HomeMy WebLinkAboutTIS 2023-11-06 Item 2A - Update - Public Works Operations Campus: Phase 2City of Tukwila Allan Ekberg, Mayor INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Committee FROM: Brandon Miles, Business Relations Manager CC: Mayor Ekberg DATE: October 31, 2023 SUBJECT: Public Works Operations Campus Update ISSUE Staff will provide an update on the design of the Public Works Operations Campus. BACKGROUND In June of this year City Council authorized staff to move forward with the design of the Public Works Operations Campus. Staff has been working on a very aggressive timeline to deliver schematic design by the end of the year. The City is also using the GC/CM delivery method which means that a contractor is brought in as part of the design process. After receiving nearly a dozen responses to the City's RFQ, BNBuilders was the apparent selected contractor for the project. DISCUSSION Staff would like to provide an overview of the design of the campus. No action is needed as this time. FINANCIAL IMPACT The City Council has already approved the funding for the design and pre -construction of the building and site. RECOMMENDATION Discussion only. Forward to the November 13, 2023 Council meeting. ATTACHMENTS • Draft site plan, floor plan, and elevations. 1 ABANDONED DRIVEWAY NEW DRIVEWAY ENTRY/EXIT - VISITOR, STAFF, AND MAINTENANCE AND OPERATIONS VEHICLES / o CALL 811 BEFORE YOU DIG 18"0 IP CUT @ GRADE ELEC EASEMENT REC. NO.2609159 CONNECT TRAIL TO CHINOOK WIND PATH WATER EASE NT EC. NO. 50530 POLICE EVIDENC /L I ASPH CC&GUTTER NOPV LINE 10' WA ER EAS C. NO.: 53062 CEDAR RIVER CITY OF SEATTLE PIPELINE R/W (S 112TH 5T) STD EET LI TEAS ENT C. NO. 0030517100375 0' COMM EASE ENT REC. NO' 9105300398 & 9111201395 CC& SIITTFR S 112 ST F&F BUILDING EXISTING DRIVEWAY ENTRY/EXIT - STAFF ONLY OWNER: SE ATTLE CITY OF SCL PARCEL N .: 09230*9387 11 iiiiiiiiiiiiiiiiii u n iiiiii u n iiiiiiiiiiiiiiillln n iiiiiiiiiiiiiiiiiiiiiiiiiiiil liiiiiiiiiiiiiiiiiiiiiiillllilll� OWNER: KING COUNTY-WLRD MRP PARCEL NO.: 092304-9153 STAFF ONLY ACCESS TO CHINOOK WIND CHINOOK WIND MITIGATION PROJECT KEY NOTES _x x OWNER: KING COUNTY-WLRD MRP PARCEL NO.: 092304-9242 x CONNECT TRAIL TO CHINOOK WIND PATH POLICE IMPOUND 0 SECURITY ISLAND WITH CARD READER AND INTERCOM O2 LARGE VEHICLE SWING GATES WITH DETECTOR LOOP FOR OUTBOUND LANE ONLY O3 PASSENGER VEHICLE AND LIGHT TRUCK SWING GATES WITH DETECTOR LOOP FOR OUTBOUND LANE ONLY CD PASSENGER VEHICLE AND LIGHT TRUCK SLIDING GATE WITH DETECTOR LOOP FOR OUTBOUND LANE ONLY O PEDESTRIAN GATES WITH CARD READER, INTERCOM, AND PROTECTED PUSH -BAR TO EXIT 0ADA ACCESSIBLE RAMP "FIRE LANE' —x—x /..."