HomeMy WebLinkAboutWS 2024-11-04 Item 3A - Document - 2025-2030 Capital Improvement ProgramCity of Tukwila Capital Improvement Program 2025-2030 MIll City of Tukwila, Washington Page 1 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM City of Tukwila Capital Improvement Program Overview INTRODUCTION Providing infrastructure is a primary function of a local government. Maintaining public safety, city services, parks and recreation facilities, and the community's quality of life are heavily dependent on how the City plans for future infrastructure needs. The Capital Improvement Program (CIP) is a comprehensive multi -year plan of proposed capital projects that will support the continued growth and development of the City. It represents the City's plan for physical development and it intended to identify, and balance the needs, within the financial capabilities and limitations of the City. The plan is reviewed and updated every two years to reflect changing priorities and provides an ongoing framework for identifying capital needs, scheduling projects over a period of time, coordinating related projects, and identifying future fiscal impacts. The Capital Improvement Program: • Is characterized by a six -year plan document • Is a funding plan, rather than a spending plan • Denotes funding sources that are being planned for projects, based on preliminary, rough order of magnitude cost estimates. A large portion of the CIP focuses on the much -needed work to maintain and renew existing infrastructure and amenities around Tukwila to keep them in safe and serviceable condition. The remainder of the capital program is investments in new and expanded infrastructure and amenities to serve a changing population and growing economy. Generally, the CIP includes projects that are relatively expensive, have a multi -year useful life, and result in capital assets. These include the additions to or renovations of existing streets, buildings, parks and trails, technology, infrastructure for utilities, and land purchases. However, the CIP can also include projects that do not result in a capital asset upon completion but are associated with significant maintenance and repair of existing capital assets. An example of this would be street overlay, in which the City typically expends in excess of $1 million annually on overlay projects but does not result in a new capital asset or an improvement to an existing capital asset. Due to the nature and total costs of the projects identified in the CIP, the City will most often fund these projects with dedicated revenue sources including grants, impact fees, bond proceeds, and taxes externally restricted to certain types of projects. In some limited circumstances and when there are insufficient dedicated revenue sources, projects may be funded with general fund dollars. The CIP process is intended to identify the funding sources available for projects prioritized in the next six years. The first two years of the CIP is the basis for actual appropriations authorized by the City Council for projects when adopting the biennial budget. The remaining four years are a guide for future funding requirements to complete current projects as well as a guide for future planned projects. The projects reflected in the out years (years four through six) reflect projects the City believes is has the financial ability to fund within that time frame. The out years of the plan reflect projects that are important to the community, however, if funding capabilities are not realized, then the projects will necessarily be pushed further out. City of Tukwila, Washington Page 2 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM The overall CIP schedule is formulated to reflect the City's priorities and needs, by taking into consideration the City's goals and policies, various master and strategic plans, the urgency of a project, the potential for future project funding, and ongoing operational requirements. The CIP is a dynamic process, with anticipated projects being changed, added, and deleted from the plan as the six - year timeline moves forward. The purpose of the CIP is to systematically identify, plan, schedule, finance, track, and monitor capital projects. Most capital projects are included in the CIP, rather than the operating budget, except for equipment purchases for the general fund. The objectives used to develop the CIP include the following: • Preserve and improve basic infrastructure of the City through construction and rehabilitation. • Maximize the useful life of capital investments by scheduling renovations and modifications at the appropriate time in the life cycle of the asset. • Identify and examine current and future infrastructure needs and establish priorities among projects so that available resources are used to the community's best advantage. • Improve the financial planning by comparing needs with resources, estimating future needs, and identifying future implications. Major changes in the development of the 2025-26 CIP include: • Consolidated Operating and Capital Budget: The CIP has previously been adopted by resolution separate from but aligned with the biennial budget. A separate document, Financial Planning Model and Capital Improvement Program, was produced providing a summary of capital projects along with detailed project sheets organized by project type. The 2025-26 Biennial Budget reflects a consolidation of the CIP and the Operating Budget into a single streamlined document. The previous documents unnecessarily duplicated much of the same information. This consolidation supports improved long-term financial planning, as both operating and capital costs are now viewed together, providing a clearer picture of the City's overall fiscal health and priorities. The core elements of the CIP—such as expenditure and revenue projections, policy context, detailed project narratives, and summary analysis —remain, ensuring that all critical information is still easily accessible. • Dissolving Select Fund Structures and Transferring Funds: Fund 302 Urban Renewal Fund is recommended to be dissolved. The projected year-end fund balance of $1,917,220 will be transferred to the City's General Fund. Upon adoption of the 2025-26 operating and capital budget ordinance, the City Council accepts the Six Year Capital Improvement Program, representing the City's commitment to the plan but does not in itself authorize expenditures except as noted in City policy. For capital projects in the approved CIP, the Mayor may approve contracts up to $99,000. For projects in excess of this amount and all other purchases above $60,000 requires City Council approval. City of Tukwila, Washington Page 3 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM POLICY FRAMEWORK The CIP is informed by a series of independent but coordinated planning documents and policies (see Appendix X), including: • Resolution 2096- Financial Policies • Resolution 2097- Procurement Policies • Resolution 1840- City of Tukwila Debt Policy • Resolution 2099- Transportation Improvement Plan (TIP) • City of Tukwila Comprehensive Plan (2024-2030) • City of Tukwila Comprehensive Water Plan- 2015 (update slated for adoption Q4 2024) • City of Tukwila Surface Water Comprehensive Plan- 2024 Update • City of Tukwila Comprehensive Sanitary Sewer Plan -2013 (update slated for adoption Q4 2024) • City of Tukwila Parks, Recreation and Open Space (PROS) Plan- 2020 (to be updated in 2025-26) • Resolution 1906- Green Tukwila 20 Year Stewardship Plan (2017) • Strategic Arts Plan (2024) • Economic Development Strategy (2023) • ADATransition Plan (2017) • City Strategic Plan (2012) • Urban Tree Canopy Assessment (2012) • Facilities Needs Assessment and Feasibility Study City of Tukwila, Washington Page 4 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT FINANCING STRATEGY Consistent with established financial and debt service policies, CIP funding for the next two years relies on existing, available fund balances and projected revenues from Real Estate Excise Tax (REET), Impact Fees, Utility Rates, bond proceeds, state and federal grants, loans and other sources. These revenues are usually dedicated to capital purposes and are not available to support operating costs. Most revenues for capital projects come with restrictions. Utility rates may only be used for projects of the respective utility; REET 1 and 2 is reserved for capital projects to help develop a community's public infrastructure (e.g., parks, open space, and streets). The City's capital financing strategy has been to use these restricted revenues on a "pay as you go" basis for needed improvements. While City Financial Policies discourage reliance on General Fund support for funding of capital projects, General Fund project transfers are made to support certain capital and governmental projects. The contribution required is based on the financial status of the project fund (such as the Arterial Street Fund, the Land/Parks Acquisition Fund, etc.), the amount of dedicated revenues received into the fund, the amount of specific funding sources such as grants and the amount of the existing fund balance. City of Tukwila, Washington Page 5 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM The following table provides an overview of the CIP financing strategy: REET 1 REET 2 Capital Improvement Program Financing General Purpose Revenues Utilities Impact Fees Grants Purpose Planning, acquisition, construction, reconstruction, repair, replacement, rehabilitation, improvement Planning, acquisition, construction, reconstruction, repair, replacement, rehabilitation, or improvement of Varies Operating, managing, maintaining, erecting, acquiring One-time charges assessed by a local government against a new development project to help pay for new or expanded public facilities that will directly address the increased demand for services created by that development. Varies Eligible Streets; roads; highways; sidewalks; street and road lighting systems; traffic signals; bridges; domestic water systems; storm and sanitary sewer systems; parks; Streets, roads, highways, sidewalks, street and road lighting systems, traffic signals, Water- waterworks, • Public streets and roads • Publicly owned parks, open Non -repayable funds sometimes requiringa local storing/retaining water, erecting aqueducts, pipe lines, dams or waterworks, protection ofwatersuppyfrom pollution, etc. Sewer - related to sanitary or combination of Activities/Projects recreational facilities; law enforcement facilities; fire protection facilities; trails; libraries; administrative facilities; judicial facilities; river flood control projects; waterway flood control projects bridges, domestic water systems, storm and sanitary sewer systems Flexible purposes sewers, pumping stations, disposal plants, water mains, hydrants, reservoirs or appertenances• Stormwater- space, and recreation facilities • School facilities • Fire protection facilities match (money; in -kind services; materials; equipment; labor, etc.) water supply, water quality, water resource and habitat protection & management Parks Bridges&Streets Equipment Sanitary Sewer Parks Parks Construction Construction Vehicle Replacement Construction System improvements Construction Maintenance Maintenance Maintenance Maintenance Technology Fire Open Space Computers Storm Water System improvements Open Space Property Acquisition Software Construction Property Acquisition Planning Communications Maintenance Planning Improvements Improvements Bridges&Streets Water Transportation Public Buildings Construction Construction System improvements Public Buildings Repair Maintenance Maintenance Repair Maintenance Maintenance Planning & Design Planning & Design Tukwila Financing Strategy Streets Construction Maintenance Sanitary Sewer Construction Maintenance Storm Water Construction Maintenance Water Construction Maintenance City of Tukwila, Washington Page 6 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Capital Improvement Program by Fund Capital Improvement Program by Fund Fiscal Year 2025-2026 $ in thousands Total: $78.9 MILLION Water, $6,400 , 8% Surface Water, $19,874 , 25% Special Projects, $1,100 ,1% Sewer, $11,925 , 15% Arterial Streets , $15,480 , 20% viaCity Facilities $3,526 , 4% General Fund , $838 , 10/0 Golf Course , $1,430 , 2% New Facilities, $1,825 , 2% Parks & Trails , $10,374 ,13% Residential Streets, $6,853 , 9% Capital Outlay in the Operating Budget In addition to the CIP, the City funds an equipment replacement internal service fund for vehicles owned and operated by the City. Funds and departments that utilize the equipment transfer funds to the internal service fund to purchase and replacement of the vehicles. The City also funds equipment for general fund departments out of general fund tax dollars. Capital outlay in the general fund includes technology, exercise equipment, and department specific equipment. Impact on the Operating Budget The City's operating budget is directly affected by the CIP. When certain types of capital projects are developed and completed, they also have ongoing financial impacts. For example, if the City were to construct a new park, the operating budget would either increase to accommodate additional staffing and supplies or existing staffing and supplies would remain at the same level but be required to be spread across more parks. City of Tukwila, Washington Page 7 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Project Accounting Capital Improvement Projects are categorized within the following Funds and adopted on a multi -year basis: Government Funds • Fund 000 Special Projects: New to the 2025-2030 CIP, this includes projects that don't meet traditional definition of a single fund. In the 2025-26 biennium, Special Projects will support World Cup preparations as well as Tukwila's first -ever People's Project, a participatory budgeting initiative that allows residents to have a direct say in a capital improvement for their community. • Fund 103 Residential Streets: Established in accordance with RCW 35A.37.010 to account for maintenance and improvement of the City's residential streets. Major sources of support are the State - levied tax on motor vehicle fuels distributed to Tukwila to be used for City street purposes, state and federal grants, and transfers in from the General Fund. • Fund 104 Bridges and Arterial Streets: was established in accordance with RCW 82.36.020 for the administration of the State -levied motor vehicle half -cent gasoline tax distributed to Tukwila and is used primarily to account for capital arterial street projects. In addition to the State -levied motor vehicle gasoline tax, other revenue includes state and federal grants, impact fees, and transfers in from the general fund. • Fund 301 Land Acquisition, Recreation, and Park Development: Accounts for the acquisition of land, development of land, and construction of park facilities. • Fund 302 Urban Renewal: Established in 1988, this fund accounts for costs associated with property owned by the City that will be utilized for redevelopment or renewal purposes. This fund will be dissolved and its fund balance transferred to the General Fund. • Fund 303 City Facilities: This fund was established in 1992 to provide funding for minor capital improvements not related to parks, land acquisition, or major building replacements. • Fund 304 Fire Improvements: This fund is to be used for the acquisition of land, development of land and construction of fire facilities. Revenue for this fund comes primarily from fire impact fees. • Fund 305 Public Safety: The Public Safety Plan fund was established in 2016 after voters approved a $77.4 million bond measure to construct a justice center, rebuild 3 fire stations, and provide for life -cycle replacement of fire department apparatus and equipment. • Fund 306 New Facilities: was established in 2016 to account for costs of building a new Public Works Shop facility. The public works shop facility is part of the City's public safety plan but is not included in the voter - approved bonds. The City issued bonds in 2021 for the general fund portion of the phase 1 improvements associated with the Public Works Shop project. The Tukwila Parks and Recreation Department is currently in discussions with a local non-profit concerning the construction, staffing, and potential programmatic offerings to be provided by a future proposed mixed -used health center and recreational facility. Proprietary Funds • Fund 401 Water Utility Fund accounts for operations and capital improvements to provide water services to the City. • Fund 402 Sewer Utility Fund accounts for operations and capital improvements to provide sanitary sewer services to the City. • Fund 412 Surface Water Utility Fund accounts for the operations and capital improvements for the City's storm drainage and surface water management function • Fund 411 Foster Golf Course Fund is used to account for the operation, maintenance, and improvements of the municipal golf course facility and its associated equipment. City of Tukwila, Washington Page 8 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM The 2025-30 CIP provides an implementation schedule for each of the projects that provides for: • Coordination and timing of project construction/acquisition among other competing needs • Estimate of each project's costs • Estimated timeline for completing of the project • Anticipated sources of revenue for financing the project • Estimate of the impact on each project on ongoing operating expenditures, where possible Operating impact information has been forecasted, where possible, from the scheduled completion date of the project. The CIP attempts to meet the highest priority needs of the community. It will be continually evaluated in the future to ensure that it is consistent with the priorities of the City Council, with financial policies, and the available resources of the City. The major items in the CIP are categorized by type of project, then itemized by project title, year, and cost on the summary sheets of the CIP document. The project detail sheets for individual projects anticipated within the next six years of the program follow the summary sheets.. The types of projects included in the CIP are categorized and associated with a designated Fund that groups similar projects for tracking revenues and expenditures: The total CIP budget for the six -year CIP is as follows: Summary of Capital Improvement Program Projects in the 2025-2030 CIP Project Type (costs in thousands) 2025 2026 2027 2028 2029 2030 Total Arterial Streets $6,660 $9,359 $49,360 $21,273 $6,550 $6,610 $99,812 City Facilities Golf Course $2,981 $575 $1,375 $774 $290 $155 $6,150 $615 $820 $3,739 $345 $351 $357 $6,227 New Facilities $1,075 $900 $0 $0 $0 $0 $1,825 Parks & Trails $4,137 $6,494 $6,947 $7,171 $3,237 $2,746 $30,732 Residential Streets $1,239 $6,305 $5,143 $770 $3,885 $765 $18,107 Sewer $6,770 $5,265 $5,665 $3,170 $3,265 $3,565 $27,700 Special Projects $305 $805 $55 $55 $55 $55 $1,330 Surface Water $10,473 $10,601 $18,670 $9,848 $5,523 $9,253 $64,368 Water $3,750 $2,865 $1,780 $5,300 $13,610 $14,225 $41,530 Grand Total $38,005 $43,989 $92,734 $48,706 $36,766 $37,731 $297,931 City of Tukwila, Washington Page 9 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CAPITAL PROJECT HIGHLIGHTS Below are the significant new elements of the 2025-2030 Capital Improvement Program. Residential Streets Residential street improvements in the 2025- 2026 CIP include several key projects aimed at enhancing pedestrian and cyclist safety, as well as general street improvements. Notable projects include the South 152nd Street Pedestrian and Bike Improvements, which focus on creating a safer route for students walking to nearby schools, and the 46th Avenue South Safe Routes to School Project, which will enhance safety for students. Additionally, the City remains committed to ongoing neighborhood traffic calming efforts through the Traffic Calming/Residential Safety Improvements Program, maintaining funding levels following the loss of ARPA funding. Bridges The 42nd Avenue South Bridge Replacement, the bridge next to the Tukwila Community Center, will be a major focus in the next biennium. The project has been delayed but will begin construction in early 2027. Arterial Streets The 2025-2026 CIP includes significant improvements to Tukwila's arterial streets, with a focus on enhancing safety, accessibility, and infrastructure resilience. A key highlight is that the City has secured grant funding for three major overlay projects: Boeing Access Road Overlay, Orillia Road South Overlay, and Interurban Avenue South Overlay. These overlays will ensure that these critical roadways remain in good condition and are able to support increased traffic volumes, with minimal impact on local funds. In addition to these grant -funded projects, the South Ryan Way improvements will provide vital upgrades to one of Tukwila's busiest corridors, while the Southcenter Boulevard/65th Avenue South Signal project will enhance traffic flow and safety at a key intersection. The Annual Overlay and Repair Program will continue to maintain the overall integrity of arterial streets, focusing on resurfacing and repairing roadways before significant deterioration occurs. By leveraging state and federal grants, the City is able to pursue these critical improvements with substantial external funding support, maximizing the value of local dollars. CIP Projects by Biennial Expenses (2025-2026) Bouievartl Par White Cen INO.Fry Re. Rtignis 5 0e X,, pe • A e'4• e•eew !• Pult 1 Fame, Leans • Searec r,. CLIFfIKS CIP projects by Biennial Expenses • '- $3003 • S6903'S65M • $1.5M-$3.131 . SS.4M-W1 Ranier Beeen Ae ere, v,.w •. • Tukwila • • • • Bryn Mawr buzu rawer tK E ailin0OnXrll RY: e- lncv, City of Tukwila, Washington Page 10 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Parks & Recreation The 2025-2030 Capital Improvement Program for the City of Tukwila Parks system will include both long-term strategic planning and physical asset investment. A new Parks, Recreation, and Open Space (PROS) Plan will be finalized by Q1 of 2026. Additionally, the 2025-2030 CIP includes the execution of Master Plan projects for the Tukwila Community Center, S 116`h Street Parcel, Joseph Foster Memorial Park, and Crestview Park. Improvements and repairs are also planned at Riverton and Crystal Springs Parks, including playground replacements. Parks and Recreation staff continue to research and seek funding sources to support execution of these projects. Facilities The 2025-2026 CIP includes key upgrades to City facilities and significant Public Works projects that are essential to Tukwila's infrastructure and community services. However, funding for these facilities has historically been limited, and some major projects currently do not have secure funding moving forward. For City Facilities (Fund 303), essential projects such as the Tukwila Community Center (TCC) HVAC Replacement Phase 2 will improve energy efficiency and enhance the overall functionality of the building. The City Facilities Furnishings, Fixtures, and Electrical Enhancements project will ensure that city buildings are equipped with modern, functionalfurnishings and equipment. Additionally, the City Hall Roof Replacement and Pedestrian Bridges Maintenance are critical for maintaining the safety and longevity of city assets. In Fund 306, two significant projects face challenges due to the lack of established funding moving forward. The first is the Intergenerational Teen and Senior Center, a facility aimed at providing recreational and community space for both teens and seniors, fostering engagement across generations. While this project remains a priority for the City, securing future funding will be essential to its progress. Similarly, the Public Works Consolidated Shops project is part of a long-term effort to modernize public safety and operations facilities. This project will streamline operations for Tukwila's engineering, utility, and street services, but like the Teen and Senior Center, it currently lacks a funding plan for its next phases for which new debt service would need to be issued. These projects are critical to Tukwila's future, but the limited availability of funds for facility improvements continues to present challenges. The City will need to explore alternative and additional funding sources and partnerships to advance these projects in the coming years. Water The capital component of the Water Enterprise Fund focuses on critical infrastructure improvements needed to support the City's water distribution system. The key project in the 2025-2026 biennium is the Tukwila Water Reservoir, which is vital for ensuring the City has sufficient water storage capacity to meet current and future demand. This project is also necessary to maintain water pressure and supply in the event of system disruptions or emergencies. In addition to the reservoir, the Fund supports ongoing infrastructure enhancements such as water main replacements and improvements to ensure the system's reliability and longevity. These projects are essential for meeting the City's growth targets and maintaining compliance with water quality standards. The City's strategy includes phased capital investments to avoid system failures and reduce the need for costly emergency repairs. Sewer City of Tukwila, Washington Page 11 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM The Sewer Enterprise Fund capital component for 2025-2026 includes critical projects such as the Sewer Lift Station 12 Retrofit, the Sewer Lift Station 5 Rebuild, and the Southcenter Blvd Sewer, to increase capacity and system reliability. The Annual Sewer Repair Program will address ongoing maintenance and system improvements, while the Ryan Hill Sewer Revitalization focuses on upgrading failing septic systems. These projects ensure the City's sewer infrastructure meets current and future demands. Surface Water The Surface Water Enterprise Fund supports the City's stormwater management efforts, ensuring compliance with federal, state, and local regulations such as the National Pollution Discharge Elimination System (NPDES) permit. The 2025-2026 CIP focuses on several critical drainage and water quality projects, including the S 131st Place Drainage Improvements, the Gilliam Creek Fish Barrier Removal and Habitat Enhancement, and the Chinook Wind Extension. These projects aim to improve stormwater management, reduce flooding, and enhance the ecological health of Tukwila's water bodies. NOTES TO ENTERPRISE FUNDS The City of Tukwila's Enterprise Funds account for utility and service operations that are self -sustained through user charges, operating similarly to private businesses. These funds include the Water, Sewer, Surface Water, and Golf Funds, each responsible for financing its operations, capital improvements, maintenance, and debt service obligations. The following notes provide detailed information regarding the rate structures, major capital projects, debt service schedules, and operational updates for the 2025-2030 period. These notes also cover reserve fund policies and interfund utility taxes that impact the financial performance of each fund. Rates are regularly reviewed to ensure they support ongoing operations and necessary capital improvements while adhering to Federal, State, and local regulations. Throughout 2023 and 2024, FCS Group conducted a comprehensive utility rate study to ensure the fiscal sustainability of the enterprise funds. The reflected rate increases in the 2025-2030 CIP are a result of this study. However, it is important to note that these increases do not account for the additional revenue requirements needed to fund debt service associated with Public Works Shops Phase II. Should that project move forward, rates would need to be further adjusted to meet the corresponding financial obligations. Key Highlights: Water Enterprise Fund: Significant rate increases (9% annually from 2025-2029 and 5% in 2030) are planned to maintain reserves, fund key infrastructure projects (e.g., the construction of a new water reservoir), and cover potential cost increases from the Cascade Water Alliance (CWA). Additionally, the fund's debt service obligations include Public Works Trust Fund loans and bonds related to past infrastructure projects. Sewer Enterprise Fund: The Sewer Fund is impacted by both Tukwila's sewer rate adjustments and King County Metro sewer fees, which are passed directly to ratepayers. Capital projects such as the Sewer Lift Station 12 Retrofit and the Ryan Hill Sewer Revitalization are critical components of the 2025-2026 CIP. This fund also manages debt service obligations, including loans and bonds from previous infrastructure projects. Additionally, sewer connection fees are being collected for major projects like those in the Allentown/Foster Point area. Surface Water Enterprise Fund: Surface water management is a primary focus of this fund, driven by the need for compliance with the National Pollutant Discharge Elimination System (NPDES) permit. Capital improvements for drainage and water quality, such as the S 131 st Place Drainage Improvements and the Gilliam Creek Fish Barrier Removal, are key elements of City of Tukwila, Washington Page 12 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM the 2025-2026 capital plan. The fund also leverages grant funding from agencies like the Department of Ecoogy and the King County Flood Control District to supplement ratepayer contributions. Golf Enterprise Fund: Supported by green fees, merchandise sales, and contributions from the General Fund, the Golf Fund aims to operate on a break-even basis. While other enterprise funds serve essential utility services, the Golf Fund operates differently, relying on voluntary users. The fund's capital investments are focused on maintaining and enhancing the municipal golf facility, including debt service for prior improvements. City of Tukwila, Washington Page 13 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Revenues Monthly Water Charges Rate Increases Cascade Water Alliance Regular City Water Subtotal Water Other Miscellaneous Revenue Interlocal Ags\PWTF\Grants/Bonds Water Connection Fees (2) Actuals 2023 $ 2,781,245 5,039,013 WATER ENTERPRISE 2025-2030 Forecast Bud.et Bud.et 2024 2025 9.00% $ 2,768,293 $ 2,897,608 5,620,430 6,322,248 FUND Forecast Forecast Forecast 2028 9.00% $ 3,211,000 9,029,778 Forecast 2029 9.00% $ 3,323,385 10,130,178 Forecast 5.00% $ 3,439,703 10,804,181 2026 9.00% $ 2,972,958 7,160,378 2027 9.00% $ 3,141,000 7,996,321 $ 7,820,258 $ 231,922 - 25,654 $ 8,388,723 $ 216,545 - 20,000 $ 9,219,856 $ 192,813 2,000,000 20,000 $ 10,133,336 $ 129,877 - 20,000 $ 11,137,321 $ 90,074 3,500,000 20,000 $ 12,240,778 $ 164,879 500,000 20,000 $ 13,453,563 $ 100,694 30,125,000 20,000 $ 14,243,884 $ 398,058 1,125,000 20,000 Total Revenues $ 8,077,834 $ 8,625,268 $ 11,432,669 $ 10,283,213 $ 14,747,395 $ 12,925,657 $ 43,699,257 $ 15,786,942 Expenses 2023 2024 2025 iF%r 20. 