HomeMy WebLinkAboutReg 2022-05-16 Item 5C - Final Acceptance - 2020 Central Business District Sanitary Sewer Rehabilitation with Michels Corporation for $626,926.18COUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Mayor's review
Council review
05/16/22
JR
ITEM INFORMATION
ITEM NO.
5.C.
1
STAFF SPONSOR: ADIB ALTALLAL
ORIGINAL AGENDA DATE: 04/29/22
AGENDA ITEM TITLE Sewer
Completion
Fund — 2020 Central Business District (CBD) Sanitary Sewer Rehabilitation
and Acceptance
CATEGORY ❑ Discussion
Mtg Date
Motion
Date 05/16/22
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
1
Mtg
SPONSOR ❑Council Mayor HR DCD ❑Finance Fire TS P&R ❑Police PIV Court
SPONSOR'S The Notice to Proceed for Contract No. 20-111 with Michels Corporation was issued on
SUMMARY November 3, 2020. The project included the installation of approximately 5,950 linear feet
of cured -in-place pipe within the right-of-way of Andover Park West and Strander Blvd and
was physically completed on August 3, 2021. Council is being asked to formally accept the
2020 CBD Sanitary Sewer Rehabilitation project with Michels Corporation as complete and
authorize the release of retainage and performance bonds.
REVIEVG'ED BY
Trans&Infrastructure
❑ CommunitySvs/Safety ❑ Finance Comm. ❑ Planning/Economic Dev.
❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
COMMITTEE CHAIR: KATE KRULLER
❑ LTAC
DATE: 05/02/22
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITTEE
Public Works Department
Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$626,926.18 $709,907.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/16/22
MTG. DATE
ATTACHMENTS
05/16/22
Informational Memorandum dated 04/29/22
2021 CIP, Pg. 70
Notice of Completion
State Release Letters
Photos
Minutes from Transportation and Infrastructure Committee meeting of 05/02/22
1
2
City of Tukwila
Allan Ekberg, Mayor
Public Works Department - Hari Ponnekanti, Director/City Engineer
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Services Committee
FROM: Hari Ponnekanti, Public Works Director/ City Engineer
BY: Adib Altallal, Utilities Engineer
CC: Mayor Ekberg
DATE: April 29, 2022
SUBJECT: Sewer Fund — 2020 Central Business District (CBD) Sanitary Sewer Rehabilitation
Project No. 91140203, Contract No. 20-111
Project Completion and Acceptance
ISSUE
Accept contract 20-111 with Michels Corporation as complete and authorize release of retainage.
BACKGROUND
The City of Tukwila has thousands of feet of aging sewer mains throughout, but especially in the Central Business District
(CBD). The City has been conducting regular inspections and assessments of mains at the CBD for the last 15 years. A
typical repair includes digging up the road to create a deep trench where the new sewer main will go. It is costly and typically
inconvenient to the public.
In certain scenarios, an aging sewer main loses some of its structural integrity, but has not started cracking, sagging, or
crumbling. In such cases, we are able to utilize a minimally -disruptive technology where a lining is inserted through a manhole
and into the existing sewer main to strengthen it and increase its useful life. The aforementioned trenchless technology
minimizes disruptions to the public and greatly reduces the damage to the road. The technology is utilized when possible, but
it is not applicable in all scenarios.
DISCUSSION
The Notice to Proceed for Contract No. 20-111 with Michels Corporation was issued on November 3, 2020. The project
included the installation of approximately 5,950 linear feet of cured -in-place pipe within the right-of-way of Andover Park West
and Strander Boulevard to rehabilitate the existing sewer main. Rehabilitation and lining of the CBD sewer mains within scope
was physically completed on August 3, 2021. The final affidavits of Wages Paid was approved by the Department of Revenue
on April 7, 2022.
FINANCIAL IMPACT
The total 2020 CBD Sanitary Sewer Rehabilitation contract budget was $709,907.00. Underruns credited $82,980.82,
resulting in a final contract amount of $626,926.18. Retainage outstanding totals $28,466.28. This contract was fully funded by
the sewer enterprise fund.
