HomeMy WebLinkAboutCOW 2022-06-13 Item 6A - Resolution - 2023-2028 Six-Year Transportation Improvement ProgramCOUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Preaareel by
Major review
Council review
06/13/22
JR
AI Resolution
❑ Ordinance
Mtg Date
06/27/22
JR
❑ Other
Mtg Date
Mtg Date 06/13/22
SPONSOR Council ❑Mayor ❑HR ❑DCD ❑Finance ❑Fire ❑TS ❑P&R ❑Police II PTV ❑Court
SPONSOR'S The Transportation Improvement Program (TIP) must is updated annually per the RCW and
SUMMARY must be adobted by June 30, 2022. The TIP is primarily a financial planning document for
projects competing for grants. Only one project has been removed from the draft 2023-
2028 TIP because of its anticipated completion at the end of this year. Council is being
asked to approve the Resolution for the Six -Year Transportation Improvement Program for
2023 - 2028.
REVIEWED BY
Trans&Infrastructure
❑ CommunitySvs/Safety ❑ Finance Comm. ❑ Planning/Economic Dcv.
❑ Arts Comm. ❑ Parks Comm. Planning Comm.
COMMITTEE CHAIR: KATE KRULLER
❑ LTAC
DATE: 06/06/22
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITTEE
Public Works Department
ITEM INFORMATION
ITEM No.
5&6.A.
7
STAFF SPONSOR: CYNDY KNIGHTON
ORIGINAL AGENDA DATE: 06/13/22
AGENDA ITEM TITLE Resolution for Six -Year Transportation Improvement Program (2023 - 2028)
CATEGORY ❑ Discussion
Mtg Date
❑ Motion
Mtg Date
AI Resolution
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
Mtg Date 06/13/22
SPONSOR Council ❑Mayor ❑HR ❑DCD ❑Finance ❑Fire ❑TS ❑P&R ❑Police II PTV ❑Court
SPONSOR'S The Transportation Improvement Program (TIP) must is updated annually per the RCW and
SUMMARY must be adobted by June 30, 2022. The TIP is primarily a financial planning document for
projects competing for grants. Only one project has been removed from the draft 2023-
2028 TIP because of its anticipated completion at the end of this year. Council is being
asked to approve the Resolution for the Six -Year Transportation Improvement Program for
2023 - 2028.
REVIEWED BY
Trans&Infrastructure
❑ CommunitySvs/Safety ❑ Finance Comm. ❑ Planning/Economic Dcv.
❑ Arts Comm. ❑ Parks Comm. Planning Comm.
COMMITTEE CHAIR: KATE KRULLER
❑ LTAC
DATE: 06/06/22
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITTEE
Public Works Department
Forward to Committee of the Whole and Special Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
06/13/22
06/27/22
MTG. DATE
ATTACHMENTS
06/13/22
Informational Memorandum dated 06/03/2022
06/27/22
Draft Resolution
Draft 2023-2028 TIP Summary
2023-2028 "Draft" Transportation Improvement Program
Current Adopted 2022-2027 TIP
Minutes from Transportation and Infrastructure Committee meeting of 06/06/2022
7
8
TO:
FROM:
BY:
CC:
DATE:
SUBJECT:
City of Tukwila
Allan Ekberg, Mayor
Public Works Department - Hari Ponnekanti, Director/City Engineer
INFORMATION MEMORANDUM
Transportation and Infrastructure Services Committee
Hari Ponnekanti, Public Works Director / City Engineer
Cyndy Knighton, Senior Program Manager
Mayor Ekberg
June 3, 2022
Resolution for Six -Year Transportation Improvement Program (2023 - 2028)
ISSUE
Approve a Resolution adopting the annual update of the Six -Year Transportation Improvement Program
for 2023 - 2028.
BACKGROUND
The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code
of Washington (RCW) and must be adopted by June 30th of each year. The TIP is adopted by resolution
after a public hearing at the local agency level and incorporated into regional and state TIPs. The TIP
is primarily a financial planning document for projects competing for grants. Any project submitted for
federal grant funding must be included in the local, regional, and state adopted TIPs. The TIP is a rolling
plan showing various funding sources: grants, developer, and local funds. Projects "roll" as funds or
stages occur (design report, final design, and construction).
Tukwila's TIP and Capital Improvement Program (CIP) list many of the same transportation -related
projects. The TIP generally lists only those transportation -related projects planned within the next six
years that are deemed regionally significant or that have grant funding awarded or expected. The TIP
is scheduled for adoption on June 27, 2022.
