HomeMy WebLinkAboutReg 2024-10-07 Item 5B - Update - Public Works Operations Facility Phase 2COUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Mayor's review
Council review
10/7/24
BJM
ITEM INFORMATION
ITEM NO.
5.B.
STAFF SPONSOR: BRANDON MILES
ORIGINAL AGENDA DATE: 10/7/24
AGENDA ITEM TITLE Public Works Phase 2 Update
CATEGORY ® Discussion
Mtg Date 10/7/24
❑ Motion
Mtg Date
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Altg Date
SPONSOR ❑ Council ❑ Mayor ❑ Admin Svcs ❑ DCD ❑ Finance ❑ Fire ❑ P&R ❑ Police ❑ PW
SPONSOR'S
SUMMARY
The project team has completed the design and development phase for pre -construction
and design. The project team will present the the updated construction estimates and also
discuss phasing options for the project.
REVIEWED BY
❑ Trans&Infrastructure Svcs ❑ Community Svcs/Safety ❑ Finance & Governance ❑ Planning & Community Dev.
❑ LTAC
DATE: N/A
❑ Arts Comm.
❑ Parks Comm. ❑ Planning Comm.
COMMITTEE CHAIR: N/A
RECOMMENDATIONS:
SPONSOR/ADMIN. N/A
COMMITTEE N/A
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED
$N/A
AMOUNT BUDGETED
$N/A
APPROPRIATION REQUIRED
$N/A
Fund Source: N/A
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
10/7/24
MTG. DATE
ATTACHMENTS
10/7/24
Powerpoint Presenation
175
176
Tukwila Maintenance and Engineering - East Campus Project
Council Update
October 7, 2024
AGENDA
Reconciled Design Development Phase Cost Estimate
Project Building Blocks
Goal: Council direction on budget (resultant scope to be refined)
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 2
PUBLIC WORKS COMBINED SHOPS, COST TO DATE
Site Acquisition
Year
Cost
Notes
2017
283, 709
Preliminary Design and Faeal Estate Services
2018
13,237,891
Land Purcahse, Business Assistance, and Legal Costs
2019
12,704 012
Land Purcahse, Business Assistance, and Legal Costs
Subtotal:
26,225,612
Phase 1
2020
756, 352
Design and Pre -Construction Phase 1
2021
5,744 843
Construction Phase 1
2022
2,272 488
Construction Phase 1
2023
1, 392,111
Construction Phase 1
a bt of a l :
10,165, 794
Phase 2
2022
185,124
Test to Fit
2023
1,354 449
Design and Pre-Const rucct i on
2024
3,109, 932
Design and Pre-Const rucct i on
Su bt of al :
4,649 505
Total 4)end To Date:
41,040,911
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 3
RECONCILED DESIGN DEVELOPMENT PHASE ESTIMATE
COUNCIL REPORTING SUMMARY -
Tukwila Public Works Maintenance & Engineering Building
Test to Fit Budget
2nd Quarter '23
Schematic Design Budget
1st Quarter '24
Design Development Budget
4th Quarter '24
Architect/Engineering Services (Design & Construction
Adminstration)
$ 6,278,000
$
$
6,215,000
1,930,000
$
4,970,000
Permits/Fees
$ 1,940,000
$
1,154,000
General Contractor/Construction Management
Pre -Construction
$ 360,000
$
360,000
$
400,000
Construction (includes escalation to Jan 2026)
$ 54,513,000
$
55,807,089
6,123,797
$
$
53,491,237
5,933,395
Construction Tax (Pre -Construction, Construction & Construction
Contingency)
$ 6,092,754
$
Construction Related Costs (Owner Consultants, Furniture Fixtures
& Equipment, Insurance)
$ 3,198,000
$
5,155,035
$
4,683,798
Project Management Services (SOJ, Legal, Project Neutral)
$ 2,241,000
$
2,279,000
$
2,100,000
Contingency (including Construction & Project)
$ 9,242,246
$
6,111,257
$
5,434,475
TOTAL
$ 83,865,000
$
83,981,179
$
78,166,905
* The following have been eliminated from the Design Development Budget
- City of Tukwila Building Permit Fee
- City of Tukwila Traffic Impact Fees
- Shoreline Restoration (separate project)
- Truck Wash (removed the scope)
- Off -Site Improvements (separate project)
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 4
ED PARKIN
PUMPSTER PLATFO
TOOL &
EQUIPMENT
STORAGE
COVERED PARKIN
4:1011121- um_
MAINTENANCE
ENGINEERING
BUILDING
;Al
ERALL SITE
IMPROVEMENTS
ROJECT BUILDING BLOCKS
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 5
BASIS OF BUILDING BLOCK ESTIMATING
Cost estimate numbers are based on the current design with the full project construction
starting inJUNE2025.