Original Contract Amount
Unit Price Underruns
Total Contract Amount
Contract
$709,907.00
(82,980.82)
$626,926.18
RECOMMENDATION
Council is being asked to formally accept the 2020 CBD Sanitary Sewer Rehabilitation project with Michels Corporation in the
amount of $$626,926.18 as complete and authorize the release of retainage subject to standard claim and lien release
procedures, and to consider this item on the Consent Agenda at the May 16, 2022 Regular Council Meeting.
Attachments: 2021 CIP, Page 70
Notice of Completion
State Release Letters
Photos
3
4
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2021 to 2026
PROJECT: CBD Sanitary Sewer Rehabilitation Project No. 91140203
DESCRIPTION: The asbestos concrete pipe in the CBD (commercial business district) is approximately 45 years old and
becoming soft. Slip lining the pipe will reinforce the strength with little impact to roadways and minimal excavation.
JUSTIFICATION: If the pipe collapses, the street will have to be excavated and the cost of the repairs will be significant. We have
had four major pipe failures on Andover Park West and Andover Park East.
STATUS: In 2014 and 2015, over 10,500 feet of asbestos sanitary sewer pipe were relined. In 2020 through 2024,
15,000 feet of asbestos sewer is scheduled to be relined.
MAINT. IMPACT: Reduced maintenance and repair costs.
COMMENT: A Public Works Trust Fund loan was successfully obtained in 2012 for $750k.
FINANCIAL Through Estimated
(in $000's)
2019 2020 2021
2022
2023
2024
2025
2026
BEYOND TOTAL
EXPENSES
•,--, Project Location
5YS,56��L■J1�`�
�peTh ilik -.1•.-�=
St
Q`T��
' -
fti
Design
436
45
45
50
50
50
676
Land (R/W)
1
-`
__
a Ile
tinkler Blvd
1
Const. Mgmt.
429
120
150
120
50
50
/,
iQ./
919
Construction
2,418
1,100
1,500
1,000
450
450
6,918
TOTAL EXPENSES
3,284
1,265
1,695
1,170
550
550
0
0
0
8,514
FUND SOURCES
Awarded Grant
0
PW Trust Fund
750
750
Mitigation Actual
0
Mitigation Expected
0
Utility Revenue
2,534
1,265
1,695
1,170
550
550
0
0
0
7,764
TOTAL SOURCES
3,284
1,265
1,695
1,170
550
550
0
0
0
8,514
2021 - 2026 Capital Improvement Program
70
5
•,--, Project Location
5YS,56��L■J1�`�
�peTh ilik -.1•.-�=
St
Q`T��
' -
fti
5160
at
-`
__
a Ile
tinkler Blvd
.upland
AW r
W
NW
or
Midlantl or
Trnendor`?
/,
iQ./
1 , 5 18 St
1
1 Co
I® m Y
-
4GIS
2021 - 2026 Capital Improvement Program
70
5
6
NOTICE OF COMPLETION OF
PUBLIC WORKS CONTRACT
Department Use Only
Assigned to:
Date Assigned:
Date 01/19/2022
Form Version Original
Revision Reason
Awarding Agency Information
Prime Contractor Information
Name TUKWILA, CITY OF
UBI 179000208
Name MICHELS CORP
UBI 601061071
Address 6300 S CENTER BLVD #200 TUKWILA,WA-98188
Address 6300 Southcenter Blvd Tukwila,WA-98002
Email Address Adib.Altallal@TukwilaWA.gov
Email Address Adib.Altallal@TukwilaWA.gov
Contact Name Adib Altallal
Phone 206-240-0633
x
Contact Name MICHELS
CORP
Phone
206-240-0633 x
Detailed Description of Work Completed Installation of Cured In Place Pipe
Project Information
Project Name 2020 Central Business District Sanitary Sewer
Rehabilitation - Phase 4
Contract # 91140203
Affidavit ID 1052470
Jobsite Address Various Locations in Tukwila WA
Date Awarded
10/05/2020
Date Work Commenced
06/28/2021
Date Work Completed
07/23/2021
Date Work Accepted
08/06/2021
Federally Funded Transportation Project If yes, attach Contract Bond Statement. ❑
Bond Waived?
