HomeMy WebLinkAboutTIS 2024-07-22 Item 2D - Agreement - Sewer Lift Station #12 Upgrade Design with ParametrixCity of Tukwila
Thomas McLeod, Mayor
Public Works Department - Pete Mayer, Interim Director
INFORMATIONAL MEMORANDUM
TO: Transportation & Infrastructure Services Committee
FROM: Pete Mayer, Interim Public Works Director
BY: Adib Altallal, Utilities Engineer
CC Mayor Thomas McLeod
DATE: July 19, 2024
SUBJECT: Sewer Lift Stations 12 Upgrade
Project 90440207
Design Services Agreement
ISSUE
Approve design services agreement with Parametrix for the Sewer Lift Station 12 Upgrade project.
BACKGROUND
The aging electrical and physical assets of Sewer Lift Station 12 prompted further investigative work in
2016 and 2020. In 2021, minor repairs were made to extend the life of the assets until a comprehensive
repair or a rebuild can be completed. The City is now beginning a comprehensive repair, starting with
an alternatives study and subsequently design.
DISCUSSION
Parametrix was selected as the primary design consultant after reviewing list of 9 other well -qualified
consultants due to their familiarity with the sewer lift station and their proactive work to help the City find
a solution long before it becomes a catastrophic failure.
FINANCIAL IMPACT
The Parametrix design services contract is proposed in the amount of $221,304.48. Although
previously identified as project to be completed in a future biennium, further degradation of the Lift
Station has moved the project up in priority. The funds required to complete the design will be from
provided by cost savings from the 2023 Annual Sewer Repair Project.
Contract 2023 Cost Savings
Parametrix Contract $221,304.58 $ 698,454.11
RECOMMENDATION
Council is being asked to approve the design agreement with Parametrix in the amount of $221,304.58
for the Sewer Lift Station 12 Upgrade project and to consider this item on the Consent Agenda at the
August 5 Regular Meeting.
Attachments: 2023 CIP Page
Parametrix Scope and LOE
https://tukwilawa.sharepoint.com/sites/publicworks/engineering/PW Drop Box/01 TIC Agenda/2024 Agenda Items/TIC 07-22-24/4. Sewer Lift Station 12 Retrofit Design Contract Parametrix/1. Info Memo LS12 Upgrade.docx
74
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
PROJECT:
DESCRIPTION:
JUSTIFICATION:
STATUS:
MAINT. IMPACT:
COMMENT:
2023 to 2028
Sewer Lift Station No. 12 Project No. 90440207
Rebuild sewer lift station 12 to better serve the northeast corner of the Commercial Business District.
Lift Station No. 12 is at capacity due to its limited wetwell size. If substantial growth occurs in the basin
due to the expansion of the mall or other large projects, the existing lift station will need to be upgraded.
A study to repair the wet well is being conducted in 2022.
None at this time.
A Sewer bond issue is proposed to cover financing of this project. Coordinate with Southcenter Blvd Sewer
Upgrade and future LS13.
FINANCIAL
(in $000's)
Through Estimated
2021 2022 2023
2024
2025
2026
2027
2028
BEYOND TOTAL
EXPENSES
Design
300
300
Land (R/W)
500
500
Const. Mgmt.
350
350
Construction
2,500
2,500
TOTAL EXPENSES
0
0
0
0
0
0
0
0
3,650
3,650
FUND SOURCES
Awarded Grant
0
Proposed Grant
0
Bond
0
Mitigation Actual
0
Mitigation Expected
0
Utility Revenue
0
0
0
0
0
0
0
0
3,650
3,650
TOTAL SOURCES
0
0
0
0
0
0
0
0
3,650
3,650
e •~ aT. /n
, 5 B� __� .k",�� 0
I rojec Location
Projectca
51565t
\ \t i�fh 40 �'`
�-'
St
\ VI."
.�
a
— 2
fTT 51fi05t
��`
��
D ,
TOila
M
Pkwy
�
it
_
�1
•^
O
g
f
imEnwer sOr
or
z
9
s
} a
o.
o.sa.onsTo.
EEi
S ; 1 S 180 SI
Jj
� r
C
o r Q�m
.
1r
2023 - 2028 Capital Improvement Program
75
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Contract Number:
PROFESSIONAL SERVICES AGREEMENT
(Includes consultants, architects, engineers, accountants, and other professional services)
THIS AGREEMENT is entered into between the City of Tukwila, Washington, hereinafter
referred to as "the City", and Parametrix, hereinafter referred to as "the Consultant", in consideration
of the mutual benefits, terms, and conditions hereinafter specified.
1. Project Designation. The Consultant is retained by the City to perform design services in
connection with the project titled Sewer Lift Station 12 Upgrade.
2. Scope of Services. The Consultant agrees to perform the services, identified on Exhibit "A"
attached hereto, including the provision of all labor, materials, equipment and supplies.
3. Duration of Agreement; Time for Performance. This Agreement shall be in full force and
effect for a period commencing upon execution and ending 31 December 2025, unless sooner
terminated under the provisions hereinafter specified. Work under this Agreement shall
commence upon written notice by the City to the Consultant to proceed. The Consultant shall
perform all services and provide all work product required pursuant to this Agreement no later
than 31 December 2025 unless an extension of such time is granted in writing by the City.
4. Payment. The Consultant shall be paid by the City for completed work and for services
rendered under this Agreement as follows:
A. Payment for the work provided by the Consultant shall be made as provided on Exhibit
"B" attached hereto, provided that the total amount of payment to the Consultant shall not
exceed 221,304.58 without express written modification of the Agreement signed by the
City.
B. The Consultant may submit vouchers to the City once per month during the progress of
the work for partial payment for that portion of the project completed to date. Such
vouchers will be checked by the City and, upon approval thereof, payment shall be made
to the Consultant in the amount approved.
C. Final payment of any balance due the Consultant of the total contract price earned will be
made promptly upon its ascertainment and verification by the City after the completion of
the work under this Agreement and its acceptance by the City.
D. Payment as provided in this section shall be full compensation for work performed,
services rendered, and for all materials, supplies, equipment and incidentals necessary to
complete the work.
E. The Consultant's records and accounts pertaining to this Agreement are to be kept
available for inspection by representatives of the City and the state of Washington for a
period of three (3) years after final payments. Copies shall be made available upon
request.
