HomeMy WebLinkAboutRes 2072 - 2024-2029 Transportation Improvement ProgramWashington
Resolution No.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX-YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2024-
2029), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26, the
City Council of the City of Tukwila has previously adopted a Transportation Improvement
Program and thereafter periodically modified said Transportation Improvement Program
by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six -Year Transportation Improvement Program for the
ensuing six calendar years (2024-2029); and
WHEREAS, on June 12, 2023, a public hearing was held regarding the City's Six -
Year Transportation Improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six -Year Transportation Improvement Program
for the calendar years 2024 to 2029, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the Secretary
of Transportation and the Transportation Improvement Board of the State of Washington
CC:\Legislative Development\TIP 2024-2029 5-2-23
Cyndy Knighton Review by Andy Youn Page 1 of 2
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Special Meeting thereof this 2A6- day of (Apk, , 2023.
ATTEST/AUTHENTICATED:
1.—DocuSigned by:
aCriShl FL4ALVIL(1
88678483C8594E7 .
Christy O'Flaherty, MMC C n hia Delostrinos Johnson
City Clerk Council President
APPROVED AS TO FORM BY:
f—DoctiSigned by:
co\LL
5F ACM r AA 165F d
Office of the City Attorney
Filed with the City Clerk: ‘P-1-°-7-3
Passed by the City Council: 6-L6
Resolution Number:
Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2024 to 2029
CCALegislative Development\TIP 2024-2029 5-2-23
Cyndy Knighton Review by Andy Youn
Page 2 of 2
Washington State
War Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
S.
05
STBG(UL)
/ 1037(004) TUK-62
42nd Ave S Bridge Replacement
42nd Ave S over the Duwamish River
Interurban Ave S to Northern end of bridge
Replace the existing 42nd Ave S steel truss bridge. The replacement will require
preliminary engineer design, right-of-way, and construction phases. The new
structure will meet current road and bridge design standards. The replacement
structure configuration will be two through -lanes, possibly a turn pocket, and include
sidewalks.
06/12/23
06/26/23
1,100,000
2,600,000
11
RW
0.100
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2024
STBG(UL)
1,500,000
0
0
1,100,000
2,600,000
S
RW
2024
BR
86,500
0
0
13,500
100,000
S
CN
2024
BR
11,913,500
MAW
17,000,000
0
28,913,500
Totals
13,500,000
17,000,000
1,113,500
31,613,500
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
800,000
0
0
0
0
RW
100,000
0
0
0
0
CN
0
15,636,500
13,500,000
0
0
Totals
900,000
15,636,500
13,500,000
0
0
Report Date: May 04, 2023
Page 1
Washington Stato
VAIII Department of Transportation
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
-n
c
z
n
0 mt
..7 o
N
x. a
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
RW
WA -1111::
46th Avenue Safe Routes to School
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
06/12/23
06/26/23
90,000
270,000
05
RW
0.370
0
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2024
RW
0
SRTS
180,000
90,000
270,000
P
RW
2024
0
0
SRTS
220,000
20,000
240,000
P
CN
2025
0
SRTS
1,660,000
410,000
2,070,000
Totals
0
2,060,000
520,000
2,580,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th 8 6th
PE
270,000
0
0
0
0
RW
240,000
0
0
0
0
CN
0
2,070,000
0
0
0
Totals
510,000
2,070,000
0
0
0
Report Date: May 04, 2023
Page 2
W shn t
DopHrtmo+ntingtost of T mttportotkm
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class)
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type'
RW Required''.
00
WA05409
Allentown Truck Reroute Project
to
Study alternatives for truck access to reroute outside of residential neighborhood.
