HomeMy WebLinkAboutReg 2024-05-20 Item 6A - Update - 42nd Avenue South Bridge ReplacementCOUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Mayor's review
Council review
05/20/24
JR
ITEM INFORMATION
ITEM No.
6.A.
STAFF SPONSOR: ADAM COX
ORIGINAL AGENDA DATE: 05/20/24
AGENDA ITEM TITLE 42nd Ave S Bridge Replacement Project — Detour Bridge Discussion
CATEGORY I1 Discussion
5/20/24
❑ Motion
Mtg Date
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
Mtg Date
SPONSOR ❑Council ❑Mayor ❑HR ❑DCD ❑Finance ❑Fire ❑TS ❑Pe.,R ❑Police 11PW ❑Court
SPONSOR'S
SUMMARY
Project staff, stamping structural engineer, and the permit liaison recommend that the
detour bridge not be constructed during the replacement of the 42nd Ave S Bridge
replacement due to the discovery of the Native American traditional fishing access to the
Duwamish River and a culturally sensitive site. the design and project team have discussed
the risks that would be associated with constructing the detour bridge as well as removing
the detour bridge from the project.
❑ Trans&Infrastructure ❑ CommunitySvs/Safety ❑ Finance
❑ LTAC ❑ Arts Comm. ❑ Parks
DATE: COMMITTEE
Comm.
Comm
❑ Planning/Economic
Dev.
REVIEWED BY
❑ Planning Comm.
CHAIR:
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITTEE
Public Works Department
Forward to Regular New Business Agenda Meeting
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/20/24
MTG. DATE
ATTACHMENTS
05/20/24
Informational Memorandum dated 05/17/24
Powerpoint Presentation
307
308
City of Tukwila
Public Works Department - Had Ponnekanti, Director/City Engineer
Thomas McLeod, Mayor
INFORMATIONAL MEMORANDUM
TO: Full Council Meeting
FROM: Hari Ponnekanti, P.E., Public Works Director/ City Engineer
BY: Adam Cox, P.E., Interim Traffic Engineer
CC: Mayor Thomas McLeod
DATE: May 17, 2024
SUBJECT: 42nd Ave S Bridge Replacement Project — Detour Bridge Discussion
ISSUE
Project update on the 42nd Ave S Bridge detour discussion of the temporary bridge.
BACKGROUND
The 42nd Ave South Bridge is an important arterial that crosses the Duwamish River and connects the
City of Tukwila to surrounding communities and resources. The bridge serves over 10,000 vehicles
daily, as well as pedestrians and cyclists connecting to the Green River Trail, the Tukwila Community
Center, the Tukwila Park & Ride, and the Allentown neighborhood. It was built in 1949 and designed to
last 50 years; it has exceeded its original design life by over 20 years.
On December 15, 2021, an over height truck struck multiple members of the bridge truss system.
Flame On, Inc., a structural steel heat straightening contractor, was then contracted to make the
structural repairs to the bridge. The repairs to the bridge allowed it to open with load restrictions that
would accommodate only one-way travel, and on April 4th, 2022, the bridge was reopened in the
southbound direction only. It was determined that the best way to have vehicles leave the Allentown
neighborhood was to use the traffic signal at Interurban Ave and 42nd Ave S.
In November of 2020, Council awarded a design contract to TranTech Engineering, LLC (TranTech) to
create an ad -ready design for the 42nd Ave S Bridge Replacement. The project received grant funding
($31.5M) in early 2022 with awards from Puget Sound Regional Council (PSRC), the Local Bridge
Program (WSDOT), and Move Ahead Washington. The project has since completed the industry
standard milestones of the Type, Size, and Location (TS&L) report, 30% plans and estimate (P&E)
review, 60% P&E review, and the 90% P&E submittal.
Throughout the TS&L report, 30% P&E, 60% P&E, 90% P&E milestones the timeline for ad -ready plans
was extended due to external permit review/acceptance delays. At the 30% P&E submittal milestone,
TranTech's permit subconsultant began verifying what agencies require permit applications, but the
permitting agencies would not field/take applications for permits until after the 30% P&E threshold was
complete. With the transition to 60% P&E, permit agencies informed project staff that internal permit
processes required additional time for review and acceptance. With a continuing understanding and
external communication of the required permit applications and timeline, the timeline has now been
adjusted to have advertisement ready documents ready in late 2026 or early 2027. For the bridge
replacement, the project team is continuing to coordinate with over 10 different state and federal
organizations for permit applications/acceptance.