2029 s • CWA Purchased Water $ 2,781,245 $ 2,768,293 $ 2,897,608 $ 2,972,958 $ 3,141,000 $ 3,211,000 $ 3,323,385 $ 3,439,703 Water Operations & Maintenance 2,394,727 2,843,187 3,440,694 3,903,260 4,096,479 4,301,373 4,518,796 4,722,383 Debt Service 127,820 127,677 215,172 215,198 463,046 463,046 2,904,564 2,904,564 Debt Service/Costs for PW Shops 618,363 711,646 358,050 323,621 323,795 323,484 323,676 324,253 Interfund Utility Tax 10% 782,026 838,872 921,986 1,013,334 1,113,732 1,224,078 1,345,356 1,424,388 Engineering Labor 587,949 - - - - - - - Subtotal $ 7,292,131 $ 7,289,675 $ 7,833,510 $ 8,428,371 $ 9,138,053 $ 9,522,981 $ 12,415,777 $ 12,815,293 Water Capital - CIP Program $ 1,579,000 $ 729,040 $ 4,130,187 $ 2,996,032 $ 1,878,523 $ 6,621,399 $ 16,424,814 $ 17,904,264 Total Ex.enditures $ 8,871,131 $ 8,018,715 $ 11,963,696 $ 11,424,403 $ 11,016,576 $ 16,144,381 $ 28,840,591 $ 30,719,557 Fund Balances 1 2025 ZUZ6 2027 2028 2029 - 2030 Change in Fund Balance $ (793,297) $ 606,553 $ (531,027) $ (1,141,190) $ 3,730,820 $ (3,218,724) $ 14,858,666 $ (14,932,615) Beginning Fund Balance 5,170,176 4,441,675 5,048,228 4,517,200 3,376,011 7,106,831 3,888,107 18,746,772 Ending Fund Balance $ 4,376,878 $ 5,048,228 $ 4,517,200 $ 3,376,011 $ 7,106,831 $ 3,888,107 $ 18,746,772 $ 3,814,157 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 9.00% eee City of Tukwila Water Enterprise Fund 2025-2030 Forecast 9.00% ▪ um Nos II. NMI 9.00% ass 9.00% 9.00% moo 5.00% ENO 2024 2025 2026 2027 2028 2029 2030 - Cash Operating Expenses Phase 2 of PW Project Existing Debt Service New Debt Service - Additions to Operating Fund Balance Rate Funded Capital -Total Revenues - Total Revenues with Rate Increases City of Tukwila, Washington Page 14 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM NOTES TO WATER ENTERPRISE FUND 1) Rates reflect increases of 9% 2025-2029 and 5% in 2030. These rate increases are essential to sustain our reserve balance, site and construct a new water reservoir, which is required for the City to meet growth targets and cover any possible increases from Cascade Water Alliance (CWA). The City will continue to review the annual rate model to confirm that the proposed increases are necessary. Future water purchased at additional costs will be passed on to ratepayers. The City has identified Cascade Water Alliance's revenues and expenditures to better reflect the actual water charges and the respective increases. 2) Connection fees are estimated for the Allentown/Foster Point and Duwamish projects. 3) Cascade Water Alliance is split out to identify the actual costs of purchased water. CWA has scheduled increases in their six -year planning model that will affect our water rates. 4) Debt schedule includes Public Works Trust Fund (PWTF) loans and Bonds. Public Works debt service could increase with Phase II. Water Debt Service includes: Expires 2025 2026 2006 Bond Allentown (26%) 12/31/26 46,791.70 46,817.75 Subtotal $ 46,791.70 $ 46,817.75 2018 Public Works Shops (17%) 12/31/38 260,814.00 260,431.50 2019 Public Works Shops (17%) 12/31/39 97,235.92 63,189.17 Total $404, 841.62 $370,438.42 5) An Interfund Utility Tax was approved in October 2009 for the water, sewer, and surface water utilities. Gross revenues are currently taxed 10% through December 31, 2027. 6) The Working Capital Reserve Fund's policy was updated in 2012 per Resolution No. 1774 to maintain an adequate fund balance in each of the enterprise funds. For the Enterprise Funds, the unrestricted fund balance shall equal or exceed 20% of the previous year's revenue, exclusive of significant non -operating, non -recurring revenues. FCS Group is proposing new operating reserve requirements in line with best practices. 7) The Senior Water/Sewer Engineer's salary and benefits are split evenly between the water department and the sewer department. For 2025 and 2026, Technology staff will continue to charge at 22% for the GIS Coordinator and 10% for the Information Systems Project Analyst. Water Enterprise Fund The City's Enterprise Funds account for utility operations that are self -supported through user charges. The utilities are financed and operated like a private business enterprise which requires periodic determination of revenues earned; expenses incurred, and net income for capital maintenance, public policy, management control and accountability. The Water Fund accounts for operations and capital improvements to provide water to a portion of City residents. King County Water District 125 and Highline Water District also supply water to City residents. City of Tukwila, Washington Page 15 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Actuals SEWER ENTERPRISE FUND 2025-2030 Forecast Budget Pro-ected Pro'ected Pro eeted Pro ected Pm'ected Pro'ected Revenues 2023 2024 2025 2026 2027 2028 2029 2030 Rate Increase (Regular City) 3.00% 3.00% 3.00% 3.00% 3.00% 3.00% King County wastewater $ 4,458,822 $ 5,830,000 $ 6,165,225 $ 6,519,725 $ 6,943,507 $ 7,394,835 $ 7,875,499 $ 8,426,784 Regular City Sewer 5,283,844 5,499,713 5,711,880 5,932,232 6,161,084 6,398,765 6,645,615 6,901,988 Subtotal Sewer Revenue $ 9,742,666 $ 11,329,713 $ 11,877,105 $ 12,451,957 $ 13,104,591 $ 13,793,600 $ 14,521,115 $ 15,328,773 Other Miscellaneous Revenue 831,951 846,101 596,796 1,978,440 324,090 346,569 313,984 384,496 Grants and Loan Proceeds - - - - 5,500,000 - 5,900,000 - Sewer Connection Fees 40,800 25,000 25,000 25,000 25,000 25,000 25,000 25,000 Total Revenues S 10,615,417 $ 12,200,814 $ 12,498,902 S 14,455,397 $ 18,953,681 $ 14,165,169 S 20,760,099 S 15,738,269 Expenses 2023 2024 2025 2026 2027 2028 2029 2030 Sewer Operations & Maintenance King County wastewater $ 4,458,822 $ 5,830,000 $ 6,165,225 $ 6,519,725 $ 6,943,507 $ 7,394,835 $ 7,875,499 $ 8,426,784 Regular City Sewer 2,886,734 2,836,754 2,444,110 2,546,191 2,657,491 2,774,284 2,896,882 3,025,618 Debt Service 348,036 347,489 154,402 154,258 505,457 505,251 1,001,768 1,001,562 Debt Service/Casts for PW Shops 389,949 397,684 200,087 180,847 180,944 180,770 180,878 181,200 Interfund Utility Tax 1,005,699 1,132,971 1,187,711 1,245,196 1,310,459 1,379,360 1,452,111 1,532,877 Engineering Labor - - - - - - - - Subtotal $ 9,089,241 $ 10,544,898 $ 10,151,535 $ 10,646,217 $ 11,597,859 $ 12,234,501 $ 13,407,138 $ 14,168,042 Sewer Capital - CIP Program $ 592,500 $ 5,066,880 $ 7,325,067 $ 5,640,544 $ 6,338,609 $ 3,667,507 $ 3,935,872 $ 4,472,903 Total Ex. • nditures $ 9,681,741 $ 15,611,778 $ 17,476,602 $ 16,286,761 $ 17,936,467 $ 15,902,007 $ 17,343,010 $ 18,640,944 Fund Balances 2023 2024 2025 2026 2027 2028 2029 2030 Change in Fund Balance $ 933,676 $ (3,410,964) $ (4,977,700) $ (1,831,364) $ 1.017,214 $ (1,736,838) $ 3,417,088 $ (2,902,676) Beginning Fund Balance 12,278,125 13,609,612 10,198,648 5,220,948 3,389,584 4,406,798 2,669,959 6,087,047 Ending Fund Balance $ 13,211,800 $ 10,198,648 $ 5,220,94.9 $ 3,389,584 $ 4,406,798 $ 2,669,959 $ 6,087,047 $ 3,184,371 $18 ,000, 000 $16,000, 000 $14,000,000 $12,000,000 $10,000, 000 $8,000,000 $6,000,000 $4,000,000 $2,000,000 $0 • 3.00% City of Tukwila Sewer Enterprise Fund 2025-2030 Forecast 3.00% 3.00% Ger 3.00% 3.00% ▪ + 3.00% + 2024 2025 2026 2027 2028 2029 2030 Cash Operating Expenses Phase 2 of PW Project - Existing Debt Service New Debt Service - Additions to Operating Fund Balance Rate Funded Capital -Total Revenues - Total Revenues with Rate Increases City of Tukwila, Washington Page 16 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM NOTES TO SEWER ENTERPRISE FUND 1) King County Metro sewer and Tukwila's sewer have been split out to present the revenues separately. Metro increases will be passed through to the sewer ratepayers. King County Metro sewer fees will increase 5.75% in 2025 (KC Ordinance 19782) and the City has factored in potential King County increases for 2027 through 2030. 2) 3 percent increases are proposed for Tukwila sewer in 2025 and 2026. The City will continue with the annual rate model review to confirm that the proposed increases are necessary. 3) Sewer connection fees for Allentown Phase I and Allentown/Foster Point Phase II. 4) King County Metro Sewer treatment fees are passed through to ratepayers. 5) Includes the Public Works Trust Fund (PWTF) Loan and the 2006 Bond for the Allentown/Foster Point Phase II Sewer Improvement Project. Public Works debt service could increase with Phase II. Sewer Debt Service includes: Expires 2025 2026 2006 Bond Allentown (62%) 12/31/26 111,580.21 111,642.32 2013 PWTF CBD Sewer Rehab 12/31/33 42,822.00 42,616.00 Subtotal $154,402.21 $154,258.32 2018 Public Works Shops (10%) 12/31/38 145,749.00 145,535.25 2019 Public Works Shops (10%) 12/31/39 54,337.72 35,311.60 Total $354,488.93 $335,105.17 6) An Interfund Utility Tax was approved in October 2009 for the water, sewer, and surface water utilities. Gross revenues are currently taxed 10% through December 31, 2027. 7) The Working Capital Reserve Fund's policy was updated in 2012 per Resolution No. 1774 to maintain an adequate fund balance in each of the enterprise funds. For the Enterprise Funds, the unrestricted fund balance shall equal or exceed 20% of the previous year's revenue, exclusive of significant non -operating, non -recurring revenues. FCS Group is proposing new operating reserve requirements in line with best practices. 8) The Senior Water/Sewer Engineer's salary and benefits are split evenly between the water department and the sewer department. For 2025 and 2026, Technology staff will continue to charge at 22% for the GIS Coordinator and 10% for the Information Systems Project Analyst to assist with the GIS Inventory of the sewer fund. The Sewer fund is also splitting a GIS Technician position with the Surface Water fund. Sewer Enterprise Fund The City's Enterprise Funds account for utility operations that are self -supported through user charges. The utilities are financed and operated like a private business enterprise which requires periodic determination of revenues earned; expenses incurred, and net income for capital maintenance, public policy, management control and accountability. The Sewer Fund accounts for operations and capital improvements to provide sanitary sewer to a portion of City residents. Valley View Sewer District also provides sewer in the City. City of Tukwila, Washington Page 17 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM SURFACE WATER ENTERPRISE FUND 2025-2030 Forecast Bud el Pro eeted Pro-ected Pro-ected Pro-ected Proected Pro-ected Revenues 2024 2025 2026 2027 2028 2029 2030 Rate Increases 3.25% 3.25% 3.25% 3.25% 3.25% 3.25% Annual Billings $ 8,103,375 $ 8,436,412 $ 8,783,137 $ 9,144,112 $ 9,519,922 $ 9,911,177 5 10,318,513 Other Miscellaneous Revenue 450,852 327,728 184,474 100,859 165,406 105,884 198,201 Grants and Loan Proceeds 3,306,000 5,956,000 5,810,000 19,361,000 2,247,000 8,545,000 3,705,000 Total Revenues $ 11,860,227 $ 14,720,140 $ 14,777,611 $ 28,605,970 $ 11,932,327 $ 18,562,062 $ 14,221,714 Expenses 2024 2025 2026 2027 2028 2029 2030 Operations & Maintenance $ 3,471,491 $ 4,691,494 $ 4,422,494 $ 4,615,884 $ 4,818,680 $ 5,031,401 $ 5,254,601 Debt Service 282,183 21,596 21,608 715,617 715,617 1,262,854 1,262,854 Debt Service/Costs for PN Shops 869,965 494,951 447,358 447,599 447,169 447,434 448,232 Interfund Utility Tax 810,338 843,641 878,314 914,411 951,992 991,118 1,031,851 Engineering Labor - - - - - - - Subtotal $ 5,433,976 $ 6,051,683 $ 5,769,774 $ 6,693,512 $ 6,933,458 $ 7,732,806 $ 7,997,538 Storm Ca'ital - CIP Pr + «ram 5 7.023.588 $ 10,613,547 $ 11,715.891 $ 16,685,116 $ 7,974,926 $ 6,213,446 $ 11.308.156 Total Ex « nditures $ 12,457,564 $ 16,665,230 $ 17,485,665 $ 25,378,627 $ 14,908,384 $ 13,946,253 $ 19,3,65,695 Fund Balances 2024 2025 2026 2027 2028 2029 2030 Change in Fund Balance $ (597,337) $ (1,945,090) $ (2,708,055) $ 3,22.7,343 $ (2,976,056} $ 4,615,809 $ (5,083,981) Be.innin+ Fund Balance 10,293,419 9,696,082 7,750,992 5,042,937 8,270,280 5,294,224 9,910,033 Endin Fund Balance $ 9,696,082 $ 7,750,992 $ 5,042,937 $ 8,270,280 $ 5,294,224 $ 9,910,033 $ 4,826,052 $14,000,000 $12,000,000 $10,000,000 $8,000,000 $6,000,000 $4,000,000 $2,000,000 $o 2024 2025 City of Tukwila Surface Water Enterprise Fund 2025-2030 Forecast 2026 Cash Operating Expenses Existing Debt Service 3.25% 3.25% 3.25% 2027 2028 2029 2030 Phase 2 of PW Project New Debt Service Additions to Operating Fund Balance Rate Funded Capital —Total Revenues — Total Revenues with Rate Increases City of Tukwila, Washington Page 18 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM NOTES TO SURFACE WATER ENTERPRISE FUND 1) Reflects proposed rate increases of 3.25% in 2025 through 2030. The City will continue with the annual rate model review to confirm that the proposed Surface Water rate increases are necessary. 2) The National Pollution Discharge Elimination System (NPDES) permit required by the State Department of Ecology is having a significant impact on the Surface Water fund. 3) Potential grants and/or bond revenue. Included is the estimated Department of Ecology grant for NPDES and King County Flood Control District Opportunity grants as well as significant grant funding for the Nelsen Side Channel, the Storm Quality Retrofit Project, S 131 st Pl Drainage Improvements, the Gilliam Creek Fish Barrier Removal Project and the Chinook Wind Project. 4) Debt schedule includes the 2006 Allentown Bond. Public Works debt service could increase with Phase II. Debt Service includes: Expires 2025 2026 2006 Bond Allentown (12%) 12/31/26 21,596.17 21,608.19 Subtotal $21,596.17 $21,608.19 2018 Public Works Shops (23%) 2019 Public Works Shops (23%) Total 360,537.00 360,008.25 12/31/38 134,414.36 87,349.73 $ 516,547 53 $ 468,966 17 5) An Interfund Utility Tax was approved in October 2009 for the water, sewer, and surface water utilities. Gross revenues are currently taxed 10% through December 31, 2027. 6) The Working Capital Reserve Fund's policy was updated in 2012 per Resolution No. 1774 to maintain an adequate fund balance in each of the enterprise funds. For the Enterprise Funds, the unrestricted fund balance shall equal or exceed 20% of the previous year's revenue, exclusive of significant non -operating, non -recurring revenues. FCS Group is proposing new operating reserve requirements in line with best practices. 7) Cost of engineering to support capital projects, NPDES, and operation efforts in-house. For 2024 and 2026, Technology staff will continue to charge 22% for the GIS Coordinator and 10% for the Information Systems Project Analyst to assist with the GIS Inventory of the Surface Water fund. The Surface Water Fund is funding a Green Infrastructure Program, with three new FTES projected in 2025. Surface Water Enterprise Fund The City's Enterprise Funds account for utility operations that are self -supported through user charges. The utilities are financed and operated like a private business enterprise which requires periodic determination of revenues earned; expenses incurred, and net income for capital maintenance, public policy, management control and accountability. The Surface Water Enterprise Fund accounts for operations and capital improvements for the City's storm drainage and surface water management function. Surface Water projects are required to meet Federal, State and local mandates. The largest contributor to the surface water enterprise fund is the City of Tukwila. City of Tukwila, Washington Page 19 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Rctuats GOLF COURSE ENTERPRISE FUND 2025-2030 Forecast Budget Budget Forecast Forecast Forecast Forecast Forecast Revenues 2023 2024 2025 2026 2027 2028 2029 2030 0 pe ratl ng Revenue Green Fees $ 1,631,463 $ 1,512,500 $ 1,610,000 $ 1,610,000 $ 1,670,000 $ 1,725,000 $ 1,785,500 $ 1,848,000 Cart + Club Rentals 379,076 350,000 368,500 363,500 382,000 395,000 410,000 425,000 Facility Improvement Fee 180,033 150,000 160,000 160,000 165,000 170,000 175,000 180,000 Other Revenue 79,611 15,000 24,000 24,000 25,000 25,000 25,000 25,000 Operating Revenue Total $ 2,270,183 $ 2,027,500 $ 2,162,500 $ 2,162,506 $ 2,242,000 $ 2,315,000 $ 2,395,500 $ 2,478,000 Resale Revenue Merchandise Sales $ 142,842 $ 125,000 5 135,000 $ 135,000 $ 140,000 $ 145,000 $ 150,060 $ 155,000 Food & Beverage Sales 29,357 25,000 30,000 30,000 31,000 32,000 33,000 35,000 Resale Revenue Total $ 172,199 $ 150,000 5 165,000 $ 165,000 $ 171,000 $ 177,000 $ 183,000 $ 190,000 Non -Operating Revenue General Fund Transfer -In $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 Concessionaire Revenue 105,280 100,000 100,000 100,000 104,000 107,000 111,000 115,000 Investment Interest 72,111 50,000 60,000 60,000 50,000 50,000 50,000 50.000 Non -Operating Revenue Total $ 477,391 $ 450,000 $ 460,000 $ 460,000 5 454,000 $ 457,000 $ 461,000 $ 465,000 Total Revenues $ 2.919.773 $ 2,627.500 $ 2,787,500 $ 2,787,500 $ 2,867,000 $ 2,949,000 5 3,039,500 $ 3.133.000 Expenses 2023 2024 2025 2026 2027 2028 2029 2030 Salaries & Benefits $ 1,303,682 $ 1,416,850 5 1,473,296 $ 1,561,720 $ 1,639,806 $ 1,721,796 $ 1,807,886 $ 1,898,280 SupplleS 224,750 235,953 362,145 373,155 391,500 405,250 419,560 435,000 Services 335,130 310,649 360,225 381,843 337,250 348,100 359,560 438,500 Indirect Cost Allocation 219,309 230,274 241,788 253,877 266,571 279,900 293,895 308,590 Subtotal $ 2,082,871 $ 2,193,735 $ 2,437,454 $ 2,575,595 $ 2,635,127 $ 2,755,046 $ 2,880,781 5 3,080,370 Dolt Capital- CIP Program $ 410,000 $ 335,000 $ 675,000 $ 570,000 $ 339,000 $ 345,000 $ 351.060 $ 357,000 Total Expenditves $ 2,492,871 5 2,528,735 $ 3,112,454 $ 3,145,595 $ 2,974,127 5 3,100,046 $ 3,231,781 5 3,437,370 Fund Balances 2023 2024 2025 2026 2027 2028 2029 2030 Change in Fund Balance $ 426,902 $ 98,765 $ (324,954) $ (358,095) $ (107,127) $ (151,046) $ (192,281) $ (304,370} Beginning Fund Balance 1,468,130 1,993,797 2,092,562 1,767,608 1,409,512 1,302,385 1,151,339 959,058 Ending Fuld Balance $ 1,895,032 $ 2,092,562 $ 1,767,608 $ 1,409,512 $ 1,302,385 $ 1,151,339 $ 959,058 $ 654,688 City of Tukwila, Washington Page 20 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM NOTES TO GOLF ENTERPRISE FUND 1) Green Fees and Instruction are expected to increase modestly as a function of both increased instruction for new and young players and periodic greens fee increases. This model allows for a slight growth in golf rounds and includes an increase in green fees every two years to keep current with the market. 2) General Fund Contribution is the portion of the City's sales tax revenue that will be transferred to the 411 Golf fund to cover Admission tax, Indirect Cost Allocation, and Working Capital Reserves. 3) Operations and Maintenance does not include the Parks and Recreation's Director's 25% of salary and benefits. The Golf Maintenance building is covered 50%/50% between Golf and the Parks Department. 4) Indirect Cost Allocation will be calculated on an annual basis. 5) The Working Capital Reserve Fund's policy was updated in 2012 per Resolution No. 1774 to maintain an adequate fund balance in each of the Enterprise Funds. For the Enterprise Funds, the unrestricted fund balance shall equal or exceed 20% of the previous year's revenue, exclusive of significant non - operating, non -recurring revenues. Golf Enterprise Fund The City's Enterprise Funds account for operations that are self -supported through user charges. The funds are financed and operated like a private business enterprise which requires periodic determination of revenues earned, expenses incurred, and net income for capital maintenance, public policy, management control and accountability. The Golf Enterprise Fund accounts for operation, maintenance, debt service and improvements of the municipal golf facility. The difference between the other utility enterprise funds is that Golf has voluntary users as opposed to involuntary users of the water, sewer, and surface water funds. City of Tukwila, Washington Page 21 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CAPITAL PROJECT DETAIL SHEETS The following pages outline individual CIP projects scheduled for completion or funding during the 2025-2030 period. Projects with expenses in 2025 or 2026 are listed first on the fund summary sheets, followed by projects scheduled for later years. Each project includes an estimated future operating budget impact where it can be identified at this point in the project's lifecycle. These projects focus on critical infrastructure improvements, public facility upgrades, and community services that align with the city's strategic goals. While most projects are asset -producing, some are included because they support the City's broader capital needs, ensuring that Tukwila continues to effectively manage its long-term growth and development. City of Tukwila, Washington Page 22 of 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) Special Projects (000) JL Key Project Name 92510101 World Cup _ Preparations 92551001 The People's Project Total 2029 2030 Total After Costs six years $- $- $1,000 $- $55 $55 $55 $55 $55 $55 $330 $55 1 1 I $305 I $805 I $55 I $55 1 $55 i $55 i $1330 $55 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: World Cup Preparations Project # 92510101 Project Manager Brandon Miles Department Special Projects DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The City of Tukwila is undertaking a series of infrastructure and public space enhancements in preparation for the 2026 FIFA World Cup. This project includes improvements to city -owned facilities, enhancements to public spaces, and the development of temporary visitor facilities, such as fan zones, to accommodate the anticipated influx of international visitors. The project also involves coordination with King County Metro and Sound Transit to ensure seamless public transportation access for visitors. The 2026 FIFA World Cup is expected to draw a significant number of visitors to the Seattle -Tacoma area, including Tukwila. Enhancing the city's infrastructure and public spaces will ensure that Tukwila can effectively support increased tourism, resulting in higher sales and lodging tax revenues. The City Council authorized funding for these improvements in 2024, based on projections of the economic benefits associated with the event. The project is currently in the planning and design phase. Completion of design is expected by mid-2025, with construction and implementation scheduled to begin in late 2025. The project aims to be fully completed byearly 2026, ahead of the World Cup. N/A Funded by Lodging Tax. The project includes close coordination with King County Metro and Sound Transit to enhance public transportation access, although Tukwila will not directly manage these systems. FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 250 250 $ 250 250 2026 $ 750 750 $ 750 750 2027 2028 2029 2030 Beyond TOTAL 1,000 1,000 1,000 1,000 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Griffin Lerner DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The People's Project Project # 92551001 Department Special Projects The People's Project is Tukwila's inaugural participatory budgeting initiative, allowing residents to directly propose and vote on small-scale capital improvement projects. An annual allocation of $50,000 will be set aside for the implementation of selected projects, funded for the 2025-2026 biennium from the Arterial Streets (Fund 104). This project aims to enhance civic engagement by inviting residents to propose and prioritize projects that improve public spaces, infrastructure, and city amenities. Examples of potential projects may include park improvements, pedestrian safety enhancements, or small-scale beautification efforts. The People's Project provides an opportunity for Tukwila residents to take part in shaping their community by voting on which projects should be funded and implemented. This initiative enhances transparency in the city's budget process and fosters a sense of community ownership over city improvements. This is the first year Tukwila is implementing a participatory budgeting program, aligning with the city's goals of increasing public engagement and empowering residents in decision -making processes. The People's Project will launch in the first half of 2025. Residents will have the opportunity to submit project proposals in the second quarter, with a city-wide vote to follow in the third quarter. Projects selected through the voting process will begin implementation in mid-2025. The program will run annually, with a new round of proposals and voting each year. Selected projects may lead to minor increases in ongoing maintenance depending on the nature of the improvements. Each proposed project will be reviewed for its long-term impact on city resources and maintenance needs before final selection. This is Tukwila's first -ever participatory budgeting initiative. Funding for the 2025-2026 biennium is provided by the Arterial Streets Fund (Fund 104). Future funding sources will be evaluated based on the success of the program and community feedback. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 5 50 55 $ 55 $ 55 2026 $ 5 50 55 $ 55 $ 55 2027 $ 5 50 55 $ 55 $ 55 2028 $ 5 50 55 $ 55 $ 55 2029 $ 5 50 55 55 $ 55 2030 $ 5 $ 50 $ 55 $ 55 $ 55 Beyond $ 5 50 55 55 $ 55 TOTAL $ 35 350 385 385 $ 385 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) Residential Streets (103) J L II1F1111V026 91710303 S 152nd St Pedestrian and Bike Improvements $774 $5,252 $1,900 2030 Total Costs r After six years $- $- $7,926 $- 80010301 Traffic $465 $715 $740 $740 $765 $765 $4,190 $770 Calming/Residential Safety Improvements 91710301 46th Ave S Safe $- $338 $2,083 $- $- $- $2,421 $- Routes to School 91710302 Macadam Rd South $- $- $420 $30 $3,120 $- $3,570 $- Complete Street Total $1,239 $6,305 $5,143 $770 $3,885 $765 $18,107 $770 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: S 152nd St Pedestrian and Bike Improvements Adam Cox Project # 91710303 Department Residential Streets Install curb, gutter, shared use path and sidewalks on S 152nd St, including widening pavement and construct as a buffer between the roadway and sidewalk on the south side. Enhance safety for students walking to Foster High School, Showalter Middle School, and Thorndyke Elementary School and encourage transportation choices for the neighborhood. Design funded, construction pending Ped and Bike grant funding. The streets division will be required to sweep and maintain the vegetation. Sound Transit System Access Fund Grant of $369k for design. Apply for ped and bike grant in 2026 for construction. INANCIAL (in thousands) roject Costs roject Mgmt (Staff Time/Cost) esign and (R/W) onstruction Mgmt. onstruction otal Project Costs roject Funding warded Grant roposed Grant and Balance tility Revenues otat Project Funding 2025 274 300 200 $ 774 $ 100 $ 624 50 774 2026 $ 274 $ 30 $ 500 $ 4,448 $ 5,252 $ 448 $ 3,530 $ 274 $ 1,000 $ 5,252 2027 $ 400 $ 1,500 $ 1,900 $ 1,900 2028 2029 2030 Beyond TOTAL 548 300 230 900 5,948 7,926 548 5,554 274 1,550 7,926 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 Traffic Calming/Residential Safety PROJECT: Improvements Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project# 80010301 Department Residential Streets Programmatic approach to addressing neighborhood traffic concerns through a variety of methods. Residential street improvements with sidewalks, safety improvements, and bike facilities. Neighborhood revitalization by improving residential streets. Future candidates are listed in the citywide comprehensive update and safety -based prioritization of residential street improvements, sidewalks, and bike lanes. Varies, depends on treatment(s) used. Primarily Streets would be affected. Residential improvements and traffic calming features to reduce speeds and improve pedestrian and bicycle safety such as the speed cushions, RRFB crossings, LED enhanced signs, Radar driver feedback signs, etc. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Total Project Costs Project Funding Proposed Grant Dedicated/Restricted Rev Fund Balance General Fund Transfer Total Project Funding 2025 $ 65 $ 150 $ 250 465 $ 400 $ 65 465 2026 $ 65 $ 155 $ 495 715 $ 250 $ 400 $ 65 715 2027 $ 70 $ 160 $ 510 740 $ 250 $ 70 $ 420 740 2028 $ 70 $ 160 $ 510 740 $ 250 $ - $ 70 $ 420 740 2029 $ 75 $ 165 $ 525 765 $ 250 $ 75 $ 440 765 2030 $ 75 $ 165 $ 525 $ 765 $ 250 $ - $ 75 $ 440 $ 765 Beyond $ 75 $ 170 $ 525 $ 770 $ 250 $ 75 $ 440 765 TOTAL 495 1,125 3,340 4,960 1,500 800 495 2,160 4,955 DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: 46th Ave S Safe Routes to School Project # 91710301 Project Manager Cyndy Knighton Department Residential Streets Install curb, gutter, and sidewalk on the west side of 46th Avenue South. Install a curb bulb -out at the southeastern corner of 46th Ave S and S 144th St and a raised crosswalk on S 144th St with pedestrian -activated flashing beacons. Enhance safety for students walking to Foster High School and Showalter Middle School and encourages transportation choices for the neighborhood. RRFB at 46th Ave S & S 144th St Intersection in 2019 as part of the Neighborhood Traffic Calming Program. Nominal maintenance increase in costs related to maintaining sidewalks and slightly widened pavement. If additional lighting is added, nominal maintenance increase in maintenance needs. Safe Routes to School grant submitted in April 2018, but unsuccessful. Apply for SRTS grant for design in 2024 and in 2026 for construction. i FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Contingency otal Project Costs Project Funding Proposed Grant Fund Balance otat Project Funding 2025 13 13 2026 338 $ 235 $ 103 338 2027 $ 13 $ 279 $ 1,584 $ 207 $ 2,083 $ 1,660 $ 410 $ 2,070 2028 2029 2030 Beyond TOTAL 26 250 75 279 1,584 207 2,421 $ 1,895 526 2,421 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Macadam Rd South Complete Street Project # 91710302 Project Manager Cyndy Knighton Department Residential Streets Construction of a complete street design for Macadam Rd South between South 144th St and S 150th St. DESCRIPTION: The project will require roadway widening and re-channelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of the roadway, and includes illumination, curb, and storm drainage. JUSTIFICATION: Enhance safety for students walking to Foster High School and Showalter Middle School and encourages transportation choices for the neighborhood. STATUS: MAINTENANCE IMPACT: COMMENT: Pending successful grant award(s) Streets will be responsible for road maintenance, including striping. Any improvements/changes to surface water will be maintained by that crew. WSDOT Pedestrian/Bicycle grant submitted in April 2018, but unsuccessful. Match will be the Water Improvements. Apply for same grant in 2024 or 2026 for design and later for construction. Sidewalk on East side of roadway completed in 2022. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Contingency Total Project Costs Project Funding Proposed Grant Fund Balance General Fund Transfer Total Project Funding 2025 2026 2027 $ 20 $ 400 $ - $ - 420 $ 350 $ 20 $ 50 420 2028 30 30 2029 $ 20 $ 390 $ 2,400 $ 310 $ 3,120 $ 2,800 $ 20 $ 300 $ 3,120 2030 Beyond TOTAL $ 60 $ 400 $ 10 $ 390 $ 2,400 $ 310 3,570 3,180 40 350 3,570 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) Arterial Streets (104) Jjegiii. Project Name 2025 2026 ' '2029 2030 Total After Costs six years 80010401 Annual Overlay $2,550 $- $2,520 $2,520 $2,720 $2,720 $13,030 $2,920 and Repair Program 92110402 Southcenter $1,208 $- $- $- $- $- $1,208 $- Blvd/65th Ave S Signal 92510404 S Ryan Way $675 $915 $12,781 $- $- $- $14,371 $- 82510402 Boeing Access $574 $3,439 $- $- $- $- $4,013 $- Road Overlay 91810404 42nd Ave S $300 $600 $17,750 $17,600 $- $- $36,250 $- Bridge Replacement 71301302 Wetland & $250 $110 $115 $115 $125 $130 $845 $135 Environmental Mitigation 91610407 S 119th St $202 $- $- $- $- $- $202 $- Pedestrian Bridge Painting and Inspection 98610403 Strander $200 $- $- $- $- $- $200 $- Bo u leva rd Extension Phase 3 80010404 Annual Traffic $130 $130 $160 $160 $170 $190 $940 $200 Signal Program 82510404 Orillia Road $125 $1,224 $- $- $- $- $1,349 $- South Overlay 70010402 Annual Bridge $102 $222 $232 $237 $242 $242 $1,277 $242 Inspections and Repairs 92510406 Southcenter $100 $135 $2,755 $- $- $- $2,990 $- Blvd Road Diet (62nd Ave S - 66th Ave S) 92510401 42nd Avenue S $68 $308 $- $- $- $- $376 $- Bikeway 92510405 Southcenter $65 $325 $- $- $- $- $390 $- Blvd Bikeway 1 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM '''W and Pedestrian Crossing Upgrades 91510405 Americans with Disabilities Act (ADA) Improvements 92110405 Allentown Truck Reroute Environmental Impact Statement City Project 72010405 Transportation Element of Comprehensive Plan 82510403 Interurban Avenue S Overlay 90310404 S 144th St Bridge - Sidewalks 90310405 Andover Park E/Minkler Blvd Intersection 92510402 S 124th St/50th Pl S Reconfiguration 98410407 Minkler Blvd (Andover Park W - Southcenter Pkwy) 98910405 E Marginal Way S(BAR-S112 St) 99110405 Andover Park East/Industry Dr Intersection 99510405 S 133 St/SR599 Southbound Intersection Total $- $- $- $- $117 $417 $534 $417 $- $447 $4,610 $- $- $- $5,057 $- $- $609 $2,720 $- $- $- $3,329 $- $- $278 $2,413 $- $- $- $2,691 $- $- $275 $1,830 $- $- $- $2,105 $- $- $- $- $- $385 $2,850 $3,235 $- $- $88 $- $- $- $- $88 $- $- $193 $1,413 $- $- $- $1,606 $- $- $- $- $580 $2,730 $- $3,310 $- $6,660 $9,359 $49,360 $21,273 $6,550 $6,610 $99,812 $3,975 2 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Annual Overlay and Repair Program Project Manager David Baus Project # 80010401 Department Arterial Streets DESCRIPTION: Select, design, and construct asphalt and concrete pavement overlays of arterial and residential streets. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Preserve and maintain the street structure in a safe and useable state by resurfacing before failure which also minimizes costs. Some individual sites may be coordinated with water, sewer, and surface water projects. Each year various sections of roadway throughout the City are designed and constructed for asphalt overlay. Roughly 1,300 hours go to filling in potholes per year, so if budget is increased this could be cut in half. Ongoing project. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Dedicated/Restricted Rev General Fund Transfer Total Project Funding 2025 $ 50 $ 300 $ 200 $ 2,000 $ - $ 2,550 $ 2,550 $ 2,550 2026 2027 $ 20 $ 150 $ 200 $ 2,000 $ 150 $ 2,520 $ 1,520 $ 1,000 $ 2,520 2028 $ 20 $ 150 $ 200 $ 2,000 $ 150 $ 2,520 $ 1,520 $ 1,000 $ 2,520 2029 $ 20 $ 150 $ 200 $ 2,200 $ 150 $ 2,720 $ 1,650 $ 1,070 $ 2,720 2030 $ 20 $ 150 $ 200 $2,200 $ 150 $2,720 $1,650 $1,070 $2,720 Beyond $ 20 $ 150 $ 200 $ 2,400 $ 150 $ 2,920 $ 1,650 $ 1,360 $ 3,010 TOTAL $ 150 $ 1,050 $ 1,200 $ 12,800 $ 750 $ 15,950 $ 10,540 $ 5,500 $ 16,040 3 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Southcenter Blvd/65th Ave S Signal Project Manager Cyndy Knighton Project # 92110402 Department Arterial Streets DESCRIPTION: Design and construct a traffic signal at the Southcenter Boulevard/65th Avenue S intersection. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The intersection experiences significant delay for southbound left turn movements during the PM Peak Hour. Signal warrants have been met. Design underway in 2024 Streets responsible for annual signal maintenance and operation. Project on Traffic Impact Fee list. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Mgmt. Construction Contingency Total Project Costs Project Funding Awarded Grant Fund Balance Total Project Funding 2025 26 160 904 118 $ 1,208 $ 782 $ 426 $ 1,208 2026 2027 2028 2029 2030 $ - $ - $ - $ - $ - $ - Beyond TOTAL 26 160 904 118 1,208 $ 782 426 1,208 4 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: -111111 S Ryan Way Project Manager Cyndy Knighton DESCRIPTION: Project # 92510404 Department Arterial Streets Design and construct major road improvements on S Ryan Way from east of Martin Luther King, Jr. Way to east City limits. Project will include full overlay/roadway reconstruction, re-channelization to a 3-lane roadway section with protected bike lanes, new and/or replacement sidewalk and curb ramps to meet ADA requirements, enhanced pedestrian crossings, intersection realignment at 47th Ave S/S 107th St, and new illumination. New water for project length and new sewer main to extend existing sewer limits. New drainage system for length of project with treatment and detention. Undergrounding of certain overhead utilities may be included. New walls may be required for sidewalk construction. ROW acquisition will be necessay. Pavement condition is extremely poor. History of speeding and safety concerns warrant the road diet. Area JUSTIFICATION: development off 47th Ave S require channelization changes. Improvements to pedestrian and bicycle network are needed. STATUS: New project for 2025. Project scope under development in 2024. MAINTENANCE IMPACT: Reduction in Streets maintenance will come from the overlay. Increases in Streets will result from new COMMENT: illumination and bike lanes. Overall reduction in impacts to Streets is anticipated. Improvements to S Ryan Way have been needed for many years. A full overlay is warranted due to poor pavement condition. Full reconstruction of the road may be warranted in some locations. Speeding and safety concerns can be addressed by road diet to 3 lane section and intersection realignments. Pedestrian and bike facilities are needed. New development in the area wilt be increasing demand for transportation efficiency and safety. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Contingency Total Project Costs Project Funding Proposed Grant Dedicated/Restricted Rev Fund Balance Utility Revenues General Fund Transfer Total Project Funding 2025 675 675 2026 $ 15 $ 600 $ 300 $ - 915 $ 400 $ 500 $ 15 915 2027 $ 21 $ - $ 1,530 $ 9,960 $ 1,270 $ 12,781 $ 8,650 $ 21 $ 1,690 $ 2,420 $ 12,781 2028 2029 2030 Beyond TOTAL $ 36 $ 1,275 $ 300 $ 1,530 $ 9,960 $ 1,270 $ 14,371 $ 9,050 $ 1,175 $ 36 $ 1,690 $ 2,420 $ 14,371 5 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager David Baus Boeing Access Road Overlay Project # 82510402 Department Arterial Streets DESCRIPTION: Grind and overlay roadway, replace concrete overlay of bridge deck over BNSF railway JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Existing bridge deck concrete is breaking off making an uneven surface with the potential to cause flying debris. Project was awarded full funding by National Highway Performance Program January of 2024 N/A Construction must be completed as a single contract and authorized by August 31, 2026. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Awarded Grant Fund Balance Total Project Funding 2025 $ 10 $ 564 $ - 574 $ 564 10 574 2026 $ 15 $ 400 $ 2,750 $ 274 $ 3,439 $ 3,426 $ 13 $ 3,439 2027 2028 2029 2030 $ - $ - Beyond TOTAL 25 564 400 2,750 274 4,013 $ 3,990 23 4,013 6 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Adam Cox DESCRIPTION: 42nd Ave S Bridge Replacement Project # 91810404 Department Arterial Streets Design and construct a replacement structure for the existing 42nd Ave S Bridge adjacent to the Tukwila Community Center. The current bridge has been restricted to one lane for southbound traffic due to the bridge being struck by an over JUSTIFICATION: height truck. The current through truss bridge is fracture critical, structural deficient, and has lasted longer than its deign life. STATUS: The project is currently in the design phase, with 90% design complete. Project construction is anticipated to begin in early 2027 and be complete by end of 2028. MAINTENANCE IMPACT: Streets crews will be responsible to sweep the bridge and maintain any vegetation that is planted. COMMENT: The City has secured project costs through multiple grants- $1.5M in Surface Transportation Program funding (13.5% match), $12M in Local Bridge Programs funding (no match), and $17M in Move Ahead Washington funding (no match). FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Contingency Total Project Costs Project Funding Awarded Grant Proposed Grant Fund Balance Total Project Funding 2025 $ 100 $ 200 300 $ 200 100 300 2026 $ 100 $ 500 600 $ 500 100 600 2027 $ 100 $ 50 $ 100 $ 1,500 $ 15,000 $ 1,000 $ 17,750 $ 16,500 $ 1,150 $ 100 $ 17,750 2028 $ 50 $ 50 $ - $ 1,500 $ 15,000 $ 1,000 $ 17,600 $ 14,650 $ 2,950 $ 17,600 2029 2030 $ - $ - $ - Beyond TOTAL $ 350 $ 800 $ 100 $ 3,000 $ 30,000 $ 2,000 $ 36,250 $ 31,850 $ 4,100 $ 300 $ 36,250 7 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: Wetland & Environmental Mitigation Mike Ronda Project # 71301302 Department Arterial Streets Some of our CIP projects (typically roads and bridges) have impacts to sensitive areas that have to be mitigated with special restoration areas. These areas need to be maintained to meet standards set in the permit for a minimum of five years after the project is complete. Not all projects have these conditions but for those that do, we need specialty resources to provide this level of effort that are generally not available through current staffing levels. Permit requirements from previous projects. We currently have four project sites that are in various stages of restoration. Currently this work is being performed by specialty consultants because in-house resources are not available or allowed to focus on this effort. The work is more specialized than typical roadway maintenance but it is only slightly more complicated than other aspects of the RoW or Parks maintenance. The reporting does require specialty consultant staff but most of the maintenance activities could be performed by City resources if those MAINTENANCE IMPACT: people could be reserved for this function when it's necessary. If the Roadway landscaping plants die that is unfortunate. If the mitigation site plants die, we have to start all over again with a new mitigation effort. The work could be performed by any capable landscape maintenance crew with knowledge of native plants. Street Department crews have traditionally served a limited function to support these efforts but those resources are general fund supported and that volatile funding has not been a good match for a long term obligation like this one. COMMENT: Four current locations for the sites include: - Southcenter Parkway west side south of Segale Park Drive C - TUC Pedestrian Bridge Mitigation between West Valley and Christensen Road - Fort Dent/Starfire riverside bank - 42nd Ave Culvert Mitigation (near Southcenter Blvd) FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Awarded Grant Fund Balance General Fund Transfer Total Project Funding 2025 10 40 25 150 25 $ 250 $ 150 $ 100 250 2026 10 20 15 55 10 $ 110 $ 50 $ 60 110 2027 15 20 15 55 10 115 115 2028 15 25 10 55 10 $ 115 115 2029 20 25 10 60 10 125 $ 125 125 2030 $ 20 $ 30 $ 10 $ 60 $ 10 $ 130 $ - $ 130 $ - $ 130 Beyond 25 30 10 60 10 135 $ 135 $ 135 270 TOTAL 115 190 95 495 85 980 200 780 135 1,115 8 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 119th St Pedestrian Bridge Painting and T Inspection Project Manager Adam Cox DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 91610407 Department Arterial Streets Ongoing maintenance (painting) of the S 119th St Pedestrian Bridge in the Allentown/Duwamish neighborhoods. Included is a specialized inspection to verify the condition of the timber. Safety or repair needs completed in the early stages minimizes hazards and costs. In the past, King County has provided inspection and some repair services. The bridge deck was completed in 2018 with additional repairs still needed. Streets department will be required to clean the bridge. N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Mgmt. Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 2 $ 10 $ 190 202 202 202 2026 2027 2028 2029 2030 $ - $ - $ - Beyond $ TOTAL 2 10 190 202 202 202 9 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Strander Boulevard Extension Phase 3 Project Manager Derek Speck DESCRIPTION: JUSTIFICATION: Project # 98610403 Department Arterial Streets Design and construct arterial improvements for a new roadway extending Strander Blvd from West Valley Highway to SW 27th St in Renton. The east -west capacity will stimulate new development and relieve traffic from 1-405 and S 180th Street. The project has three phases. Phase 1 extended SW 27th St from Oaksdale Ave to Naches Ave SW. Phase II STATUS: constructed a 2 lane road from Naches into the Sounder commuter rail station. Phase III will extend Strander Blvd under the UPRR and connect to SW 27th Ave at Naches as a 4 lane road. MAINTENANCE IMPACT: COMMENT: N/A Funding shown below in 2025 is to evaluate the project's design, estimate costs and identify potential funding sources. FINANCIAL (in thousands) Project Costs Design Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 200 200 200 200 2026 2027 2028 2029 2030 Beyond TOTAL 200 200 $ 200 200 10 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Annual Traffic Signal Program Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: that are beyond routine maintenance work LEDs are on a 4 to 5 year replacement cycle. Work includes adding additional signal heads, luminaires, loop STATUS: repairs, and controller upgrades including signal timing and coordination plans. Project # 80010404 Department Arterial Streets Design and construct minor traffic signal upgrades and repairs of signals that exceed routine maintenance work; loop replacement, head replacement, and controllers. Replace direct bury cable for existing lighting system. City is adding traffic signals to inventory every year. Older signals may need extra maintenance or modifications MAINTENANCE IMPACT: Likely small reduction in annual maintenance costs with ability to do larger maintenance needs through this fund. COMMENT: Annual program. FINANCIAL (in thousands) Project Costs Design Construction Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 50 $ 80 130 $ 130 130 2026 $ 50 $ 80 130 $ 130 130 2027 $ 60 $ 100 160 $ 160 160 2028 $ 60 $ 100 160 $ 160 160 2029 $ 70 $ 100 170 $ 170 170 2030 $ 70 $ 120 $ 190 $ 190 $ 190 Beyond $ 80 $ 120 200 $ 180 180 TOTAL $ 440 700 1,140 $ 1,120 1,120 11 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager David Baus Orillia Road South Overlay Project # 82510404 Department Arterial Streets DESCRIPTION: Complete pavement repairs, overlay, and curb and gutter, sidewalk, and guardrail repair JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Preserve and maintain the street structure in a safe and useable state by resurfacing before failure which also minimizes costs. Project was awarded full funding by National Highway Performance Program January of 2024 Subtracts 520 hours that would be used for pothole repair/crack sealing. Construction must be completed as a single contract and authorized by August 31, 2026. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Awarded Grant Fund Balance Total Project Funding 2025 $ 20 $ 105 125 $ 105 20 125 2026 $ 20 170 939 95 $ 1,224 $ 1,204 $ 20 $ 1,224 2027 2028 2029 2030 $ - $ - Beyond TOTAL 40 105 170 939 95 1,349 $ 1,309 40 1,349 12 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Annual Bridge Inspections and Repairs Project Manager Adam Cox DESCRIPTION: JUSTIFICATION: i Project # 70010402 Department Arterial Streets Ongoing program of bi-annual inspections, repairs, painting and rehabilitation of the 26 City vehicle and pedestrian bridges. Federally required program identifies safety or repair needs in the early stages to minimize hazards and costs. The number of bridge inspections necessary each year can vary year to year. Inspection frequencies vary from bridge to bridge and King County has provided some inspection services. STATUS: Construction projects will be determined from inspection reports and noted deficiencies/problems. MAINTENANCE IMPACT: COMMENT: N/A Ongoing project, only one year actuals are shown in the first column. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 2 $ 100 102 $ 102 102 2026 $ 2 220 222 $ 222 222 2027 $ 2 $ 230 232 $ 232 232 2028 $ 2 235 237 $ 237 237 2029 $ 2 $ 240 242 $ 242 242 2030 $ 2 $ 240 $ 242 $ 242 $ 242 Beyond $ 2 $ 240 242 TOTAL 14 $ 1,505 1,519 $ 1,277 1,277 13 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Southcenter Blvd Road Diet (62nd Ave S - 66th Ave S) Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 92510406 Department Arterial Streets Narrow Southcenter Blvd from 5 lanes to 3 lanes between approximately 62nd Avenue S to 66th Avenue S. Reconfigure signal operations at 66th Avenue S to include dual left turn lanes for WB travel and one single thru lane. Widened shared use path on north side will be created by King County Parks as part of the Lake to Sound trail project, from approximately 66th Avenue S to Macadam Road. Coordination on design and construction between agencies is required. Possible inclusion of water or sewer utility projects. Road section is on the City's High Injury Network and a road diet to slow traffic and improve visibility is the optimal solution. Coordination with King County's Lake to Sound Trail system is desirable. The County will be presenting the section of the L2S trail to voters in 2025, which will include design and construction. The road diet is necessary to the trail construction. New project TBD. Annual maintenance of the street system may remain the same, but if the project includes the desired improvements for street trees/Landscaping, and increase in annual maintenance would occur. Negotiations between City and King County on ownership and maintenance of the trail portion are required. KCParks has already indicated the desire to turn the trail over to Tukwila for ownership and maintenance. Internal discussions would need to occur to determine responsible department (PW vs. PnR). N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 100 $ 100 100 2026 135 $ 135 135 2027 $ 2,050 $ 2,755 $ 372 $ 2,755 2028 2029 2030 $ - $ - Beyond TOTAL $ 2,050 2,990 $ 607 2,990 14 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: 42nd Avenue S Bikeway Project # 92510401 Department Arterial Streets Develop a traffic -calmed bikeway along 42nd Ave S between S 150th St and Southcenter Blvd. On the west side of the street, add striped southbound bike lane between Southcenter Blvd and S 150th St. On the east side of the street, add striped bike lane between Southcenter Blvd and S 151 st St. Remove on -street parking to widen the sidewalk on the east side of the street between S 151 st St and S 150th St, creating a shared path; add shared lane markings to the roadway Sound Transit has provided funding to improve bike/vehicle separation for improve bike safety, improving the bike accessibility for locals to access the Link Light Rail station. Providing improved non -motorized connections to the Link station alleviates the concerns over locals being unable to find parking at the popular station and giving a safe alternative to area residents who can connect the "last mile" to their homes without the need of a car. New project for 2025 Small increase to Streets for maintaining new striping and signage. Project is fully funded for design and construction through a grant from Sound Transit. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 13 $ - 68 13 68 2026 $ 13 226 308 13 308 2027 2028 2029 2030 $ - $ - Beyond TOTAL 26 226 376 26 376 15 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Southcenter Blvd Bikeway and Pedestrian — Crossing Upgrades Project Manager Cyndy Knighton DESCRIPTION: Project # 92510405 Department Arterial Streets Improve the existing bike lanes and crosswalks on Southcenter Blvd within a half -mile of Tukwila International Boulevard Station (TIBS). Re-channelize to 11 ft general purpose lanes to accommodate separated (tuff curb and post) bike lanes. Tighten intersection with 40th Ave S to shorten crossing distance. Add bike channelization and upgrade to high -visibility crosswalk markings at Southcenter Blvd/TIBS station entrance and Southcenter Blvd/42nd Ave S intersections. Sound Transit is improving non -motorized connections near the Link Light Rail station. Visual separation of JUSTIFICATION: existing bike facilities and the travel lane will improve safety and visibility of bicyclists. Shortening pedestrian crossing lengths at intersections and improving crosswalk visibility improves pedestrian safety. STATUS: New project in 2025 MAINTENANCE IMPACT: Increased costs to Streets for maintenance of the bicycle separators (tuff curb & post or similar) and paint. COMMENT: Funding provided by Sound Transit through ST3. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 65 65 2026 248 325 325 2027 2028 2029 2030 $ - $ - Beyond TOTAL 248 390 390 16 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Americans with Disabilities Act (ADA) Improvements Project Manager Adam Cox Project # 91510405 Department Arterial Streets DESCRIPTION: Construct ADA compliant upgrades to City infrastructure in conjunction with a City developed plan JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The enforcement of ADA laws and standards was delayed pending legal challenges and studies. Recent court rulings now mandate ADA compliance. The City must provide upgrades with most construction projects. Provide annual funding to construct improvements as necessary. Began the ADA Transition Plan in 2016 with adoption in 2017. The goal is to resolve ADA compliance issues within a reasonable time period N/A Project will be ongoing until City facilities and infrastructure meet ADA requirements. This will also include ADA compliance by utilities and private development. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 1 50 61 61 61 2026 $ 1 50 61 61 61 2027 $ 1 50 61 61 61 2028 $ 1 $ 50 61 61 61 2029 $ 1 50 61 61 61 2030 $ 1 $ 50 $ 61 $ 61 $ 61 Beyond $ 1 50 61 61 61 TOTAL 7 350 427 427 427 17 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Mark Hafs Allentown Truck Reroute Environmental Impact Statement City Project Department Arterial Streets Project# 92110405 The project entails studying alternatives for rerouting freight trucks that currently use the Allentown neighborhood to access the BNSF yard on Allentown's east side. Upcoming work will include evaluating existing conditions in the project area, determining the impacts that the proposed reroute alternatives could have on the project area, and documenting the results of these studies in an environmental impact statement, as required by Washington State's State Environmental Policy Act. The impacts of the 1,000-plus freight truck trips made through Allentown on a typical day - noise, vibration, diesel fumes, traffic, water surface water contamination, concerns for pedestrian and bicyclist safety, etc. - are not compatibleAllentown's residential and public park land uses. The project is within budget and project work is expected to be complete in early Q1 2025. N/A The project has a very high level of complexity, with project elements that include traffic engineering, civil engineering, wildlife ecology, surface and storm water, historic preservation, public health, environmental justice, pedestrian safety, noise and vibration, visual resource analysis, public open space protection, land use planning, public engagement, etc. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 10 $ 40 50 50 50 2026 2027 2028 2029 2030 Beyond TOTAL $ 10 $ 40 50 50 50 18 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Transportation Element of Comprehensive Plan Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72010405 Department Arterial Streets Update Transportation Element of the Comprehensive Plan to include updated traffic model and street network plan. Growth Management Act transportation concurrency and traffic impact mitigations need updated traffic and capital planning. Adoption by 2032 required by Community Trade and Economic Development (CTED). Update every 8 years. Transportation Element will be coordinated with updates to Comprehensive Plan by the Department of Community Development. Next update is scheduled for 2032. N/A Work begins 1-2 years in advance of Comp Plan Element updates. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 2027 2028 $ 2029 $ 17 117 17 $ 117 2030 $ 17 $ - $ 417 $ 17 $ 417 Beyond $ 17 $ 417 400 TOTAL 51 $ 951 34 934 19 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager David Baus DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Interurban Avenue S Overlay Project # 82510403 Department Arterial Streets Complete pavement repairs, overlay, and curb and gutter repair Preserve and maintain the street structure in a safe and useable state by resurfacing before failure which also minimizes costs. Project was awarded full funding by National Highway Performance Program January of 2024 1,300 staff hours not needed to fill in potholes/crack sealing Construction must be completed as a single contract and authorized by August 31, 2026. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 $ 50 447 50 447 2027 $ 50 $ 3,650 $ 4,610 49 $ 4,610 2028 2029 2030 Beyond TOTAL $ 100 $ 3,650 5,057 99 5,057 20 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 144th St Bridge - Sidewalks Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 90310404 Department Arterial Streets Design of pedestrian improvements to the S 144th Street bridge over 1-5, to include structural, civil, environmental, and traffic design to obtain PS&E. Project will widen the existing pedestrian pathway on the bridge from three feet to six feet with a barrier to separate automobile and pedestrian traffic. Improve pedestrian safety, particularly for Foster High School and Showalter Middle School students. Design work to determine feasibility of widening the sidewalk on the existing bridge over 1-5 and gain WSDOT approval. If feasible, construction funding will need to be identified. Streets may have nominal increases to maintenance due to additional sidewalk width and new striping. New approach is to widen the sidewalks on the existing bridge instead of modifying the bridge to provide extra width as was originally proposed. Grant applications submitted in 2013, 2016 and 2018 were unsuccessful. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 $ 30 609 109 $ 609 2027 $ 30 $ 2,055 $ 2,720 $ 30 $ 2,720 2028 2029 2030 $ - $ - $ Beyond TOTAL 60 2,055 3,329 $ 139 3,329 21 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Andover Park E/Minkler Blvd Intersection Project Manager Cyndy Knighton Project # 90310405 Department Arterial Streets DESCRIPTION: Design and construct left turn lanes on Andover Park East and reconstruct traffic signal. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Improve safety and provide needed capacity. Design completed to 60% in 2015. Project on hold pending additional funding. Streets will be responsible for road, striping and signal maintenance. Amount change is negligible. Project is on Traffic impact fee list. Mitigation of $19,622.55 from Westfield Mali. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 $ 13 278 13 278 2027 $ 13 $ 1,840 $ 2,413 493 $ 2,413 2028 2029 2030 $ - $ - $ Beyond TOTAL 26 1,840 2,691 506 2,691 22 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 124th St/50th Pl S Reconfiguration Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 92510402 Department Arterial Streets Reconfigure intersection to remove EB slip lane, new c/g/s on S 124th from 49th to 51 st, new paved shoulder walkway on south side of 124th connecting to existing walkway on west side of 50th Pl, new stormwater treatment/rain garden in old slip lane ROW. Project can be done in phases, with phase 1 including just the intersection reconfiguration and phase 2 including the sidewalk on S 124th but cost would be greater. Removing the free -flow right turn movement will improve safety at the S 125th St/50th Pl S intersection and generally on S 124th St and 50th PLS. Narrowing pedestrian crossing distance at the intersection and improving pedestrian facilities will improve safety and livability for the neighborhood. Identified in the Allentown Neighborhood Transportation Study in 2022. New project for 2025 Minor impacts to Streets for additional sidewalk. Increases to Surface Water with maintenance of storm water treatment facilities. If project is done in phases, the stand-alone sidewalk project could be double the cost of including them in a single project. Approximate estimate in 2024 dollars is $600k for construction and design and construction management costs approaching $250k. Phasing the project may be necessary due to funding constraints. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 275 $ 275 $ 275 2027 $ 1,350 $ 1,830 $ 1,830 2028 2029 2030 $ - $ - Beyond TOTAL 1,350 2,105 275 2,105 23 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Minkler Blvd (Andover Park W - Southcenter Pkwy) Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 98410407 Department Arterial Streets Widen Minkler Blvd from Andover Park West to Southcenter Parkway. Add third lane and curb, gutter, and sidewalk on the south side. Accommodate anticipated future development frontal improvements to complete three lane street section Construction of half street road to Southcenter Pkwy with 2 lanes, sidewalks on one side with water, sewer & drainage improvements in 1995. North side completed by Southcenter Square frontage in 2008 Minor addition for maintenance of widened pavement. Remaining improvements on south side of Minkler are anticipated to occur with future redevelopment. On Traffic Impact Fee List FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 2027 2028 2029 $ 15 $ - 385 15 385 2030 $ 15 $2,095 $2,850 $2,850 Beyond TOTAL 30 2,095 3,235 15 3,235 24 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: E Marginal Way S (BAR - S 112 St) Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 98910405 Department Arterial Streets Design and construct curb, gutter, drainage, lighting, turn lanes, and traffic control. Safety, capacity, and drainage items needed to serve this area of increasing vehicle and pedestrian traffic. Design feasibility report began in 2014 to identify infrastructure needs over the next 20 year. The west half of the road was improved by Sound Transit with the Light Rail construction. Streets will have nominal increase in maintenance costs due to additional pavement and potentially for new traffic control. Surface Water will see a small reduction with improved drainage. Project is on impact fee list for only the design costs. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 2026 $ 13 88 13 $ 88 2027 $ 2028 2029 2030 Beyond TOTAL 13 88 13 88 25 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Andover Park East/Industry Dr Intersection Project Manager Cyndy Knighton Project # 99110405 Department Arterial Streets DESCRIPTION: Design and construct traffic signal with Andover Park East left turn lanes and crosswalks. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Signal control and left turn lanes will improve safety and provide needed capacity. Design completed to 60% in 2015. Project on hold pending additional funding. Streets will have small increase in staff time for routine signal maintenance work and may see nominal increase due to striping. Project is on Traffic impact fee list. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 $ 13 193 13 193 2027 $ 13 $ 1,100 $ 1,413 193 $ 1,413 2028 2029 2030 $ - $ - $ Beyond $ TOTAL 26 1,100 1,606 206 1,606 26 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 133 St/SR599 Southbound Intersection Project Manager Cyndy Knighton DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 99510405 Department Arterial Streets Design and construct intersection improvements, which could include a new roundabout, lighting, pedestrian facilities, and drainage. Intersection level of service is degrading without improvement. Traffic Study and feasibility analysis recommended roundabout, not a traffic signal, as project. Project is in WSDOT limited access area. Increase to Streets to maintain landscaping, if installed, including irrigation costs. Project is on impact fee list. ROW is available for conversion to a roundabout. WSDOT supports roundabouts in lieu of signalization, where appropriate. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 2027 2028 $ 30 580 580 2029 $ 30 $ 2,070 $ 2,730 30 $ 2,730 2030 $ - $ - Beyond TOTAL 60 2,070 3,310 30 3,310 27 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) Parks and Trails (301) JL Key Project Name 92330301 TCC HVAC Replacement Project 92030101 Tukwila Pond Master Plan 91730103 Park & Open Space Acquisition 71330101 Parks, Recreation, & Open Space Plan 82530104 Park Signage, kiosk, and wayfinding improvements 92530106 Trail and Park Lighting 32401501 Crystal Springs Park Lighting Replacement 92530103 Green River Trail to Chief Sealth Trail Connection 82530102 Numbered Trail Improvements 82530106 Playground impact attenuation surfacing replacement 82530105 Parks Events Setup Retrofits 11601500 Trail/Park/Parking Lot Pavement 11930151 MunicipalArts Fund 72530101 Comprehensive Park Master Planning 2030 • $860 $860 After six years $- $1,800 $- Total Costs $- $1,720 $15,100 $215 $215 $- $215 $- $215 $860 $- $200 $50 $- $- $- $- $250 $- $170 $140 $- $- $- $- $310 $- $160 $320 $- $- $- $- $480 $- $150 $50 $150 $- $- $- $350 $- $125 $125 $1,075 $1,075 $- $- $2,400 $- $100 $100 $100 $100 $100 $100 $600 $100 $61 $61 $61 $61 $61 $61 $366 $25 $60 $- $60 $- $60 $- $180 $60 $50 $50 $50 $50 $50 $50 $300 $50 $50 $50 $50 $50 $50 $50 $300 $50 $50 $50 $50 $50 $50 $50 $300 $- CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM 82530107 82530108 92530102 72530102 Riverton Park $46 I $- Green waste haul out Riverton Park $25 $1,343 Playground Renovation Crystal Springs $15 $680 Playground Replacement Crestview Park $- $- Master Plan ;46 I $46 $138 $46 $- $- $1,600 $600 $- $1,368 $695 $2,200 $- $- $- 72530103 Joseph Foster $- $1,845 $1,725 $1,725 $- $- $5,295 $- Memorial Park Master Plan 72530301 Tukwila Community Center Campus Master Plan 82530101 Green River Trail $- $- $50 Facility Improvements 92530104 S 116th St Parcel $- $145 $145 $- $- $- $290 $- Improvements 92530105 TCC Fitness $- $- $200 $- $- $- $200 $- Facilities remodel $- $410 $3,160 $2,170 $2,145 $2,145 $10,030 $50 $50 $50 $200 $- $50 Total $4,137 $6,494 $6,922 $7,146 $3,212 $2,721 $30,632 $15,481 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: TCC HVAC Replacement Project Project Manager Shawn Christie DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 92330301 Department Parks &Trails Complete rehabilitation, renovation, and in some areas replacement of the Tukwila Community Center Heating, Ventilation, & Air Conditioning (HVAC) system. This will include efficiency upgrades as well as the addition of cooling to the Tukwila Community Center gymnasium. The Tukwila Community Center was built in 1997 and is still utilizing its original HVAC system, whose various components are now either at or beyond their expected service life. The system's overall stability and efficiency are currently lacking and present operational risks for the Community Center's operations. Furthermore, lack of stable cooling/heating systems on site hinder the Community Center's potential for usage as a heating/cooling shelter during an extreme weather event. In Progress - Phase 1 (Controls Upgrade & Boiler Replacement) was approved by City Council in May 2024. Funding for further Phases is currently being sought. It is my current understanding that the replacement of the HVAC system may reduce operational expenses for the Tukwila Community Center by tens of thousands of dollars annually as electrical and natural gas savings are recognized. This is not to mention potential staff time (and thus staff wage/benefits savings) saved through lower maintenance callout frequency as well as lower contractor callout frequency for service on site. Expenses already incurred in 2024 are listed as 2025 expenses for transparency. Completion of this project is necessary to ensure operations delivery readiness at Tukwila Community Center as well as to maintain an adequate customer and staff experience on site. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Proposed Grant Dedicated/Restricted Rev Total Project Funding 2025 $ 50 $ 150 $ 200 $ 1,356 $ 44 $ 1,800 $ 1,315 $ 485 $ 1,800 2026 2027 2028 2029 2030 $ - $ - Beyond TOTAL 50 150 200 1,356 44 1,800 $ 1,315 485 1,800 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Tukwila Pond Master Plan Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: Project # 92030101 Department Parks &Trails Master planning, designing, and developing the Tukwila Pond Park in coordination with surrounding property developments and in response to the community. Provides improved access to open spaces, gathering places, and enhances the Tukwila Urban Center for greater cultural, economic, and recreation activity. Activation of the site also meets the city's CPTED design as well as surface water and other environmental/conservation goals. STATUS: Master Plan is complete. Staff are seeking funding to support a phased approach to the project. MAINTENANCE IMPACT: COMMENT: Site is approximately 24.77 acres per KC Parcel Viewer, about half of which is the "pond" itself so this assumes the other half is what must be actively maintained which may still be an overage as most of that may be just woodland/forestland. Regardless, NRPA Agency Review statistics state the median cost per acre of actively maintained park is $8,260, multiplied out gives us the number provided in previous answer. Project is on Park Impact Fee list at 75%. Wetland mitigation of $86,000 from WIG Properties & a 2008 KC grant for buffer enhancement. 1 % Municipal Arts Fund for City funded construction included. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Awarded Grant Proposed Grant Dedicated/Restricted Rev Fund Balance Utility Revenues Total Project Funding 2025 $ 10 250 100 500 860 $ 25 250 370 215 860 2026 $ 10 250 100 500 860 250 395 215 860 2027 2028 2029 2030 Beyond $ 100 $ 1,440 $ 500 $ 500 $ 1,650 $ 10,910 $ 15,100 $ - $ 7,000 $ 3,000 $ 3,100 $ 2,000 $ 15,100 TOTAL $ 120 $ 1,440 $ 500 $ 1,000 $ 1,850 $ 11,910 $ 16,820 25 7,000 3,500 3,865 2,430 $ 16,820 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKVVILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Park & Open Space Acquisition Project* 9173D103 Kris Kelly Department Parks & Trails Acquisition of Land to preserve open space or park Land for future generations. Focus areas are identified by the Parks, Recreation, & Open Space (PROS) PLan. There are recreational deserts within Tukwila, defined es areas more than a 10-minute weLk from a quality park. The City desires to provide equitable access to a quality park for all TukwiLe residents and acquisition of key properties is needed. ALso, open spaces are continuaLLy being deveLoped and need to be preserved for future generations. To support new deveLopment within the city, and the increase of population associated with development (housing, work, or Leisure), additionaL recreational spaces need to be provided to support those that Live, work, and pLey in TukwiLa. Staff continue to monitor parceLsthat are put on the market within the city Limits. The estimate above is for a smaller parceL (Up to 0.5 acres) to be maintained at its current state of undeveLoped Land. This does NOT reflect the M&O costs of acquired parcels once they have been deveLoped. Project is on the Park Impact Fee List. Neighborhoods of interest where current park/recreation gaps exist include northern Cascade View, the southern end of the Urban Center, Thorndyke directLy north of SR-518, and Ryan HILL. FINANCIAL (in thousands) Project Costs Planning Land (R!W) Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 15 $ 200 $ 215 $ 215 $ 215 2029 $ 15 $ 200 $ 215 $ 215 $ 215 2027 $ $ $ $ 2028 $ 15 $ 200 $ 215 $ 215 $ 215 2029 $ $ $ $ 2030 $ 15 $ 200 $ 215 $ 215 $ 215 Beyond $ $ $ $ TOTAL S 60 800 860 $ 860 $ 860 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Parks, Recreation, & Open Space Plan Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 71330101 Department Parks &Trails Prepare a citywide Parks, Recreation and Open Space Plan. A current six -year Parks, Recreation, & Open Space (PROS) Plan is required to be eligible to apply for any state and federal park grants, and also serves as a planning document for the Parks & Recreation Department. RFP for Consultant Will Occur in Q4 2024 It is possible that the PROS Plan could inform necessary service levels of parks, but that impact is indeterminate at this time. This is a planning tool crucial for planning of Parks & Recreation system improvements as well as overall operations. FINANCIAL (in thousands) Project Costs Design Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 200 200 200 200 2026 50 50 50 50 2027 2028 2029 2030 Beyond TOTAL 250 250 250 250 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Park Signage, kiosk, and wayfinding improvements Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: Project # 82530104 Department Parks &Trails Design, planning, and Installation of new park signage, information kiosks, and wayfinding. The lack of wayfinding was a need that was outlined in the PROS plan, having a common style and wayfinding would benefit park users and help with branding within the city. Kiosk will help inform park users of amenities, and opportunities within the area. STATUS: We are currently working with OTAK for trail masterplanning and wayfinding . MAINTENANCE IMPACT: COMMENT: Maintenance of signage will be performed by park staff and will likely require maintenance work such as pressure washing, graffiti removal and misc. repairs. As identified in the PROS plan wayfinding is a crucial component that is missing within the park system. Common style in signage also helps users identify with the branding of the city and recognize that they are enjoying an amenity that the city has to offer and helps ground users in what it means to be a part of Tukwila. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Construction Contingency Total Project Costs Project Funding Fund Balance Total Project Funding 2025 10 40 10 100 10 $ 170 170 170 2026 10 140 140 140 2027 2028 2029 2030 Beyond TOTAL 20 60 10 200 20 310 310 310 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Matthew Austin DESCRIPTION: Trail and Park Lighting Project # 92530106 Department Parks &Trails Park trail and lighting improvements have been identified by the community in surveys for the previous and current PROS Plans. Much of the Green River trail as it passes through the Southcenter area from approximately Fort Dent Park to 180th has sufficient sun exposure to allow for the use of solar powered lighting on the trail. The lighting identified would enhance the look and feel of the trail in the Southcenter area and enhance the corridor. JUSTIFICATION: Lighting improvements were identified in the PROS plan STATUS: Planning MAINTENANCE IMPACT: Maintenance of the lighting will likely be on demand. COMMENT: Improved visibility for trail users, especially at night or during low -light conditions and can help prevent accidents Like tripping or collisions with other users. Lighting can deter crime and make users feel safer and a generally accepted CPTED approach. Accessibility: Lighting can make trails more accessible for people with limited vision or who are uncomfortable using unlit trails. Usability: Extends the usable hours of the trail. allowing people to eniov it after dark. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Construction Mgmt. Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 10 30 10 10 100 $ 160 160 160 2026 300 320 320 $ 320 2027 $ 2028 $ 2029 $ 2030 Beyond $ TOTAL 20 30 20 10 400 480 480 $ 480 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Crystal Springs Park Lighting Replacement Project# 32401501 Project Manager Matthew Austin Department Parks & Trails DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Replacement/Rehabilitation of lighting at the upper and lower levels of Crystal Springs Park New/Improved lighting on site at Crystal Springs Park supports cityCPTED goals, increasing park activation and park user safety on site. Funding has been secured through the RCO Local Parks Maintenance Grant to partially fund a portion of the project. This work is currently being done, but further funding must be found and secured. New lighting may actually decrease M&O expenses on site due to greater reliability. N/A FINANCIAL (in thousands) Project Costs Design Construction Total Project Costs Project Funding Awarded Grant Proposed Grant Fund Balance Total Project Funding 2025 $ 150 150 $ 76 $ - $ 74 150 2026 $ 50 50 50 50 2027 $ $ 150 150 $ 150 150 2028 2029 2030 $ Beyond $ TOTAL $ 50 300 350 76 150 124 350 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Green River Trail to Chief Sealth Trail Connection Project # Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: 92530103 Department Parks &Trails Study, Design, Permitting, and Construction of pedestrian/bike facilities between the Green River Trail in Tukwila to the future Boeing Access Road Light Rail Station (Set to open in 2031) and then to the Chief Sealth Trail terminus located in Seattle. Connection of these two trails satisfies PROS Plan and other comprehensive planning documents/plans within the City of Tukwila, City of Seattle, Sound Transit, and King County portfolios. Integration between the multiple transit facilities would allow for greater accessibility to multiple recreation, residential, and commercial areas throughout the surrounding areas. STATUS: This project has been proposed between the multiple jurisdictions and is in concept/fund seeking stage. MAINTENANCE IMPACT: COMMENT: Complete estimate. Preliminary discussions have been had with parties from the Seattle Department of Transportation, King County Department of Natural Resources and Parks, Sound Transit, and the City of Tukwila with all parties expressing an interest in this project's viability and benefits to all communities involved. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Construction Mgmt. Construction Total Project Costs Project Funding Proposed Grant Total Project Funding 2025 $ 25 $ 100 125 $ 125 $ 125 2026 $ 25 $ 100 $ - 125 $ 125 $ 125 2027 $ 1,075 $ 1,075 $ 1,075 2028 $ 25 $ - $ 50 $ 1,000 $ 1,075 $ 1,075 $ 1,075 2029 2030 Beyond TOTAL 100 100 100 100 2,000 2,400 $ 2,400 2,400 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Numbered Trail Improvements Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 82530102 Department Parks &Trails Wide array of necessary trail improvements to the existing numbered trail system infrastructure. Renovate trails that improve neighborhood and community access and connectivity. Repair trails with decreased functionality and/or safety issues. Acquire easements where needed. Manage property issues such as encroachments, donations, rights -of -entry, and leases. Pursue local and regional multi -modal connectivity. Facilitate design and construction of active transportation improvements consistent with the City's update to the Tukwila Transportation Element. Numbered Trails are in place throughout the City of Tukwila that assist in walkability of multiple neighborhoods. Trail usage, safety, ease of use, and ease of maintenance can be improved with more investment in their facilities. Funding must be identified and projects prioritized. In theory, improved facilities/assets could call for more maintenance, but said improvements could also offset current maintenance needs/callouts currently serviced by the Parks Maintenance team. Project may be eligible for Park Impact Fee usage and/or Puget Sound Regional Council Transportation funding. FINANCIAL (in thousands) Project Costs Design Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 50 $ 50 100 100 100 2026 $ 50 $ 50 100 100 100 2027 $ 50 $ 50 100 100 100 2028 $ 50 $ 50 100 100 100 2029 $ 50 $ 50 100 100 100 2030 $ 50 $ 50 $ 100 $ 100 $ 100 Beyond $ 50 $ 50 100 100 100 TOTAL $ 350 $ 350 700 700 700 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Parks Events Setup Retrofits Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: Project # 82530105 Department Parks &Trails The retrofitting of parks/open spaces throughout the city parks system for electric and sound systems utilized during parks and/or other public/community events. Hosting events in parks is currently hindered by not having proper electric and sound system setups conducive to optimal equipment deployment and ease of use. Installation of utilities and systems that streamline this process will make park event activation easier and improve overall usability of the locations for said events. STATUS: Concept Phase, staff will continue to research feasibility and prioritization of various park sites MAINTENANCE IMPACT: COMMENT: Indeterminate at this time. May be minimal to zero as these systems once installed likely do not require much in the way of ongoing maintenance as long as they are not vandalized. Currently, event setups require noisy and emission producing generators for powering necessary systems and likely increase costs of putting events on due to relying on vendors to provide their own systems/setups. Park activation would be made much easier for all involved with professional systems put in place. FINANCIAL (in thousands) Project Costs Design Planning Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 5 $ 5 $ 50 $ 60 $ 60 $ 60 2026 $ $ 2027 $ 5 $ 5 $ 50 $ 60 60 $ 60 2028 $ $ 2029 5 5 50 $ 60 $ 60 $ 60 2030 $ - $ - $ - Beyond 5 5 50 $ 60 60 $ 60 TOTAL 20 20 200 240 240 $ 240 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKVVILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Playground impact attenuation surfacing replacement Project Manager Matthew Austin Project wiLL consist of removing engineered wood fiber at parks that are not due to be replaced within the next 5 years. Fort Dent Park, Lee PhiLLips fieLd(Joseph Foster Park), BicentenniaL Park, TukwiLa Community DESCRIPTION: Center, Duwamish Park, and Riverton Park. IncLudes a overLayof Engineered wood fiber at the remaining parks on an annuaL basis. Project # 82536106 JUSTIFICATION: Department Parks & Trails Playgrounds periodicaLLy receive fresh EWF to maintain impact attenuation, after a severaL applications the materiaL at the bottom affects drainage and Lowers the impact attenuation of the drainage. Overtime as the materiaL ages and drainage is compromised the existing Lower Levels of EWFwiLL harden and greatLy decrease the impact attenuation and increase the chances for injury. Performing a compLete repLacement must be done periodicaLLy when the drainage becomes compromised to ensure a safe impact attenuation is maintained within the faLLzones around the pLay structures. EWFthat is added overtime in non compromised areas helps maintain impact attenuation of the fall zones. STATUS: The Last reapplication of EWF was performed in 2023 and will need to be done again in 2025. Periodic inspection of the playgrounds is not considered part of this project. The inspection and MAINTENANCE IMPACT: maintenance of the playgrounds are separate of this request. This request is entireLyforthe EWF and drainage onLy. ParkswiLL be responsibLeforthe ongoing inspection and maintenance related to that. COMMENT: Maintaining the impact attenuation with proper EWF Levels is keyto keeping playgrounds safe to use. Once drainage and hauL out is complete itwiLL Likely be sometime before infiLL and drainage will need to be repaired or replaced, but this wiLL be continued to be monitored in our periodic inspections. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 1 $ 60 $ 61 $ 61 $ 61 2026 $ 1 $ 60 $ 61 $ 61 61 2027 $ 1 $ 60 $ 61 $ 61 $ 61 2028 $ 1 $ 60 $ 61 $ 61 61 2029 $ 1 $ 60 $ 61 $ 61 $ 61 $ 1 $ 60 $ 61 $ 61 $ 61 Beyond $ $ 25 $ 25 $ TOTAL $ 6 $ 385 $ 391 $ 366 $ 366 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Trail/Park/Parking Lot Pavement Repair & Trip Hazard Mitigation Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 11601500 Department Parks &Trails Assessment and mitigation of trip hazards throughout parks and trails to mitigate risk and liability exposure to the city and maximize recreational user safety of said facilities. Failure to properly maintain city park and trail facilities with known trip hazards exposes the city to costly litigation from potential injuries. Staff actively identify and monitor trip hazards throughout the parks system for annual grinding, repaving, and other mitigating work to be performed. Ideally, costs for this work can be contained by annual revenue sources within Fund 301 such as the King County Parks Levy. Staff time devoted to this work would be limited to the identification aspect and contract management which is already captured within the day-to-day workload. This work is only one aspect of risk management that should be exercised by the city. Proper lighting, signage, bollard installation, and other risk mitigating assets must also be installed, maintained, and identified to users to adequately reduce and/or mitigate risk to said user. FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 50 50 50 50 2026 50 50 50 50 2027 50 50 50 50 2028 50 50 50 50 2029 50 50 50 50 2030 $ 50 $ 50 $ 50 $ 50 Beyond 50 50 50 50 TOTAL 350 350 350 350 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Kris Kelly DESCRIPTION: Municipal Arts Fund Project # 11930151 Department Parks &Trails The Municipal Arts Fund captures 1 % of qualifying Capital Improvement Project funds not otherwise integrated into Capital Projects. The Fund supports the acquisition and advancement of public art within the City of Tukwila. Projects include the Utility Box Arts Program, art installations within parks and other city facilities, and public arts programming. JUSTIFICATION: Tukwila Municipal Code 2.30.050 STATUS: Funding is determined on a biennium basis and is spent based on the Tukwila Arts Strategic Plan MAINTENANCE IMPACT: COMMENT: Indeterminant at this time but it is plausible that art installations could be vandalized, requiring repair that would fall upon the General Fund. N/A FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 50 50 50 50 2026 50 50 50 50 2027 50 50 50 50 2028 50 50 50 50 2029 $ 50 50 50 50 2030 $ 50 $ 50 $ 50 $ 50 Beyond $ 50 50 50 50 TOTAL $ 350 350 350 350 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Comprehensive Park Master Planning Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: Project # 72530101 Department Parks &Trails The park master plans will be used to help support Tukwila Parks in procuring local and state grants and use of Real Estate Excise Tax (REET) and Park Impact Fee (PIF) funding sources to construct the proposed park improvements. As well as permitting assistance, construction documents, estimation of probable construction cost, bidding assistance and construction phase services. Work will include but not be limited to the following tasks: Park master planning will ensure that parks are purpose built with community feedback. Master plans and facility design are needed to provide additional design guidance on all projects and help ensure they adhere to national, state and local regulations. Master plans are a crucial aid in obtaining grants and other funding mechanisms to ensure funds are fully maximized and fit the intended users. Master planning would start with Bicentennial Park, then Cascade view Community Park, followed By Tukwila Park, Green River/Interurban Trail, Crystal Springs park. Project could be added to existing on call and masterplanning services that are currently under contract or go out to bid again. MAINTENANCE IMPACT: This is for the acquisition of planning documents to aid in grant proposals and requests. COMMENT: Park master planning will ensure that parks are purpose built with community feedback. Master plans and facility design are needed to provide additional design guidance on all projects and help ensure they adhere to national, state and local regulations. Master plans are a crucial aid in obtaining grants and other funding mechanisms to ensure funds are fully maximized and fit the intended users. FINANCIAL (in thousands) Project Costs Design Total Project Costs Project Funding Fund Balance Total Project Funding 2025 50 50 50 $ 50 2026 50 50 50 $ 50 2027 50 50 50 $ 50 2028 50 50 50 $ 50 2029 50 50 50 $ 50 2030 $ 50 $ 50 $ 50 $ 50 Beyond TOTAL 300 300 300 300 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Riverton Park Green waste haul out Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: Project # 82530107 Department Parks &Trails Project will consist of removing the green waste that has accumulated over the last 2 years and taking it to a facility to process, estimated cost 45k every 2 years. The Riverton green waste/compost area is quickly reaching capacity and will need hauling out beginning 2025, and every 2 years there after. STATUS: Project is waiting for funding and bidding/contractor selection can be done in a relatively short period of time. MAINTENANCE IMPACT: COMMENT: Parks is responsible for the management of the location, cycling the debris pile and pushing it back when needed. This is the primary M&O aside from the periodic haul