76
5. Ownership and Use of Documents. All documents, drawings, specifications and other
materials produced by the Consultant in connection with the services rendered under this
Agreement shall be the property of the City whether the project for which they are made is
executed or not. The Consultant shall be permitted to retain copies, including reproducible
copies, of drawings and specifications for information, reference and use in connection with
the Consultant's endeavors. The Consultant shall not be responsible for any use of the said
documents, drawings, specifications or other materials by the City on any project other than
the project specified in this Agreement.
6. Compliance with Laws. The Consultant shall, in performing the services contemplated by
this Agreement, faithfully observe and comply with all federal, state, and local laws, ordinances
and regulations, applicable to the services rendered under this Agreement.
7. Indemnification. The Consultant shall defend, indemnify and hold the City, its officers,
officials, employees and volunteers harmless from any and all claims, injuries, damages,
losses or suits including attorney fees, arising out of or resulting from the acts, errors or
omissions of the Consultant in performance of this Agreement, except for injuries and damages
caused by the sole negligence of the City.
Should a court of competent jurisdiction determine that this Agreement is subject to RCW
4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or
damages to property caused by or resulting from the concurrent negligence of the Consultant
and the City, its officers, officials, employees, and volunteers, the Consultant's liability
hereunder shall be only to the extent of the Consultant's negligence. It is further specifically
and expressly understood that the indemnification provided herein constitutes the Consultant's
waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this
indemnification. This waiver has been mutually negotiated by the parties. The provisions of
this section shall survive the expiration or termination of this Agreement.
8. Insurance. The Consultant shall procure and maintain for the duration of the Agreement,
insurance against claims for injuries to persons or damage to property which may arise from
or in connection with the performance of the work hereunder by the Consultant, its agents,
representatives, or employees. Consultant's maintenance of insurance as required by the
agreement shall not be construed to limit the liability of the Consultant to the coverage provided
by such insurance, or otherwise limit the City's recourse to any remedy available at law or in
equity.
A. Minimum Amounts and Scope of Insurance. Consultant shall obtain insurance of the
types and with the limits described below:
1. Automobile Liability insurance with a minimum combined single limit for bodily injury
and property damage of $1,000,000 per accident. Automobile Liability insurance
shall cover all owned, non -owned, hired and leased vehicles. Coverage shall be
written on Insurance Services Office (ISO) form CA 00 01 or a substitute form
providing equivalent liability coverage. If necessary, the policy shall be endorsed to
provide contractual liability coverage.
2. Commercial General Liability insurance with limits no less than $2,000,000 each
occurrence, $2,000,000 general aggregate. Commercial General Liability
insurance shall be at least as broad as ISO occurrence form CG 00 01 and shall
cover liability arising from premises, operations, stop -gap independent contractors
and personal injury and advertising injury. The City shall be named as an
additional insured under the Consultant's Commercial General Liability insurance
policy with respect to the work performed for the City using an additional insured
endorsement at least as broad as ISO endorsement form CG 20 26.
3. Workers' Compensation coverage as required by the Industrial Insurance laws of
the State of Washington.
CA revised May 2020
Page 2
77
4. Professional Liability with limits no less than $2,000,000 per claim and $2,000,000
policy aggregate limit. Professional Liability insurance shall be appropriate to the
Consultant's profession.
B. Public Entity Full Availability of Contractor Limits. If the Contractor maintains higher
insurance limits than the minimums shown above, the Public Entity shall be insured for the
full available limits of Commercial General and Excess or Umbrella liability maintained by
the Contractor, irrespective of whether such limits maintained by the Contractor are greater
than those required by this Contract or whether any certificate of insurance furnished to
the Public Entity evidences limits of liability lower than those maintained by the Contractor.
C. Other Insurance Provision. The Consultant's Automobile Liability and Commercial
General Liability insurance policies are to contain, or be endorsed to contain that they shall
be primary insurance with respect to the City. Any Insurance, self-insurance, or insurance
pool coverage maintained by the City shall be excess of the Consultant's insurance and
shall not be contributed or combined with it.
D. Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M.
Best rating of not less than A:VII.
E. Verification of Coverage. Consultant shall furnish the City with original certificates and a
copy of the amendatory endorsements, including but not necessarily limited to the
additional insured endorsement, evidencing the insurance requirements of the Contractor
before commencement of the work. Upon request by the City, the Consultant shall furnish
certified copies of all required insurance policies, including endorsements, required in this
Agreement and evidence of all subcontractors' coverage.
F. Notice of Cancellation. The Consultant shall provide the City with written notice of any
policy cancellation, within two business days of their receipt of such notice.
G. Failure to Maintain Insurance. Failure on the part of the Consultant to maintain the
insurance as required shall constitute a material breach of contract, upon which the City
may, after giving five business days notice to the Consultant to correct the breach,
immediately terminate the contract or, at its discretion, procure or renew such insurance
and pay any and all premiums in connection therewith, with any sums so expended to be
repaid to the City on demand, or at the sole discretion of the City, offset against funds due
the Consultant from the City.
9. Independent Contractor. The Consultant and the City agree that the Consultant is an
independent contractor with respect to the services provided pursuant to this Agreement.
Nothing in this Agreement shall be considered to create the relationship of employer and
employee between the parties hereto. Neither the Consultant nor any employee of the
Consultant shall be entitled to any benefits accorded City employees by virtue of the services
provided under this Agreement. The City shall not be responsible for withholding or otherwise
deducting federal income tax or social security or for contributing to the state industrial
insurance program, otherwise assuming the duties of an employer with respect to the
Consultant, or any employee of the Consultant.
10. Covenant Against Contingent Fees. The Consultant warrants that he has not employed or
retained any company or person, other than a bonafide employee working solely for the
Consultant, to solicit or secure this contract, and that he has not paid or agreed to pay any
company or person, other than a bonafide employee working solely for the Consultant, any
fee, commission, percentage, brokerage fee, gifts, or any other consideration contingent upon
or resulting from the award or making of this contract. For breach or violation of this warrant,
the City shall have the right to annul this contract without liability, or in its discretion to deduct
from the contract price or consideration, or otherwise recover, the full amount of such fee,
commission, percentage, brokerage fee, gift, or contingent fee.
