HomeMy WebLinkAboutReg 2022-05-02 Item 8C - Reports - City Administrator / Public Safety Plan Monthly Construction and Budget ReportTO:
City of Tukwila
Allan Ekberg, Mayor
Mayor's Office - David Cline, City Administrator
The City of opportunity, the community of choice
Mayor Ekberg
Councilmembers
FROM: David Cline, City Administrator
DATE: April 27, 2022
SUBJECT: City Administrator's Report
The City Administrator Report is meant to provide the Council, staff and community an update on
the activities of the City and on issues that concern Tukwila. Please let me know if you have any
questions or need additional information about any of the following items.
�. Intergovernmental Update
• Sound Cities Association Mayors Meetings: Mayor Ekberg participated in Sound Cities
Association Mayors meetings on April 12 and 19.
• Tukwila Village Community Development Association Board Meeting: Mayor Ekberg and
Economic Development Administrator Derek Speck participated in a Tukwila Village
Community Development Association Board meeting on April 19.
• Meeting with Superintendent Herndon: Mayor Ekberg and City Administrator Cline met
with Tukwila School District Superintendent Dr. Flip Herndon on April 20.
II. Community Events
• Re -Think Waste Video, Photo and Art Contest: The City's Recycling program, in conjunction
with Waste Management, awarded prizes to winners of the annual Re -Think Waste Video,
Photo, Art Contest for K-12 Tukwila students. Students submitted artwork or videos that
focused on teaching others how to reduce waste, reuse items, and recycle properly. See the
City's Recycling program webpage for a link to selected winners.
III. Staff Updates
Public Safety
• First Responders Support Local Easter Egg Hunt: The Tukwila Police Department and Fire
Department participated in the First Annual Easter Egg Hunt at Foster Presbyterian Church on
April 16. The Fire Crew offered tours of the Fire Engine and Police Officers displayed one of
their patrol cars.
• Andover Park West Bus Stop Clean -Up: The Community Policing Team reached out to King
County Metro, Westfield Mall, and other stakeholders in an emphasis to clean up bus stops on
Tukwila City Hall • 6200 Southcenter Boulevard • Tukwila, WA 98188 • 206-433-1800 • Website: TukwilaWA.gov
201
City Administrator's Report
April 27, 2022
Page 2
Andover Park West. They have been conducting emphasis patrols and are working to arrange
changes in environmental design to assist with the issue.
Project Updates
• Riverton Creek Flapgate Removal Project Estimated Completion: April 2022
The project is nearing completion. The City has received feedback from WSDOT and adjacent
property owner's irrigation testing. WSDOT has requested additional information on localized
rust occurring on the WSDOT tie -back wall.
• 42nd Ave S Bridge Replacement: The bridge was opened to southbound traffic on April 4.
City Staff continues to monitor traffic movements at the 42nd Ave S and Interurban Ave to
adjust traffic signs and barricades as needed. At the March 28 Committee of the Whole
meeting council voted to replace the 42nd Ave S Bridge in its current location. With the bridge
location selected, the type, size, and location report can be finalized and sent to WSDOT for
review.
• Invasive Plant Removal at Foster Golf Links: EarthCorps spent two days at Foster Golf Links
cutting brush as a part of riparian habitat restoration along the river. Additional invasive
plant removal, followed by native plantings are scheduled throughout the summer.
Boards, Commissions and Committees
• Arts Commission: The next meeting is scheduled for April 27, 2022.
2 Resident position terms expire December 31, 2022.
VACANT: 2 resident positions.
• Civil Service Commission: The next meeting is scheduled for May 19, 2022.
No terms set to expire in 2022.
No vacancies.
• COPCAB: The next meeting is scheduled for May 12, 2022.
1 Business Representative position term expires December 31, 2022.
1 Resident position term expires December 31, 2022.
1 School District Representative position term expires December 31, 2022.
VACANT: 2 Resident positions, 1 School District Representative and Student Representative.
• Equity & Social Justice Commission: The next meeting is scheduled for May 5, 2022.
1 City Employee position term expires December 31, 2022.
1 Education/Community position terms expires December 31, 2022.
2 Community Representative position terms expire December 31, 2022.
VACANT: Student Representative.
• Human Services Advisory Board: The next meeting is scheduled for May 12, 2022.
1 Medical/Health position term expires December 31, 2022.
1 School District Representative position term expires December 31, 2022.
1 Resident position term expires December 31, 2022.
VACANT: 1 Business Community Representative.