`-SOUND TRANSIT EASEM REC. NO. 200508010020y EXISTING DRIVEWAY ENTRY/EXIT - STAFF AND MAINTENANCE AND OPERATIONS S 1 VEHICLES ONLY 1--X—X— x rlrlr Th r 1 LJLJLJLJLJ /ER CITY OF IPELINE R/W TH ST) CITY OF SEATTLE TRANSMISSION LINE RAN X X X X X X—X—X—X— FLEET PARKING DECANT AND / III=i TOOL 0 TO AGE 1 ysxsl I=1 I=I 1=1 ' 1= IE 1=i - =1 I_I I 1= 1=1 Illlilln��n�iuu�—, _ _ I -I 1 1 L-L ►um►umnii�in�i� 1 - — — — — — I11111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111` 1111111111:::Pla ;11i1111".. M&E BUILDING k\k H' ETBAC00'00K \k\ (DUWAMISH GARDENS) x� /k 200' SHORELINE SETBACK ler STAFF ONLY ACCESS TO CHINOOK WIND S H O R E L I N 0ETBAC0 5H(1KRELINE S DUWAM/SH GARDENS) RESTORATIO 100' SHORELLVE SETBACK (5(R I El ED) SEE SHORELINE RESTORATION PLANS (UNDER SEPARATE CONTRACT FOR WORK IN THIS AREA 6 VISITOR PARKING SOUND T M REC. N01102 SPOILS MODULAR kSTROOM IIIII�! X— x ``` ��1 `````` Illl m i llll m dill m iiilillii��l��ii�1�milli� m illlllllli r 11111111111� I111111111111111111 x x x x x x x x x CONNECT TRAIL TO DUWAMISH GARDENS GRAVEL PATH *-DU \fr DP - VET • DP-2 el .I, —�— .t-- — — — AMISH GARDENS PARK WETLAND A (AS LOCATED ALONG UPLAND LIMIT) WATERWARD WETLAND BOUNDARY NOT DELINEATED THIS SURVEY sk SOUND T STAFF ONLY ACCESS TO DUWAMISH GARDENS .� ) \ EXISTING DRIVEWAY ENTRY/EXIT - STAFF AND MAINTENANCE AND OPERATIONS VEHICLES ONLY \ \ \ \ STAFF ENTRY ONLY \ \ STAFF EXIT ONLY Ur O EXISTING DRIVEWAY ENTRY/EXIT - VISITOR - STAFF AND 1 40 MAINTENANCE AND 1 OPERATIONS VEHICLES ONLY \ 0 40 \ 1 80 1 "=40' ARCHITECT Miller Hayashi Architects PLLC 118 North 35th St. Suite 200 Seattle, Washington 98103 Tel: 206 634 0177 STAMP � � of '< ' A p ` co ,;y,�,.` CONSULTANT BUILDING Maintenance City of & SKETCH TAG REVISIONS 100% SCHEMATIC DESIGN SET ACCESS PLAN SITE ACCESS Tukwila Tukwila Engineering Project #2219 "�''`+' • Campus Project DATE SHEET NO. East `;• /i EX?•\�L� gNDSCAP� Any �� H herrera E RRE RA i nc.com 11210 Tukwila Tukwila, Tukwila International Blvd WA 981681 0/3 /� 0 L-1.01 40 NOTE: DRAWING SET SCALED FOR 24x36 SHEET MILLER HAYASHI ARCHITECTS PLLC HEC PROJECT #: 22-07903-001 O:\PROJ\Y2022\22-07903-001\CAD\SHEET\SITE ACCESS PLAN.DWG 2 WORK AREA WORK AREA OUTDOOR SEATING AREA 1 UP I I I I I I TRASH / RECYCLING REF KITCHEN MW1 L_J r- I L_ FITNESS CENTER STAIR 2 - BIKE STORAGE DECON D:CON RR DRYING ROOM LOCKERS (125) MEN'S SHOWER M&E Building - Floor Plan - Level 1 SIGN STORAGE r--r 4 • w 0 a v • -1 L ❑ J 0 0 MEN'S LOCKER ROOM REQ'D: 57 PROVIDED: 64 • II D IL _I SIGNAL SHOP ❑- II II Ik^ II SIGNAL STORAGE • I I I I I I L 1 1 r T T T I I I I I I I I I I r T T T T I I I I I 1 1 1 tLFV AA,JG Z\ \ RECEPTION 0) w w ▪ - WOMEN'S LOCKER ROOM 111111 II I I REQ'D:14 PROVIDED: 34 0 0 O WOMEN'S