CA revised May 2020
Page 3
78
11. Discrimination Prohibited. Contractor, with regard to the work performed by it under this
Agreement, will not discriminate on the grounds of race, religion, creed, color, national origin,
age, veteran status, sex, sexual orientation, gender identity, marital status, political affiliation,
the presence of any disability, or any other protected class status under state or federal law,
in the selection and retention of employees or procurement of materials or supplies.
12. Assignment. The Consultant shall not sublet or assign any of the services covered by this
Agreement without the express written consent of the City.
13. Non -Waiver. Waiver by the City of any provision of this Agreement or any time limitation
provided for in this Agreement shall not constitute a waiver of any other provision.
14. Termination.
A. The City reserves the right to terminate this Agreement at any time by giving ten (10) days
written notice to the Consultant.
B. In the event of the death of a member, partner or officer of the Consultant, or any of its
supervisory personnel assigned to the project, the surviving members of the Consultant
hereby agree to complete the work under the terms of this Agreement, if requested to do
so by the City. This section shall not be a bar to renegotiations of this Agreement between
surviving members of the Consultant and the City, if the City so chooses.
15. Applicable Law; Venue; Attorney's Fees. This Agreement shall be subject to, and the
Consultant shall at all times comply with, all applicable federal, state and local laws,
regulations, and rules, including the provisions of the City of Tukwila Municipal Code and
ordinances of the City of Tukwila. In the event any suit, arbitration, or other proceeding is
instituted to enforce any term of this Agreement, the parties specifically understand and agree
that venue shall be properly laid in King County, Washington. The prevailing party in any such
action shall be entitled to its attorney's fees and costs of suit. Venue for any action arising
from or related to this Agreement shall be exclusively in King County Superior Court.
16. Severability and Survival. If any term, condition or provision of this Agreement is declared
void or unenforceable or limited in its application or effect, such event shall not affect any other
provisions hereof and all other provisions shall remain fully enforceable. The provisions of this
Agreement, which by their sense and context are reasonably intended to survive the
completion, expiration or cancellation of this Agreement, shall survive termination of this
Agreement.
17. Notices. Notices to the City of Tukwila shall be sent to the following address:
City Clerk
City of Tukwila
6200 Southcenter Boulevard
Tukwila, WA 98188
Notices to Consultant shall be sent to the following address:
18. Entire Agreement; Modification. This Agreement, together with attachments or addenda,
represents the entire and integrated Agreement between the City and the Consultant and
supersedes all prior negotiations, representations, or agreements written or oral. No
amendment or modification of this Agreement shall be of any force or effect unless it is in
writing and signed by the parties.
CA revised May 2020
Page 4
79
DATED this day of , 2024.
CITY OF TUKWILA
Thomas McLeod, Mayor
ATTEST/AUTHENTICATED:
Andy Youn, City Clerk
APPROVED AS TO FORM:
Office of the City Attorney
CONSULTANT:
By:
Printed Name:
Title:
CA revised May 2020
Page 5
80
Parametrik
let's create tomorrow, together
Exhibit A - Scope of Work
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
Introduction
This scope of work (SOW) describes the services to be provided by Parametrix, Inc. (Parametrix) for
the Lift Station 12 Upgrade Project for the City of Tukwila (City). The City seeks to upgrade Lift
Station 12 to improve reliability, provide renewed longevity, enhance operational efficiency, and
bring the station into compliance with current codes. The City tasked Parametrix to provide
alternatives on how to address these concerns.
List Station 12 was initially built in 1972 and serves Drainage Basins 4 and 8. Upgrades to the lift
station were completed between 2001 and 2003, including pump replacements and a new on -site
generator. According to the City's 2014 Comprehensive Sanitary Sewer Plan (Carollo 2014), the
average annual flow for List Station 12 is approximately 0.19 million gallons per day (MGD) and peak
day average flow is approximately 0.72 MGD. Peak instantaneous flows were estimated to reach
approximately 1.18 MGD with infiltration and inflow contributing to approximately 0.57 MGD.
As identified in the City's 2014 Comprehensive Sanitary Sewer Plan (Carollo 2014), it was
anticipated that the pumps and the lift station structure would reach their useful life by 2023. The
City has considered alternative options to serve Drainage Basin 4 and currently, the pumps at the
existing lift station have not been able to keep up with the variable flows due to wear.
0n June 5, 2024, City staff and the Parametrix team conducted a site visit at Lift Station 12 to
discuss the project. Alternatives initially discussed at the site visit with City staff included upgrades to
the existing station, converting the station to a submersible pump station, or building a new wet well.
The Lift Station 12 Upgrade Project includes developing and evaluating potential upgrade
alternatives through collaborative workshops with City personnel, conducting an alternatives
analysis, and determining a preferred design alternative for improvements at the existing lift station.
Subsequently, a preliminary design submittal will be prepared, including 30% design plans, an
outline of technical specifications, and a construction cost estimate.
This SOW does not include the Final Design Phase, which will be determined during the Preliminary
Design Phase, encompassing final design plans, specifications, construction cost estimates, and
necessary permit applications. This SOW also does not include bid support or services during
construction, which will be provided under a separate task order.
Document Organization
• Exhibit A: Scope of Work
• Exhibit B: Limits of Survey
• Exhibit C: Preliminary Sheet List - Preliminary Design
• Exhibit D: Rates and Fee Estimate
• Exhibit E: Subconsultant Proposals
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
1
216-2067-833
July 2024
81
Exhibit A - Scope of Work
■ Exhibit F: Projected Project Schedule
Scope Work Breakdown Structure
Work Breakdown Summary:
■ Task 01 Project Management and Quality Control
■ Task 02 Data Collection and Review
■ Task 03 Develop Alternatives
■ Task 04 Alternatives Analysis
■ Task 05 Preliminary Design
■ Task 06 Subconsultant Allocation
■ Task 07 Management Reserve
Task 01 - Project Management and Quality Control
Objective
Task 01 provides tracking scope, schedule, and budget for the project; overseeing project
administration (filing, invoicing, etc.); coordination and communication with the City; and ensuring
that Parametrix properly implements quality assurance/quality control (QA/QC) procedures over the
duration of this project.
Subtask 01.1 - Project Management
Subtask 01.1 includes project start-up and establishing a project SharePoint site; documenting and
communicating the scope of work, budget, and schedule as a road map for the project team;
coordinating with the project team and addressing issues throughout the project; tracking the project
budget using Parametrix in-house tools to verify that progress aligns with spending; and conducting
check -in meetings with the City's project manager (PM) to discuss and review information and issues
that may affect the work's progress.
