HomeMy WebLinkAboutPCD 2024-06-10 Item 1D - Code Amendments - Related to Recently Passed House Bill 1293 and State Bill 5290City of Tukwila
Thomas McLeod, Mayor
INFORMATIONAL MEMORANDUM
TO: Planning and Community Development
FROM: Nora Gierloff, DCD Director
BY: Isaac Gloor, Associate Planner
Maxwell Baker, Development Review Supervisor
CC: Mayor Thomas McLeod
DATE: June 10, 2024
SUBJECT: Permitting Process Improvements
ISSUE
Amendments to Tukwila Municipal Code Titles 8, 16, 17, 18, and 19 are needed to consolidate and
simplify permit procedures and comply with recently passed Washington State legislation SB 5290
and HB 1293.
BACKGROUND
Tukwila's Permitting Process
The City of Tukwila Department of Community Development accepts and reviews applications for
land use projects and development. The Tukwila Municipal Code (TMC) distinguishes various
permits by type and contains standards for the processing of those permits. Review of land use
permits is subject to timelines for various steps, which are broken down below. These timelines are
largely dictated by State law.
• Notice of Complete / Incomplete Application:
o The City of Tukwila must determine whether an applicant has submitted all
necessary documents for review, like site plans, building plans, environmental
reports, etc.
o This step is subject to the following timelines:
■ The Department must determine whether a permit application is complete
or incomplete within 28 calendar days of permit submittal. Should the
Department fail to provide a determination within that time, the application
shall be deemed automatically "Complete" for the purposes of this step.
■ An application is "Incomplete" if the Department determines that the permit
submittal doesn't contain all required documents.
• The applicant has 90 calendar days from the date of the "Notice of
Incomplete Application" to provide required materials. If the
applicant fails to do so, the Permit Application will expire. Any
refundable fees paid will be returned to the applicant.
■ If the Department determines that the permit submittal is "Complete", the
Department shall provide a "Notice of Complete Application" that informs
the applicant that formal review of the application will begin.
• Notice of Application:
o Some permit types require the public to be notified that an application has been
submitted. In those cases, the Department has 14 calendar days to issue this
61
INFORMATIONAL MEMO
Page 2
62
"Notice of Application". That notice can be provided via email to all interested
parties and agencies with jurisdiction, via mail to nearby property owners and
residents, and by a physical sign erected on the subject property. Some permit
types require all these notice formats to be utilized.
o A "Notice of Application" is accompanied by a comment period. This is a set period
in which the Department will accept comments from the public or agencies with
jurisdiction regarding the project. During the comment period, the Department will
not make a final determination on the project's compliance with Tukwila Municipal
Code. This period can range from 14 calendar days to 21 calendar days, depending
on the Permit Type.
o If the Permit Type requires that the final decision be made in a hearing, this step will
also include a "Notice of Hearing". This notice must be provided at least 14
calendar days prior to the hearing.
• Permit Review:
o The Department must provide a final determination regarding whether a proposal
complies with the TMC within 120 calendar days from the date that the applicant
was sent a "Notice of Complete Application".
o The 120-calendar day countdown runs for the entire time that the Department is
reviewing a project. However, that countdown stops whenever the Department
determines that the application must be revised to comply with the TMC. At that
point, the status of the application is changed to "Corrections Required" and a
Correction Letter will be sent to the applicant that details all required submittals.
■ When the status is changed to "Corrections Required", the applicant has 90
calendar days to submit all required materials. If they fail to do so, the
application will expire.
Tukwila's Zoning code was adopted in 1995 and is approximately 29 years old. Original sections
have been built on, expanded, and edited over time. Because of the patchwork nature of Tukwila's
code, sections are occasionally repetitive, confusing, refer to nonexistent permits or standards, or
conflict with other sections. It has been a goal of the Department of Community Development to
simplify and correct the TMC, as well as to bring all the TMC's Titles into alignment with each other.
New Legislation
2023 was an active year for State Legislation, with Governor Inslee signed into law many bills
affecting Tukwila. Among them were Senate Bill 5290, now called the "Local Project Review Act"
(LPRA), and House Bill 1293. These bills mandate sweeping changes to permit reviews for all local
governments planning under the Growth Management Act, including Tukwila. They are intended to
increase the timeliness and predictability of local review, both of which have large impacts on
project costs for development.