ANALYSIS
The attached spreadsheet is the "Draft" 2023 - 2028 TIP and was created by modifying the 2022 - 2027
TIP to add or remove projects and adjust project costs. No prioritization was assigned, and the list of
projects is presented in alphabetical order. Only one project was removed because it is expected to be
completed before the end of this year.
Deleted: West Valley Highway/Longacres Way
FINANCIAL IMPACT
None.
RECOMMENDATION
Council is being asked to approve the Resolution for the 2023 - 2028 Six -Year Transportation
Improvement Program and consider this item at a Public Hearing at the June 13, 2022 Committee of
the Whole and subsequent June 27, 2022 Special Meeting.
ATTACHMENTS: Draft Resolution
Draft 2023-2028 TIP Summary
2023-2028 "Draft" Transportation Improvement Program
Current Adopted 2022-2027 TIP
9
10
DRAFT
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX-YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2023-
2028), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26, the
City Council of the City of Tukwila has previously adopted a Transportation Improvement
Program and thereafter periodically modified said Transportation Improvement Program
by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six -Year Transportation Improvement Program for the
ensuing six calendar years (2023-2028); and
WHEREAS, on June 13, 2022, a public hearing was held regarding the City's Six -
Year Transportation Improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six -Year Transportation Improvement Program
for the calendar years 2023 to 2028, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the Secretary
of Transportation and the Transportation Improvement Board of the State of Washington.
CC:\Legislative Development\TIP 2023-2028 5-31-22
CK:bjs Review and analysis by Barbara Saxton
Page 1 of 2
11
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Special Meeting thereof this day of , 2022.
ATTEST/AUTHENTICATED:
Christy O'Flaherty, MMC, City Clerk Thomas McLeod, Council President
APPROVED AS TO FORM BY:
Filed with the City Clerk:
Passed by the City Council:
Resolution Number:
Office of the City Attorney
Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2023 to 2028
CC:\Legislative Development\TIP 2023-2028 5-31-22
CK:bjs Review and analysis by Barbara Saxton
12
Page 2 of 2
2021-2026
CIP Sheet
DRAFT 2023 - 2028 TIP SUMMARY
PROJECT TITLE
June 1, 2022
Project Costs in Thousands of Dollars FUNDING SOURCES
2023 2024 2025 2026 2027 2028 TOTAL Federal State/TIB City Unsecured
9 42nd Avenue S Bridge Replacement 2,200 9,450 9,450 0 0 0
4 46th Avenue Safe Routes to School 0 515 2,065 0 0 0
Allentown Truck Reroute Project 700 200 0 0 0 0
14 ADA Improvements 50 50 50 50 50 50
20 APE/Minkler Blvd Intersection 144 1,570 0 0 0 0
13 Annual Bridge Inspections and Repairs 200 200 200 200 200 200
12 Annual Overlay and Repair Program 1,400 1,400 1,500 1,500 1,650 1,650
11 Green River Trail 1,297 0 0 0 0 0
Keeping South King County Moving with TDM 105 210 210 210 105 0
5 Macadam Road S Complete Streets Project 0 0 0 0 0 3,600
18 S 119th St Pedestrian Bridge Painting 0 0 200 0 0 0
S 140th St Intersection Improvements 0 0 0 200 1,200
21 S 144th St Bridge Sidewalks 0 550 2,690 0 0 0
3 S 152nd Street Safe Routes to School 0 2,600 0 0 0 0
South King County Regional TDM 263 263 0 0 0 0
19 Southcenter Blvd/65th Avenue S Signal 100 900 0 0 0 0
Transportation Demand Management Impleme 37 37 37 37 37 38
21,100
2,580
900
300
1,714
1,200
9,100
1,297
840
3,600
200
1,400
3,240
2,600
526
1,000
223
13,500 17,000
2,275 305 2,275
900
300
1,714 1,570
1,200
9,100
989 308
672 168
3,250 350 3,250
200
1,400
2,778 462 2,778
2,340 260 2,340
450 61 15
550 450 550
223 148
TOTAL
PROJECTS REVISED FROM 2021-2027 TIP
New
none
6,496 17,945 16,402 1,997 2,242 6,738 51,820 16,728 27,360 17,132 12,911
Deleted/Completed:
West Valley Highway/Longacres Way
i
Sjrz Washington State
-P VA. Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
STP
TUK-62
42nd Ave S Bridge Replacement
42nd Ave S over the Duwamish River
Interurban Ave S to Northern end of bridge
Replace the existing 42nd Ave S steel truss bridge. The replacement will require
preliminary engineer design, right-of-way, and construction phases. The new
structure will meet current road and bridge design standards. The replacement
structure configuration will be two through -lanes, possibly a turn pocket, and include
sidewalks.