Subtask 01.2 - Invoicing & Progress Reports
Subtask 01.2 includes preparing monthly progress reports to accompany each monthly invoice.
Progress reports will include a narrative of work completed, anticipated work for the next period, and
a description of issues affecting project progress and proposed resolutions if necessary.
Subtask 01.3 - Correspondence and Coordination with the City
Subtask 01.3 includes regular communication with the City's PM to discuss and review information
and issues that may affect the progress of the work. Communication may include phone
conversations, scheduled meetings, and electronic communication.
Subtask 01.4 - Coordination with the Parametrix Team
Subtask 01.4 includes regular communication with the Parametrix team to discuss and review
information needs, project information, and issues that may affect the progress of the work.
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
2
216-2067-833
July 2024
82
Exhibit A - Scope of Work
Communication may include phone conversations, scheduled meetings, and electronic
communication.
Subtask 01.5 - Project QAQC
Subtask 01.5 includes time to perform quality assurance to verify quality checks have been
completed and addressed, and time to review design as contract plans and specifications are being
prepared. QA/QC will be performed to ensure that City comments have been thoroughly addressed
and internal reviews have been completed prior to delivery of all work products to verify consistency
with internal standards of practice and care.
Task 01 Assumptions
• Project duration is eight (8) months.
• Budget assumes up to six PM check -in meetings to be attended virtually by up to two
Parametrix staff for up to 0.5 hours each.
• Budget assumes up to 10 design team meetings to be attended virtually by up to three
Parametrix staff for up to 0.5 hours each.
Task 01 Deliverables
• Miscellaneous correspondence to document project management issues.
• Monthly progress reports enclosed with invoices (in PDF file format).
• Project Schedule (in PDF file format).
Task 02 - Data Collection and Review
Objective
Task 02 includes the collection, review, and assessment of available information and mapping prior
planning efforts before beginning the alternatives analysis and preliminary design. The Parametrix
team will provide comprehensive written request for information (RFI) lists, which may include record
drawings and relevant planning studies.
Subtask 02.1 - Data Collection and Review
Subtask 02.1 includes collecting and reviewing available historical data, design specifications,
performance metrics, and maintenance records as they pertain to the existing lift station, as well as
collecting and reviewing available technical specifications, performance data, and cost estimates for
submersible pumps, dry pit pumps, and new wet well designs.
Subtask 02.2 - Survey and Mapping
Subtask 02.2 includes determining the right-of-way for Andover Park W, as delineated in Exhibit A.
Parametrix will provide topographic mapping for the lift station located near the southeast corner of
the Westfield Shopping Center, as delineated in Exhibit A. The topographic limits will include the
location of the lift station and the surrounding parking lot of Key Bank. Parcel boundaries will be
limited to within the area to be surveyed and easements of record depicted on the subject property's
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
3
216-2067-833
July 2024
83
Exhibit A - Scope of Work
binding site plan will be plotted on the basemap. The setting of any survey monuments at any of the
exterior boundary points of the subject properties.
All physical improvements —such as signs, guardrails, fences, driveways, utility poles, water features,
telecommunication features, storm drainage features, sewer manholes, and other features —will be
mapped during the survey within the right-of-way as well. All storm drainage and sewer structure
invert elevations will be included within the scope of work. Trees will be mapped on -site but will be
limited to trees that have trunk diameters of 6 inches or larger
Parametrix will coordinate with Applied Professional Services (APS) to have the utilities marked out.
Conductible utilities will be mapped per the locate company's markings. Potholing is not included.
Subtask 02.3 - 3D Scanning
Subtask 02.3 includes 3D laser scanning of the site property, building structure exterior and
internals, and existing equipment. This will include both wet well and dry well locations. Laser
scanning provided will initially only be used to confirm and view structure and component locations
and dimensional relevance to each other. Scanning performed will not be to any survey coordinate
system but will be tied into surveyed temporary benchmarks so it can later be combined with the
survey basemap during Task 05 Preliminary Design. Scanning will require physical access to areas
and spaces needed to complete this project and owner shall provide access as required to complete
this effort.
Task 02 Assumptions
• Up to three RFIs will be prepared and provided to the City.
• City response for each RFI list is 7 business days.
• RFIs and shared documents will be shared and accessed via an established Project
SharePoint site.
• Parametrix survey crews will be provided reasonable access to all areas requiring surveys.
• Parametrix will be omitting topographic mapping with Andover Park. The topographic survey
will extend to the west face of the curb within the right-of-way of Andover Park.
• All electronic mapping standards will be based on Parametrix drafting standards.
• Parametrix survey crews have client permission to perform minor brushing with machetes to
conduct this survey, if needed, for field crews to perform work described within this SOW.
• Unless otherwise specified by the client, horizontal datum shall be North American Datum
(NAD) 83/11 Washington Coordinate System, North Zone, and vertical datum shall be North
American Vertical Datum of 1988 (NAVD 88).
• The boundary of the property will be merged into the topographic mapping, as appropriate,
and shown for graphical purposes only. This service can be provided if required at a later
date; however, any setting of property corners, and filing of a record of survey (if required) will
be considered Additional Services and billed separately as described below.
• For safety reasons, Parametrix survey crews are not allowed to enter subsurface vaults.
Parametrix work will be conducted from the surface, using measure -down techniques.
Parametrix survey crews will also not open any structure covers over 80 pounds.
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
4
216-2067-833
July 2024
84
Exhibit A - Scope of Work
■ Site scanning will be approximately 20 to 35 scans. Once complete, scans will then be
combined and stitched together providing a single site scan.
■ Budget assumes up to six hours of scanning time shall be required and up to eight hours to
combine all scans into a single site scan.
Task 02 Deliverables
■ RFI lists (provided electronically).
■ One PDF copy of the topographic survey.
■ An electronic drawing file of the topographic survey in AutoCAD Civil 3D 2020 format in one
drawing file.