S •WER ■ ' MDF ROOM n I I REF WATER QUALITY ROOM STAIR 1 141 MECHANICAL ROOM ELECTRICAL ROOM J UP RR STODIAL lirp E SPRINKL R LEV MACHINE ROOM SMALL MEETING ROOM 7=11 L LJ LJ LJ LJ LJ I I I I I I I I I I I I LARGE MEETING ROOM )M MAIN ENTRANCE Tukwila Maintenance & Engineering East Campus Project SCHEMATIC DESIGN DRAFT 10/31/23 Miller HayashiArchitects 3 riE3uE 3uE, L\37-E3r1 SMALL MEETING ROOM HALLWAY r/E31_/E 3uE3A, IFU���JT 11 r- , , J °i II (1 idn ▪ ,I i91 k --_Y e II u_L u_JU SURFACE WATER / SEWER DEPARTMENT F===F RECDVERY ROOM L 1 c( )l L_L ■ , , I , I , I STREET DEPARTMENT WATER DEPARTMENT HALLWAY I�I�I�I�I�I I�I�I�I�I�I 1=1 1 1=1=1=1=1 ICI=1=11 KITCHENETTE CUSTODIAI4 IDF RAFFIC SERVER RO ELECTRICAL RgOM OPEN OFFICE °nr� °n� °nR\ °nn9) ADD'L UuH ADD'L°uH ADD'L iUuH ADD'L °uuH ADD'L ▪ 7 r 1I r 1 r 7 r 1 o°n� o01H) 11o°n�, I°unrn uuo uuo lluuo IuLJ] uuu) I ADD'L I ADD'L I ADD'L ADD'L ADD'L COVERED OUTDOOR SPACE HALLWAY EMPLOYEE RESOURCE CENTER u°u rd --1 ono n 1\ —H u°u ry Hion u°u MEDIUM MEETING ROOM M&E Building - Floor Plan - Level 2 VIEW TO DUWAMISH RIVER Tukwila Maintenance & Engineering East Campus Project SCHEMATIC DESIGN DRAFT 10/31/23 Miller HayashiArchitects 4 DN STAIR ruf 2LrE 3LiE3 r I I I I I I SMALL MEETING ROOM OFFICE OFFICE 77 1 I1� II II n f111 11 II �nn1l ono °L10 ENGG IIii ENGG ,'un1 1 u u 1 1 L _L J 0i I I I I I I I I I I I I 3LrE343vE�, I I I 1- g3ngi-L gr 3r1 n =__r_r ===r II I I li ENGG quu1Y ENGG PI ii I 1 1 IL L L 1 II rr II ME110.1t4149,NG ROOM 11 1j I ▪ ENGG iuLi) ENGG 11u dr 11u dr 7 I ■ ,------T---T---T---T---T---, ▪ ,---T---, OPEN OFFICE 1 u ° ENGG ��L1o° �u1 IL L I 11 I I I I I I I I �3nF3�F3nF3� ■ ==r=T rPn°j ENGG nu L 1=1=1=1=1=1 1=1=1=1=1=1 1=1 1 I • RECORDS STORAGE - CITY 1 1 1 ■L ENGG H 1 7 nLi ENGG 7--7 I1I 1 u°ub), ENGG OPEN OFFICE 1IIio°uiT ENGG I u dr 9 n II IL -7 1111 III n °°n 11 0i ENGG KITCHENETTE 7 111 I h-1 1 1 I I II 1 1 r Tr I REF STAIR 3 (ROOF ACCESS) ELEd CLOSET • CHAIR STORAGE AV CLOSET (O V II L. • MEN'S RR HALLWAY • / r J N y y N y ,d d °d 6▪ , rr ▪ rr FP, y y NI y N y -\•CY cY� �Y -1•CY -uE n 1 1 1 j -\CY �Y -,LY y kd y N y 1 1 1 1 COVERED OUTDOOR SPACE O 0 LJ COVERED OUTDOOR SPACE O 0 M&E Building - Floor Plan - Level 3 VIEW TO DUWAMISH RIVER Tukwila Maintenance & Engineering East Campus Project SCHEMATIC DESIGN DRAFT 10/31/23 Miller HayashiArchitects 5 If �ll�i�• s��•q I �• MIME 11121111 SOUTH ELEVATION 1111 ■ 1. lilil lilil 1111 li lili Mil lilil 1■1....___:=."A„.A,.:1;4,,, ,....„ ,V. .. ....fri - - - -- ----- NORTH ELEVATION EAST ELEVATION it i 1111 111 111 it 1 111 WEST ELEVATION Tukwila Maintenance & Engineering East Campus Project SCHEMATIC DESIGN DRAFT 10/31/23 Miller HayashiArchitects 6