06/13/22
06/27/22
0
2,600,000
11
CN
0.100
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2023
STP
1,500,000
OTHER
1,100,000
0
2,600,000
S
CN
2024
STP(BR)
12,000,000
OTHER
15,900,000
0
27,900,000
Totals
13,500,000
CN
17,000,000
0
30,500,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
2,200,000
0
0
0
0
CN
0
9,450,000
9,450,000
0
0
Totals
2,200,000
9,450,000
9,450,000
0
0
Report Date: June 01, 2022
Page 1
i
Washingtan State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -1111,1
46th Avenue Safe Routes to School
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
06/13/22
06/27/22
85,000
265,000
05
RW
0.370
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2024
0
SRTS
180,000
85,000
265,000
P
RW
2024
0
SRTS
230,000
20,000
250,000
P
CN
2025
0
SRTS
1,865,000
200,000
2,065,000
Totals
0
0
2,275,000
305,000
2,580,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
265,000
0
0
0
RW
0
250,000
0
0
0
CN
0
0
2,065,000
0
0
Totals
0
515,000
2,065,000
0
0
C31 Report Date: June 01, 2022
Page 2
i
Sjrz Washington State
a) VADepartment of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA05409
Allentown Truck Reroute Project
to
Study alternatives for truck access to reroute outside of residential neighborhood.
06/13/22
06/27/22
1,000,000
1,000,000
18
0
700,000
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2023
0
0
1,000,000
1,000,000
Totals
0
700,000
0
1,000,000
1,000,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
700,000
200,000
0
0
0
Totals
700,000
200,000
0
0
0
Report Date: June 01, 2022
Page 3
i
Was-hingto, State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
4th
WA -05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
06/13/22
06/27/22
300,000
300,000
06
0
50,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2023
4th
0
5th & 6th
0
300,000
300,000
Totals
0
50,000
0
300,000
300,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
50,000
50,000
50,000
50,000
100,000
Totals
50,000
50,000
50,000
50,000
100,000
�1 Report Date: June 01, 2022
Page 4
i
Sjrz Washingtm, State
Co liar Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -07746
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
06/13/22
06/27/22
134,000
134,000
03
C G O P S
TW
2023
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2023
0
0
134,000
134,000
S
RW
2023
0
0
10,000
10,000
P
CN
2024
0
10,000
0
1,570,000
1,570,000
Totals
0
0
0
1,714,000
1,714,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
134,000
0
0
0
0
RW
10,000
0
0
0
0
CN
0
1,570,000
0
0
0
Totals
144,000
1,570,000
0
0
0
Report Date: June 01, 2022
Page 5
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
4th
WA -03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
06/13/22
06/27/22
1,200,000
1,200,000
06
0
200,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2023
4th
0
5th & 6th
0
1,200,000
1,200,000
Totals
0
200,000
0
1,200,000
1,200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
200,000
200,000
200,000
200,000
400,000
Totals
200,000
200,000
200,000
200,000
400,000
CO Report Date: June 01, 2022
Page 6
i
Washington State
O VW Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
4th
WA -03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/13/22
06/27/22
9,100,000
9,100, 000
06
C G O P S
TW
1,400,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2023
4th
0
5th & 6th
0
9,100,000
9,100, 000
Totals
0
1,400,000
0
9,100,000
9,100,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
1,400,000
1,400,000
1,500,000
1,500,000
3,300,000
Totals
1,400,000
1,400,000
1,500,000
1,500,000
3,300,000
Report Date: June 01, 2022
Page 7
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
TAP(UL)
TUK-50A
Green River Trail Improvements
Green River Trail
Christensen Road to TUC Pedestrian Bridge
The Green River Trail Connector Project will replace approximately 700 feet of
existing trail with a widened 12 -foot paved pathway, 2 -foot gravel shoulders,
illumination and security cameras. A new pedestrian plaza will also be constructed
where the Green River Trail intersects with Christensen Road, including way -finding
signs to major destinations. The TUK-50A programming is only for the construction
phase of these improvements. The PE phase is included in TUK-50.