06/12/23
06/26/23
600,000
600,000
18
0
600,000
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2024
0
0
600,000
600,000
Totals
0
600,000
0
600,000
600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
600,000
0
0
0
0
Totals
600,000
0
0
0
0
Report Date: May 04, 2023
Page 3
Ai
Washington State
Department at Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
-n
c
0
0
o 0:
a, 2
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes]
Total Length
Environmental Type
RW Required
00
4th
WA -05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
06/12/23
06/26/23
435,000
435,000
06
0
50,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2024
4th
0
5th & 6th
0
435,000
435,000
Totals
0
50,000
0
435,000
435,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
50,000
50,000
50,000
50,000
100,000
Totals
50,000
50,000
50,000
50,000
100,000
Report Date: May 04, 2023
Page 4
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted:.
Amendment
Resolution No.
Improvement Type
r)
o,
Total Length
Environmental Type
RW Required
16
WA -07746
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
06/12/23
06/26/23
134,000
134,000
03
C G O P S
TW
2025
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2025
0
0
134,000
134,000
S
RW
2025
0
0
0
0
10,000
10,000
P
CN
2026
0
0
0
1,570,000
1,570,000
Totals
0
0
1,714,000
1,714,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
134,000
0
0
0
RW
0
10,000
0
0
0
CN
0
0
1,570,000
0
0
Totals
0
144,000
1,570,000
0
0
Report Date: May 04, 2023
Page 5
�� W*sh ttjton Stat
7/1 Dona meat of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
n,
,
u 0
m
Priority Number
A, PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
c
Adopted
Amendment
Resolution No.
Improvement Type
Ei
2
r1
oa
m
Total Length
Environmental Type',
RW Required
04
RW
WA -15107
Andover Park East/Industry Dr Intersection
Andover Park E
Industry Drive to
Design and construct traffic signal with Andover Park East left turn lanes and
crosswalks.
06/12/23
06/26/23
75,000
75,000
03
P
0.100
657,000
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2025
RW
0
10,000
0
75,000
75,000
S
RW
2025
657,000
0
0
0
10,000
10,000
P
CN
2026
0
0
657,000
657,000
Totals
0
0
742,000
742,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
75,000
0
0
0
RW
0
10,000
0
0
0
CN
0
0
657,000
0
0
Totals
0
85,000
657,000
0
0
Report Date: May 04, 2023
Page 6
MIL
IV;Washington Stator
Department at Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
-ri
c
3
°
0 at
rii g
r, B.
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E Begin 8 End Termini
F. Project Description G. Structure ID
2
a
ID
m.
2,
Adopted
Amendment
Resolution No,
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
06/12/23
06/26/23
1,345,000
1,345,000
06
0
205,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2024
0
0
1,345,000
1,345,000
Totals
0
205,000
0
1,345,000
1,345,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th 8, 6th
ALL
205,000
215,000
220,000
230,000
475,000
Totals
205,000
215,000
220,000
230,000
475,000
Report Date: May 04, 2023
Page 7
411111a
Washington State
V. Department of Transportatton
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/12/23
06/26/23
8,850,000
8,850,000
06
CGOPS
TW
1,500,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2024
0
0
8,850,000
8,850,000
Totals
0
1,500,000
0
8,850,000
8,850,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th 8. 6th
ALL
1,400,000
1,400,000
1,400,000
1,500,000
3,150,000
Totals
1,400,000
1,400,000
1,400,000
1,500,000
3,150,000
Report Date: May 04, 2023
Page 8
Wathksgton State
Vapr Department at Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C, Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
ALL
00
WA -15104
Annual Traffic Signal Program
Varies
to
Design and construct traffic signal upgrades and repairs of signals that exceed
routine maintenance work;loop replacement, head replacement, and controllers.
Replace direct bury cable for existing lighting system,
06/12/23
06/26/23
1,040,000
1,040,000
44
P
130,000
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2024
0
0
1,040,000
1,040,000
Totals
0
130,000
0
1,040,000
1,040,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
130,000
130,000
130,000
150,000
300,000
Totals
130,000
130,000
130,000
150,000
300,000
Report Date: May 04, 2023
Page 9
Wath
DepairrtligtnnS
torransportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
-n
a
n
0—.
a7 g
rf; E
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
g?
0
a
p
z
p
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
RW
WA -15109
E Marginal Way S (BAR - S 112 St)
E Marginal Way S
Boeing Access Road to S 112th St
Design and construct curb, gutter, drainage, lighting, turn lanes, and traffic control.