out. With the addition of the lake to sound connection to the green river trait at Fort Dent, and the planned sate of the George long facility, The parks department lost it's two locations in which green waste would be stored, composted and periodically hauled out. This left the selection of the Gully Gardens/Riverton park green waste storage area which the parks department has been utilizing to store all green waste such as storm debris, grass clippings, leaves collected, etc. FINANCIAL (in thousands) Project Costs Construction Mgmt. Construction Total Project Costs Project Funding Dedicated/Restricted Rev General Fund Transfer Total Project Funding 2025 $ 1 $ 45 46 $ 46 46 2026 2027 $ 1 $ 45 46 $ 46 46 2028 2029 $ 1 45 46 46 46 2030 $ - $ - $ - $ - Beyond $ 1 45 46 46 46 TOTAL 4 180 184 92 92 184 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Riverton Park Playground Renovation Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: Project # 82530108 Department Parks &Trails Replacement, renovation, addition, and/or improvement of amenities within Riverton Park informed by the 2020 PROS Plan as well as consultant design services performed by the firm GGLO. The project will focus on increasing activation and overall capacity of the parks and its facilities. Improvements a full playground and picnic shelter replacement, new walk path installation, installation of more tree canopy and understory flora, and replacement of picnic tables, park benches, garbage cans, and BBQ grills. Riverton Park is the only local park within the immediate area for access within the Riverton neighborhood. Its current playground, furnishings, and overall asset setup are outdated. A full replacement of the playground and furnishings in the northern half of the park will provide for greater recreation capacity, variability, and access. STATUS: Renovation plan has been completed, funding is currently being sought through state grant programs Increased tree canopy and plants on site may slightly increase overall M&O costs of maintain. However, this is MAINTENANCE IMPACT: likely offset by reduced maintenance needs presented by new amenities requiring less on-demand/responsive maintenance. COMMENT: Project is on the Park Impact Fee list. Status of current grants being sought will be determined in FY 2025. FINANCIAL (in thousands) Project Costs Construction Mgmt. Construction Mitigation Total Project Costs Project Funding Proposed Grant Dedicated/Restricted Rev Total Project Funding 2025 $ 25 25 25 25 2026 $ 50 $ 1,293 $ - $ 1,343 $ 500 843 $ 1,343 2027 2028 2029 2030 $ - $ - $ - $ - $ - Beyond TOTAL 50 1,293 25 1,368 $ 500 868 1,368 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Crystal Springs Playground Replacement Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: Project # 92530102 Department Parks &Trails Playground location and features have become out dated and is currently past it's planned replacement. Replacing the playground would give an opportunity to redesign the layout of the park to ensure that playground users do not need to cross a street to use the restroom. In addtion to this it would allow the park users to have a centralized play structure and recreation area. The replacement would also allow for an opportunity to integrate Inclusive play within the play structure. The current structure and location is not easily accessible. Pre -Planning MAINTENANCE IMPACT: The M&O is similar to the existing structure and would result in a wash, Parks is responsible for the maintenance COMMENT: The replacement of the playground was due in FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Construction Contingency Total Project Costs Project Funding Proposed Grant Fund Balance Total Project Funding 2025 $ 15 15 2026 $ 10 10 600 60 680 $ 660 35 695 2027 2028 2029 2030 $ - $ - Beyond TOTAL 10 15 10 600 60 695 $ 660 35 695 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Crestview Park Master Plan Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72530102 Department Parks &Trails Replacement, renovation, addition, and/or improvement of amenities throughout Crestview Park informed by the 2020 PROS Plan as well as a master plan produced in consultation with the firm GGLO. The project will focus on increasing activation and overall capacity of the park. Improvements include a full playground and picnic shelter rehabilitation/replacement, new walk paths and landscaping installation and grading, installation of more tree canopy and understory flora, replacement of furnsihings, and more. Crestview Park has the needed physical space for greater amenities that will lead to higher activation/usage in the park. Master plan is completed and work estimates have been generated. Funding is being sought for project execution at this time. Installation of new park amenities not previously in place will necessitate greater M&O investment from the General Fund. The above amount is an estimate of this impact. Project is on Park Impact Fee list FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning Construction Mgmt. Construction Total Project Costs Project Funding Proposed Grant Total Project Funding 2025 2026 2027 2028 $ 50 $ 50 $ 1,500 $ 1,600 $ 1,600 $ 1,600 2029 $ 50 $ 50 500 600 600 600 2030 Beyond TOTAL 50 50 100 2,000 2,200 2,200 2,200 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Joseph Foster Memorial Park Master Plan Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72530103 Department Parks &Trails Replacement, renovation, addition, and/or improvement of amenities within Joseph Foster Memorial Park informed by the 2020 PROS Plan as well as consultant design services performed by the Berger Partnership. The project will focus on increasing activation and overall capacity of the parks and its facilities. Improvements include turf field, lighting, and overall athletic facility installation, new pickleball and sport court installation, walk path installation/improvement, installation of more tree canopy and understory flora, potential street vacation, replacement of park furnishings, and other improvements. Joseph Foster Memorial Park's current physical asset setup/condition is not conducive to year-round activation/usage of the park, improvements such as those proposed within the created Master Plan will allow for recreation staff to more adequately program the park as well as provide for communal usage at much higher rates and variability. Master plan has been completed, funding for project execution is currently being sought through state and county grant programs. Installation of additional assets within the park will require higher levels of maintenance than is currently required. The amount provided is an estimate. N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning Land (R/w) Construction Mgmt. Construction Total Project Costs Project Funding Proposed Grant Total Project Funding 2025 2026 $ 50 $ 25 $ - $ 50 $ 1,720 $ 1,845 $ 1,845 $ 1,845 2027 $ 50 $ 25 $ 100 $ 50 $ 1,500 $ 1,725 $ 1,725 $ 1,725 2028 $ 50 $ 25 $ 100 $ 50 $ 1,500 $ 1,725 $ 1,725 $ 1,725 2029 2030 Beyond TOTAL 150 75 200 150 4,720 5,295 5,295 5,295 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Tukwila Community Center Campus Master Plan Project# Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: 72530301 Department Parks &Trails Replacement, renovation, addition, and/or improvement of amenities throughout the Tukwila Community Center Campus informed by the 2020 PROS Plan as well as a master plan produced in consultation with the Berger Partnership. The project will focus on increasing activation and overall capacity of the TCC Campus. Improvements are split into multiple two overarching sections of campus, one being the riverside campus on its southern half and the other being the upland campus on its northern half. Improvements include a full playground and picnic shelter replacement, new walk path and boardwalk installation and grading, installation of more tree The Tukwila Community Center is the most used recreation asset within the Tukwila parks system per the 2020 PROS Plan, creating recreation capacity, variability, and accessibility on campus is critical for providing a full recreation experience to users of the community center. STATUS: Master planning work is complete, grant funding is currently being sought for phases of the project. MAINTENANCE IMPACT: COMMENT: Inclusion of more amenities on site is reasonably estimated to call for greater M&O investment on an annual basis to maintain said assets. The number above is a base estimate at this time. Project is on Park Impact Fee list. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning Construction Mitigation Total Project Costs Project Funding Proposed Grant Fund Balance Total Project Funding 2025 2026 25 25 335 25 $ 410 $ 410 410 2027 $ 3,160 $ 1,375 $ 1,785 $ 3,160 2028 $ 25 $ 25 $ 2,120 $ - $ 2,170 $ 500 $ 1,670 $ 2,170 2029 $ 2,145 $ 2,000 $ 170 $ 2,170 2030 $ 25 $ - $2,120 $ - $2,145 $ 500 $1,620 $2,120 Beyond TOTAL 125 50 9,830 25 $ 10,030 $ 4,785 5,245 $ 10,030 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Green River Trail Facility Improvements Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: Project # 82530101 Department Parks &Trails Improvement of trails via wayfinding, drainage, trail bed, and other aspects of asset improvement that create and support greater utilization by community members. Safety and usability have been expressed concerns regarding the Green River Trail by community members and city administration, this project will support necessary/desired safety and usability improvements STATUS: Planning for the trail is in progress with funding sources yet to be identified MAINTENANCE IMPACT: COMMENT: Indeterminant at this time, improved facilities/assets may lessen the need for M&O expenditures in certain areas while newly installed facilities/assets may increase the need in other areas COuld be a potential Park Impact Fee project FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 2027 50 50 50 50 2028 50 50 50 50 2029 $ 50 50 50 50 2030 $ 50 $ 50 $ 50 $ 50 Beyond $ 50 50 50 50 TOTAL 250 250 250 250 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKVVILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 116th St Parcel Improvements Project Manager Matthew Austin DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project* 92530104 Department Parks & Trails ❑eveLopment ofS 116th St Parcel informed bythe2020 PROS Plan as weLL as a design pLan produced in consultation with the firm GGLO. The project wiLL focus on increasing activation and overall capacity of the TCC Campus. Improvements are spLit into muLtipLe two overarching sections of campus, one being the riverside campus on its southern half and the other being the upLand campus on its northern half. Improvements incLude a fuLL pLayground and picnic shelter replacement, new weLk path and boardwalk installation and grading, installation of more tree canopy and understoryftora, replacement of picnic tabLes, installation of muLti-use sport courts, a permanent skate park, bouLdering weLLs, and more, es weLL as new furnishings such as park benches, garbage cans, and BBQgriLLs. DeveLopment ofthe S 116th St ParceLwiLL fill a neighborhood park gap currentLy existing within the park's LocaL area. PLanning has been compLeted. Project scoping, management, and fund recognition is now needed. Further deveLopment of the site from its current condition wiLL necessitate a higher service LeveL from our Parks Department. The above amount is an estimate et this time. Besides procurement of furnishings and other necessaryitems/assets, work is sLated to be done in-house. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) PLanning Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2426 S 10 S 10 S 125 145 S 145 145 2027 $ 145 $ 145 145 2028 $ $ $ $ 2029 $ $ $ $ $ $ 2U36 $ $ $ $ $ $ $ $ TOTAL $ $ $ 20 20 250 $ 290 $ 290 $ 290 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager John Dunn DESCRIPTION: JUSTIFICATION: STATUS: TCC Fitness Facilities remodel Project # 92530105 Department Parks &Trails Redesign Fitness Room and Spin Studio with upgraded equipment, Audio and Visual systems in the rooms. this will include; redesign and construction of the staff counters, layout change, upgraded fitness equipment, replacement of sound system and wiring, replacement of TV's with the addition of wireless sound connectivity to TV's. The current space and equipment are getting outdated and is in need of a refresh. These spaces provide a non intimidating option for residents and guest so maintain their wellness. With this remodel, the space will continue to provide safe, inviting and high quality experiences for our residents and guests. Currently not planned or funded. MAINTENANCE IMPACT: This will provide a reduction in operating expenses as there will be less repairs needed. COMMENT: N/A FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 2027 $ 200 200 200 200 2028 2029 2030 Beyond TOTAL 200 200 200 200 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) City Facilities (303) JL Key Project Name 2025 2026 2027 2028 2029 2030 Total 92530307 Tukwila Community $2,378 $- $- $- $- $- $2,378 Center (TCC) HVAC replacement Phase 2 92530304 City Facilities $225 $225 $225 $- $- $- $675 $- Furnishings, Fixtures, and Electrical Enhancements 82530303 TCC flat roof $168 $- $- $- $- $- $168 $- replacement 82530103 Park Restroom $135 $135 $135 $135 $135 $- $675 $- replacements 92530303 Fort Dent Plumbing $40 $- $- $- $- $- $40 $- 82530307 Pedestrian Bridges $30 $30 $30 $30 $30 $30 $180 $30 92530302 City Hall Roof $5 $175 $- $- $- $- $180 $- Replacement 92530306 HVAC replacement $- $10 $485 $- $- $- $495 $- for Building 6300 82530302 Tukwila Community $- $- $175 $125 $125 $125 $550 $- Center Operational Resiliency 82530306 TCC utilities update $- $- $- $200 $- $- $200 $- 92530305 Tukwila Community $- $- $150 $- $- $- $150 $- Center Rear Exit Rollup Doors 82530304 Roof replacement $- $- $- $284 $- $- $284 $- for the 6300 building 92530308 City Hall HVAC $- $- $175 $- $- $- $175 $- replacement Total $2,981 $575 $1,75 $774 $290 $155 $6,150 $30 After Costs six years $- JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Tukwila Community Center (TCC) HVAC replacement Phase 2 Project Manager Shawn Christie Project # 92530307 Department City Facilities Phase 2 of the HVAC replacement at TCC would include Cooling upgrades for the Gym, Replacing and DESCRIPTION: upgrading the Chiller, Replacing and upgrading the air handlers and VAV boxes, Replacing the Cabinet Heaters and the exhaust fans, Installing a split system in the electrical room. The HVAC equipment at TCC are past their useful life and needs to be replaced. The system has had multiple breakdowns in the past two years as the equipment continues to deteriorate. Phase one of this project is currently in process and we expect it to be complete by December 1st of 2024. Phase one of this project includes replacing the boilers and the controls in the building. N/A Project is grant -dependent. Any necessary grant matches will come from non -general fund sources. FINANCIAL (in thousands) Project Costs Construction otal Project Costs Project Funding Proposed Grant Dedicated/Restricted Rev otal Project Funding 2025 $ 2,378 $ 2,378 $ 2,000 $ 378 $ 2,378 2026 2027 2028 2029 2030 Beyond $ TOTAL 2,378 2,378 $ 2,000 $ 378 2,378 JUSTIFICATION: STATUS: CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Shawn Christie City Facilities Furnishings, Fixtures, and Electrical Enhancements Department City Facilities Project # 92530304 This project involves the regular replacement, upgrade, and acquisition of furnishings, fixtures, and DESCRIPTION: equipment (FF&E) for city facilities. This includes furniture, office equipment, safety fixtures, and other non- structural elements that support city operations. City facilities are central to providing services to Tukwila residents and staff. Ensuring that these facilities are well -furnished and equipped with up-to-date, functional fixtures enhances operational efficiency and Planning for three years of improvements. MAINTENANCE IMPACT: By keeping furnishings and fixtures updated, this project reduces the need for emergency repairs and COMMENT: This project will maintain the high quality facilities we offer to the public. FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding General Fund Transfer Total Project Funding 2025 $ 225 225 $ 225 225 2026 $ 225 225 $ 225 225 2027 $ 225 225 $ 225 225 2028 2029 2030 Beyond TOTAL 675 675 675 675 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: TCC flat roof replacement Project # 82530303 Project Manager Shawn Christie Department City Facilities DESCRIPTION: Replace 10,00 square feet of flat roof membrane at TCC JUSTIFICATION: The flat roof membrane at TCC has started to fail and is beyond it's useful life. We will replace all of the STATUS: MAINTENANCE IMPACT: COMMENT: flat roof membrane and repair any roof decking which is compromised This project has not started and does not have an official quote With the roof replacement there should be a reduction in roof maintenance. The future costs avoidance is difficult to project N/A FINANCIAL (in thousands) Project Costs Construction Contingency Total Project Costs Project Funding General Fund Transfer Total Project Funding 2025 $ 140 $ 28 168 $ 168 168 2026 2027 2028 2029 2030 Beyond TOTAL $ 140 28 168 168 168 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Park Restroom replacements Project # 82530103 Matthew Austin Department City Facilities Replace park restrooms to increase capacity, lower maintenance and refresh the system with a common design with lower overall maintenance burden and a design that will comply with current ADA standards. Restrooms at various parks are in need of replacements. Several restrooms need updating to allow for more robust design to holdup to heavy usage, to institutional structures as well as updating to a more environmentally and fire resistant designs. Some facilities no longer fit the park need and size requirements, or have undersized utilities resulting in frequent closures and clogs. This would be a phased approach replacing one a year to a new standard as well as updating to a park wide style of lower maintenance and better public appearance. By utilizing preapproved state purchasing contracts these projects can be ready to go in the time it takes to go through permitting. Day to day maintenance and upkeep of the restrooms would be managed by Facilites. It is estimated that this would result in slight reduction, due to the more robust construction resulting in less downtime and repairs. With the addition of electronic locks there may be the possibility of reducing the costs associated with private security locking the restrooms at night. Estimated labor costs for restroom maintenance and daily cleaning, among other items including painting, pressure washing, etc is $55,000 per year for all 5 restrooms, estimating 20 hours of supervision work, 40 hours of foreman work, and 680 hours of custodial and facilities technician hours with an estimated $10,000 annually in supplies and materials. Since existing labor resources are not currently allocated in this fashion a direct comparison of existing hours is not available at this time. This would replace restrooms in a phased cycle of one per year, and replace all of them within a 5 year period, new structures would have metal roofs, fiber cement siding, and overall be more resistant to arson and fire. Lee phillips was lost to fire last year, and the parks department has lost several park fixtures over the years to fire. Project will be paid for by 301 Fund. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Mgmt. Construction Contingency Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 10 5 110 10 135 $ 135 135 2026 $ 10 5 110 10 135 $ 135 135 2027 $ 10 5 110 10 135 $ 135 135 2028 $ 10 5 110 10 135 $ 135 135 2029 $ $ 10 5 110 10 135 $ 135 135 2030 $ Beyond TOTAL 50 25 550 50 675 675 675 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Shawn Christie Fort Dent Plumbing Project # 92530303 Department City Facilities This project will replace the undersized toilets in the Fort Dent Restrooms. The replacement will include DESCRIPTION: fixtures, hangers and new connections to the waste line. Currently the restrooms at Fort Dent are closed and we have portable toilets and hand washing stations on site because the toilets were repeatedly being clogged. The toilets in the bathrooms have undersized JUSTIFICATION: traps which can easily be clogged, which causes them to over flow and create an unsanitary condition in the restrooms. The toilets need to be replaced with a modern toilet design with a larger trap to allow waste to flow through the system. STATUS: We are currently soliciting information on toilet design MAINTENANCE IMPACT: We will see a reduction in expenses when we discontinue the rental and servicing of the portable toilets COMMENT: N/A FINANCIAL (in thousands) Project Costs Construction Contingency Total Project Costs Project Funding General Fund Transfer Total Project Funding 2025 $ 35 $ 5 40 40 40 2026 2027 2028 2029 2030 Beyond TOTAL $ 35 5 40 40 40 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Shawn Christie DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Pedestrian Bridges Project # 82530307 Department City Facilities Annual program for maintenance, rehabilitation, and/or potential reconstruction of pedestrian bridges throughout the City of Tukwila's physical asset portfolio. Maintaining the pedestrian bridges throughout the city in working order is a key risk management activity necessary for their safe operation and continued use. Failure to perform adequate preventative maintenance and other related activities can expose said assets to premature failure and/other liability producing events. City staff need to inventory and prioritize bridges by current condition. The assumption is this work is already being performed at an adequate level, if not then further estimation will be necessary. Funding responsible for this project could be split across General Fund (000), City Facilities (303), and Parks Capital (301), depending upon each asset being worked. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Dedicated/Restricted Rev Total Project Funding 2025 $ 5 25 30 30 30 2026 $ 5 25 30 30 30 2027 $ 5 25 30 30 30 2028 $ 5 25 30 30 30 2029 $ 5 25 30 30 $ 30 2030 $ 5 $ 25 $ 30 $ 30 $ 30 Beyond $ 5 25 30 30 30 TOTAL $ 35 175 210 210 210 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: City Hall Roof Replacement Project# 92530302 Project Manager Shawn Christie Department City Facilities DESCRIPTION: JUSTIFICATION: Replace the architectural grade asphalt shingle roof on City Hall will a new architectural grade asphalt shingle roof The existing asphalt shingle roof on city hall was installed in 1998 and is approaching the end of it's useful life. The roof should be replaced before a major failure occurs which would cause additional impacts and damage to City Hall. STATUS: This project has not started. By Replacing the roof we should see a reduction in service calls for leaks which will reduce our expenses MAINTENANCE IMPACT: for this location COMMENT: N/A FINANCIAL (in thousands) Project Costs Design Construction otat Project Costs Project Funding General Fund Transfer otal Project Funding 2025 $ 5 5 $ 5 5 2026 $ 175 175 $ 175 175 2027 2028 2029 2030 Beyond TOTAL 5 175 180 180 180 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Shawn Christie DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: HVAC replacement for Building 6300 Project # 92530306 Department City Facilities Replacing all of the HVAC package units at the 6300 building We need to replace all of the package HVAC units at 6300. The units are beyond their useful life and several units are broken and non -operable. We can not maintain a comfortable temperature in all office in the building currently Not Started N/A Some of these units are 40 years old and should have been replaced last decade FINANCIAL (in thousands) Project Costs Planning onstruction otal Project Costs Project Funding Fund Balance General Fund Transfer otal Project Funding 2025 2026 $ 10 10 $ 10 10 2027 $ 485 485 $ 485 485 2028 2029 2030 $ Beyond TOTAL $ 10 $ 485 495 $ 10 485 $ 495 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Tukwila Community Center Operational Resiliency Shawn Christie Project # 82530302 Department City Facilities Installation of equipment and systems that support Tukwila Community Center's operational resiliency such as generators, more robust refrigeration/freezer units, backup lighting, etc. Tukwila Community Center's service delivery capacity is dependent on provision of a safe and secure environment to staff and program participants on site, currently systems are absent that would allow for this provision to continue in the event of power loss, refrigeration unit failure, lighting failure, etc. This is especially critical in the case of an extreme weather or natural event requiring the use of Tukwila Community Center as housing, warming, and/or cooling shelter. The TCC HVAC Replacement Project is the first step in securing day-to-day operational stability. Staff will need to begin seeking quotes for future work. Addition of new systems such as a generator on site will require some form of routine preventative maintenance that will be expended via the General Fund. It is also possible that new equipment lessens the need for staff and/or contractor callouts. At this time, the amount provided above is an estimate. N/A FINANCIAL (in thousands) Project Costs Design Construction otal Project Costs Project Funding Proposed Grant Fund Balance General Fund Transfer otal Project Funding 2025 2026 2027 $ 50 $ 125 175 $ 50 $ 125 175 2028 $ 125 125 50 75 125 2029 $ 125 125 50 75 125 2030 $ - $ 125 $ 125 $ 50 $ 75 $ - $ 125 Beyond TOTAL $ 50 500 550 200 225 125 550 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: TCC utilities update John Dunn Project # 82530306 Department City Facilities Replace Faucets, toilets, urinals and lights with motion activation. Also replace light fixtures with energy efficient fixtures. Replacement will improve sanitation with touch free items. This will also conserve water in faucets as they are many times Left on with no one in the bathrooms. This project will also conserve electricity in lighting to turn off lights in rooms and offices that are not in use after a set period of time. Currently not planned or funded. This will save on utility costs to the city. N/A 1 FINANCIAL (in thousands) Project Costs Construction otal Project Costs Project Funding General Fund Transfer Total Project Funding 2025 2026 2027 2028 $ 200 200 $ 200 200 2029 2030 Beyond TOTAL $ 200 200 200 200 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: Tukwila Community Center Rear Exit Rollup Doors Matthew Austin Department City Facilities Demolition of current rear exit configuration at Tukwila Community Center and replacement installation with new rollup doors. This new setup will allow for greater activation of the space as well as integrate better with the amenities, assets, and features to be installed via the Tukwila Community Center Master Plan Project # 92530305 STATUS: Project is on standby as staff await the results of related grants. I do not believe that this project would cause any M&O impacts at this time, we are simply swapping one MAINTENANCE IMPACT: configuration of the building for another. COMMENT: N/A FINANCIAL (in thousands) Project Costs Construction otal Project Costs Project Funding Proposed Grant Total Project Funding 2025 2026 2027 $ 150 150 $ 150 150 2028 2029 2030 Beyond TOTAL 150 150 150 150 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Roof replacement for the 6300 building Project# 82530304 Project Manager Shawn Christie DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Department City Facilities Replace the existing roof membrane on the 6300 building and install insulation under the membrane The current roof membrane on the 6300 building is past it's useful life expectancy. The roof membrane needs to be replace to ensure we have a water tight roof. When replacing the membrane we also need to install insulation under the membrane. This project has not been started or received a qualified bid When the roof is replaced it should reduce future roof repair costs. This is an unknow future cost reduction which would be hard to perdict N/A FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 2028 $ 284 284 $ 284 284 2029 2030 Beyond TOTAL $ 284 284 284 284 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: City Hall HVAC replacement Project # 92530308 Project Manager Shawn Christie Department City Facilities DESCRIPTION: Replacing 10 HVAC units and the economizer at City Hall JUSTIFICATION: STATUS: MAINTENANCE IMPACT: CO M M ENT: The 10 HVAC units in City Hall are past their useful life and are frequently breaking down. The HVAC system for the Finance Department and City Clerks area is undersized and needs to be redesigned. The project has not started and no bids or pricing have been received N/A N/A FINANCIAL (in thousands) Project Costs Planning Construction Total Project Costs Project Funding General Fund Transfer Total Project Funding 2025 2026 2027 $ 10 $ 165 175 $ 175 175 2028 2029 2030 Beyond TOTAL $ 10 165 175 175 175 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) New Facilities (306) JL Key 92230601 92030601 Project Name 2025 2 2027 2028 2029 2030 Total Costs Public Works $1,000 $825 $- $- $- $- $1,825 Consolidated Shops Intergenerational $75 $75 $- $- $- $- $150 $- Teen and Senior I I Center Total J $1,075 $900 I $0 $0 $0 $0 $0 $0 After six years $- CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Public Works Consolidated Shops Project Manager Brandon Miles DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 92230601 Department New Facilities In 2015 the City committed to replacing all public safety related buildings, which resulted in the replacement of two new fire stations, the construction of the justice center, and the completion of the Fleet and Facilities Building. The final remaining project is to construction modern facilities to house engineering and utility and street operations currently taking place on Minkler Shops. This project was identified in the 2015 public safety plan. The City Council has already authorized funding in 2023 and 2024 for design and preconstruction. The project completed the SD phase and is currently in DD phase of development. Further design is on hold until ultimate project budget and funding are determined. Ideally, the M&O costs will be neutral since the City will no longer of operating costs for Minkler, Longacres, and George Long once the City have disposed of those properties. N/A FINANCIAL (in thousands) Project Costs Design otal Project Costs Project Funding Dedicated/Restricted Rev Utility Revenues otal Project Funding 2025 $ 1,000 $ 1,000 $ 841 $ 1,000 $ 1,841 2026 $ 825 825 $ 841 841 2027 2028 2029 2030 Beyond TOTAL 1,825 1,825 $ 1,682 $ 1,000 2,682 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Intergenerational Teen and Senior Center Project # 92030601 Jefri Peters Department General Fund Develop a multi -generational flex space and community hub in the Tukwila International Boulevard neighborhood. Strategically located near Foster High School, Showalter Middle School, the senior community, and the new HealthPoint location. Address the need for an accessible multi -generational community hub, free from physical, economic, cultural, and other barriers. This facility will create a welcoming environment and provide programs and resources aimed at fostering personal growth, promoting wellness, and cultivating meaningful connections across generations. Initial community outreach has been performed. Siting for project is to be determined. N/A Potential funding/programmatic partners are being sought from the local philanthropic and business community. 