06/13/22
06/27/02
308,000
1,297,000
28
989,000
0.130
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2023
TAP(UL)
989,000
0
308,000
1,297,000
Totals
989,000
1,297,000
0
308,000
1,297,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
1,297,000
0
0
0
0
Totals
1,297,000
0
0
0
0
N
Report Date: June 01, 2022
Page 8
i
Washington State
N VADepartment of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
4th
TUK-63
Keeping South King County Moving with TDM
South King County
Various to Various
This project will help people access sustainable transportation options that reduce
drive -alone travel and traffic congestion in South King County. TDM programming
and services will be provided to residents, workers, visitors, employers, property
managers, and students in Tukwila and the partnering jurisdictions of Burien, Des
Moines, Kent, Renton, and SeaTac. The program will target those willing and able to
try sustainable modes of transportation at activity centers (community hubs,
commercial areas, business parks, multifamily housing complexes, and educational
institutions). Examples of activity centers include the Tukwila International Boulevard
District, Southcenter, and Sea -Tac Airport. The TDM Program will work in partnership
with transit agencies, nonprofits, employers, and community organizations to reach
priority populations through trusted channels. The project aims to reduce 542,997
vehicle trips and 8,093,549 vehicle miles traveled.
06/13/22
06/27/22
168,000
840,000
44
0
0.000
672,000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2023
4th
0
OTHER
672,000
168,000
840,000
Totals
0
210,000
672,000
168,000
840,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
105,000
210,000
210,000
210,000
105,000
Totals
105,000
210,000
210,000
210,000
105,000
Report Date: June 01, 2022
Page 9
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
4th
WA -1111(
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
and rechannelization to add 5 -foot bike lanes and 5 -foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
06/13/22
06/27/22
40,000
400,000
04
RW
0.350
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2028
4th
0
Ped/Bike Program
360,000
40,000
400,000
P
RW
2028
0
Ped/Bike Program
90,000
10,000
100,000
P
CN
2028
0
Ped/Bike Program
2,800,000
300,000
3,100,000
Totals
0
3,250,000
350,000
3,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
3,600,000
Totals
0
0
0
0
3,600,000
N
W Report Date: June 01, 2022
Page 10
Washington State
-P VW Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -13494
S 119th St Pedestrian Bridge Painting
S 119th Street
West bank Duwamish River to East bank Duwamish River
Ongoing maintenance of the S 119th Street Pedestrian Bridge in the
Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance
needed.
06/13/22
06/27/22
200,000
200,000
06
0
0.040
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2024
0
0
200,000
200,000
Totals
0
0
0
200,000
200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
0
0
200,000
0
0
Totals
0
0
200,000
0
0
Report Date: June 01, 2022
Page 11
i
Washingta, State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
4th
WA -09873
S 140th St Intersection Improvements
S 140th Street
Tukwila International Blvd to
Design and construct a new traffic signal at the S 140th Street/Tukwila International
Blvd intersection
06/13/22
06/27/22
150,000
150,000
04
C G P S T
W
0.100
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2027
4th
0
5th & 6th
0
150,000
150,000
P
RW
2027
0
0
50,000
50,000
P
CN
2028
0
0
1,200,000
1,200,000
Totals
0
0
1,400,000
1,400,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
150,000
RW
0
0
0
0
50,000
CN
0
0
0
0
1,200,000
Totals
0
0
0
0
1,400,000
N
C31 Report Date: June 01, 2022
Page 12
i
Washington State
a) 074Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
SRTS
WA03782
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1-5 between 51st Ave S and 53rd Ave S
06/13/22
06/27/22
74,250
550,000
28
CN
0.250
SRTS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2024
SRTS
475,750
0
74,250
550,000
P
CN
2025
SRTS
2,302,000
0
388,000
2,690,000
Totals
2,777,750
CN
0
462,250
3,240,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
550,000
0
0
0
CN
0
0
2,690,000
0
0
Totals
0
550,000
2,690,000
0
0
Report Date: June 01, 2022
Page 13
i
Was-hingto, State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -1111'
S 152nd Street Safe Routes to School
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Design and construct curb, gutter and sidewalks on both sides including widening
pavement width by 3 feet to construct on -street parking lane on north side of street.