Phone: 206-433-1800 • Email: Mayor@TukwilaWA,gov • Website: TukwilaWA.gov
202
City Administrator's Report
April 27, 2022
Page 3
• Library Advisory Board: The next meeting is scheduled for June 7, 2022.
4 Resident position terms expire December 31, 2022.
VACANT: Student Representative.
• Lodging Tax Advisory Committee: The next meeting is scheduled for May 13, 2022.
All positions are 1 -year terms.
VACANT: 1 Business Collecting Tax Representative and 1 Funded by Tax Representative.
• Park Commission: The next meeting is scheduled for May 11, 2022.
2 Community position terms expire December 31, 2022.
VACANT: 1 Community Representative and Student Representative.
• Planning Commission: The next meeting is scheduled for April 28, 2022.
2 Resident position terms expire December 31, 2022.
No vacancies.
Phone: 206-433-1800 • Email: Mayor@TukwilaWA,gov • Website: TukwilaWA.gov
203
204
TUKWILA PUBLIC SAFETY PROJECTS
Public Works
SOJ
Construction Management Monthly Report
April 2022
Report Reviewed by: Justine Kim
Owner's Representative: Shiels Obletz Johnsen (SOJ)
Architect: SH KS Architects
Development Progress:
• Punch listed interiors
Upcoming Construction Activities:
• Finish Intrusion Detection system installation
• Mechanical lift and crane installation
• Additional electrical scope for crane and lifts
• Certificate of Occupancy Inspection
• Fire Lanes painting
Budget Status:
• Revised contract amount now $5,262,982
Change Order Status:
• Total Change Orders (1-12) approved to date: $835,761
• There will be one or more change orders.
Schedule Status:
• Final completion date remains unchanged. (The Substantial Completion date is changing due to Fire
and Building Inspections).
Critical Issues:
• None
Tukwila Public Safety Plan - Public Works - Monthly Report
1
205
Tukwila Public Safety Plan - Public Works - Monthly Report
206
2
Tukwila Public Safety Plan - Public Works - Monthly Report
3
207
Tukwila Public Safety Plan - Public Works - Monthly Report
208
4
Tukwila Public Safety Plan - Public Works - Monthly Report
5
209
Will rvi
tVir
e
Tukwila Public Safety Plan - Public Works - Monthly Report
210
6
Tukwila Public Safety Plan - Public Works - Monthly Report
7
211
Tukwila Public Safety Plan - Public Works - Monthly Report
212
8
City of Tukwila - Public Works Fleet & Facilities
TOTAL PROJECT
MONTHLY Budget Report
(REVISED Budget; D-20 Plan Adopted by Council)
Life to Date Costs
as of April 26, 2022 (reconciled w/acctg thru March 2, 2022 GL)
N
W
COUNCIL REPORTING SUMMARY-
PUBLIC WORKS
Original Budget
Budget Transfers
Current Budget
Committed Budget
Life to Date Cosh
Committed Conitted Remaining Budget
A/E Services (Design & CA)
Permits/Fees
Construction
Construction (Tax)
Construction Related Costs
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
$ 670,768
$ 130,000
$ 6,715,000
$ 662,618
$ 378,186
$ 350,000
$ 843,437
$ -
$ 24,315
$ 194,192
$ -
$ 54,635
$ 93,900
$ (367,042)
$ 670,768
$ 154,315
$ 6,909,192
$ 662,618
$ 432,821
$ 443,900
$ 476,395
$ 611,393
$ 132,105
$ 5,586,919
$ 555,073
$ 302,489
$ 414,301
$ -
$ 590,059
$ 112,105
$ 5,521,958
$ 525,000
$ 272,495
$ 398,790
$ -
$ 21,334
$ 20,000
$ 64,962
$ 30,073
$ 29,994
$ 15,511
$ -
$ 59,375
$ 22,210
$ 1,322,273
$ 107,545
$ 130,332
$ 29,599
$ 476,395
h11$
SUBTOTAL-CURRENT MANAGED PROJECT
$ 9,750,009
$ -
$ 9,750,009
$ 7,602,280
$ 7,420,407
$ 181,873
2,147,729
Previously Managed Svcs (Land,A/E,Bond,Demo)
$ 25,949,992
$ -
$ 25,949,992
$ 25,936,198
$ 25,936,198
$ -
$ 13,794
TOTAL-COMBINED PROJECT
$ 35,700,000
$ -
$ 35,700,000
$ 33,538,478
$ 33,356,605
$ 181,873 $ 2,161,523