Retainage Waived?
Subcontractors Used? If yes, complete
Addendum A. '/
Detailed Description of Work Completed Installation of Cured In Place Pipe
DOR Tax Information
"Right -click on the total field and select Update Field to auto -calculate.
Contract Amount
$645,370.00
Liquidated Damages
$ 0.00
Additions (+)
$ 0.00
Amount Disbursed
$598,459.90
Reductions (-)
$75,437.11
Amount Retained
$28,466.28
Sub -Total*
$569,932.89
Other
$ 0.00
Sales Tax Amount
$56,993.29
Sales Tax Rate If multiple rates, attach a list.
10.00%
TOTAL*
$626,926.18
TOTAL*
$626,926.18
These two totals must be equal.
Apprentice Utilization Information
Was Apprentice Utilization Required? If yes, complete this entire section. ❑
Engineer's Estimate $ 0.00
Utilization % 11.89%
Was a Good Faith Effort approved?
Comments
The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM THE RETAINED FUNDS until receipt of all release certificates and affidavits.
Submitting Form: Submit the completed form by email to all three agencies below.
crAla Department of Revenue
Public Works Section
(360) 704-5650
PWC@dor.wa.gov
Washington State Department of
)Labor & Industries
Contract Release
(855) 545-8163, option # 4
ContractRelease@ LN I. WA. GOV
Employment Security Department
Registration, Inquiry, Standards &
Coordination Unit
(360) 890-3499
publicworks@esd.wa.gov
7
Addendum A: Please List all Subcontractors and Sub -tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor's Name:
UBI Number: (Required)
Affidavit ID*
ADVANCED GOVERNMENT SERV
INC
603585454
1048203
OLSON BROTHERS PRO -VAC LLC
602170975
1051848
8
2889
STATE OF WASHINGTON
DEPARTMENT OF REVENUE
CITY OF TUKWILA
C/O ADIB ALTALLAL
6300 SOUTHCENTER BLVD
TUKWILA WA 98188-2545
April 7, 2022
Letter ID: L0019236032
U B I : 601-061-071
Account ID: 601-061-071
Account Type: Excise Tax
Audit ID: A16803
Audit Period: 10/01/20 - 11/30/21
We hereby certify that taxes, increases and penalties due or to become due from the contractor listed below
under Chapter 180, Laws of 1935, as amended, with respect to the following publics works contract:
MICHELS PIPELINE CONSTRUCTION INC
Public Agency: TUKWILA, CITY OF
Project Name: 2020 Central Business District Sanitary Sewer Rehabilitation - Phase 4
Contract Number: 91140203
Description of Work: Installation of Cured In Place Pipe
has been paid in full, or is in the Department's opinion readily collectible without recourse to the state's lien
on the retained percentage.
This certificate is issued pursuant to the provision of Chapter 60.28 Revised Code of Washington for the sole
purpose of informing the state, county, or municipal officer charged with the duty of disbursing or authorizing
the payment of public funds to said contractor that the Department of Revenue hereby releases the state's
lien on the retained percentage provided by this Chapter for excise taxes due from said contractor.
This certificate does not release said contractor from liability for additional tax that may be later determined to
be due with respect to the above-mentioned contract or other activities.
Dated April 7. 2022 at Olympia, Washington,
State of Washington
Department of Revenue
Certifying Officer
Public Works Audit Unit
6500 Linderson Way SW Tumwater, WA 98501
ggL0050 dor.wa.gov Phone (360) 704-5650 Fax (360) 704-5647
9
10
Employment Security Department
WASHINGTON STATE
January 20, 2022
ESD# 000657299005
UBI# 601061071000
MICHELS CORP
6300 Southcenter Blvd
Tukwila,WA-98002
TUKWILA, CITY OF
Employment Security Department hereby certifies those contributions, penalties and
interest due from the above named contractor under the Employment Security Act have
been paid in full or provided for with respect to the following public works contract:
Description 2020 Central Business District Sanitary Sewer
Rehabilitation - Phase 4
Contract number 91140203
The Employment Security Department hereby certifies that it has no claim pursuant to RCW
50.24.130 against the public body named above for tax attributable to service performed for said
public body by the above named contractor on the above described contract. The Employment
Security Department releases its lien on the retained percentage which is provided by RCW
60.28.040 for contributions, penalties and interest due from said contractor.