06/13/22
06/27/22
260,000
2,600,000
05
0
0.300
2,340,000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2024
0
SRTS
2,340,000
260,000
2,600,000
Totals
0
0
2,340,000
260,000
2,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
0
2,600,000
0
0
0
Totals
0
2,600,000
0
0
0
N
�1 Report Date: June 01, 2022
Page 14
Washington State
CO VW Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
CMAQ
TUK-64
South King County TDM
South King County
N/A to N/A
This project will provide TDM programming and services at selected activity centers
in Tukwila and partnering South King County jurisdictions. Activity centers include
community hubs, commercial areas, business parks, multifamily housing complexes,
and educational institutions. For example, places such as Tukwila International
Boulevard District, Southcenter, and Sea -Tac Airport. By providing transportation
resources and incentives, the project will encourage people to choose sustainable
transportation options that reduce drive -alone travel and traffic congestion in South
King County. TDM services will be provided to residents, commuters, and visitors,
targeting those willing and able to try sustainable modes of transportation. The
program will work in partnership with partner agencies, nonprofits, employers, and
community organizations.
06/13/22
06/27/22
15,000
525,750
24
450,000
0.000
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2023
CMAQ
450,000
OTHER
60,750
15,000
525,750
Totals
450,000
262,875
60,750
15,000
525,750
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
262,875
262,875
0
0
0
Totals
262,875
262,875
0
0
0
Report Date: June 01, 2022
Page 15
MIL
vingtun State
Department o! Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA -13495
Southcenter Blvd/65th Avenue S Signal
Southcenter Boulevard
65th Avenue S to
Design and construct a new traffic signal at the Southcenter Boulevard/65th Avenue
S intersection to improve level of service and safety.
06/13/22
06/27/22
50,000
100,000
21
CN
2023
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2023
0
TIB
50,000
50,000
100,000
P
CN
2023
0
TIB
500,000
400,000
900,000
Totals
0
CN
550,000
450,000
1,000,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
100,000
0
0
0
0
CN
0
900,000
0
0
0
Totals
100,000
900,000
0
0
0
N
CO Report Date: June 01, 2022
Page 16
Was-hin a, StateO VW Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2023 to 2028
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -13491
Transportation Demand Management Implementation
to
Provision of TDM services to Commute Trip Reduction -affected employment sites.
Facilitate employer reporting and records associated with biennial CTR survey.
Engage CTR employment sites with opportunities for improvement and remain
connected via technical meetings with other CTR jurisdictional representatives.
06/13/22
06/27/22
0
74,204
44
ALL
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2023
0
WSDOT
74,204
0
74,204
P
ALL
2023
0
WSDOT
148,408
0
148,408
Totals
0
222,612
0
222,612
Expenditure Schedule
Federal Funds
State Funds
Local Funds
Total Funds
Phase
17,716,750
1st
26,370,362
2nd
61,319,362
3rd
4th
5th & 6th
ALL
37,102
37,102
37,102
37,102
74,204
Totals
37,102
37,102
37,102
37,102
74,204
Report Date: June 01, 2022
Page 17
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
17,716,750
26,370,362
17,232,250
61,319,362
Report Date: June 01, 2022
Page 17
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
STP
TUK-62
42nd Ave S Bridge Replacement
42nd Ave S over the Duwamish River
Interurban Ave S to Northern end of bridge
Replace the existing 42nd Ave S steel truss bridge. The replacement will require
preliminary engineer design, right-of-way, and construction phases. The new
structure will meet current road and bridge design standards. The replacement
structure configuration will be two through -lanes, possibly a turn pocket, and include
sidewalks.