06/12/23
06/26/23
288,000
288,000
03
CGOPS
TW
0.270
0
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2025
RW
0
0
0
288,000
288,000
P
RW
2029
0
0
TIB
280,000
420,000
700,000
P
CN
2029
0
TIB
970,000
1,460,000
2,430,000
Totals
0
1,250,000
2,168,000
3,418,000
Expenditure Schedule
Phase
let
2nd
3rd
4th
5th & 6th
PE
0
50,000
0
0
170,000
RW
0
0
0
0
700,000
CN
0
0
0
0
2,430,000
Totals
0
50,000
0
0
3,300,000
Report Date: May 04, 2023
Page 10
Ana
ItZapairtmtent on Sol Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
-n
c
n
0 =
E. o
0, 2
. B.
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E, Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
TUK-63
Keeping South King County Moving with TDM
South King County
Various to Various
This project will help people access sustainable transportation options that reduce
drive -alone travel and traffic congestion In South King County. TDM programming
and services will be provided to residents, workers, visitors, employers, property
managers, and students in Tukwila and the partnering jurisdictions of Burien, Des
Moines, Kent, Renton, and SeaTac. The program will target those willing and able to
try sustainable modes of transportation at activity centers (community hubs,
commercial areas, business parks, multifamily housing complexes, and educational
institutions). Examples of activity centers include the Tukwila International Boulevard
District, Southcenter, and Sea -Tac Airport, The TDM Program will work in partnership
with transit agencies, nonprofits, employers, and community organizations to reach
priority populations through trusted channels. The project aims to reduce 542,997
vehicle trips and 8,093,549 vehicle miles traveled.
06/12/23
06/26/23
0
672,000
44
ALL
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2024
0
WSDOT
672,000
0
672,000
S
ALL
2024
0
OTHER
168,000
0
168,000
Totals
0
840,000
0
840,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
210,000
105,000
0
0
0
Totals
210,000
105,000
0
0
0
Report Date: May 04, 2023
Page 11
7 Wash' on Stat.
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
i
c,
zi
3 .
2,
Adopted
Amendment
0,7
2.
5.
S
Z
9
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
RW
WA -1111(
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
and rechannelization to add 5 -foot bike lanes and 5 -foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
06/12/23
06/26/23
50,000
400,000
04
RW
0.350
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2024
RW
0
Ped/Bike Program
350,000
50,000
400,000
P
RW
2024
0
0
Ped/Bike Program
90,000
10,000
100,000
P
CN
2025
0
Ped/Bike Program
2,800,000
300,000
3,100,000
Totals
0
3,240,000
360,000
3,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
400,000
0
0
0
0
RW
100,000
0
0
0
0
CN
0
3,100,000
0
0
0
Totals
500,000
3,100,000
0
0
0
Report Date: May 04, 2023
Page 12
41111‘
Z117. leffishington State
Deportment of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
c
9.
0 ,
F =
a E
Priority Number
A. PIN/Project No, B. STIP ID
C. Project Title
D. Road Name or Numberii*
E. Begin & End Termini
F. Project Description G. Structure ID
x
a
i
.
Adopted
Amendment
?D'
a
ci
9
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -13494
S 119th St Pedestrian Bridge Painting
S 119th Street
West bank Duwamish River to East bank Duwamish River
Ongoing maintenance of the S 119th Street Pedestrian Bridge in the
Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance
needed.
06/12/23
06/26/23
200,000
200,000
06
0
0,040
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2024
0
0
200,000
200,000
Totals
0
0
0
200,000
200,000
Expenditure Schedule
Phase
let
2nd
3rd
4th
5th & 6th
CN
0
200,000
0
0
0
Totals
0
200,000
0
0
0
Report Date: May 04, 2023
Page 13
AIM
Washington State
VA, Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Funding
Priority Number
Phase
Phase Start Year (YYYY)
Hearing
Adopted
Amendment
Resolution No.
