 601290396 1019153
EVERGREEN HOUSE 603492821 1022527
EZ SYSTEMS 602619251 1024728
THOMPSON ELECT CONSTRS INC 602011056 1022689
VESTA HOUSING SOLUTIONS LLC 603595759 1011828
WELCOME RAMP SYSTEMS INC 602096666 1019184
30