06/14/21
06/21/21
0
2024
11
CN
0.100
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2022
STP
1,500,000
0
0
1,500,000
P
CN
2024
STP(BR)
12,000,000
TIB
3,000,000
0
15,000,000
P
CN
2024
STP
2,000,000
FMSIB
500,000
3,029,000
5,529,000
Totals
15,500,000
9,450,000
3,500,000
3,029,000
22,029,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
750,000
1,250,000
0
0
0
CN
0
0
9,450,000
9,450,000
0
Totals
750,000
1,250,000
9,450,000
9,450,000
0
W
Report Date: June 15, 2021
Page 1
i
Washinglan State
N "sir Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -11113
46th Avenue Safe Routes to School
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
06/14/21
06/21/21
85,000
2024
05
RW
0.370
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
SRTS
180,000
85,000
265,000
P
RW
2023
0
SRTS
230,000
20,000
250,000
P
CN
2024
0
SRTS
1,865,000
200,000
2,065,000
Totals
0
0
2,275,000
305,000
2,580,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
265,000
0
0
0
0
RW
0
250,000
0
0
0
CN
0
0
2,065,000
0
0
Totals
265,000
250,000
2,065,000
0
0
Report Date: June 15, 2021
Page 2
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
4th
WA -05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
06/14/21
06/21/21
285,000
2024
06
0
50,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2022
4th
0
5th & 6th
0
285,000
285,000
Totals
0
50,000
0
285,000
285,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
35,000
50,000
50,000
50,000
100,000
Totals
35,000
50,000
50,000
50,000
100,000
W
W Report Date: June 15, 2021
Page 3
i
Washin an:matte
� IVA. Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
RW
WA -07746
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
06/14/21
06/21/21
134,000
2024
03
C G O P S
TW
2022
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
RW
0
0
0
134,000
134,000
P
RW
2022
0
0
0
0
10,000
10,000
P
CN
2023
0
0
1,570,000
1,570,000
Totals
0
0
1,714,000
1,714,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
134,000
0
0
0
0
RW
10,000
0
0
0
0
CN
0
1,570,000
0
0
0
Totals
144,000
1,570,000
0
0
0
Report Date: June 15, 2021
Page 4
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
4th
WA -03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
06/14/21
06/21/21
1,075,000
2024
06
0
200,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2022
4th
0
5th & 6th
0
1,075,000
1,075,000
Totals
0
200,000
0
1,075,000
1,075,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
75,000
200,000
200,000
200,000
400,000
Totals
75,000
200,000
200,000
200,000
400,000
W
C31 Report Date: June 15, 2021
Page 5
i
Washington State� VW Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
4th
WA -03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/14/21
06/21/21
8,850,000
2024
06
C G O P S
TW
1,400,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2022
4th
0
5th & 6th
0
8,850,000
8,850,000
Totals
0
1,400,000
0
8,850,000
8,850,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
1,400,000
1,400,000
1,400,000
1,500,000
3,150,000
Totals
1,400,000
1,400,000
1,400,000
1,500,000
3,150,000
Report Date: June 15, 2021
Page 6
i
Watlington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
4th
WA05409
BNSF Regional Center Access Study
to
Study access to the BNSF Regional Distribution Center.
06/14/21
06/21/21
100,000
2024
18
0
0
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2027
4th
0
5th & 6th
0
100,000
100,000
Totals
0
0
0
100,000
100,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
100,000
Totals
0
0
0
0
100,000
W
�1 Report Date: June 15, 2021
Page 7
Washington State
CO VW Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -11115
Green River Trail
Green River Trail
Christensen Road to Green River
Replace the existing 8 -foot wide Green River Trail with 12 -foot wide concrete paved
trail with 2 -foot gravel shoulders, including illumination, CCTV, wayfinding, and
pedestrian plaza.
06/14/21
06/21/21
8,000
2024
28
CN
0.140
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
Ped/Bike Program
66,000
8,000
74,000
P
CN
2023
0
Ped/Bike Program
900,000
300,000
1,200,000
Totals
0
CN
966,000
308,000
1,274,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
74,000
0
0
0
0
CN
0
1,200,000
0
0
0
Totals
74,000
1,200,000
0
0
0
Report Date: June 15, 2021
Page 8
i
WiWashingtan State
r Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
TUK-63
Keeping South King County Moving with TDM
South King County
Various to Various
This project will help people access sustainable transportation options that reduce
drive -alone travel and traffic congestion in South King County. TDM programming
and services will be provided to residents, workers, visitors, employers, property
managers, and students in Tukwila and the partnering jurisdictions of Burien, Des
Moines, Kent, Renton, and SeaTac. The program will target those willing and able to
try sustainable modes of transportation at activity centers (community hubs,
commercial areas, business parks, multifamily housing complexes, and educational
institutions). Examples of activity centers include the Tukwila International Boulevard
District, Southcenter, and Sea -Tac Airport. The TDM Program will work in
partnership with transit agencies, nonprofits, employers, and community
organizations to reach priority populations through trusted channels. The project
aims to reduce 542,997 vehicle trips and 8,093,549 vehicle miles traveled.