9
-0
0
Utility Codes
Total Length
Environmental Type
RW Required
-n
c
=
A. PIN/Project No.
C. Project Title
B. STIP ID
a
2
D. Road Name or Number
P
RW
in
E. Begin & End Termini
F. Project Description
G. Structure ID
2,070,000
03
50,000
50,000
WA -15108
06/12/23
06/26/23
0
03
CGOPS
0,100
2,070,000
Yes
0
0
2,420,000
2,420,000
TW
S 133 St/SR599 Southbound Intersection
S 133rd Street
SR 599 SB Ramp to
Design and construct intersection improvements, which could include a new traffic
signal or a roundabout,
lighting, pedestrian facilities, and drainage.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2028
RW
0
0
0
300,000
300,000
P
RW
2028
0
0
2,070,000
0
50,000
50,000
P
CN
2029
0
0
2,070,000
2,070,000
Totals
0
0
2,420,000
2,420,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
300,000
RW
0
0
0
0
50,000
CN
0
0
0
0
2,070,000
Totals
0
0
0
0
2,420,000
Report Date: May 04, 2023
Page 14
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
�.
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
STBG(UL)
WA03782
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1-5 between 51st Ave S and 53rd Ave S
06/12/23
06/26/23
79,000
579,000
28
CN
0.250
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2026
STBG(UL)
500,000
0
0
79,000
579,000
P
CN
2025
SRTS
2,302,000
0
0
388,000
2,690,000
Totals
2,802,000
0
467,000
3,269,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
579,000
0
0
CN
0
0
0
2,690,000
0
Totals
0
0
579,000
2,690,000
0
Report Date: May 04, 2023
Page 15
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
c,
z.
C)—.
a7 2
E
0
0
q
z
§
?,.
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E . Begin & End Termini
F. Project Description G. Structure ID
x
m
2.
2,
Adopted
Amendment
Resolution No,
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -1111;
S 152nd Street Safe Routes to School
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Design and construct curb, gutter and sidewalks on both sides including widening
pavement width by 3 feet to construct on -street parking lane on north side of street.
06/12/23
06/26/23
815,000
4,015,000
05
0
0.300
3,200,000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2024
0
TIB
3,200,000
815,000
4,015,000
Totals
0
3,200,000
815,000
4,015,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
4,015,000
0
0
0
0
Totals
4,015,000
0
0
0
0
Report Date: May 04, 2023
Page 16
Washington State
W. Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
Functional
Class
15
o
.
...7
z
c
3:
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
z
a
a
=,
2
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
CMAQ
TUK-64
South King County TDM
South King County
N/A to N/A
This project will provide TDM programming and services at selected activity centers
in Tukwila and partnering South King County jurisdictions. Activity centers include
community hubs, commercial areas, business parks, multifamily housing complexes,
and educational institutions. For example, places such as Tukwila International
Boulevard District, Southcenter, and Sea -Tac Airport, By providing transportation
resources and incentives, the project will encourage people to choose sustainable
transportation options that reduce drive -alone travel and traffic congestion in South
King County. TDM services will be provided to residents, commuters, and visitors,
targeting those willing and able to try sustainable modes of transportation. The
program will work in partnership with partner agencies, nonprofits, employers, and
community organizations.
06/12/23
06/26/23
15,000
520,232
24
450,000
0.000
55,232
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2024
CMAQ
450,000
OTHER
55,232
15,000
520,232
Totals
450,000
280,116
55,232
15,000
520,232
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
280,116
0
0
0
0
Totals
260,116
0
0
0
0
Report Date: May 04, 2023
Page 17
Washington State
TI/ Department of Then
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
,
o
H w
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Numberin
E. Begin & End Termini
F. Project Description G. Structure ID
=
ro
Adopted
o
?
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
CN
WA -13495
Southcenter Blvd/65th Avenue S Signal
Southcenter Boulevard
65th Avenue S to
Design and construct a new traffic signal at the Southcenter Boulevard/65th Avenue
S intersection to improve level of service and safety.