Additional escalation would need to be applied to construction costs for building block
phasing starting AFTER JUNE 2025.
Building block cost estimates could vary -10% to +20% dependent on phasing schedule.
*These costs are estimated holistically and will vary when phased into single projects.
*Civil design will need to be recalibrated.
What does site work costs include?
*Land clearing, grading, excavation, the installation of infrastructure necessary
for future development, etc.
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 6
PROJECT BUILDING BLOCKS
Tool and Equipment Storage
7,600 SF enclosed warehouse & tools
9,300 SF covered storage & loading
Building ($350/SF)
Site (allocated)*
Construction subtotal
Project Related Costs
Estimated Project Cost
$5,900,000
$4,000,000
$9,900,000
$4,500,000
$14,400,000
Salt/Sand/Gravel Storage
5,500 SF covered
Building ($273/SF)
Site (allocated)*
Construction subtotal
Project Related Costs
Estimated Project Cost
Spoils Storage
6,600 SF covered
Building ($242/SF)
Site (allocated)*
Construction subtotal
Project Related Costs
Estimated Project Cost
$1,500,000
$ 800,000
$2,300,000
$1,100,000
$3,400,000
$1,600,000
$1,200,000
$2,800,000
1,300,000
$4,100,000
03
Site costs have been allocated to buildings
°an percent basis for analysis purposes
TOOL &
EQUIPMENT
STORAGE
4011
SPOILS
STORAGE.
Building and
Site Area
Esti mated
Project Cost
Tool &
Equipment
Storage
Salt, Sand,
Gravel Storage
Spoils Storage
$14,400,000
$3,400,000
$4,100,000
Running Total
$21,900,000
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 7
PROJECT BUILDING BLOCKS
Decant Facility
5,900 SF covered
Building ($271/SF)
Site (allocated)*
Construction subtotal
Project Related Costs
Estimated Project Cost
$1,600,000
$ 900,000
$2,500,000
$1,100,000
$ 3,600,000
*Site costs have been allocated to buildings
on percent basis for analysis purposes
SALT
SAND
GRAVEL
1/4114
TOOL &
EQUIPMENT
STORAGE
SPOILS
STOR G
Building and
Site Area
Esti mated
Project Cost
Tool &
Equipment
Storage
Salt, Sand,
Gravel Storage
Spoils Storage
Decant Facility
$14,400,000
$3,400,000
$4,100,000
$3,600,000
Running Total
$25,500,000
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 8
PROJECT BUILDING BLOCKS
Maintenance & Engineering
Building
35,500 SF, 3-story, Admin + Shops
3,000 SF, outdoor covered areas
Building ($648/SF) $23,000,000
Site (allocated)* $4,700,000
Construction subtotal $27,700,000
Project Related Costs $12,800,000
Estimated Project Cost $40,500,000
03
Site costs have been allocated to buildings
n percent basis for analysis purposes
TOOL &
EQUIPMENT
STORAGE
•
Building and
Site Area
Esti mated
Project Cost
Tool &
Equipment
Storage
Salt, Sand,
Gravel Storage
Spoils Storage
Decant Facility
Dumpster
Platform
$14,400,000
$3,400,000
$4,100,000
$3,600,000
$3,300,000
Running Total
$28,800,000
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 9
PROJECT BUILDING BLOCKS
Dumpster Platform
9000 SF covered
Building ($133/SF)
Site (allocated)*
Construction subtotal
Project Related Costs
Estimated Project Cost
$1,200,000
$1,000,000
$2,200,000
$1,100,000
$3,300,000
*Site costs have been allocated to buildings
on percent basis for analysis purposes
DECANT FACILITY
TOOL &
EQUIPMENT
STORAGE
Building and
Site Area
Esti mated
Project Cost
Tool &
Equipment
Storage
Salt, Sand,
Gravel Storage
Spoils Storage
Decant Facility
Dumpster
Platform
Maintenance
& Engineering
Building
$14,400,000
$3,400,000
$4,100,000
$3,600,000
$3,300,000
$40,500,000
Running Total
$69,300,000
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 10
PROJECT BUILDING BLOCKS
WEST CAM':._
t-:
IMPROVEMEN
West Campus Improvements
2,950 SF covered
Covered Parking
Site (West)
Construction subtotal
groject Related Costs
estimated Project Cost
$ 700,000
$ 3,000,000
$3,700,000
$1,700,000
$ 5,400,000
SALT
SAND