06/14/21
06/21/21
0
2024
44
ALL
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2022
0
OTHER
672,000
0
672,000
S
ALL
2022
0
OTHER
168,000
0
168,000
Totals
0
840,000
0
840,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
210,000
210,000
210,000
210,000
0
Totals
210,000
210,000
210,000
210,000
0
W
CO Report Date: June 15, 2021
Page 9
i
miz Washingtan State
O liar Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -11110
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
and rechannelization to add 5 -foot bike lanes and 5 -foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
06/14/21
06/21/21
40,000
2024
04
RW
0.350
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
0
Ped/Bike Program
360,000
40,000
400,000
P
RW
2022
0
Ped/Bike Program
90,000
10,000
100,000
P
CN
2023
0
Ped/Bike Program
2,800,000
300,000
3,100,000
Totals
0
0
3,250,000
350,000
3,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
400,000
0
0
0
RW
0
100,000
0
0
0
CN
0
0
3,100,000
0
0
Totals
0
500,000
3,100,000
0
0
Report Date: June 15, 2021
Page 10
i
Was-hingto, State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -13494
S 119th St Pedestrian Bridge Painting
S 119th Street
West bank Duwamish River to East bank Duwamish River
Ongoing maintenance of the S 119th Street Pedestrian Bridge in the
Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance
needed.
06/14/21
06/21/21
200,000
2024
06
0
0.040
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2024
0
0
200,000
200,000
Totals
0
0
0
200,000
200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
0
0
200,000
0
0
Totals
0
0
200,000
0
0
Report Date: June 15, 2021
Page 11
i
jrz Washinglan State
N "sir Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -09873
S 140th St Intersection Improvements
S 140th Street
Tukwila International Blvd to
Design and construct a new traffic signal at the S 140th Street/Tukwila International
Blvd intersection
06/14/21
06/21/21
150,000
2024
04
C G P S T
W
0.100
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2027
0
0
150,000
150,000
P
RW
2027
0
0
50,000
50,000
P
CN
2027
0
0
0
1,200,000
1,200,000
Totals
0
0
0
1,400,000
1,400,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
150,000
0
0
0
RW
0
50,000
0
0
0
CN
0
0
1,200,000
0
0
Totals
0
200,000
1,200,000
0
0
Report Date: June 15, 2021
Page 12
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
SRTS
WA03782
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1-5 between 51st Ave S and 53rd Ave S
06/14/21
06/21/21
43,000
2024
28
400,000
0.250
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2023
SRTS
400,000
0
43,000
443,000
Totals
400,000
0
0
43,000
443,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
443,000
0
0
0
Totals
0
443,000
0
0
0
W Report Date: June 15, 2021
Page 13
miz Washington State
-P liar Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -11112
S 152nd Street Safe Routes to School
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Design and construct curb, gutter and sidewalks on both sides including widening
pavement width by 3 feet to construct on -street parking lane on north side of street.
06/14/21
06/21/21
260,000
2024
05
0
0.300
2,340,000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2023
0
SRTS
2,340,000
260,000
2,600,000
Totals
0
0
2,340,000
260,000
2,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
0
2,600,000
0
0
0
Totals
0
2,600,000
0
0
0
Report Date: June 15, 2021
Page 14
i
Washington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
CMAQ
TUK-64
South King County TDM
South King County
N/A to N/A
This project will provide TDM programming and services at selected activity centers
in Tukwila and partnering South King County jurisdictions. Activity centers include
community hubs, commercial areas, business parks, multifamily housing complexes,
and educational institutions. For example, places such as Tukwila International
Boulevard District, Southcenter, and Sea -Tac Airport. By providing transportation
resources and incentives, the project will encourage people to choose sustainable
transportation options that reduce drive -alone travel and traffic congestion in South
King County. TDM services will be provided to residents, commuters, and visitors,
targeting those willing and able to try sustainable modes of transportation. The
program will work in partnership with partner agencies, nonprofits, employers, and
community organizations.
06/14/21
06/21/21
15,000
2024
24
450,000
0.000
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2023
CMAQ
450,000
OTHER
60,750
15,000
525,750
Totals
450,000
100,000
60,750
15,000
525,750
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
100,000
175,000
175,000
75,750
0
Totals
100,000
175,000
175,000
75,750
0
C31 Report Date: June 15, 2021
Page 15
miz Washington State
a) liar Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
CN
WA -13495
Southcenter Blvd/65th Avenue S Signal
Southcenter Boulevard
65th Avenue S to
Design and construct a new traffic signal at the Southcenter Boulevard/65th Avenue
S intersection to improve level of service and safety.
