Notice of Application: Optional DNS Process
Date of Issuance: August 3, 2021
COMMENT DUE DATE: August 17, 2021
Project:
Agency File Number:
Applicant / Owner:
Location:
Agency Contact:
Klickitat Drive and 53rd Avenue South Site (Stormwater Project)
E21-0006 SEPA and 121-0041 Special Permission, Director Decision
Ryan Larson, City of Tukwila Public Works
Ryan.Larson@TukwilaWA.gov, 206/431-2456
Klickitat Drive and 53rd Avenue South Site (Latitude: 47.46 Longitude: -
122.268, Township: 23N Range: 04E Section: 23 Quarter Section: SW 1/4).
Nancy Eklund, AICP, Long Range Planning Manager,
Nancy.Eklund@TukwilaWA.gov, 206/433-7141
Description of Project: On June 17, 2021, the City of Tukwila received an application for a water
quality retrofit project within city right-of-way that involves replacing a section of 18 -inch storm water
pipe and tying into an existing storm system. The project involves removing/abandoning the existing
storm drain pipe; sawcutting road pavement to install storm drain; removing two trees, debris, and
ground cover from channel and banks; installing drain system; revegetating disturbed areas with native
plantings; and restoring modifications to pavement, curb, and sidewalk. The project area is within both
Class 2 steep slopes and the 80 -buffer of a Type 3 stream.
SEPA Environmental Review:
The City of Tukwila has reviewed the proposed project for probable adverse environmental impacts
and expects to issue a Determination of Nonsignificance (DNS). This determination is based on review
of the SEPA environmental checklist, and other documents submitted with the application for permit
approval.
➢ The City has concluded that the requirements and mitigation measures defined in the City's
Development regulations are sufficient to address any potential adverse impacts of the project.
The proposal may include mitigation measures under applicable codes and the project review process
may incorporate or require mitigation measures regardless of whether an EIS is prepared. This
anticipated determination is issued using the Optional DNS process in WAC 197-11-355. This may be
your only opportunity to comment on the environmental impacts of the proposed project.
Public Comment and Review:
You are encouraged to review and comment on the proposed project and its probable environmental
impacts. Comments must be submitted by August 17, 2021, to Nancy Eklund,
nancy.eklund@TukwilaWA.gov or 6200 Southcenter Blvd, Tukwila, WA 98188.
Any person has the right to comment on this application, receive notice of and participate in the
public meetings or hearings, and request a copy of the land -use decision once made. Project files are
available for public review by emailing the agency contact (above) or researching the project at
https://tukw-egov.aspgov.com/PZ/index.html.
Tukwila City Hall • 6200 Southcenter Boulevard • Tukwila, WA 98188 • 206-433-1800 • Website: TukwilaWA.gov
E21 -0006/L21-0041 Klickitat Water Quality/Stormwater Project
SEPA Determination — Optional DNS
Notice of Preliminary Decision
August 3, 2021
Page 2 of 2
Required Permits: The following permits/approvals are needed for the proposed project:
• Hydraulic Project Approval, Washington Department of Fish and Wildlife; and
• Special Permission Director Decision (Work in Critical Area), City of Tukwila.
Required Studies:
• KPG, 2021 Small Drainage Project (Plan Set), No. 920412, 2/2021
• GeoDesign, Report of Geotechnical Engineering Services, for KPG, October 6, 2020
• Special Permission Exemption Request, 2020 Small Drainage Program: Klickitat, February 4,
2021, updated 8/3/2021
Existing Environmental Documents:
• SEPA Checklist, 5/10/2021, updated 8/3/2021
Application Submitted:
Application Complete:
Permit Application Type:
June 17, 2021
July 15, 2021
SEPA Determination and Special Permission: Director Decision (Work in
Critical Area) - Type 2
PROPERTY BOUNDARY
Type 3 Stream in Pipe.
Current flow for stream.
Klickitat Dr & 53rd Ave S Pipe
Replacement Location
CITY TO CONFIRM TYPE 3
STREAM ENDS HERE, AND
CONTINUES THROUGH PIPE
CONVEYANCE UNDER.
KLICKITAT DR.
BUILDING FOOTPRINT ON
PARCEL
15815)
15819
17
15 824
Request this
maintenance project
does not require
special permissions
permit, A Type 3
Stream does not
continue as shown on
existing map. This is
City secondary storm
conveyance. The
upstream channel
enters conveyance
and crosses under
Klickitat Dr. prior to
this City proposed
maintenance project.
Type 3 Watercourse
Buffer