06/12/23
06/26/23
200,000
200,000
21
CN
2025
0
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2024
CN
0
0
0
200,000
200,000
P
CN
2025
0
0
TIB
500,000
500,000
1,000,000
Totals
0
500,000
700,000
1,200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
100,000
0
0
0
0
CN
1,000,000
0
0
0
0
Totals
1,100,000
0
0
0
0
Report Date: May 04, 2023
Page 18
Adis
EhspartmentSate otl Transportation
Agency; Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2024 to 2029
N Outside
-n
c
=
ri
0 .4:
p7 °
r, E
Priority Number
A. PIN/Project No, B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -13491
Transportation Demand Management Implementation
to
Provision of TOM services to Commute Trip Reduction -affected employment sites.
Facilitate employer reporting and records associated with biennial CTR survey.
Engage CTR employment sites with opportunities for improvement and remain
connected via technical meetings with other CTR jurisdictional representatives.
06/12/23
06/26/23
0
88,526
44
ALL
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2024
0
WSDOT
88,526
0
88,526
P
ALL
2025
0
WSDOT
46,650
0
46,650
Totals
0
135,176
0
135,176
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
46,650
46,650
0
0
0
Totals
46,650
46,650
0
0
0
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
16,752,000
28,280,408
23,504,500
68,536,908
Report Date: May 04, 2023
Page 19
Christy O'Flaherty
From: Christy O'Flaherty
Sent: Tuesday, June 27, 2023 10:05 AM
To: Andi Markley
Cc: Cyndy Knighton
Subject: Tukwila Transportation Improvement Program 2024-2029
Importance: High
June 27, 2023
TO: PUGET SOUND REGIONAL COUNCIL
RE: CITY OF TUKWILA 2024-2029 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to City of Tukwila Resolution #2072 passed June 26, 2023, adopting the Transportation
Improvement Program for 2024-2029.
Res 2072 - 2024-2029 Trsportatad„�r Irnprover ehr grar��
Please contact me with any questions.
Please respond to this email to ensure it was received satisfactorily. Thank you.
Sincerely yours,
Christy O'Flaherty, MMC, Records Governance Manager/City Clerk
xc: Cyndy Knighton, Transportation Engineer
Christy O'Flaherty
From: Christy O'Flaherty
Sent: Tuesday, June 27, 2023 10:02 AM
To: 'G regA@TI B.wa.gov'
Cc: Cyndy Knighton
Subject: Tukwila Transportation Improvement Program 2024-2029
Importance: High
June 27, 2023
TO: TRANSPORTATION IMPROVEMENT BOARD
RE: CITY OF TUKWILA 2024-2029 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to City of Tukwila Resolution #2072 passed June 26, 2023, adopting the Transportation
Improvement Program for 2024-2029.
Res 2072 - 2024-2129 "t'r ins ortation Improvement Pr ue am
Please contact me with any questions.
Please respond to this email to ensure it was received satisfactorily. Thank you.
Sincerely yours,
Christy O'Flaherty, MMC, Records Governance Manager/City Clerk
xc: Cyndy Knighton, Transportation Engineer
Christy O'Flaherty
From: Christy O'Flaherty
Sent: Tuesday, June 27, 2023 10:08 AM
To: 'millarr@wsdot.wa.gov'
Cc: Cyndy Knighton
Subject: Tukwila Transportation Improvement Program 2024-2029
Importance: High
June 27, 2023
TO: WASHINGTON STATE DEPARTMENT OF TRANSPORTATION
RE: CITY OF TUKWILA 2024-2029 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a Zink to City of Tukwila Resolution #2072 passed June 26, 2023, adopting the Transportation
Improvement Program for 2024-2029.
Res 2072 - 2024-2029 Traa sport tiion Imp'ovent Progr
Please contact me with any questions.
Please respond to this email to ensure it was received satisfactorily. Thank you.
Sincerely yours,
Christy O'Flaherty, MMC, Records Governance Manager/City Clerk
xc: Cyndy Knighton, Transportation Engineer