HomeMy WebLinkAboutTIS 2023-08-07 Item 2A - Update - Public Works Operations CampusCity of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Brandon Miles, Business Relations Manager
CC: Mayor Ekberg
DATE: July 31, 2023
SUBJECT: Public Works Operations Campus Update
ISSUE
Staff will provide regular updates on the progress of the design and preconstruction work for the
buildout of the Public Work's Operations Campus.
BACKGROUND
On June 5, 2023, the City Council gave approval for staff to begin design and preconstruction of
the Public Work's Operations. The project will consolidate all facilities related to public works
operations onto one property with modern, safe, and efficient facilities. Design and
preconstruction work is anticipated to run through May 1, 2025, the soonest construction could
begin.
DISCUSSION
Staff committed to providing monthly reports to the City Council regarding the status of the
project. Attached to this memo is the first report. Staff would like input on the overall framework
of the report and if it provides the City Council with the information it would like to have in the
report.
FINANCIAL IMPACT
N/A
RECOMMENDATION
Discussion Only.
ATTACHMENTS
1. Public Works Operations Campus, July 2023 Report.
2. Current Site Plan and Cross Section
1
Public Safety Plan
Tukwila Public Works Operation Campus
Monthly Update
July, 2023
Key Project Metrics
Report Date
July, 2023
Previous Month
Discussion
Current Anticipate
Construction Start Date:
May 1, 2025
N/A
No change from
information
provided to the City
Council in May of
2023.
Design/Preconstruction
Cost Estimate:
$5,974,412
N/A
Total Preliminary
Construction Cost:
$79,265,000
N/A
Near Term Council Decision
and Key Dates:
Review schematic
design and cost
estimates by end of
year.
N/A
Key Tasks
Program
• Architects held several program confirmation meetings/workshops with the user groups for
sizes of spaces and adjacencies.
• Architects had a meeting to understand the server and IT equipment needs. Looking to see if
there is space to bring other IT equipment from the City Hall campus to the Public Works site.
Entitlements
GC/CM Approval
• On July 27, 2023 the City received unanimous approval from the State of Washington Capital
Projects Advisory Review Board to utilize alternative contractor selection for the project. The
City's application included two parts, 1) to utilize GC/CM for the general contractor for the
project and 2) and, on the recommendation from John Palewicz, to utilize an alternative
selection process for the earthwork subcontractor on the site. As the Council is aware, the City
utilized the GC/CM process for the construction of the Justice Center and the Fire Station
projects. GC/CM allows the City to bring in a contractor early in the design process and allows
the City to get cost estimates as the project progresses. GC/CM should allow the City to better
2
understand costs and to control cost as it moves through the design and preconstruction
process.
• The Review Board was very complimentary of the City's application, specifically the qualified
team the City had assembled; the commitment to meeting DBE, apprenticeship, and local hiring
goals; and the City's utilization of the PMQA for the project and the reporting structure the
PMQA has directly with the City Council.
• The Review Board also remarked that utilization of the alternative selection process for the
earthwork subcontractor was an innovative way to better manage costs for the project that will
have a significant amount of earth moving associated with it.
Permitting
• Project team and environmental consultant team met with Public Works and Department of
Community Development (DCD) to understand the administrative approval process for the
proposed bioswales for stormwater management for the project.
• Upcoming meeting in August with DCD to understand permitting requirements and process for
the project.
Reports
• Geotechnical borings have been drilled to prepare the project's geotechnical report for the
project.
• Hazardous Material assessment (on the existing structure) work has started.
Project Partners
• Project staff met with King County Parks and Natural Resources to discuss an interim project to
relocate stormwater draining from the Fleet and Facilities site onto the Chinook Wind property.
King County has offered to design and construct an interim conveyance system.
• Public Works and project staff met with King County Metro to discuss partnership regarding a
joint decant and solid's facility. King County Metro will lose access to its solid's facility in north
Tukwila sometime in 2024. There is an opportunity for the City and King County Metro to
partner on a joint facility.
Bidding and Construction
• Not applicable at this time.
Grants
Grant Name
Granting Agency
Status
Amount
Purpose
DOE Water
Quality Combined
Funding Program
Washington State
Department of
Ecology
Awarded and
accepted by the
City Council.
Finalizing grant
agreement.
$462,043 (grant
funds). These
funds will reduce
the City financial
commitment for
the design and
Development of
an EMP and
design only of a
decant facility.
3
4
preconstruction
phase.
Open Space and
River Corridor
Grant Program-
Chinook Wind
Extension.
King County Parks
and Natural
Resources
Preliminary
awarded,
waiting for final
action from King
County Council.
$280,000
Design of
shoreline
enhancement
project along
project site.
Building Resilient
Infrastructure and
Communities
(BRIC).
FEMA
Preapplication
Up to $50 million.
To be
determined.
Could include
construction
costs,
remediation at
Minkler Shops, or
other items.
Inflation
Reduction Act
TBD
Researching
TBD
Funds could be
used for
alternative
heating and
cooling systems,
such as
geothermal, etc.
4
Fleet and Facilities to
remain operational
throughout construction
■
TRANS
POLICE
IMPOUND
S 112 ST
'0'0®'ow0,
BASE, TVP
SCL easement for high
voltage power
ATTACHMENT E
j00oo�b�gw..1.�v,�o.�sowv
oOpo 6:Al lottoV0�
lO�4jj�s�41m1h1i �
p e�
111
STAFF
PARKING
EXISTING
FLEET AND FACILITIES
BUILDING
INTERIOR
FLEET
PARKING
FLEET PARKING
COVERE ILS �I 1 I 1-
111
(12) 9%20 SPO
000
(E) TRANSMISSION
TOWER BASE
EATTLE CITY
L HT EASEMENT
R5 Elevated
Link Light
9 Rail Tracks
PdLE
srpR
TROC
WASH
OLICE
VIDENO
SALT
SAND
GRAVEL
BRINE TANKS
V E
.� k
(i OB
o� eis: _ a_aasaaa
TOOL STORAGE BUILDING
[_][_] COVERED LOADING
EXTERIOR COVERED STORAGE
Hilwrttld11111111111
(E)LIGHT RAIL
S PPORT PYLON
SO ND TRANSIT
EAS MENT
MAINTENANCE &
ENGINEERIN
BUILDING
/ CHINOOK WINDS
MITIGATION PROJECT
Existing Recent Proposed Shoreline
Shoreline Restoration
Restoration
ENERAT DS X1111111111111®
N
A
VISITOR PARKING
•
000 00 !Ovo �s�os�, j
!►�%
//-7-
GARDENS
we4O�0 �
d0 DUWAMISH
E4000 — GARDENS PARK /
�r.�d®
�` 0r;,i•POS
Od0
roof S�RELI ��o
00�00'ESTORATI• 0 0
0
Pre -Design Concept June 2023
Tukwila Public Works
Maintenance & Engineering wilding
Miller Hayashi Architects PLLc
EECTRICAT
VAULT
48'
RESTORATION SITE I, STORMWATER FACILITY t
CONCEPUTAL SECTION: VIEW LOOKING WEST FROM SHORELINE RESTORATION SITE
SCALE 1:30
ATTACHMENT F
MAINTENANCE
AND
ENGINEERING
BUILDING
Pre -Design Concept June 2023
Tukwila Public Works
Maintenance & Engineering Building
Miller Hayashi Architects Puc 6