Task 03 -Develop Alternatives
Objective
Task 03 provides developing and evaluating viable alternatives for upgrading Lift Station 12,
ensuring improved performance and compliance with current standards while minimizing bypass
pumping. Initial concept alternatives include:
■ Alternative 1: Upgrade Existing Station
■ Alternative 2: Convert to Submersible Pump Station
■ Alternative 3: Build New Wet Well
Subtask 03.1 - Determine Alternatives
Subtask 03.1 includes providing technical evaluation and support in preparation for Workshop 1
(see Task 03) in support of a concept screening to determine the two design alternative types
to develop for refinement, selected from the three concept alternatives: submersible, dry pit, and
new wet well. Parametrix will assess available information to determine the practicality of
implementing each alternative. This subtask includes developing a description of each of the three
alternatives as listed above, a concept feasibility layout, a brief list of advantages and
disadvantages, and a Class 5 engineer's opinion of construction cost. If initial evaluation determines
the alternative has a fatal flaw, the concept layout and opinion of construction cost will not be
developed.
Subtask 03.2 - Refine Alternatives
Subtask 03.2 includes providing technical evaluation and support to refine two design alternatives in
preparation for Workshop 2 (see Task 04). This subtask includes developing a detailed description of
two design alternatives and identifying potential risks and challenges for each alternative, including
technical, financial, and operational. This subtask includes developing confirmation layouts for each
alternative and an evaluation of real estate needs, including staging area, traffic impacts during
construction, construction feasibility, as well as a Class 4 engineer's opinion of construction cost.
Estimate of property purchase costs are not included.
Task 03 Assumptions
■ The number of evaluated alternatives will remain as listed in this task.
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
5
216-2067-833
July 2024
85
Exhibit A - Scope of Work
■ No computer sewer model development will be included in this task.
■ Sufficient data on the current pump station's performance, maintenance, and operational
history, and technical specifications will be available to evaluate and prepare cost estimates
for submersible, dry pit, and new wet well alternatives for accurate comparison and
evaluation.
■ The three concept feasibility layouts will be one page each.
■ The two planning -level confirmation layouts will be one page each.
■ Subtasks 03.1 and 03.2 engineer's opinion of construction costs will be prepared to the
Association for the Advancement of Cost Engineering (AACE) Classes 5 and 4, respectively.
Typical accuracy ranges for AACE classes vary depending on the technological complexity of
the project, appropriate reference information, and the inclusion of an appropriate
contingency determination.
Task 03 Deliverables
■ Information and documentation to support Alternative Analysis Workshops. See Task 03
(various file formats).
■ Three concept layouts (in PDF file format).
■ Two feasibility layouts (in PDF file format).
■ Class 5 and Class 4 engineer's opinion of construction costs (in PDF file format).
Task 04 — Alternatives Analysis
Objective
Task 04 provides a holistic evaluation of viable options for upgrades to Lift Station 12 with City staff.
Two workshops will be conducted: the first to screen initially identified alternatives, and the second
to evaluate alternatives using a Triple Botton Line (TBL) Analysis to determine a preferred upgrade
design option. This task also includes a technical memorandum (tech memo) summarizing the
decision process in determining the preferred alternative.
Subtask 04.1 - Alternatives Analysis Workshops
Subtask 04.1 includes providing key services to prepare for and conduct two Alternative Analysis
Workshops, including the development of presentation materials, facilitating the workshops,
providing technical expertise during the workshop, and providing documentation of discussion,
decisions, and action items.
Parametrix will meet with City personnel to evaluate the identified alternatives, as well as discuss the
information collected and analyzed in Task 03. These workshops include:
■ Workshop 1: Review project goals and preferences with City staff to conduct a concept
screening of the three identified concept alternatives to determine two alternatives to further
refine and evaluate.
■ Workshop 2: Conduct an alternatives comparison (TBL Analysis) of two identified alternatives
to determine one preferred design alternative.
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
6
216-2067-833
July 2024
86
Exhibit A - Scope of Work
Subtask 04.2 - Alternatives Analysis Tech Memo
Subtask 04.2 includes documenting and summarizing the alternatives and decisions made during
the Alternatives Analysis Workshops into a tech memo, ensuring clear communication of the
selection process, alternative descriptions, and supporting exhibits.
Preliminary Alternative Analysis Tech Memo sections include:
• Project Introduction and Background.
• Workshop 1 and Alternative Descriptions.
• Workshop 2 and Alternative Descriptions.
• Preferred Alternatives and Recommendations.
• Attachments:
—> Concept and Confirmation Layouts.
Engineer's opinions of construction cost.
Workshop Agendas and Summaries.
Presentation Materials.
Task 04 Assumptions
• Budget assumes each Alternative Analysis Workshop will be attended to three Parametrix
staff (two in -person and one virtually) for up to 1.5 hours each. Budget includes travel time to
the City of Tukwila Public Works Office/Conference Room from the Parametrix Puyallup office
and mileage.
• Each Alternative Analysis Workshop may be attended by up to five City personnel.
• Criteria for the TBL Analysis will be developed with the City via check -in meetings with the City
PM (see Subtask 01.3). The criteria for evaluation shall include financial, environmental, and
social benefits, impacts, and risks.
• Workshop materials may include tables, charts, and a decision matrix to facilitate discussion
and engagement.
• The Alternative Analysis Tech Memo will be up to 15 pages with up to approximately four
attachments, as described above.
• The Draft Alternative Analysis Tech Memo review comments will be collected and
consolidated by the City PM and returned to the Parametrix team within 10 business days of
Draft Tech Memo delivery.
• Budget assumes that review comments will not involve changes to decision made in the
workshops, and will include limited tracked edit suggestions and margin comments provided
by the City on the Draft Alternative Analysis Tech Memo.
• Parametrix will finalize the Alternative Analysis Tech Memo within 10 business days after
receiving City review comments.
Task 04 Deliverables
• An agenda for each Alternative Analysis Workshop (in PDF File Format).
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
7
216-2067-833
July 2024
87
Exhibit A - Scope of Work
• Workshop presentation materials (various File Formats).
• Alternative Analysis Workshop Summaries (in PDF File Format).
• Alternative Analysis Tech Memo (Draft and Final in PDF File Format).
Task 05 - Preliminary Design
Objective
Task 05 provides initiating the Preliminary Design Phase of the preferred alternative determined in
Task 04. This task includes an initial design meeting with City staff, preparation and submission of
the Preliminary Design (30%) Submittal, including plans, specification outline, and engineer's opinion
of construction cost, as well as a design review workshop with City staff.