GRAVEL
DUMPSTER PLATFO
TOOL &
EQUIPMENT
STORAGE
Covered Parking (East)
10,100 SF covered
Building ($130/SF)
Site (allocated)*
Construction subtotal
Project Related Costs
Estimated Project Cost
$1,300,000
$1,100,000
$ 2,400,000
$1,100,000
$3,500,000
DECANT FACILITY
Site costs have been
allocated to buildings
on percent basis for
analysis purposes
Building and
Site Area
Esti mated
Project Cost
Tool &
Equipment
Storage
Salt, Sand,
Gravel Storage
Spoils Storage
Decant Facility
Dumpster
Platform
Maintenance
& Engineering
Building
Covered Parking
West Campus
Improvements
$14,400,000
$3,400,000
$4,100,000
$3,600,000
$3,300,000
$40,500,000
$3,500,000
$5,400,000
Running Total
$78,200,000
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 11
ROJECT BUILDING BLOCKS
SALT
SAND
GRAVEL
SROREONE-
R_ESTORATIO
Pk
TOOL &
EQUIPMENT
STORAGE
DECANT FACILITY
Building and
Site Area
Esti mated
Project Cost
Tool &
Equipment
Storage
Salt, Sand,
Gravel Storage
Spoils Storage
Decant Facility
Dumpster
Platform
Maintenance
& Engineering
Building
Covered Parking
West Campus
Improvements
$14,400,000
$3,400,000
$4,100,000
$3,600,000
$3,300,000
$40,500,000
$3,500,000
$5,400,000
Running Total
Shoreline
Restoration
$78,200,000
(separate project)
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 12
Building and
Site Area
Esti mated
Project Cost
Tool &
Equipment
Storage
Salt, Sand,
Gravel Storage
Spoils Storage
Decant Facility
Dumpster
Platform
Maintenance
& Engineering
Building
Covered Parking
West Campus
Improvements
$14,400,000
$3,400,000
$4,100,000
$3,600,000
$3,300,000
$40,500,000
$3,500,000
$5,400,000
Running Total
Shoreline
Restoration
$78,200,000
(separate project)
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 13
GRANT UPDATE
Element
Grant Name
Potential Amount
Status
Anticipated Award Date?
Shoreline Design
WRIA 9 — Salmon
Recovery Funding Board
(RCO) or Flood Control
District (CWM/FR)
$2 Million
Will apply in Spring 2026
Fall of 2026
Decant Construction
Department of Ecology
Water Quality Combined
$4 Million
Will apply in Fall 2025
July of 2026
Shops Generator
(Phase 2)
FEMA Hazard Mitigation
$1 Million
Invited to submit full
application, due October
25.
Summer of 2025.
Tool Building
(Phase 2)
FEMA BRIC
$10 Million
Submitted preapplication,
waiting on state to respond
if we can submit a full
application.
Summer of 2025
Various Project Elements
Congressional Direct
Spending
TBD, likely less than
$1 Million
TBD
TBD
Various Project Elements
Department of
Commerce Clean Energy
Grant Program
$2 Million
Will know after 2025
legislative session if this
program is returning.
TBD
Various Project Elements
King County/EPA Climate
Pollution Reduction
Grant
$3-$5 Million
King County is developing
the sub -application process
now. Will apply once open.
TBD
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 14
PROJECT SCHEDULE
JAN
2023
SCHEMATIC
DESIGN
GCCM
Procurement
JAN
2024
Nov 2023
City ownershi
of UPS parcel
DESIGN
DEVELOPMENT
JAN JAN JAN
2025 2026 2027
CONSTRUCTION
DOCUMENTS
ENVIRONMENTAL REVIEW AND PERMITTING
April 2025
UPS Lease Expires
REPORTTO COUNCIL REPORTTO COUNCIL REPORTTO COUNCIL
March 2023 April 2024 October 2024
• STATE ENVIRONMENTAL POLICY ACT (SEPA) CHECKLIST SUBMITTED ON 5/2/2024
• RECEIVED SEPA DETERMINATION OF NON -SIGNIFICANCE (DNS) ISSUED ON 9/25/2024
• BUILDING PERMIT TARGET: FEBRUARY2025
CONSTRUCTION
REPORT TO COUNCIL
(Target: August 2025)
MOVE
IN
January
2027
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects 15
CD
N
EXISTING SITE FOR REFERENCE
S 11 2th St
West Parcel
Lot Size
3.95 acres
Chinook Wind Mitigation Project
(King County)
SCL Easement (permanent access)
East Parcel
Lot Size
6.9 acres
Duwamish Gardens Park
(City Owned)
Duwamish River
Tukwila Maintenance & Engineering
East Campus Project
October 7, 2024
Miller Hayashi Architects
16