Changes mandated by these two bills, and relevant to this code update proposal, are summarized
below:
• SB 5290: New Permit Review Timelines
o For projects that do not require public notice, the final decision must be issued
within 65 calendar days of the "Notice of Complete Application".
o For projects that do require public notice, the final decision must be issued within
100 calendar days of the "Notice of Complete Application".
https://tukwilawa.sharepoint.com/sites/departmentofcommunitydevelopment/DCDPlanning/Code Updates/2024/SB 5290 Edits/PCD Documents/PCD Info Memo
- Permitting Process Improvements.docx
INFORMATIONAL MEMO
Page 3
o For project permits which require both notice and a public hearing, the final
decision must be issued within 170 calendar days of the "Notice of Complete
Application".
o If a project permit fails to meet these timelines, in addition to other measures that
an applicant may seek, the local jurisdiction would be required to refund up to 20%
of an applicant's permit fees.
■ However, local jurisdictions may implement at least 3 of 10 optional
measures set forth in SB 5290 that are intended to further speed up permit
review timelines. If a jurisdiction enacts these measures, refunds would not
need to be provided even if permit timelines are not met.
• HB 1293: Limits on Design Review Meetings
o Cities may not hold more than a single public meeting for design review projects.
This severely limits the utility of public hearing for design review, as the only
possible decisions that a Design Review body can make are to approve or deny a
proposal. They cannot require corrections, as that would entail another design
review meeting.
o HB 1293 also requires that design review standards be clear, objective, and be
based on an ascertainable guideline or criterion. The intent of this is that an
applicant should be able to determine whether a design will meet the review criteria
simply by reading the criteria themselves.
While this may sound straightforward, as most code is clearly legible for
developers, many jurisdiction's design review criteria (including Tukwila's) contain
standards that are clearly subjective in nature. This includes standards such as
requirements that a project "match the character of the surrounding neighborhood"
or that a building "feature a high -quality design". These standards are necessarily
reliant on the eye of the beholder, and thus enforcement can differ based on who is
the decision maker.
The Department is not currently proposing reform to the design review standards.
That work will be presented as part of a separate code update package. However,
as the limit on the number of public meetings/hearings portion of this bill has
implications for the new standards set forth in SB 5290, the Department proposes
to implement this aspect of the bill as part of this update.
Tukwila must implement the new permitting timeline requirements by December 31 s`, 2024. The
requirements of House Bill 1293 must be implemented by mid-2025, or, 6 months after the City
adopts its next Comprehensive Plan.
DISCUSSION
This code update would amend the portions of Titles 8, 16, 17, 18, and 19, that relate to project
permitting, permit types, review timelines, appeals, and design review. It would consolidate permit
types, establish new permitting timelines, and speed up the review of applications for Design
Review by removing the requirement to hold public hearings before the Board of Architectural
Review (BAR). It also includes corrections to scrivener's errors, as well as removals of redundant or
expired code sections.
The proposal would bring the City's codes fully into compliance with the LPRA and would
implement a requirement from HB 1293 that correlates well with the rest of the amendments. It
https://tukwilawa.sharepoint.com/sites/departmentofcommunitydevelopment/DCDPlanning/Code Updates/2024/SB 5290 Edits/PCD Documents/PCD Info Memo
- Permitting Process Improvements.docx
63
INFORMATIONAL MEMO
Page 4
also would help achieve Department and City goals regarding permit review timelines, particularly
relating to the timeliness of Design Review applications.
The current City of Tukwila review timelines for most permit types already meet the new statutory
requirements, and virtually all permits currently meet the (now superseded) 120-day timeline, as
shown below.
September 2021
February 2022
February 2023
February 2024
Fire Reviews
28 — 0 Overdue
41 - 1 Overdue
48 — 0 Overdue
23 — 0 Overdue
Building
Reviews
47 — 9 Overdue
11 - 4 Overdue
3 — 0 Overdue
19 — 0 Overdue
Planning
Reviews
128 — 95 Overdue
31 - 8 Overdue
38 — 13 Overdue
51 — 0 Overdue
Engineering
Reviews
178 — 78 Overdue
60 - 8 Overdue
61 — 8 Overdue
65 — 0 Overdue
(First number are permits actively Under Review which includes those that are overdue.)