Subtask 05.1 - Initial Design Meeting
Subtask 05.1 includes kicking off the preliminary design phase with City staff and ensuring
stakeholders are aligned with the identified preferred alternative in Task 04, project goals, design
requirements, and project expectations for producing the 30% Design Submittal for Lift Station 12
upgrades. This meeting will focus on reviewing and confirming project goals and requirements;
revisiting the project schedule, including milestones and deliverables; and addressing any initial
questions or concerns from stakeholders.
Subtask 05.2 - Preliminary Design
Subtask 05.2 includes developing preliminary design plans for the proposed upgrades to Lift
Station 12 based on the preferred alternative determined in Task 04, generating a proposed list of
Construction Specifications Institute (CSI) and Washington State Department of Transportation
(WSDOT) technical specifications for the project, and preparing a 30% engineer's opinion of
construction cost.
A preliminary Drawing Sheet List is included as Exhibit C.
Subtask 05.3 - Preliminary Design Review Meeting
Subtask 05.3 includes a Preliminary Design Review Meeting with City staff to review City comments
and feedback on the Preliminary Design Submittal.
Task 05 Assumptions
• Budget assumes the Initial Design Meeting will be attended by up to four Parametrix staff
(two in -person and one virtually) for up to 1.0 hours each. Budget includes travel time to the
City of Tukwila Public Works Office/Conference Room from the Parametrix Puyallup office
and mileage.
• Budget assumes up to 12 sheets will be developed as part of the Preliminary Design
Submittal, as listed in Exhibit C. Should the preferred alternative determined in Task 04
require more Preliminary Design Plans than assumed, an amendment may be required.
• The preliminary cost estimate will be prepared to the AACE Class 3. Typical accuracy ranges
for AACE classes vary depending on the technological complexity of the project, appropriate
reference information, and the inclusion of an appropriate contingency determination.
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
8
216-2067-833
July 2024
88
Exhibit A - Scope of Work
• The preliminary cost estimate will generally be estimated as single lump sum prices, with unit
prices for earthwork and underground piping as appropriate.
• The City review of the Preliminary Design Submittal is 10 business days.
• The City will provide review comments and feedback to Parametrix prior to the Preliminary
Design Review Meeting.
• Budget assumes the Preliminary Design Review Meeting will be attended by up to four
Parametrix staff (two in -person and one virtually) for up to 2.0 hours each. Budget includes
travel time to the City of Tukwila Public Works Office/Conference Room from the Parametrix
Puyallup office and mileage.
• City review comments and feedback of the Preliminary Design Submittal will be incorporated
into the Final Design Phase.
Task 05 Deliverables
• Agenda and meeting summary for Initial Design Meeting (draft and final in PDF file format).
• Preliminary Design Plans, half-size, 11 by 17 inches (in PDF file format).
• Preliminary Design Specification Outline (in PDF file format).
• Class 3 engineer's opinion of construction cost (in PDF file format).
• Meeting summary for Preliminary Design Review Meeting (draft and final in PDF file format).
• Revised Project Schedule (in PDF file format).
Task 06 - Subconsultant Allocation
Objective
Task 06 provides a budgetary allocation for subconsultant services that will be required for the
Alternatives Analysis and Preliminary Design of the Lift Station 12 Upgrade Project.
Subtask 06.1 - Utility Locate Services
Subtask 06.1 includes a detailed proposal for utility locate services, prepared by subconsultant, APS,
included in Exhibit E. In general, APS will locate and mark known utilities within the project
boundaries and will sweep the project boundary areas to attempt to identify any unknown or
abandoned utilities. Utility potholing not included.
Task 06 Assumptions
• The City will review subconsultant's scope and fee proposals in advance of contract
execution between prime consultant (Parametrix) and subconsultant. Once proposals are
acceptable to the City, authorization will be issued in writing to allow the subconsultant to be
added to the prime consulting contract and provide authorization to proceed with the scoped
work.
• Work will not proceed for any of the subconsulting efforts until the City has provided
authorization for the subcontractor to be added to the primary contract, has approved of the
subconsultant's scope and fee, and has issued NTP for the work.
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
9
216-2067-833
July 2024
89
Exhibit A - Scope of Work
Task 06 Deliverables
■ See Exhibit E, Subconsultant Proposals, for detailed deliverables.
Task 07 - Management Reserve
Objective
Task 07 is a budgetary allocation so that the City has a discretionary budget to cover professional
services that are not defined in this SOW and are unknown at the time of the scope development.
Parametrix will provide a written scope and fee estimate for any additional services requested prior
to execution for the City's consideration. This task will remain unused unless the City issues a written
(email) authorization for work to be completed under this Task.
Assumptions
■ The budget for this work may be used by the Consultant, as authorized by the City.
■ The City will authorize the use of funds in this task in writing (email) prior to the Consultant
starting the work.
Deliverables
■ Documentation for professional services not defined in this SOW, as required or requested by the
City.
Rates and Fee Estimate
Rates and fee estimate for this scope of work (SOW) is included as Exhibit D. This budget is reflective
of this SOW, known information, and previous experience regarding the level of effort on similar
projects.
Projected Project Schedule
The schedule below summarizes project tasks based on anticipated notice to proceed (NTP) on or
around August 5, 2024. Receipt of NTP after this day may result in a corresponding delay in the
following projected schedule for tasks included in this SOW. A projected Project Schedule is included
as Exhibit F.
Task
Start Finish
Task 01 Project Management and Quality Control 08/2024 03/2025
Task 02 Data Collection and Review 08/2024 08/2024
Task 03 Develop Alternatives 08/2024 10/2024
Task 04 Alternatives Analysis 09/2024 12/2024
Task 05 Preliminary Design 10/2025 03/2025
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
10
216-2067-833
July 2024
90
Exhibit A - Scope of Work
References
Carollo (Carollo Engineers). 2014. City of Tukwila, WA, Final Comprehensive Sanitary Sewer Plan, .
Carollo Engineers, Seattle, WA.