This certificate does not release said contractor from liability for additional contributions,
penalties and interest which may be later determined to be due with respect to the above
mentioned contract.
If we may be of further assistance, please call (360) 890-3499 or email
publicworks@esd.wa.gov
EMPLOYMENT SECURITY DEPARTMENT
11
State of Washington
DEPARTMENT OF LABOR AND INDUSTRIES
PO Box 44274
Olympia WA 98504-4274
TUKWILA, CITY OF
6300 S CENTER BLVD #200
TUKWILA WA 98188
12
Page 1
STATE OF WASHINGTON
DEPARTMENT OF LABOR AND INDUSTRIES
PO Box 44274 Olympia, Washington 98504-4274
March 09, 2022
TUKWILA, CITY OF
6300 S CENTER BLVD #200
TUKWILA WA 98188
CERTIFICATE TO RELEASE L&I'S HOLD ON RETAINAGE
The Washington State Department of Labor & Industries is granting approval to release our hold on the
retained amount for 2020 CENTRAL BUSINESS DISTRICT SANITARY SEWER
REHABILITATION - PHASE 4, Contract 91140203, Affidavit 1052470 to the following contractor:
MICHELS CORP
832,318-00 601 061 071
We have determined that all workers' compensation premiums, increases, and penalties for this contractor
have been paid in full or are readily collectible without recourse to the retained funds, per chapter 60.28
RCW.
The contractor may still be liable for payment if we later determine they owe additional premiums related
to this contract or other activities.
Before final payment can be made to the contractor, you will also need to receive releases from the
Departments of Revenue and Employment Security Department in addition to ensuring:
• All liens against retainage have been satisfied
• All Affidavit of WagesPaid forms have been filed
Thank you,
Christina Summers
Contract Release Specialist
(360)902-5772
SUMC235@LNI.WA.GOV
cc: MICHELS CORP
PO BOX 15059
TUMWATER WA 98512
Page 2
13
14
Jul 22, 2021 at 23:44:05
10TET5621555852 ±5.00m
400 Andover Park W
Tukwila WA 98188
United States
111 I 28, 2021 at 04:33:2
- — --
10TET5621455845 ±30.09
40t Andover Park
1
Tukdwllp WA 9818
it Udited State
City of Tukwila
City Council Transportation & Infrastructure Services Committee
Meeting Minutes
May2, 2022 5:30 p.m. - Hybrid Meeting; Duwamish Conference Room & MS Teams
Councilmembers Present: Kate Kruller, Chair; Mohamed Abdi, Tosh Sharp
Staff Present: David Cline, Hari Ponnekanti, Griffin Lerner, Brittany Robinson, Seong
Kim, Laurel Humphrey
Chair Kruller called the meeting to order at 5:30 p.m.
I. BUSINESS AGENDA
A. Project Completion: 2020 Central Business District Sanitary Sewer Rehab
Staff is seeking Council approval of contract completion and release of retainage in the amount
of $626,926.18 to the Michels Corporation for the 2020 CBD Sanitary Sewer Rehabilitation
Project.
Committee Recommendation
Unanimous approval. Forward to the May 16, 2022 Regular Consent Agenda.
B. Project Completion: Lift Stations No. 4 & No. 12 Retrofits
Staff is seeking Council approval of contract completion and release of retainage in the final
amount of $10,021.37 to Gary Harper Construction, Inc.for the Lift Stations No. 4 and No. 12
Retrofits.
Committee Recommendation
Unanimous approval. Forward to the May 16, 2022 Regular Consent Agenda.
Councilmember Sharp announced he would not participate in discussion on item C.
C. Seattle City Light Franchise Agreement Update
Staff provided an overview and status of the Seattle City Light Franchise Agreement, which will
begin negotiations soon.
Committee Recommendation
Discussion only.
Miscellaneous
The meeting adjourned at 6:03 p.m.
//�
Committee Chair Approval
Minutes by LH
17