Tukwila City Hall • 6200 Southcenter Boulevard • Tukwila, WA 98188 • 206-433-1800 • Website: TukwilaWA.gov
309
42nd Ave S Bridge Replacement Project — Detour Bridge Discussion
May 17, 2024
Page 2
Given new specific details of the 90% P&E submittal, TranTech's permit subconsultant has the
information needed to complete the required material for all the permits listed in the permit table
attached to the info memo. The team has been informed by WSDOT that many of the permits happen
in sequence and cannot be applied/awarded at the same time.
The City continues to coordinate with our granting authorities. Staff have connected with WSDOT Local
Programs, the WSDOT Bridge Engineer, and our state lobbyist to ensure that the obligation deadlines
will be extended to match the new construction schedule.
ANALYSIS
In accordance with the National Historic Preservation Act of 1966, the bridge replacement project is
required to perform a historic analysis given the age of the bridge and the location of replacing the
structure. During the analysis, it was discovered that there are two cultural resources that are impacted
by this project. The two resources that are impacted are the Native American traditional fishing access
to the Duwamish River and a culturally sensitive site. These two cultural findings added to the permit
application delays as a cultural survey was required to better understand the sites.
When project staff were informed of the culturally sensitive items that contributed to the permit delay,
the team began to study ways to decrease the delay so that construction could start earlier. One
methodology discussed and analyzed was removing the temporary detour bridge from the project.
During the analysis, the design and project team studied the risks that would be associated with
constructing the detour bridge as well as removing the detour bridge from the project. The associated
risks for not constructing the detour bridge and constructing the detour bridge are listed below.
Risks:
- Constructing the detour bridge
o The temporary detour bridge alignment disturbs a known Duwamish site. The cultural
survey was sent to the Duwamish Tribe per the request from the WSDOT Archaeologist.
The comments received from the Duwamish tribe is they strongly preferred the project to
not disturb their sacred site. The comments received from the Snoqualmie tribes where
they trusted that WSDOT will implement proper protocols for the project. We have not
received comments from the Muckleshoot and the Yakima tribes.
o Given the complexity of the site and materials to construct the detour bridge, the
construction will cost between $4,000,000 to $6,000,000. The temporary bridge is a
rented piece of equipment, any delay in the schedule will increase the project costs.
o At the start of construction, the contractor will prioritize the construction of the detour
bridge. This diverts the contractor from prioritizing the demolition of the current bridge
which requires work within the first fish window in July 2027. If the contractor misses this
window, the construction team will not be allowed to perform in -water work until July
2028. This extends the construction timeline from 2 fish windows to 3 fish windows.
Possibly delaying the construction timeline by one year.
Not constructing the detour bridge
o Given the removal of an access/egress point to Allentown, there will be an increase in
emergency response timing.
o Currently there is a water and gas utility line attached to the underside of the current
bridge. Without the temporary detour bridge, there is a challenge to rerouting the utilities.
Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov
310
42' Ave S Bridge Replacement Project — Detour Bridge Discussion
May 17, 2024
Page 3
NEXT STEPS
Project staff will present the same information to the Allentown Community at the May 28, 2024,
Allentown meeting.
FISCAL IMPACT
There are no fiscal impacts to the project at this time.
The tables below illustrate the funding sources and amounts and the estimated costs for construction in
2017:
Grant Funding Source
Amount
Puget Sound Regional Council
$1.5 Million
Move Ahead Washington
$17 Million
WSDOT Local Bridge Program
$12 Million
Total
$31.5 Million
Project Phase
Estimated 2027 Costs
Design/Engineering
$2 Million
Construction with the detour bridge
$31 Million
Contingency for in -water pile removal
$6 Million
Total
$39 Million
RECOMMENDATION
Project staff, stamping structural engineer, and the permit liaison recommend that the detour bridge not
be constructed during the replacement of the 42nd Ave S Bridge replacement.
ATTACHMENT: 42nd Ave S Bridge Presentation
Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov
311
312
N
O
N
0
co
2
313
0
•
ocu
on
m
• 1920s — Bridge was designed.
BRIDGE ELEVATION
cu
a)
• 2024 — Design at 90%
z
0
I.
a)
C
O
V
N
i
0
V
V
a)
(O
i
a
C
a)
E
V
co
0.
a)
ce
CIA
CO
N
a)
i
314
U
Co
a)
OD
U
•
m
0
0
it out Detour Brid: -
1 IN
1
z
w
U
U
C
ci)
Ca
0
0
N
0
N
(/)
a--+
(1)
U
VI
4-1
C
0
E
N
N
4_,
0
E
00
NI
v)
-C
4-1
C
0
E
N
O
z
N
CU
C)
0
NI
Closed for extensive
v)
0
CU
L
0
I.
a)
0
a
O
U
I-
N
i
0
V
I
V
a)
..,
0
L
a
+.•
a)
E
a)
U
ca
0_
a)
ce
a)
an
i
m
tn
a)
C
N
3111.