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
11
216-2067-833
July 2024
91
Parametrik
let's create tomorrow, together
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
1
Exhibit B - Limits of Survey
216-2067-833
July 2024
92
Parametrik
let's create tomorrow, together
The Preliminary Drawing Sheet List includes:
• General
-+ Title Sheet, Vicinity Map, and Index
—> Symbols and Legend
—> Abbreviations
• Civil
—> Site Layout Plan and Survey Control
—> Plan and Elevations
—> Section and Details
• Mechanical
—> Pump and Piping Floor Plan
- Pump and Piping Sections
• Electrical
—> Legend and Abbreviations
—> One -Line Diagram
—> Site Plan
• Piping and Instrumentation Diagram (P&ID)
—> Piping and Instrumentation Diagram (P&ID)
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
1
Exhibit C - Preliminary Drawing
Sheet List - Preliminary Design
216-2067-833
July 2024
93
Exhibit D - Rates and Project Fee Estimate
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
z
Jakubowitch, Andy
Linke, Joel
Cosgrove, Sandy
Crackenberger, Sarah
Carlson, Cameron
Ortega, JJ
Taylor, Kathy
Luke McMullan
Lucas, Amanda
w
Van Cleave, Ken
Printz, Whitney
Wilson, Stephen
Wittman, Connor
Merth, Joe
,inke, Jake
Mark Mollnow
Denise Peterson
Cliff West
PIC
PM
SME/QAQC
PC
Acct
Electrical
Support
CAD
Cost Estimator
Pubs
Survey
Survey
Survey
Survey
Electrical QC
Structural QC
Structural
CAD Design
CAD Design
CAD Design
Senior
Consultant
Senior Engineer
Senior Engineer
Sr Project
Control
Specialist
Senior Project
Accountant
Electrical
Engineer VI
Engineer I
Senior Designer
Planner IV - Cost
Estimator
Publications
Supervisor
Survey
Supervisor
Senior Survey
Project
Coordinator
Surveyor III
Senior Electrical
Engineer
Senior
Consultant
Engineer VI
=
Y
,o
w o
Senior Designer
Burdened Rates:
$319.48
$226.56
$249.50
$147.52
$1.32.42
$212.06
$125.00
$202.77
$1.42.39
$142.39
$210.50
$153.99
$105.95
$136.50
5229.32
$317.00
$1.94.09
$1.52.53
$171.31
$221.22
Phase
Task
Description
Labor Hours
Labor Dollars
WI
1106
$220
8
7
111.56
0
24
ilr 60
5
5implapt40
1
Project Management & Meetings
102
$22,977.14
9
36
16
8
7
6
6
0
0
0
4
0
0
0
5
5
0
0
0
0
1.1
Project Management
13
$2,663.01.
10
3
1.2
Invoice and Progress Reports
16
$2,616.28
4
8
4
1.3
Correspondence and Coordination with the City
21
$4,618.56
1
16
2
2
1.4
Coordination with the Consultant Team
19
$4,165.04
3
6
2
4
4
1.5
Project QA/QC
33
$8,914.25
5
14
4
5
5
2
Data Collection and Review
197
$30,229.70
2
12
1
0
0
8
16
0
0
0
0
40
24
60
0
0
8
20
0
6
2.1
Data Collection and Review
47
$8,856.38
2
12
1
8
16
8
2.2
Survey and Mapping
124
$16,892.40
40
24
60
2.3
3D Scanning
26
$4,480.92
20
6
3
Develop Alternatives
302
$59,574.40
20
56
6
0
0
24
48
40
36
0
0
0
0
0
0
0
24
0
16
32
3.1
Determine Alternatives
153
$30,083.20
10
28
3
0
0
14
24
16
20
0
0
0
0
0
0
0
14
0
8
16
Concept Feasibility Layouts
123
$24,777.90
8
24
3
12
24
16
12
8
16
Cost Estimates
30
$5,305.30
2
4
2
20
2
3.2
Refine Alternatives
149
$29,491.20
10
28
3
0
0
10
24
24
16
0
0
0
0
0
0
0
10
0
8
16
Confirmation Layouts
123
$24,775.46
8
24
3
8
24
24
8
8
16
Cost Estimates
26
$4,715.74
2
4
2
16
2
4
Alternatives Analysis
168
$30,628.86
16
40
0
0
0
14
72
0
0
12
0
0
0
0
0
0
14
0
0
0
4.1
Alternatives Analysis Workshop
56
$10,456.20
10
14
0
0
0
0
28
0
0
4
0
0
0
0
0
0
0
0
0
0
Workshop 1 Prep
16
$2,919.15
2
5
8
1
Workshop 1 and Summary
12
$2,308.95
3
2
6
1
Workshop 2 Prep
16
$2,919.15
2
5
8
1
Workshop 2 and Summary
12
$2,308.95
3
2
6
1
4.2
Alternatives Analysis Tech Memo
112
$20,172.66
6
26
0
0
0
14
44
0
0
8
0
0
0
0
0
0
14
0
0
0
Draft
69
$12,389.03
4
16
8
28
5
8
Final
43
$2,283.63
2
10
6
16
3
6
5
Preliminary Design
337
$65,954.62
18
56
9
0
0
39
73
32
20
1
0
0
0
0
0
0
13
0
24
35
5.1
Initial Design Meeting
19
$3,662.48
3
3
3
8
2
5.2
Preliminary Design
301
$58,395.00
15
53
9
0
0
36
65
32
20
1
0
0
0
0
0
0
11
0
24
35
Drawings
261
$50,886.32
12
45
9
31
65
32
8
24
35
Specification Outline
10
$2,203.38
1
4
3
1
1
Cost Estimate
30
$5,305.30
2
4
2
20
2
5.3
Prelminary Design Review Meeting
17
$3,897.14
4
5
4
2
2
6
Subconsultant Allocation (Includes 10% Markup)
0
$742.50
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
5.1
Utility Locate Services
0
$242.50
7
Management Reserve (5%)
0
$10,505.36
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
7.1
Management Reserve
0
$10,505.36
Project Expenses
$692.00
Mileage (assumes 800 mi for site visits and survey @ $0.665/mile)
Survey Equipment (assumes 1 use @ $160/use)
$532.00
$160.00
Total Fee Estimate
$221,304.58
216-2067-833
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
July 2024
94
SApplied Professional Services, Inc.
43530 SE North Bend Way
North Bend, WA 98045
"Solutions that exceed expectations"
Date
Project Address/Job Number:
Services Performed For:
7/16/2024
275 Andover Park W, Tukwila
Parametrix
Justin Emery
Design Survey Locating
jemery(a�parametrix.com
253-785-3028
Scope of Work
A. APS, Inc. will employ all industry and best practices to designate and mark the known
conductible and/or non -conductible utilities within the project boundaries.
B. APS, Inc. will sweep the area, after the known utilities have been marked, to attempt
to identify any unknown or abandoned utilities.