2025-2026 expenses to be paid with King County Parks Levy Funding. FINANCIAL (in thousands) Project Costs Planning otal Project Costs Project Funding Dedicated/Restricted Rev otal Project Funding 2025 $ 75 75 75 75 2026 75 75 75 75 2027 2028 2029 2030 Beyond TOTAL 150 150 150 150 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) JL Key Project Name 92340102 S 149th and S $2,035 150th St Watermain Replacement Water (401) 2028 2029 2030 Total Costs $- $- $2,035 92540103 Ryan Hill $1,025 $1,025 $- $- $- $- $2,050 Water Infrastructure Upgrade: Bore & Expand 80040101 Annual Water $500 $500 $500 $500 $500 $500 $3,000 $500 Repair 92340101 Large Water $140 $140 $140 $140 $- $- $560 $- Meter Replacement 81640104 Update GIS $50 $- $- $- $- $- $50 $- Water System Inventory 92540102 Tukwila $- $- $110 $710 $250 $- $1,070 $- Parkway 8" Abandonment 91240102 Water $- $1,200 $- $- $9,700 $9,700 $20,600 $50 Reservoir & Pump Station - Phase 1 91640101 Strander Blvd $- $- $- $- $500 $3,525 $4,025 $- Watermain Upgrade 91840101 Baker Blvd $- $- $380 $2,000 $- $- $2,380 $- Watermain Replacement 90540104 Southcenter $- $- $650 $1,950 $510 $- $3,110 $- Blvd Watermain Replacement 92540101 133rd $- $- $- $- $2,150 $500 $2,650 $- Watermain Replacement and Intertie Rebuild Total $3,750 $2,865 $1,780 $5,300 $13,610 $14,225 $41,530 $550 After six years $- $- Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 lir S 149th and S 150th St Watermain PROJECT: Replacement Adib Altallal Department Water Design and Construct 1,400 LF of 12" DI watermain along S 149th St and S 150th St. The dead end main will also be extended to Macadam Rd. The existing watermain is reaching its useful life and does not meet Department of Health or fireflow requirements. Project # 92340102 Design almost complete, construction expected in 2025. Easement acquisitions may be needed. Maintenance should be decreased. The project will improve the quality and flow of the water. Looping of the existing dead end main will also reduce maintenance needs. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 25 50 10 200 1,750 $ 2,035 $ 2,035 $ 2,035 2026 2027 2028 2029 2030 Beyond IMMO TOTAL 25 50 10 200 1,750 2,035 2,035 2,035 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Adib Altallal DESCRIPTION: JUSTIFICATION: Ryan Hill Water Infrastructure Upgrade: Connect & Expand Department Water Project # 92540103 The project will see the Ryan Hill neighborhood connected to the rest of the City's water system to create resiliency system -wide. Boring under train tracks and a state highway will be required, as well as upgrading several critical, undersized water mains within the neighborhood. The Department of Health is requiring the City to provide storage, which Ryan Hill currently does not have access to. STATUS: Project design scheduled for 2025 MAINTENANCE IMPACT: N/A COMMENT Improving and expanding the infrastructure in the neighborhood will likely encourage the development of many lots currently sitting vacant. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 25 $ 1,000 $ 1,025 $ 1,025 $ 1,025 2026 $ 25 $ 1,000 $ 1,025 $ 1,025 $ 1,025 2027 2028 2029 2030 $ - $ - Beyond TOTAL $ 50 2,000 2,050 2,050 2,050 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Adib Altallal Annual Water Repair Project # 80040101 Department Water DESCRIPTION: Reduce leaks by performing small repairs of the water system identified by the Water Department. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The Water Department identifies small repairs throughout the City that have a high priority of affecting the health and safety of the residents. Ongoing repairs annually. N/A N/A FINANCIAL (in thousands) Project Costs Design Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 $ 100 $ 50 $ 350 500 $ 500 500 2026 $ 100 $ 50 $ 350 500 $ 500 500 2027 $ 100 $ 50 $ 350 500 $ 500 500 2028 $ 100 $ 50 $ 350 500 $ 500 500 2029 $ 100 $ 50 $ 350 500 $ 500 500 2030 $ 100 $ 50 $ 350 $ 500 $ 500 $ 500 Beyond $ 100 $ 50 $ 350 500 $ 500 500 TOTAL 700 350 2,450 3,500 3,500 3,500 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project # 92340101 Project Manager Adib Altallal Department Water DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Large Water Meter Replacement Upgrade and replace the City's existing large water meters. The new meters will enable easier and safer acces to the meters. A potential leak would also be detected much quicker. Project scheduled through 2027. Two large meters have already been replaced in 2024. N/A As most of the large water meters are within the CBD area, the construction will be phased out over several years to minimize disruption. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 70 $ 70 140 $ 140 140 2026 $ 70 70 140 $ 140 140 2027 $ 70 70 140 $ 140 140 2028 $ 70 $ 70 140 $ 140 140 2029 2030 Beyond TOTAL $ 280 $ 280 560 $ 560 560 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Update GIS Water System Inventory Adib Altallal Department Project # Water 81640104 The Geographic Information System (GIS) water system inventory update will continue processing as- builts and survey data to improve the accuracy of the existing program utilized for construction and public records request. "The GIS mapping will provide information on the water system that is easily accessible by City staff and the public. With GIS data, the City will be able to develop an asset management plan to determine the water assets needed to be upgraded or replaced." Combined Asset Management System began in 2017 and has been ongoing since. N/A CI P is part of a coordinated project with Sewer and Stormwater. FINANCIAL (in thousands) Project Costs Design Total Project Costs Project Funding Utility Revenues otal Project Funding 2025 $ 50 50 50 50 2026 2027 2028 2029 2030 Beyond TOTAL 50 50 50 50 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Tukwila Parkway 8" Abandonment Project Manager Adib Altallal Department DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE COMMENT: IMPACT: Project # Water 92540102 Abandon the existing 8" main along Tukwila Parkway and switch services to the newer 12" main along the north side of Tukwila Parkway. Boring may be utilized to minimize restoration and inconvenience. The existing 8" caste along Tukwila Parkway has reached it's useful life and needs to be replaced or abandoned. Past breaks have cost a lot of money and time, and abandonment will avoid that issue in the future. Design will begin once that budget allows. N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 $ 10 $ 100 110 $ 110 110 2028 10 100 100 500 710 $ 710 710 MEM 2029 2030 Beyond TOTAL $ 250 250 $ 250 250 20 200 100 750 1,070 1,070 1,070 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Water Reservoir & Pump Station Project # Project Manager Adib Altallal Department Water DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: 91240102 Design and construct a new 3.5 million gallon water storage reservoir with a 3,000+ gpm pump station. The Department of Health is requiring that the City provide additional water storage. A pump station is needed to convey water throughout the City. Once a site is found, a design contract will be awarded. The water crew and the water fund will be the only group responsible. It is an essential drinking water project that will the improve resiliency of the water infrastructure throughout the City. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 $ 1,200 $ 1,200 $ 1,200 2027 2028 2029 $ 75 $ 2,000 $ 1,000 $ 6,625 $ 9,700 $ 9,700 $ 9,700 2030 $ 75 $ - $ - $ 1,525 $ 8,100 $ 9,700 $ 9,700 $ 9,700 Beyond 50 50 50 TOTAL $ 200 $ 2,000 $ 1,200 $ 2,525 $ 14,725 $ 20,650 $ 20,650 $ 20,650 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Strander Blvd Watermain Upgrade Adib Altallal Department Project # Water 91640101 Design and construct 4,400 LF of 12" ductile iron watermain to replace the old cast iron main in Strander Boulevard from the Green River to 1-5. The existing watermain is 8" cast iron and is subject to breaking apart with age. It is also undersized for the area. Project has been moved out of the "Beyond" and into 6-year plan. N/A Major regional improvement that should be coordinated with other utilities/funds. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 2028 2029 25 475 500 $ 500 500 2030 $ 50 $ 150 $ 50 $ 375 $ 2,900 $ 3,525 $ 3,525 $ 3,525 Beyond TOTAL $ 75 $ 625 $ 50 $ 375 $ 2,900 $ 4,025 $ 4,025 $ 4,025 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Baker Blvd Watermain Replacement Project# Project Manager Adib Altallal Department Water DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: 91840101 Replace approximately 2,400 LF of existing 8" water line with a 12" line in Baker Blvd between Andover Park East and Andover Park West. This replacement will improve fire flows. Existing cast iron has reached its useful life and is susceptible to failure. Not expected to be started in 2025 or 2026 N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction otal Project Costs Project Funding Proposed Grant Utility Revenues Total Project Funding 2025 2026 2027 $ 20 $ 300 $ 10 $ 50 $ 380 $ 380 380 2028 $ 50 $ 250 $ 1,700 $ 2,000 $ 500 $ 1,500 $ 2,000 2029 2030 $ Beyond TOTAL 70 300 10 300 1,700 2,380 $ 500 1,880 2,380 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Southcenter Blvd Watermain Replacement Project# 90540104 Project Manager Adib Altallal Department Water DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Replace approximately 2,500 LF of existing 8" watermain with a 12" watermain along Southcenter Blvd from the Green River Trail/66th Ave S to Macadam Rd S. This replacement will improve water service and fire flows to the areas around City Hall and the residential area north of Southcenter Blvd. Coordinating timeline with sewer, storm, and street funds. 0 N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 $ 2026 $ 2027 $ 10 $ 240 $ 200 $ 200 650 $ 650 $ 650 2028 $ 10 $ 240 $ 200 $ 1,500 $ 1,950 $ 1,950 $ 1,950 2029 $ 10 $ 500 510 $ 510 510 2030 Beyond TOTAL 30 480 400 2,200 3,110 3,110 3,110 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: 133rd Watermain Replacement and Intertie Rebuild Adib Attalla'. Project # 92540101 Department Water Replace or line the watermain along 133rd, 134th, and other nearby branches all the wayto Interurban. The current intertie with the water district is aging and will also need replacing or rebuilding. Several breaks have occurred in this area since 2020. The aging main and wet and unstable ground have brought up challenges to maintenance that need addressing with a comprehensive project. Once budget allows, the next step is to start the design. N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 2028 25 475 500 $ 500 500 2029 $ 50 $ - $ 300 $ 1,800 $ - $ 2,150 $ 2,150 $ 2,150 2030 $ 500 $ 500 $ 500 Beyond TOTAL 75 475 300 2,100 200 3,150 3,150 3,150 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) Sewer (402) Project Name 2 2026 2027 2028 2029 2030 I Total Costs 90440207 Sewer Lift $2,305 $15 $- $- $- $- $2,320 Station 12 Retrofit 92340201 Sewer Lift $2,075 $100 $- $- $- $- $2,175 $- Station 5 Rebuild 80040201 Annual Sewer $1,305 $505 $1,305 $1,305 $1,305 $1,305 $7,030 $- Repair Program 91240202 Sewer Main $635 $450 $- $- $- $- $1,085 $- Repair at 14438 59th Ave S 99840202 Southcenter $265 $1,075 $900 $- $- $- $2,240 $- Blvd Sewer Upgrade 99740205 Future Sewer $155 $860 $1,810 $510 $- $- $3,335 $- Lift Station 13 80540202 GIS Sewer $30 $30 $30 $30 $30 $30 $180 $- System Inventory 80040102 Lift Stations $- $- $10 $10 $10 $10 $40 $50 Generators Load Bank Testing 90140203 Allentown $- $- $- $205 $1,360 $1,160 $2,725 $1,000 Phase III Sewer Revitalization 90440206 Sewer Lift $- $620 $300 $- $- $- $920 $- Station 3 Upgrade 90540208 Abandon $- $- $- $- $60 $1,060 $1,120 $- Sewer Lift Station 9 99940201 Ryan Hill $- $1,610 $1,310 $1,110 $500 $- $4,530 $- Sewer Revitalization Total 6,770 5,265 5,665 $3,170 $3,265 $3,565 27,700 $1,050 After six years $- CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Sewer Lift Station 12 Retrofit Project # Project Manager Adib Altallal Department Sewer DESCRIPTION: JUSTIFICATION: 90440207 Rebuild sewer lift station 12 to better serve the northeast corner of the Commercial Business District. Lift Station No. 12 is at capacity due to its limited wet well size. If substantial growth occurs in the basin due to the expansion of the mall or other large projects, the existing lift station will need to be upgraded. STATUS: Failing valves and obselete pumps have become a major maintenance concern. MAINTENANCE IMPACT: N/A Due to the limited size of the easement and adjacent space, creative measures will be utilized to increase COMMENT: capacity as needed. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 5 $ 50 $ 250 $ 2,000 $ 2,305 $ 2,305 $ 2,305 2026 15 $ 15 15 2027 2029 2030 Beyond TOTAL $ 20 $ 50 $ 250 $ 2,000 $ 2,320 $ 2,320 $ 2,320 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Adib Altaltat DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Sewer Lift Station 5 Rebuild Project # 92340201 Department Sewer Rebuilding of sewer lift station 5 will reduce maintenance costs and reduce the risk of failure. Aging sewer lift station requires the replacement of motors, pumps, and controls at older lift stations to reduce maintenance. The sewer lift station has been seeing a lot of issues with maintenance of pumps and motors. The existing panels and valves are in a confined space and will need to be moved to grade for safer access. N/A Moving controls to grade level will greatly improve the safety of the access. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 $ 15 $ 60 $ 250 $ 1,750 $ 2,075 $ 2,075 $ 2,075 2026 100 $ 100 100 2027 2028 2029 2030 Beyond TOTAL 15 60 250 1,850 2,175 2,175 2,175 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project # 80040201 Project Manager Adib Altallal Department Sewer DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Annual Sewer Repair Program Reduce sewer line infiltration and inflow (I & I) through groundwater intrusion or storm events as a result of damaged deteriorating systems or illicit connections. Includes small repairs and capital maintenance. Decreases treatment, discharge, and pumping costs. Annual program is determined after pipeline TV inspection reports are completed. N/A Ongoing project. Only one year actuals shown in fist column. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 5 $ 150 $ 150 $ 1,000 $ 1,305 $ 1,305 $ 1,305 2026 $ 5 $ 500 505 $ 505 505 2027 $ 5 $ 150 $ 150 $ 1,000 $ 1,305 $ 1,305 $ 1,305 2028 $ 5 $ 150 $ 150 $ 1,000 $ 1,305 $ 1,305 $ 1,305 2029 $ 5 $ 150 $ 150 $ 1,000 $ 1,305 $ 1,305 $ 1,305 2030 $ 5 $ 150 $ 150 $ 1,000 $ 1,305 $ 1,305 $ 1,305 Beyond TOTAL $ 30 $ 750 $ 750 $ 5,500 7,030 7,030 7,030 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Sewer Main Repair at 14438 59th Ave S Project# Project Manager Adib Altallal Department Sewer 91240202 DESCRIPTION: Replace existing 500 LF of 8" sewer and 2 manholes from Amara Pointe Apartments at 14438 59th Ave S. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The existing pipe is located in an unstable hillside and not well supported. Staff will continue to monitor hillside. N/A Hillside repair has significantly increased the cost of the project. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Land (R/W) Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 $ 10 $ 25 $ 200 $ 400 $ 635 $ 635 635 2026 $ 50 $ 400 450 $ 450 450 2027 2028 2029 2030 Beyond TOTAL 10 75 200 800 1,085 1,085 1,085 DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Southcenter Blvd Sewer Upgrade Project # 99840202 Project Manager Adib Attalla'. Department Sewer Upgrade 3,200 LF of 8"" to a larger capacity 12"" system from Macadam Rd to the 1-405 undercrossing (or new bridge crossing) on Southcenter Blvd. Flows have greatly increased with additional connections to the basin from the North Hill apartment buildings causing the system to be deficient in terms of capacity for peak discharges. Coordination with other funds is ongoing. N/A Coordinate with 1-405 improvements to Southcenter Blvd and Future Lift Station 13. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 15 $ 100 $ 150 265 $ 265 265 2026 $ - $ 250 $ 25 $ 250 $ 550 $ 1,075 $ 1,075 $ 1,075 2027 900 $ 900 900 2028 2029 2030 Beyond TOTAL 15 350 25 250 1,600 2,240 2,240 2,240 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Future Sewer Lift Station 13 Project# 99740205 Project Manager Adib Altallal Department Sewer DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Due to utility conflicts with existing utilities, a new sewer lift station will be required near 65th Ave S and Southcenter Blvd. Maintenance of the existing gravity sewer main under 1-405 is no longer possible. Existing line is undersized and has a severe sag. Increased development on the North Hill exacerbates the deficiency. Award of design late 2025 is scheduled N/A Coordination with other funds within the City will be essential to minimize inconvenience and cost. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 155 $ 155 155 2026 $ 10 $ 150 $ 50 $ 150 $ 500 860 $ 860 860 2027 $ 10 $ - $ 150 $ 150 $ 1,500 $ 1,810 $ 1,810 $ 1,810 2028 $ 10 $ 500 510 $ 510 510 2029 2030 Beyond TOTAL 35 300 200 300 2,500 3,335 3,335 3,335 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: GIS Sewer System Inventory Project# 80540202 Project Manager Adib Altallal Department Sewer DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Geographic Information Systems (GIS) provides current as -built data for the sanitary sewer system in the Central Business District. This project will expand the as -built database for Tukwila's entire sewer system. GIS mapping of the sewer system will provide information that is easily accessible by City staff and the public. With the GIS data, the City will be able to develop an asset management plan to determine the The GIS Inventory will be continually updated, mostly in-house, to improve the accuracy of the existing N/A Ongoing project cooperating with Water and Stormwater. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 5 25 30 $ 30 30 2026 $ 5 25 30 $ 30 30 2027 $ 5 25 30 $ 30 30 2028 $ 5 25 30 $ 30 30 2029 $ 5 25 30 $ 30 30 2030 $ 5 $ 25 $ 30 $ 30 $ 30 Beyond TOTAL $ 30 150 180 180 180 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Lift Stations Generators Load Bank Testing Project # 80040102 Adib Altallal Department Sewer Perform an annual test on all Lift Stations generators that's more extensive than the weekly routine check Performing load bank testing on generators annually will avoid failure of generators during a time of need. The testing will also elongate the life of generators by more than 25%. Current test was recommended after performing a study of our existing lift stations generators. N/A Generators will be tested annually on a rotating basis. FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 $ 10 10 10 10 2028 10 10 10 10 2029 10 10 10 10 2030 $ 10 $ 10 $ 10 $ 10 Beyond 50 50 $ 100 100 TOTAL 140 140 MEM CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Adib Altallat DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: CO MMENT: Allentown Phase III Sewer Revitalization Project # 90140203 Department Sewer Extend existing sewer main to serve the Allentown parcels further north, closer to the Duwamish Hill Preserve. Existing septic systems are old and failing. Phase III of an ongoing effort to revitalize the sewer system in Allentown. N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction otat Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 2028 $ 5 $ 200 205 $ 205 205 2029 $ 10 $ 200 $ 150 $ 1,000 $ 1,360 $ 1,360 $ 1,360 2030 $ 1,160 $ 1,160 $ 1,160 Beyond $ 1,000 $ 1,000 $ 1,000 TOTAL 25 400 300 3,000 3,725 3,725 3,725 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Sewer Lift Station 3 Upgrade Project # 90440206 Adib Altallal Department Sewer Upgrading sewer lift station 3, including control panel, valves, and pumps. A backup power source will also be installed. Aging sewer system requires the replacement of motors, pumps, and controls at older lift stations to reduce Sewer Lift Station 3 is at the end of its life cycle and need to be rebuilt with a backup power source. N/A Additional right-of-way or property may be required for the new backup generators to be installed. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 2026 5 100 15 100 400 $ 620 $ 620 620 2027 300 $ 300 300 2028 2029 2030 Beyond TOTAL 5 100 15 100 700 920 920 920 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Adib Altallal DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Abandon Sewer Lift Station 9 Project # Department Sewer Find a feasible way to replace the existing force main with a gravity main and abandon lift station if possible. The current lift station only benefits one business park and not the City as a whole. 90540208 Feasibility studies have been ongoing. N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 2026 2027 2028 2029 $ 10 $ 50 60 60 60 2030 $ 10 $ 100 $ 200 $ 750 $ 1,060 $ 1,060 $ 1,060 Beyond TOTAL 20 150 200 750 1,120 1,120 1,120 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Ryan Hill Sewer Revitalization Project# Project Manager Adib Attalla'. Department Sewer DESCRIPTION: Upsize and extend sewer mains throughout Ryan Hill JUSTIFICATION: Existing septic systems are failing and creating public health hazards and have halted development. STATUS: MAINTENANCE IMPACT: COMMENT: 99940201 Comprehensive plans to revitalize the neighborhood have been ongoing for years. N/A Coordination with residents and other City funds will be essential to the success of this project, specifically the coordination with the Ryan Hill Phase II Boring. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 2026 $ 10 $ 1,600 $ 1,610 $ 1,610 $ 1,610 2027 $ 10 $ 300 $ 1,000 $ 1,310 $ 1,310 $ 1,310 2028 2029 $ - $ 500 500 $ 500 500 2030 Beyond TOTAL 30 1,700 300 2,500 4,530 4,530 4,530 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) Surface Water (412) JL Key Project Name 2025 91641204 S 131st Pl $1,805 $1,625 Drainage Improvements 92341202 Chinook Wind $1,285 $- Extension 82541201 Annual Small $994 Drainage Program 91641203 Nelsen Side $988 $650 $4,645 $10 Channel 91341203 Levee Program $850 $850 $850 $850 $850 $850 $5,100 $- 2029 • 2030 Total Costs $- $- $5,855 • $- $- After six years $- $1,285 $- $994 $994 $994 $994 $994 $5,964 $- $- $- $6,293 $- 99830105 Gilliam Creek Fish $698 $1,078 $5,802 $- $- $- $7,578 $- Barrier Removal and Habitat Enhancement 91241202 Stormwater Water $625 $2,035 $125 $2,225 $125 $2,225 $7,360 $140 Quality Retrofit Program 82541202 Gilliam Creek $481 $- $- $- $- $- $481 $- Erosion Repair 91241203 Tukwila Urban $445 $435 $- $- $- $- $880 $- Center Conveyance Inspections 99341210 NPDES Program $344 $144 $144 $144 $144 $144 $1,064 $172 72541203 Lower Green $305 $- $- $- $- $- $305 $- Riverfront Master Plan 92541203 S. 104th St $272 $10 $210 $210 $5 $5 $712 $5,330 Shoreline Restoration 82541203 Riverton $260 $50 $1,580 $490 $- $- $2,380 $- Stormwater Management Action Plan - Program CIP 92241203 Duwamish Hill $230 $530 $460 $10 $2,660 $2,660 $6,550 $- Preserve Phase 3 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM 72541204 I Norfolk Outfall Trunkline Sewer Separation 91641202 Green the Green i_Program 92341201 I Decant Facility 32341201 Comprehensive Landslide Risk and Assessment 72341203 Enhanced $100 $- __Maintenance Plan 70041201 Regional Surface $80 $85 Water __Partnerships 32541201 WSDOT Stormwater Retrofit & Maintenance 72541202 Johnson Creek Fish Barrier Mitigation Alternatives Analysis 91441202 Chinook Wind $6 $- Public Access _ Project 72541201 Fish Passage $- $195 Barrier Prioritization Study 92541201 Fort Dent Park $- $- Water Quality Retrofit $180 1 $- I $- $145 $145 $145 f $145 $145 ' $145 ' $870 $145 $145 $900 $1,2301 $60 $- $- $2,335 $- $140 $150 $250 $250 $- $- $790 $- $- 1 $- $- $- $100 $- $105 1 $105 $105 $105 $585 $105 $60 $110 $110 1 $625 $10 $10 $925 $- $35 $5 i $- $- $- $- $40 $25 $- $- $- $- $- $6 $- $- $- $- $195 $- $- $- $- $445 12541201 Green $- $205 $205 $205 $205 $205 $1,025 $205 Infrastructure Program 98741202 Nelsen/Longacres $- $- $- $1,100 $- $- $1,100 $- Ph II 72541205 P17 Pond and $- $175 $175 $- $- $- $350 $- Southcenter Subarea Hydraulic Study 98641222 Regional Surface $- $230 $1,640 $- $- $- $1,870 $- 1 Water Partnerships i i i CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM 92541202 Ryan Way Pipe Rehabilitation 90341214 S 146th St Pipe & 35th Ave S Drainage System 91241205 Tukwila Parkway Gilliam Creek Outfalls 92541204 Tukwila Pond Water Quality Improvement Total $- $- $- $- $- $- $305 $305 $1,230 $- $- $- $983 $10,473 $10,601 $18,670 $9,848 $5,523 $9,253 $64,368 $9,645 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 131st Pt Drainage Improvements Project Manager Joshua Hopkins DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 91641204 Department Surface Water Developing alternate horizontal alignment for Southgate Creek in conjunction with replacing a fish barrier culvert. Scope expanded in 2024 to increase hydraulic analysis limits to address persistent flooding not addressed with the preliminary hydraulic design. Southgate Creek overtops its bank several times per year during storm events and runs through private property. Debris is deposited within a private driveway and storm system. HPA permitted dredging is performed annually on the creek to remove excess sedimentation to reduce the likelihood of flooding. Project will include 1-year contract maintenance and typically 2-to-4 years of plant establishment. Project improvements will be turned over to surface water division for routine maintenance. Project applied for Department of Ecology design development funding and Conservation Futures property acquisition grant to support the expanded hydraulic analysis. Assumes estimated 2028 construction. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning Land (R/W) Construction Mgmt. Construction Total Project Costs Project Funding Awarded Grant Proposed Grant Utility Revenues Total Project Funding 2025 $ 25 $ 780 $ 1,000 $ $ 1,805 $ 706 $ 1,105 $ 205 $ 2,016 2026 $ 25 $ 600 $ 1,000 $ 1,625 $ - $ 1,625 $ - $ 1,625 2027 2028 $ 25 $ - $ - $ 400 $ 2,000 $ 2,425 $ - $ 1,600 $ 825 $ 2,425 2029 2030 Beyond TOTAL 75 1,380 2,000 400 2,000 5,855 706 4,330 1,030 6,066 MEIN CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 V PROJECT: Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: 1 Chinook Wind Extension Project# 92341202 Department Surface Water Following the Public Works Facility Preferred Master Plan (2019) and the Duwamish Gardens Opportunities for Expansion Concept Plan (2013), this project will develop connecting shoreline habitat and the 'missing trail link' between Duwamish Gardens and Chinook Wind within recently acquired City property. This is a Tier 1 project in the WRIA 9 Salmon Recovery Plan, fulfilling a core recovery strategy of restoring, protecting and enhancing estuary habitat in the Duwamish River. The trail connection has been discussed in the community for many years and is anticipated to be part of larger, popular shoreline trail. The project is currently at 50%design. This is a work in progress. The Green Infrastructure Program Proposal is intended, in part, to address maintenance needs for PW-initiated habitat restoration projects and helping to alleviate pressure on Parks' given resource constraints. Note that vegetation management maintenance needs decrease over time as planted vegetation matures. 3 years is considered a rule of thumb for plant establishment. This grant funded project is being implemented as part of the PW Shops Ph 2 project. There are expectations by the granting agency that the project will be constructed. It is the middle link of the Duwamish Gardens/Chinook Wind trail and "blue belt" aquatic restoration corridor. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Proposed Grant Utility Revenues Total Project Funding 2025 $ 10 $ 50 $ 200 $ 1,000 $ 25 $ 1,285 $ 1,000 $ 285 $ 1,285 2026 2027 2028 2029 $ 2030 Beyond TOTAL 10 50 200 1,000 25 1,285 $ 1,000 285 $ 1,285 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Annual Small Drainage Program Project Manager Joshua Hopkins Project # 82541201 Department Surface Water DESCRIPTION: Select, design, and construct small drainage projects throughout the City. JUSTIFICATION: Provide drainage corrections for existing/ongoing drainage problems throughout the City, including culvert replacements, drain extensions, and pavement upgrades. STATUS: Projects for this annual program are taken from Small Drainage Project List. MAINTENANCE IMPACT: COMMENT: N/A Ongoing project, only one year shown in first column. Construction expenses may occur over two calendar years. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 $ 24 $ 110 $ 110 $ 750 $ 994 $ 994 994 2026 $ 24 $ 110 $ 110 $ 750 994 $ 994 994 2027 $ 24 $ 110 $ 110 $ 750 994 $ 994 994 2028 $ 24 $ 110 $ 110 $ 750 994 $ 994 994 2029 $ 24 $ 110 $ 110 $ 750 994 $ 994 994 2030 $ 24 $ 110 $ 110 $ 750 $ 994 $ 994 $ 994 Beyond TOTAL 144 660 660 4,500 5,964 $ 5,964 5,964 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Nelsen Side Channel Project # 91641203 Department Surface Water Create a multibeneficial project that restores off -channel salmon rearing habitat by setting back the 1-405 levee, reconnecting a segment of historic river channel and providing public shoreline access. Off -channel habitat for threatened Chinook Salmon and other salmon is extremely limited in the Lower Green River. WRIA 9 has identified this project in the Salmon Habitat Plan. It was identified in the 2013 Surface Water Comprehensive Plan. The City has recieved grant funds for project design. City staff is proposing to purchase adjacent property to expand the proiect site. Design will begin in 2024-25. This is a work in progress. The Green Infrastructure Program Proposal is intended, in part, to address maintenance needs for PW-initiated habitat restoration projects and helping to alleviate pressure on Parks, given resource constraints. Note that vegetation management maintenance needs decrease over time as planted vegetation matures. 3 years is considered a rule of thumb for plant establishment. This is one of the only opportunities to create critically needed off -channel habitat on public lands along the lower Green River in Tukwila. There is potential to roughly triple the project site by acquiring adjacent, vacant and largely (if not entirely) undevelopable property. 'FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Contingency otal Project Costs Project Funding warded Grant Proposed Grant Utility Revenues otal Project Funding 2025 $ 20 $ 600 $ 268 $ 100 988 $ 815 $ 173 988 2026 $ 10 $ 625 $ - 15 650 $ 150 $ 500 $ - 650 2027 $ 20 $ - $ - $ 385 $ 4,200 $ 40 $ 4,645 $ - $ 4,295 $ 350 $ 4,645 2028 10 10 10 2029 2030 Beyond TOTAL 60 1,225 268 385 4,200 155 6,293 $ 965 $ 4,795 $ 533 6,293 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Sherry Edquid DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: 111 Levee Program Project # 91341203 Department Surface Water Reconstruct levees to provide 500-year level of flood protection in the Southcenter subarea, obtain levee certification of the 205 levee and coordinate with the King County Flood Control District and/or US Army Corps of Engineers on other levee projects. The US Army Corps of Engineers no longer provides levee certification services to federally authorized levees. The existing 205 levee certification expired in August 2013. Certification is required for the Federal Emergency Management Agency to accredit the levee system as providing a 100-year level of flood protection. This also funds the Levee Project Manager position to coordinate with King County Flood Control District and US Army Corps of Engineers. This program is just in its infancy as we reconstruct levees to provide 500-year level of flood protection in the Southcenter subarea. N/A COMMENT: N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 150 $ 700 850 $ 850 850 2026 $ 150 $ 700 850 $ 850 850 2027 $ 150 $ 700 850 $ 850 850 2028 $ 150 $ 700 850 $ 850 850 2029 $ 150 $ 700 850 $ 850 850 2030 Beyond $ 150 $ 700 $ 850 $ 850 $ 850 TOTAL $ 900 4,200 5,100 5,100 5,100 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Gilliam Creek Fish Barrier Removal and Habitat Enhancement Project Project Manager Joshua Hopkins Department Surface Water DESCRIPTION: JUSTIFICATION: STATUS: Project# 99830105 Construct fish passage improvements at existing flap gate and restore salmon id habitat; replace flap gate which may include a self-regulating tide gate or flood wall. Enable fish access to lower Gilliam Creek under wider range of flow conditions; fish barrier per WDFW and City; WRIA 9 salmon habitat project. Alternatives Analysis Design completed in 2023. MAINTENANCE IMPACT: M&O is typically 3-5 years for HPA permits to revegetate streambanks following barrier removal. COMMENT: City applied to NOAA grants (Fish Passage & Transformational Habitat) in 2023 for design development and construction funding for the preferred alternative (estimated $24 M). City was not selected for one of the two grants. Meanwhile, the 66th Ave S culvert, tide gate and upstream debris rack (fish barriers) are causing erosion of the streambanks upstream of the 66th Ave S culvert. Permitting agencies may require fish passage as a condition of permits to repair the aforementioned erosion. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Total Project Costs Project Funding Awarded Grant Proposed Grant Utility Revenues Total Project Funding 2025 $ 78 $ 620 $ - 698 $ 680 18 $ 698 2026 $ 78 $ 1,000 $ 1,078 $ - $ 1,000 $ 78 $ 1,078 2027 $ 78 $ - $ 1,076 $ 4,648 $ 5,802 $ - $ 5,802 $ - $ 5,802 2028 2029 2030 $ - $ - $ - Beyond TOTAL $ 234 $ 1,620 $ 1,076 $ 4,648 7,578 $ 680 $ 6,802 $ 96 7,578 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Stormwater Water Quality Retrofit Program Project Manager Joshua Hopkins DESCRIPTION: Project # 91241202 Department Surface Water Plan, design, and install water quality treatment and other stormwater conveyance improvements at targeted drainage locations. JUSTIFICATION: Most surface water is discharged directly to receiving water bodies untreated. STATUS: Water quality retrofit has been added to CIP projects since 2015. MAINTENANCE IMPACT: COMMENT: N/A Combine with other CIP projects for design and construction, where feasible. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Total Project Costs Project Funding Awarded Grant Proposed Grant Utility Revenues Total Project Funding 2025 $ 25 $ 100 $ 100 $ 400 625 $ 125 $ 425 $ 75 625 2026 $ 25 $ 300 $ 300 $ 1,410 $ 2,035 $ 1,410 $ 300 $ 325 $ 2,035 2027 $ 25 $ 100 125 $ 125 125 2028 $ 25 $ 400 $ 1,800 $ 2,225 $ - $ 1,530 $ 695 $ 2,225 2029 125 $ 125 125 2030 $ 25 $ 400 $ 1,800 $ 2,225 $ - $ 1,530 $ 695 $ 2,225 Beyond 25 20 15 80 140 $ 140 140 TOTAL 175 620 1,215 5,490 7,500 1,535 3,785 2,180 7,500 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Gilliam Creek Erosion Repair Project Manager Joshua Hopkins Project # 82541202 Department Surface Water DESCRIPTION: Stabilize and protect eroded streambank slopes upstream of the 66th Ave S culvert inlet JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: This project is intended to protect the 66th Ave S roadway infrastructure and prevent future flooding to Southcenter. The project has been scoped for design, permitting and construction and a grant applied for with the Flood Control District to cover all costs. M&O is for three years, so 3x $8,400. Mitigation is expected in the form of vegetation restoration for temporary and permanent impacts, cost is unknown. This work is to occur during the in -water work window for the Green River and Gilliam Creek and may require mitigation for project impacts to aquatic and stream buffer habitat. FINANCIAL (in thousands) Project Costs Design Construction Mgmt. Construction otal Project Costs Project Funding Proposed Grant otal Project Funding 2025 $ 128 $ 90 $ 263 481 $ 481 481 2026 2027 2028 2029 2030 Beyond TOTAL 128 90 263 481 481 481 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Tukwila Urban Center Conveyance Inspections Project# 91241203 Project Manager Mike Perfetti Department Surface Water The network of storm pipes in the core retail area of Tukwila has not been inspected in the last several decades. Because there have been no inspections, pipe condition is unknown and rehabilitation, repair, and DESCRIPTION: replacement needs are therefore unknown. It is likely that a significant amount of sediment exists within the storm network in that area. Several stormwater pipes have been selected as higher priority because of the large pipe sizes and more significant impact should a pipe fail. The selected area includes 1)Andover Park E from S. 180th Street to Minkler Boulevard. 2) 36" pipe from Minkler Boulevard to Azteca Restaurant. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Blockage of stormwater system may lead to flooding and water quality degradation. Pipes have not been cleaned or inspected since installation. Prioritize project given the length of time its been identified. Internal discussions in 2024 to set up for work in 2025. O&M inspects and maintains pipes, catch basins and other assets as part of normal operations. This project will require participation by O&M but will largely relieve ongoing O&M burden. In order to assess the pipe conditions, the storm drain pipes will be cleaned and the sediment will be disposed of. Then the pipe interior will be inspected using a remote -control camera. The inspection will be recorded. Rehabilitation, repair, and replacement needs will then be known and prioritized. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 15 $ 200 $ 20 $ 200 $ 10 $ 445 $ 445 445 2026 $ 15 $ 390 $ 20 $ - 10 435 $ 435 435 2027 2028 2029 2030 Beyond TOTAL 30 590 40 200 20 880 880 880 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Russell Betteridge DESCRIPTION: JUSTIFICATION: NPDES Program Project # 99341210 Department Surface Water Provide programmatic implementation support of the State DOE Phase II Western Washington NPDES permit. The Annual Surface Water Management Plan specifies a NPDES reporting and action plan for City compliance. The services/supplies funds will also include any illicit discharge (spill cleanup) costs that may occur in the City's right-of-way. State Mandated Permit "National Pollutant Discharge Elimination System (NPDES) Phase II Western Washington". Federal Clean Water Act and Additional State Waste Discharge Permit RCW 90.48. NPDES requirements are ongoing with new permit requirements every 5 years (2024-2029). Requirements cover all divisions of the city including Public Works, Golf/Parks, Police, Planning, and Facilities. Costs shown include emergency supplies, testing equipment, Lab testing fees, and annual consultant support. Added requirements require changes to conform with NEW requirements, e.g. New Inspection and street STATUS: Currently Compliant with new permit updates in the planning phase. MAINTENANCE IMPACT: COMMENT: The City is typically granted Capacity Grant funds to cover much of the coordination expenses and some of the additional expenses. Each division should track costs incurred to manage pollution such as spill kits, staff time for surface water pollution prevention inspections on qualifying city facilities and during field operations within the jurisdiction. This cost is not accounted for in the impact cost above. In addition to the NPDES permit, there are specific actions undertaken to assist in the Lower Duwamish Superfund compliance effort, such as source control inspections, PCB investigations and discharge responses. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Total Project Costs Project Funding Proposed Grant Utility Revenues Total Project Funding 2025 $ 72 $ 200 $ 72 344 $ 279 279 2026 $ 72 $ - $ 72 144 $ 130 79 209 2027 $ 72 $ - $ 72 144 79 79 2028 $ 72 $ - $ 72 144 $ 130 79 209 2029 $ 72 $ - $ 72 144 79 79 2030 $ 72 $ - $ 72 $ 144 $ 130 $ 79 $ 209 Beyond $ 86 $ - $ 86 172 79 79 TOTAL 518 200 518 1,236 $ 390 753 1,143 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Lower Green Riverfront Master Plan Project Manager Joshua Hopkins DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72541203 Department Surface Water Flood protection projects sponsored by KCFCD and federal partners are imminent. City will need to begin master planning immediately in order to guide aesthetic and community considerations of these projects. The Tukwila Levee Accreditation Phase 1 (NHC, 2015) & Phase 2 (NHC, 2019) are guiding documents for City flood hazard management priorities and recommendations for implementation on the 205 Levee. The KCFCD has adopted the prioritized projects to the KCFCD CIP list for implementation. City needs to plan and develop preferred alternatives to guide the KCFCD CIP implementation. Project CI P identified in 2024 Surface Water Comp Plan. Funding needs to be budgeted and an RFQ/RFP advertised to contract with a consultant. N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning otat Project Costs Project Funding Utility Revenues otat Project Funding 2025 $ 30 $ 275 305 $ 305 305 2026 2027 2028 2029 2030 Beyond TOTAL $ 30 275 305 305 305 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S. 104th St Shoreline Restoration Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 92541203 Department Surface Water The armored bank on an outside bend of the Duwamish River adjacent to S. 104th Street is steep and subject to erosion and potential failure. This project would analyze site conditions and develop solutions to create a sustainable shoreline that can withstand hydraulic forces, reduce erosional risk to uplands and provide ecological value. This is project DUW-26 in the WRIA 9 2021 Salmon Recovery Plan Update. The City roadway and adjacent properties and utilities may be at risk under current conditions. The project is running behind schedule; the intent is to start with a geotechnical analysis of the bank, analysis of existing conditions and conceptual feasibility and alternative design. This is a work in progress. The Green Infrastructure Program Proposal is intended, in part, to address maintenance needs for PW-initiated habitat restoration projects and helping to alleviate pressure on Parks' given resource constraints. Note that vegetation management maintenance needs decrease over time as planted vegetation matures. 3 years is considered a rule of thumb for plant establishment. This project initiatlly appeared in the 2003 Surface Water Comp Plan as "S 104th St Bank Stabilization Project", in response to some observed erosion; despite this, the bank appears somewhat stable, but is extremely steep and cracking is observed on the roadway; some adjacent land uses and access routes have been altered to open up the viability of laying back and restoring the shoreline. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Proposed Grant Utility Revenues Total Project Funding 2025 $ 12 $ 250 272 $ 150 $ 122 272 2026 10 10 10 2027 $ 10 $ 200 210 $ 150 60 210 2028 $ 10 $ 200 210 $ 150 60 210 2029 5 5 5 2030 5 5 5 Beyond $ 30 $ - $ 300 $ 4,000 $ 1,000 $ 5,330 $ 4,500 $ 1,830 $ 6,330 TOTAL 82 650 300 4,000 1,010 6,042 $ 4,950 2,092 7,042 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Riverton Stormwater Management Action Plan - Project # 82541203 Project Manager Sherry Edquid DESCRIPTION: JUSTIFICATION: Program CIP Department Surface Water This CIP is a program to implement the Stormwater Management Action Plan (SMAP) a new requirement under the NPDES Permit. The SMAP directed the City to invest and prioritize one stream system the city selected Riverton. The SMAP for Riverton Creek identifies four priority stormwater retrofits and a handful of lower priority stormwater retrofits with the goal of improving water quality while accommodating future growth in the basin. Of the four short-term projects we would begin design and possibly construction for two of the four projects over the course of the next six years. Washington State Department of Ecology will likely require us via the NPDES permit to begin implementing the SMAP necessitating the need to begin design and construction these short-term retrofit projects. The SMAP was also included as part of the Surface Water Comprehensive Plan (SWCP). STATUS: The SMAP provided a basic project description and cost estimate for these projects. MAINTENANCE IMPACT: COMMENT: Surface Water and Transportation I am proposing to implement these two projects SMAP-4 Tukwila International Boulevard: Bust Stop 60983 Water Quality Retrofit and SMAP-5 South 130th St Right of Way Bioretention Planters. INANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Land (R/W) onstruction Mgmt. onstruction ontingency otal Project Costs Project Funding Proposed Grant Utility Revenues eneral Fund Transfer otal Project Funding 2025 $ 20 $ 230 $ 10 $ - $ $ 260 $ 208 $ 52 260 2026 50 $ 40 $ 10 50 2027 $ 20 $ 130 $ - $ 10 $ 120 $ 1,200 $ 100 $ 1,580 $ 1,264 $ 158 $ 158 $ 1,580 2028 $ 40 $ 35 $ 375 $ 40 490 $ 392 $ 98 $ - 490 2029 2030 $ Beyond $ TOTAL 100 390 10 10 155 1,575 140 2,380 1,904 318 158 2,380 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Duwamish Hill Preserve Phase 3 Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 92241203 Department Surface Water The goals of the project are to restore the shoreline to create off -channel habitat and expand the park visitor experience. The park master plan calls for moving a portion of S. 115th Street landward to improve shallow water habitat, water quality and enjoyment of the shoreline. Final design will be informed by a feasibility evaluation and alternatives evaluation process. This project is described in the Duwamish Hill Preserve Park Master Plan and is listed as Project DUW-63 in the WRIA 9 Salmon Habitat Plan (2021) The project has some funding in the 2023-24 CIP for initial feasibility work. Project initiation and consultant advertisement is planned for 2024. This is a work in progress. The Green Infrastructure Program Proposal is intended, in part, to address maintenance needs for PW-initiated habitat restoration projects and helping to alleviate pressure on Parks' given resource constraints. Note that vegetation management maintenance needs decrease over time as planted vegetation matures. 3 years is considered a rule of thumb for plant establishment. The City completed acquisitions of properties identified in master plan that may be used for this project. Two small additional undeveloped properties are for sale that would expand the park footprint. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Land (R/W) Construction Mgmt. Construction Contingency Total Project Costs Project Funding Proposed Grant Utility Revenues Total Project Funding 2025 $ 10 $ 200 20 $ 230 $ 230 $ 230 2026 $ 10 $ 200 $ 300 $ - 20 530 $ 460 70 $ 530 2027 $ 20 $ 400 40 $ 460 $ 400 $ 60 460 2028 $ 5 5 $ 10 $ 10 10 2029 $ 20 $ 200 $ 2,000 $ 440 $ 2,660 $ 2,000 $ 660 $ 2,660 2030 $ 20 $ 200 $ 2,000 $ 440 $ 2,660 $ 2,000 $ 660 $ 2,660 Beyond TOTAL 85 800 300 400 4,000 965 6,550 $ 4,860 1,690 6,550 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Norfolk Outfall Trunkline Sewer Separation Feasibility Project Manager Joshua Hopkins DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72541204 Department Surface Water The project is a preliminary feasibility study to document the City's and adjacent private property storm drainage systems within the right-of-way and the CSO system in the area within the City boundary, document any City storm drain connections to the CSO line, and evaluate risks and alternative solutions if connections of the City's storm drains to the CSO trunkline and private systems are discovered. The City installed a stormwater trunkline along E Marginal Way S in the 1990s for the purpose of separating stormwater flows from both the combined sewer system and the adjacent private stormwater system owned by Boeing. However, City staff has anecdotal information that the connections of City stormwater laterals into the E Marginal Way S stormwater trunkline were not completed as designed, likely due to utility conflicts encountered in the field. Advertise RFP/RFQ for consultant contract to perform preliminary feasibility. N/A This is a priority project to understand Tukwila's responsibility and potential liability related to the Duwamish River Super Fund Site cleanup. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design otal Project Costs Project Funding Utility Revenues otal Project Funding Beyond TOTAL CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Green the Green Program Project # 91641202 Department Surface Water This program supports revegetation and restoration efforts along watercourses within the City with main goal of providing habitat, improving water quality and reducing water temperatures. Funding may be utilized for costs related to planting or maintenance and include City and partner projects that contribute to the goals. WRIA 9 has identified warm water temperatures as an impediment to salmon recovery, and has a funding program called, "ReGreen the Green" which aims to support revegetation projects along the river. Pilot projects at NC Machinery & Southcenter Plaza completed in 10yr maintenance period. Funding maintenance of Riverton Creek, Duwamish Gardens; Partner Project w MidSound Fisheries and Puget Sound Partnership Cost based on rough average of contracted maintenance costs for Riverton Creek. Duwamish Gardens and Green the Green CIP (JSH/Harnish). Note that costs decrease over time. Plant establishment is usually around 3 years, but obligations are generally for 10 years. Note that, to date, these maintenance costs have been exclusively contracted. Grant funding ongoing. Funding to date has come from WRIA9 and the Rose Foundation. Note that this fund is not intended to be used for mitigation obligations associated with other CIP projects. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Contingency Total Project Costs Project Funding Proposed Grant Utility Revenues Total Project Funding 2025 $ 5 $ 20 $ 100 $ 20 145 $ 45 $ 100 145 2026 $ 5 $ 20 $ 100 $ 20 145 $ 45 $ 100 145 2027 $ 5 $ 20 $ 100 $ 20 145 $ 45 $ 100 145 2028 $ 5 $ 20 $ 100 $ 20 145 $ 45 $ 100 145 2029 $ 5 $ 20 $ 100 $ 20 145 $ 45 $ 100 145 2030 $ 5 $ 20 $ 100 $ 20 $ 145 $ 45 $ 100 $ 145 Beyond $ 5 $ 20 $ 100 $ 20 145 $ 45 $ 100 145 TOTAL $ 35 140 700 140 1,015 $ 315 700 1,015 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Soils Reclamation/Decant FacilityIr Project# 92341201 Project Manager Sherry Edquid DESCRIPTION: JUSTIFICATION: STATUS: Department Surface Water Construct soils reclamation facility to handle, treat, dispose and/or reuse non -hazardous street sweepings and catch basin cleanings, etc. (formerly named DrainageNactor Waste Facility). To meet State NPDES regulations, the City needs facilities to treat & dispose of waste materials resulting from cleaning/maintenance activities, including street sweepings and Vactor truck wastes. The Soils Reclamation/Decant Facility is being built as part of the overall new Public Works Fleets and Facility project. Currently in project design. Water, Sewer and Surface Water will fund maintenance of the new facility and possibly King County Metro MAINTENANCE IMPACT: who we will likely develop an ILA to dispose of their waste on our site. Also, not needing to use King County's decant facility for disposal would reduce expenses. COMMENT: The Enhanced Maintenance Plan (EMP) and the Soils Reclamation/Decant Facility - design is being funded by an Ecology grant. Will be applying for an Ecology grant to fund construction. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency otat Project Costs Project Funding warded Grant Proposed Grant Fund Balance Total Project Funding 2025 145 $ 325 325 2026 $ 30 $ 20 $ 100 $ 650 $ 100 900 $ - $ 1,000 $ 480 $ 1,480 2027 $ 30 $ - $ 100 $ 1,000 $ 100 $ 1,230 $ 500 500 2028 60 $ 30 30 2029 2030 Beyond TOTAL 85 150 200 1,700 200 2,335 325 1,530 480 2,335 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Comprehensive Landslide Risk and Assessment Project Manager Sherry Edquid DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 32341201 Department Surface Water This plan will build upon the state and county landslide information to identify landslide hazards and provide an understanding of comprehensive risks within the City of Tukwila, with the goals of reducing property damage and life loss from landslides. We received a Cooperative Technical Partner's Grant from FEMA with zero match. This is also included in the Surface Water Comprehensive Plan. The RFP is currently being advertised for a consultant. N/A This is a joint effort with DCD and will evaluate forest health as well as critical utilities within these landslide risk areas. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning onstruction otal Project Costs Project Funding warded Grant Proposed Grant otal Project Funding 2025 $ 20 $ 120 $ - 140 $ 140 140 2026 $ 30 $ 120 $ - 150 $ 150 150 2027 250 250 $ 250 250 2028 250 250 $ 250 250 2029 2030 Beyond TOTAL $ 50 $ 240 $ 500 790 $ 140 650 790 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Enhanced Maintenance Plan Project Manager Sherry Edquid DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72341203 Department Surface Water The Enhanced Maintenance Plan (EMP) - grant funded will evaluate the city's parks, golf and surface water's O&M program - software, equipment, staffing as well as looking at Best Management Practices (BMPs) implemented by other cities. This information will be compiled into a report and make recommendations with the overall goal of removing sediments and pollutants from roadway runoff. An EMP is required to receive design/construction grant funding from Ecology for the Soil Reclamation/Decant Facility. The other EMP recommendations will be eligible for future grant funding as well. We have held an EMP workshop to interview city staff regarding their current O&M program. We are beginning to interview other jurisdictions regarding their O&M program. This is only and plan but it may be able to grant fund O&M expense if we can demonstrate it will remove more sediments and pollutants from roadway runoff. N/A FINANCIAL (in thousands) 2025 Project Costs Project Mgmt (Staff Time/Cost) Planning Total Project Costs Project Funding Awarded Grant Utility Revenues Total Project Funding $ 20 $ 80 100 $ 85 15 $ 100 2026 2027 2028 2029 2030 Beyond TOTAL $ 20 80 100 $ 85 15 100 MEI= CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Regional Surface Water Partnerships Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: Project # 70041201 Department Surface Water The City is party to a number of ongoing inter -agency partnerships related to surface water including WRIA 9, a streamgages funding program with USGS and a Duwamish Steward ILA. These partnerships generally arise as part of collaboration to recover salmon species listed under the Endangered Species Act (ESA) and to improve water quality within the Green/Duwamish watershed. STATUS: WRIA 9 ILA is through 2025; Duwamish Steward ILA through 2026; Streamgages annually. MAINTENANCE IMPACT: COMMENT: N/A Ongoing partnerships. Some discussions about a formalization of Our Green Duwamish Partnership on going, which could have cost implications. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 5 $ 75 80 80 80 2026 $ 5 80 85 85 85 2027 $ 5 $ 100 105 $ 105 105 2028 $ 5 $ 100 105 $ 105 105 2029 $ 5 $ 100 105 $ 105 105 2030 $ 5 $ 100 $ 105 $ 105 $ 105 Beyond $ 5 $ 100 105 $ 105 105 TOTAL $ 35 $ 655 690 690 $ 690 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: WSDOT Stormwater Retrofit & Maintenance Program Project Manager Sherry Edquid DESCRIPTION: JUSTIFICATION: Project # 32541201 Department Surface Water This entails reporting, designing and constructing stormwater control facilities that directly reduce stormwater impacts from state highways. The City of Tukwila operates a surface water utility and can collect these fees from Washington State Department of Transportation (WSDOT) if they utilize these funds directly towards reporting, planning and constructing stormwater control facilities that reduce impacts of runoff from state limited access highways or implementing best management practices that will reduce the need for these facilities. These conditions are further outlined in the Revised Code of Washington (RCW) Chapter 90.03.525. STATUS: This is an annual program with annual reporting required to WSDOT to utilize these surface water fees. MAINTENANCE IMPACT: Any maintenance expenses would need to be finalized into an ILA with WSDOT. COMMENT: The 2024 Surface Water Comprehensive Plan (SWCP) recommended two bioretion boxes locations underneath elevated highways structures and a maintenance project just north of Southcenter Boulevard and 1-5. We continue to bank the fund balance which receives approximately $150,000 annually. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Planning Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues otal Project Funding 2025 60 60 60 2026 $ 10 $ 100 $ 110 $ 110 110 2027 $ 10 $ 100 110 $ 110 110 2028 $ 10 $ 100 $ 40 $ 475 625 $ 625 625 2029 10 10 10 2030 10 $ 10 10 Beyond TOTAL 60 300 50 40 475 925 925 925 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Johnson Creek Fish Barrier Mitigation Alternatives Analysis Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72541202 Department Surface Water The goal of the project will be to identify a preferred solution to improve fish access to Johnson Creek while maintaining flood protection. King County 2019 study, "Juvenile Chinook Use of Non -natal Tributaries in Lower Green River", determined that flap gate is impassable to fish. Additionally, the City of Kent's Johnson Creek Floodplain Project (LG- 34 in WRIA 9 Habitat Plan) is dependent on fish passage into Johnson Creek. King County recently purchased 30 acres of former farmland in Kent adjacent to the Tukwila boundary and Johnson Creek to facilitate floodplain restoration, flood hazard management and agricultural use. Need to determine project responsibility The flapgate is on property owned by the Curran Law Group. Its construction was required and permitted by the City and WDFW. Project and subsequent maintenance responsibility is still being determined. Johnson Creek rerouted and flapgate placed as part of Tuwila South Development ca. 2010 per City and WDFW requirements. Property turned over to Drainage District No. 2 and subsequently transferred to Curran Law Group. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Contingency otat Project Costs Project Funding Utility Revenues otal Project Funding 2025 $ 5 $ 30 35 35 $ 35 2026 5 5 $ 5 2027 $ 2028 $ 2029 $ 2030 $ Beyond $ 5 20 25 20 $ 20 TOTAL $ 15 50 65 60 $ 60 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Chinook Wind Public Access Project Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 91441202 Department Surface Water King County purchased site and will restore it as a salmon estuary and passive park in partnership with the City. City CIP project is to develop public access and maintenance trail. Plan is to connect trail through PW shops to Duwamish Gardens. The WRIA 9 Salmon Recovery Plan recommends creating 20-acres of off -channel habitat within the Duwamish Transition Zone and lists this section of the river as critical habitat for salmon recovery within the Green/Duwamish Watershed. The project is currently under construction but the contract is suspended as of 6/11/24. Anticipating summer/fall completion. This is a work in progress. The Green Infrastructure Program Proposal is intended, in part, to address maintenance needs for PW-initiated habitat restoration projects and helping to alleviate pressure on Parks' given resource constraints. Note that vegetation management maintenance needs decrease over time as planted vegetation matures. 3 years is considered a rule of thumb for plant establishment. N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Contingency Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 5 $ 1 6 $ 6 6 2026 2027 2028 2029 2030 Beyond TOTAL $ 5 $ 1 6 6 6 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Fish Passage Barrier Prioritization Study Project Manager Sherry Edquid DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72541201 Department Surface Water The study would prioritize potential fish barrier removal projects based on feasibility, potential habitat gain, importance of the stream system for fish use, and coordination with other barrier removal efforts and water quality improvement efforts in the stream system. It was identified in the 2024 Surface Water Comprehensive Plan. Not started. This is only a study at this juncture and based on collected information it may make recommendations to fund future fish barrier removals. The presence of fish passage barriers in creeks/streams is a critical risk to salmonids. Fish passage barriers that can be corrected are human -made instream features that impede upstream fish passage, such as culverts, dams, and diversions. The Northwest Indian Fisheries Commission's online map of Statewide Integrated Fish Distribution identifies the presence of multiple fish species, including salmonids, in all Tukwila streams with the exception of Nelsen. The City supports removal of barriers. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 $ 30 $ 165 195 $ 195 2027 2028 2029 2030 Beyond TOTAL $ 30 165 195 195 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Fort Dent Park Water Quality Retrofit Project Manager Sherry Edquid DESCRIPTION: Project # 92541201 Department Surface Water This project will look at implementing water quality treatment for stormwater from the artificial turf fields that is collected in a pond and then pumped into the river. 6PPD-q is an emerging pollutant of concern that is known to cause fish mortality and is found in artificial JUSTIFICATION: turf fields that use recycled tires in the foundation. Preliminary studies have shown that some biofiltration technologies are successful in removing 6PPD-a from runoff. Over the next several years. Ecology could STATUS: Project was recommended in 2024 Surface Water Comprehensive Plan. MAINTENANCE IMPACT: COMMENT: N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Total Project Costs Project Funding Proposed Grant Utility Revenues Total Project Funding 2025 2026 2027 2028 2029 2030 Beyond $ 45 $ 400 445 $ 385 60 445 TOTAL $ 45 400 445 $ 385 60 445 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Green Infrastructure Program Project# 12541201 Project Manager Mike Perfetti Department Surface Water DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The proposed initiative addresses Citywide environmental element goals and addresses overlapping priorities among PW, DCD and Parks by creating a new mechanism to address tree canopy coverage, forest conservation and stewardship. Under this proposal, Public Works would establish an inventory of open space sites and assume operations of PW CIP habitat restoration sites and some future open space acquisitions. The maintenance of (components of) Public Works' initiated habitat restoration projects, the implementation of the City's Green Tukwila Program and acquisition and maintenance of open space properties reside with the City's Parks and Recreation Department, which has limited resources to implement these tasks and programs. The GIP would bring on additional staff, creating solid green industry job pathways, expanding Green Tukwila's capacity to meet program and plan goals, reduce Parks' maintenance burden, and work towards meeting City open space and environmental goals. PW and Parks have been working through a draft program proposal and the details of the arrangement are in progress. The proposal is for an ongoing program that could be largely funded through the surface water utility (similar to other cities; Snoqualmie is a good model). Utilizing these enterprise funds will relieve burden on the general fund, which largely funds Parks and DCD staffing. This proposal modifies the existing approach for stewardship and habitat restoration stewardship, which currently falls within Parks. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design otal Project Costs Project Funding Utility Revenues otal Project Funding 2025 2026 $ 5 $ 200 205 $ 205 205 2027 $ 5 $ 200 205 $ 205 205 2028 $ 5 $ 200 205 $ 205 205 2029 $ 5 $ 200 205 $ 205 205 2030 $ 5 $ 200 $ 205 $ 205 $ 205 Beyond $ 5 $ 200 205 $ 205 205 TOTAL $ 30 1,200 1,230 1,230 1,230 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager Joshua Hopkins DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Nelsen/Longacres Ph II Project# 98741202 Department Surface Water The proposed solution is to install a 48-inch stormwater pipe crossing underneath the Burlington Northern railroad tracks connecting to a previously installed interceptor east of the tracks. This 48-inch stormwater pipe will be constructed using trenchless techniques to minimize the impact to the operation of the railroad. This new pipe will provide drainage from the existing drainage ditch west of the tracks to the P-1 interceptor. Ownership, easement, and maintenance responsibility will be determined and/or verified prior to moving forward with this project. Because of development and increased surface water runoff, flooding is occurring in the right-of-way and on private property. The design objectives are reduction of stormwater ponding and peak flow rate. The project is located within the Burlington Northern Santa Fe (BNSF) corridor. Coordinate project progression with N/A N/A FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 2028 $ 1,100 $ 1,100 $ 1,100 $ 1,100 2029 2030 Beyond TOTAL 1,100 1,100 1,100 1,100 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM L CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: P17 Pond and Southcenter Subarea Hydraulic Study Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 72541205 Department Surface Water Before confirming feasibility of decommissioning the P17 Pond and the P17 Pump Station to support a setback of the levee for habitat uplift, the City must ensure that the detention and conveyance capacity they provide can be provided elsewhere in the Southcenter subarea. The City will study hydraulics in the Southcenter subarea, including most of the P17 Basin and the interrelated portions of the Gilliam Creek basin, Green/Duwamish basin, and Johnson Creek basin to determine alternatives for providing the needed detention storage and discharge of stormwater runoff to the Green River. The City is studying the feasibility of discontinuing use of the maintenance facility and selling the property. The King County Flood Control District may express an interest in purchasing the property and setting back the levee, consistent with project LG-35 identified in the WRIA 9 Salmon Recovery Plan approved on February 11, 2021. Listed as a high priority in the 2024 Surface Water Comp Plan. No O&M costs associated with a study. The levee adjacent to P17 Pond was shown by the Corps in its 2023 SQRA to have vulnerability given its height, steepness, vegetation characteristics, and proneness to erosion to due water fluctuations in the pond. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Planning Contingency otal Project Costs Project Funding Utility Revenues otat Project Funding 2025 2026 175 $ 175 175 2027 175 $ 175 175 2028 2029 2030 Beyond TOTAL 20 300 30 350 350 350 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 143rd Street Storm Drainage System Project Manager Joshua Hopkins DESCRIPTION: JUSTIFICATION: Project # 98641222 Department Surface Water Design and construct closed pipe drainage system along S. 143rd Street and S. 143rd Place. Provide a WQ treatment manhole and a flap gate at the outlet of the drainage system. Convert existing drainage ditch, located on private property, to a bioswale. Provide asphalt overlay, curb and gutter, and sidewalks for S. 143rd Street. Provide asphalt overlay for S. 143rd Place. Longstanding drainage and flooding problem on ROW and private property along S 143rd St, east of Interurban Ave. Project Issue ID # 9 in 2013 Plan, first appeared in 2003 SWCP. Project may be eligible for grant funding from King County Flood Control District. New conveyance system will reduce ROW and private property flooding. Bioswale will treat stormwater runoff before it's routed to the Duwamish River. Flap gate will help prevent flooding when the Duwamish River is at high stages. STATUS: Scope, schedule, and budget need to be updated for funding allocation and potential grant opportunities. MAINTENANCE IMPACT: COMMENT: Seasonal WQ service of CB will be required. Couple hours per year. Assumes that parking adjacent to existing ditch will not be disturbed. Potential for LID/ND improvements are not included in estimated cost. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 $ 30 $ 200 $ - $ 230 $ 230 230 2027 $ 30 $ - $ 200 $ 1,410 $ 1,640 $ 1,640 $ 1,640 2028 2029 2030 Beyond TOTAL 60 200 200 1,410 1,870 $ 1,870 1,870 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Ryan Way Pipe Rehabilitation Project Manager Joshua Hopkins DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 92541202 Department Surface Water This project proposes to replace or repair all existing 12-in and 18-in diameter storm sewer pipes and catch basins within S Ryan Way in coordination with an eventual overlay or reconstruction. There is poor pipe condition along S Ryan Way and there are associated drainage issues. Paving is needed. If brought down to the base of the road, stormwater standards will be triggered which includes the flow control threshold. Possible solution would be funded by the Transportation funds. If the City decides to construct full roadway improvements along S Ryan Way, this may trigger stormwater requirements for flow control and runoff treatment. This project does not address flow control N/A N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 2028 2029 2030 Beyond $ 25 $ 840 865 $ 865 865 TOTAL $ 25 840 865 $ 865 865 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: S 146th St Pipe & 35th Ave S Drainage System Project# 90341214 Project Manager Sherry Edquid DESCRIPTION: Department Surface Water Replace existing storm drainage system on S 146th St and provide new storm drainage system for 35th Ave S. Provide asphalt overlay and extruded asphalt curb for both streets. JUSTIFICATION: Reduce right-of-way and private property flooding by increasing the capacity of the storm drainage system. STATUS: MAINTENANCE IMPACT: COMMENT: Maintenance is monitoring area during storm events. Expanded system will require additional maintenance. This project was identified in the 2003 Surface Water Management Comprehensive Plan and again in the 2024 plan. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 $ 2026 $ 2027 $ 2028 $ 2029 $ 30 $ 250 $ 280 $ 280 280 2030 $ 45 $ - $ 160 $ 1,400 $ 1,605 $ 1,605 $ 1,605 Beyond TOTAL 75 250 160 1,400 1,885 1,885 1,885 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Tukwila Parkway Gilliam Creek Outfalls Project Manager Mike Perfetti DESCRIPTION: JUSTIFICATION: STATUS: Project # 91241205 Department Surface Water The project expands the scope of CI P 91241205 in the City's 2021-2026 Capital Improvement Program and updates the costs. The existing 48-in diameter manhole will be replaced with an 84-in diameter manhole in Andover Park W just south of the intersection with Tukwila Parkway. A flapgate will be installed on the outgoing pipe. A manhole will be constructed over the 30-in diameter pipe on the south side of Tukwila Parkway and a flapgate installed. As a part of this project, ownership of the pipe should be confirmed. If the pipe is currently privately owned, the ownership and maintenance should be transferred to the City. The project will also add a water quality treatment device. The addition of flapgates on the 48-in diameter and the 30-in diameter storm pipes will isolate the pipes from the downstream 108-in diameter Washington State Department of Transportation (WSDOT) culvert under the 1-405 freeway to allow the City of Tukwila to inspect and maintain the 48-in diameter and the 30- in diameter storm pipes. This project relates the Gilliam Creek Fish Barrier Removal Project as well as the P-17/Southcenter Area Hydraulic Study. MAINTENANCE IMPACT: costs to inspect and maintain 1 catch basin and 1 water quality biofiltration media vault COMMENT: N/A FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction Contingency Total Project Costs Project Funding Utility Revenues Total Project Funding 2025 2026 2027 2028 2029 2030 $ 15 $ 260 $ 30 $ 305 $ 305 $ 305 Beyond $ 30 $ - $ 150 $ 950 $ 100 $ 1,230 $ 1,230 $ 1,230 TOTAL 45 260 150 950 130 1,535 $ 1,535 1,535 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Tukwila Pond Water Quality Improvement Project# 92541204 Project Manager Joshua Hopkins DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Department Surface Water The project aims to allow Tukwila's Public Works Department to support water quality treatment for surface water runoff draining to the Tukwila Pond, as part of the Tukwila Pond Park Master Plan (Master Plan) improvements. The Parks and Recreation Department will carryout the implementation of the Master Plan, including hiring and managing consultants for design, permitting and construction negotiations, and leading discussions with private property owners. The Public Works Department will contribute funds to support the design and construction of stormwater runoff treatment facilities described in this fact sheet. The recommended water quality improvements are planned for construction during Phases 1 B through 6 in the period spanning 2024 to 2038, as specified in the Master Plan. The Tukwila Pond has high phosphorus, turbidity, and high temperature under existing conditions. It is fed largely by groundwater during the summer and has additional input from precipitation and two nearby swales, which treat runoff from adjacent commercial properties. Groundwater and soils are likely contributing to nutrient loading of the pond, suggesting that even if water quality improves, it may remain high in nutrients. Additionally, there is limited treatment for surface runoff and piped stormwater entering the pond. The pond drains into the Green River either through Gilliam Creek or through pumped and piped conveyances. The Green River in this area is on the Washington State Department of Ecology's list of impaired waters (303(d) list) for temperature, dissolved oxygen, and fecal coliform. Project is contingent on Tukwila Pond Master Plan preferred alternative. N/A The Master Plan recommends further study to compare alternatives and determine the preferred option or combination of options for the water quality treatment described above. The Public Works Department's Surface Water Program plans to support the study, engineering design, and construction of the runoff treatment facilities, within the larger effort to be implemented by the Parks and Recreation Department. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Design Construction Mgmt. Construction otal Project Costs Project Funding Utility Revenues 'Total Project Funding 2025 2026 2027 2028 2029 2030 Beyond $ 30 $ 197 $ 100 $ 656 983 $ 983 983 TOTAL 30 197 100 656 983 983 983 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM Fund Cost in Thousands (000s) Foster Golf (411) JL Key - Project 2025 12026 12027 Name 11641112 Parks/Golf Maintenance Shop Fuel Depot/Area Redesign 2028 o a After Costs six _illyears $200 $- $- $- $- $- $200 $- 11641106 Foster Golf $150 $150 $150 $150 $150 $150 $900 $150 Links Greens Remodels 11641101 Foster Golf $91 $95 $58 $61 $64 $67 $436 $71 Links Cart Purchases 11641108 Foster Golf $75 $75 $75 $75 $75 $75 $450 $75 Links Tees Remodels 11641103 Foster Golf $50 $53 $56 $59 $62 $65 $345 $68 Links HVAC Replacement 11641110 Fleet $49 $92 $- $- $- $- $141 $- Purchases 11641105 Foster Golf $- $- $- $- $- $1,300 $- Links $1,300 Clubhouse Solar Panels 11641107 Foster Golf $- $200 $- $- $- $- $200 $- Links Course Pump House 11641109 Foster Golf $- $- $- $- $- $2,100 $- Links $2,100 Irrigation Replacement 11641111 Foster Fence $- $155 $- $- $- $- $155 $- Total $675 $820 $3,739 $345 $351 $357 $6,227 $364 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKVVILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Project Manager DESCRIPTION: JUSTIFICATION: STATES: MAINTENANCE IMPACT: COMMENT: Parks/Golf Maintenance Shop Fuel Depot/Area Ryan Rosevear Redesign and general bringing up to code for the fueling area Located at the joint Parks/GoLf Maintenance Shops. Redesign of the fueL depot/area at the parks/golf shops is necessary for safer manuevering of vehicLes on site asweLL es maintaining the area up to necessary fire, safety, and otherfedereL, state, and Local_ Laws, statutes, and reguLetions Project# 11641112 Redesign Department Golf Course Design/Permitting needs to be determined Unsure of anypotentieL M&O impacts bye reconfiguration, generaL fund maybe responsibLe for any changes or at Least partially show as the site is shared by the Foster GoLf Links and Parks teams N/A FINANCIAL (in thousands) Project Costs Design Planning Construction Total Project Costs Project Funding Fund BaLance Total Project Funding 2IJ25 $ 25 $ 25 $ 150 $ 200 $ 200 $ 200 2026 $ $ $ $ $ $ 2027 $ $ $ $ $ $ 2028 2029 2030 $ - $ Beyond $ $ $ $ $ $ TOTAL S 25 S 25 $ 150 $ 200 $ 200 200 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Course Greens Remodels Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: STATUS: Project # 11641106 Department Golf Course Replacement of greens areas at the Foster Golf Links course Most greens areas at the course are in their original or near -original condition since their creation on the course, meaning some are almost 100 years old. New configurations of areas can improve drainage, playability, and ease of maintenance, providing for greater revenues, lower maintenance costs, and better ecological outcomes on the course. A recent remodel of the #7 Green was completed in Late FY23/Early FY24. Staff will continue to prioritize greens for remodel as funds become available. MAINTENANCE IMPACT: Remodelling of Greens would likely reduce M&O costs incurred by the Foster Golf Links fund. COMMENT: Goal would be to on average replace a green or tee once per fiscal year FINANCIAL (in thousands) Project Costs Design Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 20 $ 130 150 150 150 2026 $ 20 $ 130 150 150 150 2027 $ 20 $ 130 150 150 150 2028 $ 20 $ 130 150 150 150 2029 $ 20 $ 130 150 150 150 2030 $ 20 $ 130 $ 150 $ 150 $ 150 Beyond $ 20 $ 130 150 150 150 TOTAL $ 140 $ 910 1,050 1,050 1,050 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Folf Links Cart Fleet Purchases Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 11641101 Department Golf Course Replacement of FGL cart fleet to maintain optimal age of golf carts optimal for operational reliability and efficiency. The FGL Golf Cart Replacement Plan, if maintained in the long-term, provides for a cart fleet with golf carts at a maximum of 7 years old, maximizing operational efficiency/stability of the fleet while providing for a high level of customer satisfaciton and comfort with the fleet in place. Ongoing Maintaining an optimally aged golf cart fleet would likely allow for a reduction in M&O costs incurred by the Foster Golf Links fund. FGL Golf Cart Fleet needs are determined by the Head Golf Pro FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Dedicated/Restricted Rev Fund Balance Total Project Funding 2025 91 91 $ 46 45 $ 91 2026 95 95 $ 95 $ 95 2027 58 58 $ 48 47 $ 95 2028 61 61 $ 31 30 $ 61 2029 64 64 $ 32 32 $ 64 2030 $ 67 $ 67 $ 34 $ 33 $ 67 Beyond 71 71 $ 36 $ 35 71 TOTAL 507 507 $ 322 222 544 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Course Tees Remodels Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: Project # 11641108 Department Golf Course Replacement of the tee areas at the Foster Golf Links course Most tees areas at the course are in their original or near -original condition since their creation on the course, meaning some are almost 100 years old. New configurations of areas can improve drainage, playability, and ease of maintenance, providing for greater revenues, lower maintenance costs, and better ecological outcomes on the course. STATUS: Staff will prioritize tees for remodel as funds become available. MAINTENANCE IMPACT: Remodelling of Tees would likely reduce M&O costs incurred by the Foster Golf Links fund. COMMENT: Goal would be to on average replace a green or tee once per fiscal year FINANCIAL (in thousands) Project Costs Design Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 25 $ 50 $ 75 75 75 2026 $ 25 $ 50 $ 75 75 75 2027 $ 25 $ 50 $ 75 75 75 2028 $ 25 $ 50 $ 75 75 75 2029 $ 25 $ 50 75 75 75 2030 $ 25 $ 50 $ 75 $ 75 $ 75 Beyond $ 25 50 75 75 75 TOTAL $ 175 $ 350 525 525 525 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Clubhouse HVAC Replacement Project# Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: Department Golf Course Replacement of HVAC units for the Foster Golf Links clubhouse. 11641103 Maintaining proper HVAC functionality of the Foster Golf Links clubhouse is necessary for ensuring staff and customer comfort on -site, ensuring maximized revenue for the golf course and on -site concessionaire. STATUS: Staff goal is to replace an HVAC unit at the clubhouse annually. MAINTENANCE IMPACT: Replacement of aging HVAC units would likely reduce M&O costs incurred by the Foster Golf Links fund. COMMENT: Certain units may be the responsibility of the on -site concessionaire depending on what areas of the clubhouse the unit services. This is a high priority project. FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Dedicated/Restricted Rev Fund Balance Total Project Funding 2025 $ 50 $ 50 $ - $ 50 50 2026 53 $ 53 $ 53 53 2027 $ 56 $ 56 $ 56 56 2028 59 $ 59 $ 59 59 2029 62 $ 62 $ 62 62 2030 $ 65 $ 65 $ 65 $ - $ 65 Beyond 68 68 $ 68 68 TOTAL 413 413 $ 254 159 413 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Operations Fleet Purchases Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 11641110 Department Golf Course Replacement of FGL operations fleet equipment as older equipment begins to meet their service life end. Proposed purchases for FY25 include a Utility Cart and Roller. Proposed purchases for FY26 include a Blower, Top Dresser, and Utility Cart. Maintaining an adequately prepared operations fleet lowers maintenance costs and provides for operational reliability and stability Ongoing Maintaining an optimally aged operations cart fleet would likely allow for a reduction in M&O costs incurred by the Foster Golf Links fund. FGL Operations Fleet needs are determined by the FGL Operations Superintendent FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 $ 49 49 49 49 2026 92 92 92 92 2027 2028 2029 2030 Beyond TOTAL 141 141 141 141 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Clubhouse Solar Panels Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: Project # 11641105 Department Golf Course Installation of solar panels on the roof of the Foster Golf Links clubhose. Installation of solar panels at the Foster Golf Links would reduce fixed cost of operations both for the course as well as for the on -site conessionaire, improviing long-term liquidity and solvency for both parties. Furthermore, there have been legislative proposals in recent years that would eventually ban the sale/usage of small gasoline engines such as those used by golf carts, self -generation of electricity on site would better prepare the course for transition to electric golf carts that may eventually be required. A preliminary Rough Order of Magnitude (ROM) estimate has been obtained. Staff continue to seek state funding sources such as those from the Climate Commitment Act to support this project. Staff does not believe installation of solar panels would create and any new M&O needs for either the Foster Golf Links or General Funds. N/A FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Proposed Grant Total Project Funding 2025 2026 2027 $ 1,300 $ 1,300 $ 1,300 $ 1,300 2028 2029 2030 Beyond TOTAL 1,300 1,300 1,300 1,300 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Course Pump House Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: STATUS: Project # 11641107 Department Golf Course Rehabilitation/Replacement of key components/assets in place at the pump house that provides water for the entire Foster Golf Links. The Pump House located at the Foster Golf Links is a pivotal component necessary for drawing the course's irrigation water from the Duwamish River. Failure of this component jeopardizes revenue earning operations. Full estimates still needed MAINTENANCE IMPACT: Do not believe this project would have any impact on M&O costs. COMMENT: Higher priority project FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 $ 200 200 200 200 2027 2028 2029 2030 Beyond TOTAL 200 200 200 200 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Irrigation Replacement Project Manager Ryan Rosevear Project # 11641109 Department Golf Course DESCRIPTION: Full replacement of the irrigation system throughout the entire Foster Golf Links course. JUSTIFICATION: STATUS: MAINTENANCE IMPACT: COMMENT: The irrigation system on -site at the Foster Golf Links is currently well in excess of its expected service life. Operations staff continue to monitor and respond to line breaks as promptly as possible. However, a main line break of the system could threaten a full shutdown of the course. Irrigation replacement with longer lasting components could guarantee course operational stability for upwards of 50 years. Lastly, it is probable that irrigation replacement would provide for less water loss on the course, helping meet city sustainability goals. Estimates were obtained about three years ago. They may need to be redone due to recent inflationary pressures. Potential funding sources are currently being identified/sought at the local, county, and state level. Feasibile that a newly installed system would lower M&O costs incurred by the Foster Golf Links fund as response maintenance needs would lower and water loss within the system would lower as well. Failure to complete this project poses a high risk to ongoing golf course operations stability and revenue generation in the event of a system failure. FINANCIAL (in thousands) Project Costs Construction Total Project Costs Project Funding Proposed Grant Total Project Funding 2025 2026 2027 $ 2,100 $ 2,100 $ 2,100 $ 2,100 2028 2029 2030 Beyond TOTAL 2,100 2,100 2,100 2,100 CITY OF TUKWILA 2025-2030 CAPITAL IMPROVEMENT PROGRAM CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2025 to 2030 PROJECT: Foster Golf Links Perimeter Fence Project Manager Ryan Rosevear DESCRIPTION: JUSTIFICATION: STATUS: Project # 11641111 Department Golf Course Installation of permeter fence around the playing area of the Foster Golf Links. Provides for greater security for course land and assets, preventing misuse/unpaid use of the course, and protecting golf carts against theft. Also, by potentially stopping accidental entrance to the course by non-playing individuals, lessens liability risk to the city from injury. Estimates have been received, funding source has yet to be determined, and project may be lower priority than others proposed for Fund 411. Maintenance would be minimal, what is necessary to address routine maintenance as well as any potential MAINTENANCE IMPACT: replacement of components as they break. Responsibility would fall to the Foster Golf Links fund although labor may be provided for by the Parks Department. COMMENT: Unpaid use of the course continues to be an issue threatening revenue generation. A fence could also further protect the course from theft and/or vandalism. FINANCIAL (in thousands) Project Costs Project Mgmt (Staff Time/Cost) Construction Total Project Costs Project Funding Fund Balance Total Project Funding 2025 2026 $ 5 $ 150 155 155 155 2027 2028 2029 2030 $ - $ - Beyond $ TOTAL $ 5 150 155 155 155