06/14/21
06/21/21
50,000
2024
21
CN
2023
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2022
CN
0
TIB
50,000
50,000
100,000
P
CN
2023
0
0
TIB
500,000
400,000
900,000
Totals
0
550,000
450,000
1,000,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
100,000
0
0
0
0
CN
0
900,000
0
0
0
Totals
100,000
900,000
0
0
0
Report Date: June 15, 2021
Page 16
i
Watlington State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -13491
Transportation Demand Management Implementation
to
Provision of TDM services to Commute Trip Reduction -affected employment sites.
Facilitate employer reporting and records associated with biennial CTR survey.
Engage CTR employment sites with opportunities for improvement and remain
connected via technical meetings with other CTR jurisdictional representatives.
06/14/21
06/21/21
0
2024
44
ALL
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2022
0
WSDOT
74,204
0
74,204
P
ALL
2022
0
WSDOT
148,408
0
148,408
Totals
0
222,612
0
222,612
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
37,102
37,102
37,102
37,102
74,204
Totals
37,102
37,102
37,102
37,102
74,204
�1 Report Date: June 15, 2021
Page 17
miz Washington State
CO liar Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2022 to 2027
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
/0181(019) TUK-60
West Valley Highway/Longacres Way Shared Use Pathways
SR 181 & Longacres Way
West end of planned Green River Bridge to Longacres Way
The West Valley Highway/Longacres Way project modifies northbound
channelization between Strander Boulevard and S 156th Street. A 600ft section of
general-purpose lane will be added, north of Strander. The existing dedicated NB
turn lane at Longacres will change to a thru-right lane, transitioning into 2 NB thru
lanes on the north leg as the existing inside lane will be changed to a dedicated NB
left turn lane. Sidewalks will be added to the east side of the roadway where there
are currently none. A wider, shared -use path will replace the existing sidewalk on the
west side of the road between Longacres Way and the new sidewalks installed for
the Pedestrian -Bicycle bridge. A new two-way cycle track will be added to Longacres
Way from WVH to the Tukwila Station, including new street and pedestrian
illumination. A pedestrian signal crossing of WVH near the landing of the Ped -Bike
bridge and a rapid flashing beacon on Longacres at the Interurban Trail crossing will
be added.
06/14/21
06/21/21
40,000
2024
28
0
0.170
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2022
0
TIB
100,000
40,000
140,000
Totals
0
140,000
100,000
40,000
140,000
Expenditure Schedule
Federal Funds
State Funds
Local Funds
Total Funds
Phase
16,350,000
1st
14,104,362
2nd
48,878,362
3rd
4th
5th & 6th
CN
140,000
0
0
0
0
Totals
140,000
0
0
0
0
Report Date: June 15, 2021
Page 18
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
16,350,000
14,104,362
18,424,000
48,878,362
Report Date: June 15, 2021
Page 18
Transportation & Infrastructure Services Committee Minutes June 6, 2022
Committee Recommendation
Unanimous approval. Forward to the June 13, 222 Special Consent Agenda.
E. Resolution: Six -Year Transportation Improvement Program
*Staff is seeking Council approval of the resolution adopting the annual update of the Six -Year
Transportation Improvement Program for 2023-2028.
Committee Recommendation
Unanimous approval. Forward to June 13, 2022 Committee of the Whole for Public Hearing.
F. Ordinance: NPDES Phase II Municipal Stormwater Permit
Staff is seeking Council approval of an ordinance to adopt the 2021 King County Surface Water
Design Manual and the 2021 King County Stormwater Pollution Prevention Manual.
Committee Recommendation
Unanimous approval. Forward to June 13, 2022 Committee of the Whole
G. Contract: Gilliam Creek Fish Barrier Removal and Habitat Consultant
Staff is seeking Council approval of a contract with Otak in an amount not to exceed $330,622
for engineering and design of the Gilliam Creek Fish Barrier Removal and Habitat
Enhancement.
Committee Recommendation
Majority approval. Forward to June 13, 2022 Special Consent Agenda.
Miscellaneous
Meeting Packets - Committee members discussed meeting packets. Staff will ensure quality
control of future hard copy packets to ensure all pages are complete.
Meeting Conduct - Committee members discussed meeting productivity. Chair Kruller
requested that questions and comments be germane to the staff request in accordance with
parliamentary procedure.
Item(s) for follow-up:
• Staff will return with an educational item on how large capital projects are sequenced,
including coordination with utility providers.
The meeting adjourned at 6:23 p.m.