C. The project boundaries are defined by civil drawings or maps provided by the Client.
Cost Estimate
LABOR DESCRIPTION
HOURS RATE AMOUNT
RMT" Conductible Locates
5
$135.00
$675.00
Total
$675.00
Statement of Work for Parametrix •
9
95
Invoicing
Net 30 days on all billing unless specified otherwise under a separate contract or
negotiation.
Disclaimer
APS, Inc, and or its employees cannot guarantee that all conductible and/or non -conductible
utilities within the project boundaries can or will be found.
Project Estimate
NOT TO EXCEED WITHOUT WRITTEN CLIENT APPROVAL:
This hourly / not to exceed project estimate is based on the estimated number of hours it will
take to perform the Scope of Work. If the project requires additional time or costs to
complete the Scope of work, then written approval to exceed the original cost estimate is
required.
By
Name
Parametrix
Title
Statement of Work for Parametrix •
2
96
City of Tukwila
Lift Station 12 Upgrade
Alternatives Analysis and Preliminary Design
Exihibit F - Projected Project Schedule
ID
Task Task Name
e Mode
Duration
Start Finish Predecessors
S pa'24 S pt S,, ,' 4 On6,'2 ORt On 2n '24 Oct 27' 4 ov 3,'24
RAVITIFISI5IMiT}wITIFISI5IL4VITIFISI5IMiT TIF18186114VITIFISISI ITIWITIFISISI II TIFISISIMITMATIFISISI IMW1TIFISISIMITM�TIFISISIMITVITIFISISIMITNITIFISISal ViTIFISISIMITMATIFISISSIM4041FISISIMMWT4IFISISSMIT
D ce,'24140,,'
TIFISI5kiFIWITIFISISfITNYMIFISISkIIT
TIFISISIMI.MMTIFISISkIIT
1 n12' S j00, t9' S 1 n26' S L'2 F b9,' S F b2 S ar9,'2 ,'
TIFISSIMI MITIFISISIMITVITIFISISiTMITIFISISIMITYITIFISISfMITMTIFISI5fITMITIFISISflITwfTIFISISIM4VITIFISISSaTIWITIFISISSMAYITIFISI5SMIT
S ,'
TIFISISS T
S
TIFIS
1
2
3
4
®•
..
1
+
1
.
.
ra.
1
.
.
+
+
1
Anticipated NTP: August 5, 2024
0 days
160 days
8 mons
8 mons
Mon 8/5/24 Mon 8/5/24
Mon 8/5/24 Fri 3/14/25
Mon 8/5/24 Fri 3/14/25
Mon 8/5/24 Fri 3/14/25
Mon 8/5/24 Fri 3/14/25
k 8/5
I Task01: Project Management and Quality Control
1
1
1
1
1
1
Subtask 01.1: Project Management
Subtask 01.2: Invoicing & Progress Reports
5
Subtask 01.3: Correspondence with City
8 mons
6
Subtask 01.4: Coordination with Consultant Team
8 mons
Mon 8/5/24 Fri 3/14/25
Mon 8/5/24 Fri 3/14/25
Mon 8/5/24 Tue 8/20/24
Mon 8/5/24 Fri 8/16/24
7
Subtask 01.5: Project OAOC
8 mons
I'I
1.
"I
"I
"I
8
Task 02: Data Collection and Review
12 days
9
Subtask 02.1: Data Collection and Review
10 days
5 days
5 days
42 days
13 days
10
Subtask 02.2:Survey and Mapping
Wed 8/14/24Tue 8/20/24
Wed 8/14/24Tue 8/20/241F5+7
Wed 8/21/247hu 10/17/2,
Wed 8/21/2r Fri 9/6/24
1FS+7 days —
days
1
9,10,11,1
11
Subtask 02.3: 3D Scanning
Task03: Develop Alternatives
Subtask 03.1: Determine Alternatives
12
13
14
M.
Concept Layouts
10 days
3 days
26 days
21 days
5 days
73 days
32 days
3 days
3 days
41 days
21 days
10 days
10 days
103 days
3 days
100 days
85 days
85 days
5 days
Wed 8/21/24Tue 9/3/24
15
1
Cost Estimates
Wed 9/4/24 Fri 9/6/24
14
16
1
re
1
.
.
1
+
Ws.
.
Subtask 03.2: Refine Alternatives
Concept Layouts
Cost Estimates
Task 04: Alternatives Analysis
Subtask 04.1: Abernethies Analysis Workshops
Workshop 1
Thu 9/12/24 Thu 10/17/2,
1
17
18
Thu 9/12/24 Thu 10/10/2,
Fri 10/11/24 Thu 10/17/2,17
Mon 9/9/24 Wed 12/18/2
Mon 9/9/24 Tue 10/22/24
Mon 9/9/24 Wed 9/11/2414,15
1Fri 10/18/24 Tue 10/22/2,17,18
Wed 10/23/: Wed 12/18/:17,18
Wed 10/23/2 Wed 11/20/222
Thu 11/21/2, Wed 12/4/2424
21
19
20
21
22
23
Workshop 2
Subtask 04.2: Abernethies Analysis Tell Memo
Draft
24
25
$
City Review
1
26
27
0
0
Final
Task 05: Preliminary Design
Thu 12/5/24 Wed 12/18/225
Wed 10/23/2 Fri 3/14/25
28
$
Subtask 05-01: Initial Design Meeting
Wed 10/23/21Fri 10/25/24 22
29
3
Subtask 05-03: Preliminary Design
Wed 10/23/:Tue3/11/25
I
30
ry
Plans
Wed 10/23/2Tue 2/18/2522
Wed 10/23/2Tue 2/18/2522
•Wed 2/19/25Tue 2/25/25
31
32
.
ra.
Specification Outline
Cost Estimate
30,31
33
.
City Review
10 days
Wed 2/26/25Tue 3/11/2530,31,32
1
34
.
Subtask 05-04: Preliminary Design Review Meeting
3 days
Wed 3/12/25 Fri 3/14/25
33
Project LS 12 Project
Date: Thu 7/11/24
♦
1 1
anal
Manual
atemalTaeks
Fmemal
Schedule Task Milestone
it Summary
Project Summary Inactive Milestone
Inactive Task Inactive Summary
enual Task
Summary Rollup Start -only C
Deadline ♦
Menual Progress
11
Duration -only
Summary 11 Finish -only D
Milestone • Progress