However, Design Review projects that require review by the BAR commonly reach or exceed
timelines, largely due to the need to schedule a Public Hearing. These hearings occasionally must
be scheduled months ahead of time to be accommodated in busy agenda schedules.
The Department has a strong interest in accelerating the review of permits that require design
review, many of which are related to the development of new housing. A commonly cited barrier to
development is timely and predictable procedures within the permitting process. This proposal
would amend the portions of Title 18 that relate to design review applications to establish that all
design review would be an administrative process. The BAR, whose members consist of the
Planning Commission, would continue to serve in their roles and perform all functions of the
Commission other than the administration of a public hearing and quasi-judicial review for Design
Review permits. Public notice would still be required for Design Review applications, and the City's
timeline for approval of a design review permit would be set at 100 calendar days, in accordance
with state requirements (as opposed to 170 days for those decisions which require a public
hearing). The Design Review standards would not change as part of this proposal; however, all
departures from the standards would be reviewed administratively as opposed to at a hearing by
the Board of Architectural Review.
As part of their implementation strategies, some jurisdictions are considering complying with these
new state requirements by changing their review procedures for certain permit types in a way that
would increase the permit timelines. This could be accomplished by adding public notice
requirements where they currently don't exist, or requiring a public hearing for a permit type when
currently it can be reviewed administratively. In this way, a permit timeline could legally be
extended from a state requirement of 65 days up to a maximum of 170 days. While these changes
would comply with the letter of the law, the Department is not proposing any amendments that
would lengthen reviews.
These changes are expected to provide greater clarity and predictability for applicants, simplify
permit review processes for both applicants and staff, speed up review timelines, and push Tukwila
another step towards compliance with new State requirements.
64
https://tukwilawa.sharepoint.com/sites/departmentofcommunitydevelopment/DCDPlanning/Code Updates/2024/SB 5290 Edits/PCD Documents/PCD Info Memo
- Permitting Process Improvements.docx
INFORMATIONAL MEMO
Page 5
FINANCIAL IMPACT
Eliminating public hearing design review would lower the fees for that permit type but also save
considerable staff time.
RECOMMENDATION
The Committee is being asked to forward this issue to the Planning Commission for a
recommendation. It will then be returned to the Council in ordinance form for a hearing and
decision.
ATTACHMENTS
Attachment A: Example Permit Timeline
https://tukwilawa.sharepoint.com/sites/departmentofcommunitydevelopment/DCDPlanning/Code Updates/2024/SB 5290 Edits/PCD Documents/PCD Info Memo
- Permitting Process Improvements.docx
65
66
Attachment A: Example Permit Timeline
Project:
New Duplex within the Medium Density Residential zoning district
Permit Case Study:
Design Review Application
Current Project
Pathway:
Application Submitted:
City has 28 days to determine whether the
application is complete. If the application is
complete, staff will notify the public of the
application.
Permit Review:
The Department will review the project for
compliance with Tukwila Municipal Code and
Design Review Guidelines and issue corrections if
necessary.
Upon determining that the project permit complies
with the TMC and Design Review Guidelines, the
Department will then prepare a detailed staff
report.
Public Hearing:
The Department must schedule a Public Hearing at
the next available Planning Commission session.
As the Commission meets monthly, if the next
meeting agenda is full the applicant may need to
wait more than 30 days.
Two weeks of notice must be given to the public
for this hearing. Staff will present the project and
explain the Design Review Criteria to the Board of
Architectural Review, who will make the final
determination.
V
Maximum Time to Issue Final
Determination:
120 calendar days
Actual review time is highly variable and
frequently extended.
r Proposed Project
Pathway:
Application Submitted:
City has 28 days to determine whether the
application is complete. If the application is
complete, staff will notify the public of the
application.
tJ
Permit Review:
The Department will review the project for
compliance with Tukwila Municipal Code and
Design Review Guidelines and issue corrections, if
necessary.
The final decision maker is the Director of
Community Development. Thus, when staff review
is complete, the Department can prepare a staff
report and issue the permit.
Maximum Time to Issue Final
Determination:
100 calendar days
No additional time for scheduling or public
notice for hearings is required.
67