HomeMy WebLinkAboutTIS 2022-06-21 Item 2D - Update - Public Safety Plan: Public Works Shops Phase IICity of Tukwila
Allan Ekberg, Mayor
Public Works Department - Hari Ponnekanti, Director/City Engineer
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Services Committee
FROM: Hari Ponnekanti, Public Works Director/ City Engineer
BY: Justine Kim, Senior Project Manager, Shiels Obletz Johnsen, Inc.
CC: Mayor Allan Ekberg
DATE: June 17, 2022
SUBJECT: Public Works (Administration Building) Shops Phase 2
Project Update
Issue
Provide update regarding Phase 2 of the Public Works Administration Building Shops Project and a
draft project schedule.
Background
The City Council has an adopted a Combined Public Works Shop Capital Project as part of the City's
Public Safety Plan. This project was most recently updated in the 2021-2022 Adopted Budget. The City
chose a site in 2017, purchased properties in 2018 and began Phase 1 design and construction in
2019. Phase 1 of the Public Works Shop is being opened this month. Phase 2 of the Public Work
Shops was discussed in the Transportation and Infrastructure Services Committee on April 18, 2022,
and at the Finance and Governance Committee on April 25, 2022. At the May 9, 2022, Committee of
the Whole meeting, Council further discussed this project, and provided their direction and approval for
staff to seek a Request for Qualifications for designing the Public Works Shops Phase 2 Project.
Per Council direction, City staff are currently in the process of procuring the Architects and Engineering
(A/E) Team via a publicly advertised Request for Qualifications process. In preparation for this process,
a more detailed overall draft project schedule has been developed which has identified that our original
timeline discussed previously was too aggressive. When accounting for proper Council engagement
and approval processes at each project phase - design, bidding, and construction contract award - the
attached project schedule shows the estimated construction start to be possible in the spring of 2025.
Project Schedule
• June — August 2022: A/E Team Selection and Contract Negotiation for Council approval
• September — October 2022: Notice to Proceed and Site Analysis/Preliminary Design/Test to
Fit studies for Council update
• November 2022 — May 2023: Schematic Design and Estimate for Council approval
• June 2023 — February 2024: Design Development and Estimate for Council approval
• November 1, 2023: Per existing agreements, City assumes ownership of the UPS property.
• March 2024 — January 2025: Construction Documents and Permitting update for Council
approval to go to bidding
• February — April 2025: Bidding and Construction Contract for Council approval
• April 2025 — November 2026: Construction Phase
• November — December 2026: Move -in process
Fleet & Facility Services - 14000 Interurban Avenue, Tukwila, WA 98168 - 206-431-0166
Tukwila City Hall • 6200 Southcenter Boulevard • Tukwila, WA 98188 • 206-433-1800 • Website: TukwilaWA.gov
35
INFORMATIONAL MEMO
Page 2
Analysis
The attached draft schedule is assuming an appropriate but timely approval process for the Council at
the end of each phase and key, milestone decision points. The project design, permitting, and bidding
process will take approximately 30 months from the start of Schematic Design (November 2022) to the
start of construction (April of 2025). There will be no active leases on the property when the City
assumes ownership of the property on November 1, 2023. Because the City will not be able to start
construction until April 2025, Economic Development staff has been engaged to identify possible
tenant(s) for the property. Lease agreements will be structured to avoid any impacts with the City's
construction project.
Having the property occupied and operating is the best option for the City, while the design and
permitting process for the new Administration building will be in progress. The additional lease income
could be beneficial toward the project funding strategy, as well as ensuring the safety and security of
the site, which will be adjacent to the soon to be occupied Public Works Fleet & Facilities (Phase I)
building.
Next Steps
1. Authorize the Mayor to enter into lease agreement(s) for the property.
2. Complete the procurement process for the A/E project team for the new Administration
Building by end of July and negotiate the contract for Council approval in August.
3. Select the Geotech consultant and Surveyor and prepare contracts for council approval in
July.
4. Examine funding path and explore grant opportunities.
5. Start the building design and permitting process after Council approval of Site Analysis and
Test to Fit studies.
6. Select the contractor and bring the recommendation to the Council in the first quarter of 2025.
7. Start construction to maximize development potential of newly acquired City property.
Recommendation
Discussion Only.
Attachment: Tukwila Public Works Administration Building Project Draft Schedule
Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov
36
TUKWILA PUBLIC WORKS ADMINISTRATION BUILDING PROJECT SCHEDULE - DRAFT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
SELECTION OF PMQA
CONSULTANT
RFQ ADVERTISEMENT OF
ARCHITECTS/ENGINEERS
PROCUREMENT OF GEOTECH
AND SURVEY CONSULTANTS
GEOTECH, SURVEY
CONTRACTS APPROVAL
PREPARE SURVEY AND
GEOTECH REPORT
A/E TEAM INTERVIEW
A/E CONTRACT
NEGOTIATIONS
A/E SELECTION AND
CONTRACT APPROVAL FROM
COUNCIL
A/E SITE ANALYSIS / TEST TO
FIT / PRELIMINARY ESTIMATE
REPORT TO COUNCIL ON
ANALYSIS AND APPROVAL
SCHEMATIC DESIGN PHASE
AND ESTIMATE
REPORT TO COUNCIL FOR
APPROVAL
DESIGN DEVELOPMENT
PHASE AND ESTIMATE
UPS PARCEL OWNERSHIP
TRANSFER
REPORT TO COUNCIL
FOR APPROVAL
CONSTRUCTION DOCUMENTS
AND ESTIMATE
SUBMIT FOR
BUILDING PERMIT
BIDDING PERIOD
CONSTRUCTION
MOVE -IN
2022
2023
2024
2025
2026
J
F
MAMJ J ASOND
J F
M
A M J J A S ON D
J FMAM
J J ASOND
J FMAMJ J ASOND
J FMAMJ J A S O N D
mid May to mid June
month of June
IeallyJunl to midJune
mid June to late June
1
Iearly July (2 weeks)
month of July
I
I mid to late July
I
month of August
II
late August to mid Oc ober
1
late October
November 2022 to May 2023
'mid to late May
June 2023 to February 2024
November 1, 2023
J I I
early February 2024
I I I
August 2024
March 2024 to end of January 2025
February to March 2025
April 2025 to October 202611111
November / December 20261
37