HomeMy WebLinkAboutReg 2023-10-02 Item 4C - Final Acceptance - 2022 Overlay Program with Tucci and Sons Inc for $1,498,073.89COUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Mayor's review
Council review
10/02/23
JR
ITEM INFORMATION
ITEM No.
4.C.
STAFF SPONSOR: MIKE RONDA
ORIGINAL AGENDA DATE: 10/02/23
AGENDA ITEM TITLE 2022 Overlay and Repair Project
Project Completion and Acceptance
CATEGORY ❑ Discussion
Mtg Date
11
Motion
Date 10/02/23
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
Mtg
SPONSOR ❑Council ❑Mayor HR ❑DCD Finance ❑Fire TS ❑P&R Police IIPIF ❑Court
SPONSOR'S The Notice to Proceed for Contract Number 22-078 with Tucci and Sons Inc was issued on
SUMMARY July 14, 2022. Construction was physically completed on August 9, 2023. Council is being
asked to formally accept the 2022 Overlay and Repair Project construction contract with
Tucci and Sons Inc as complete and authorize the release retainage, subject to standard
claim and lien release procedures.
REVIEWED BY
I Trans&Infrastructure
❑ CommunitySvs/Safety ❑ Finance Comm. ❑ Planning/Economic Dev.
❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
09/18/23 COMMITTEE CHAIR: TOSH SHARP
❑ LTAC
DATE:
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITTEE
Public Works Department
Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
10/02/23
MTG. DATE
ATTACHMENTS
10/02/23
Informational Memorandum dated 09/15/23
Photos
Project site map
Minutes from Transportation and Infrastructure Committee meeting of 09/18/23
1
2
City of Tukwila
Allan Ekberg, Mayor
Public Works Department - Hari Ponnekanti, Director/City Engineer
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Hari Ponnekanti, Public Works Director
BY: Michael Ronda, Project Manager
CC: Mayor Allan Ekberg
DATE: September 15, 2023
SUBJECT: 2022 Overlay and Repair Project - Project No. 80010401, Contract No. 22-078
Project Completion and Acceptance
ISSUE
Accept contract as complete and authorize release of insurance, retainage and performance bond.
BACKGROUND
The Notice to Proceed for Contract No. 22-078 with Tucci and Sons Inc, of Tacoma, Washington was
issued on July 14, 2022 for the 2022 Overlay and Repair Project. The project included: pavement
repairs, sidewalk improvements, signal improvements, and an asphalt overlay at seven locations
citywide. For the 2022 Overlay, multiple projects related to City street improvements were combined to
take advantage of economies of scale and improved coordination between different aspects of the
work, including Overlay & Repair, Small Drainage, ADA improvements, and the Neighborhood Traffic
Calming Program (NTCP). The attached map shows the areas for the various components.
ANALYSIS
Construction was physically complete on August 9, 2023 after an extended punch list performance by
the contractor. The budget for the 2022 Overlay & Repair construction was $1,612,609.75 prior to
contingency. An 8% contingency was applied to the bid amount, bringing that total authorized for
construction to $1,741,618.53. One Change Order was performed under the contract for additional
conduits at the 144th pedestrian crossing. A portion of the work was removed from the contract to
provide time for Water District 125 to upgrade an old waterline in 37th Ave S. That work was deferred to
this year's Annual Overlay scope. Under -runs were primarily due to fewer quantities needed during the
roadway excavation, haul and repair of the various roadway sections.
Construction Contract Amount $1,612,609.75
Additions/Change Orders 26,665.52
Under -runs (141,201.38)
Total Amount to be Paid $ 1,498,073.89
RECOMMENDATION
Council is being asked to formally accept the project as complete and authorize the release of the
insurance, retainage and performance bonds, subject to standard claim and lien release procedures, for
the 2022 Overlay and Repair Project construction contract with Tucci and Sons, Inc. in the final amount
of $1,498,073.89 and consider this item on the Consent Agenda at the October 2, 2023 Regular Meeting.
ATTACHMENT - Project Site Map
Before and After Photos
https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/2023 Agenda Items/TIC 09-18-23/2.2022 Annual Overlay - Closeout/Info Memo 2022 Overlay Closeout.docx
3
4
uo•
r1 r
t » iFl
tiiFr • f [ L%*
x r 5Lia 5 ''F �Eo
- ‘„YrL .rar
5 140TH ST. 5 14I $T 5T,
142Np ST. 37TH A1dE S • ' r.
• [yR
mar •
LLE•JT.^nra
RP.FR
�5 144TH T k
ik.lkl AVE
FEWFail
1 ..1..F - t 'Err -'
Ip Imrr''ap•r r ;
4.:„
" # t fi r �:y..1:__'
rl x: i er p � x i '
J y.� R
t _ _t r y ' , :i 4 �' - � � �
I.aa • zx A^ c
11
oat
MA
� y4t
[rY
I
BID
DOCUMENTS
2022 TUKWILA OVERLAY
Mt
UM
ElI caY.DWG
aw6 I. - 40
6
City of Tukwila
City Council Transportation & Infrastructure Services Committee
Meeting Minutes
September18, 2023 5:30 p.m. - Hybrid Meeting; Duwamish Conference Room & MS Teams
Councilmembers Present: Tosh Sharp, Chair; Mohamed Abdi, Cynthia Delostrinos Johnson
Staff Present: Hari Ponnekanti, Colleen Minion, Mike Ronda, Cyndy Knighton, Alison
Turner, Laurel Humphrey
I. PRESENTATIONS
II. BUSINESS AGENDA
A. Grant Acceptance: RE+ City Grant Program
Staff is seeking Council approval to accept RE+ grant funding from King County in the amount
of $83,000 to support food service businesses in organics services and compliance.
Committee Recommendation
Unanimous approval. Forward to October 2, 2023 Regular Meeting.
B. Project Completion: 2022 Overlay and Repair
Staff is seeking Council approval of project completion and release of retainage for the 2022
Overlay and Repair Project in the amount of $1,498,073.89.
Committee Recommendation
Unanimous approval. Forward to October 2, 2023 Regular Consent Agenda.
C. Transportation Demand Management Program Allocation
Staff is seeking Council approval to accept the biennial WSDOT TDM allocation in the amount
of $93,000.
Committee Recommendation
Unanimous approval. Forward to October 2, 2023 Regular Consent Agenda.
Miscellaneous
Councilmember Delostrinos Johnson inquired about the status of the crosswalk near the Allentown
pedestrian bridge. The project is not yet complete.
The meeting adjourned at 6:12 p.m.
Committee Chair Approval
Minutes by LH
7