HomeMy WebLinkAboutWS 2024-11-04 Item 3A - 2025-2026 Biennial Budget - 6-Year Capital Improvement Program (2025-2030)-I.
Budget Overview & Capital
Planning
• Capital Planning and Funding
• 2025-26 Capital Project Overview
• Key Policy Questions
City of Tukwila 2025-26 Budget Development 2
Capital Improvement Program Overview
▪ Six (6) Year Capital Improvement Program (CIP)
• priority investments in infrastructure and facilities
• Reviewed and updated every 2 years
▪ The CIP is fiscally constrained: projects must have
funding identified to be included in the CIP
Capital Budget = Reflects the first 2 years of the CIP
Revenue sources include grants, impact fees, taxes
restricted to capital projects (e.g. Real Estate Excise
Tax), and bond proceeds. Very little General Fund
revenues (except for debt service repayment) are used
to fund capital projects.
rirftf,RflrTtlft-ly!-rTF!a-t.Ni-g-v
City of Tukwila 2025-26 Budget Development
CA)
CIP Planning Process
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
City of Tukwila 2025-26 Budget Development 4
What's in a CIP?
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2025 to 2030
STATUS
FINANCIAL (in thousands)
Project Costs
iPro/sot Marta (Staff Tinie/Cost)
Design
Land (R/W)
_Construction Planet,
_Construction
Contingency
Total Project Costs
Project Funding
Proposed Grant
Dedicated/Restricted Rev
iFond Balance
Utility Revenues
Genera) Fund Transfer
Total Project Funding
040
2025 2026 2027 2028 2029 2030 Beyond TOTAL
15
600
300
$ 21
$ -
$ -
$ 1,530
$ 9,960
$ 1,270
ESEESIE111111111EMEN131111111EMIN
I 1111
$ 400 $ 8,650
$ 500 $ .
$ 15 $ 21
$ -
$ - $ 1,690
$ 2,420
EMINIEW511=1111ENESIIMEI
$ 36
$ 1,275
$ 300
$ 1,530
$ 9,960
$ 1,270
$ 14,371
9,050
1,175
36
1,690
2,420
$ 14,371
Project design, land acquisition,
construction costs and the projected
means of financing are integral.
components of this ptan.
• Estimated overall cost of each project
• Estimated operational and
maintenance cost for each project
• Estimated project timelines
• Funding sources
• Project prioritization
City of Tukwila 2025-26 Budget Development
5
01
Consideration Factors
Financial Maintenance Continue Public
factors feedback Existing feedback
CIP
Grant Subject Existing Part of
availability; matter projects planning and
Fund balance; experts in carry over design process
Cost versus the field year-to-year
benefit; Sunk everyday
costs;
Avoided
costs;
Stewardship
Effectiveness
Mandates
irr..tZt
Timing/ Scaling
Urgency
Alignment Meet new Project Level of
with City requirements readiness; Service (LOS);
mission and or law (comp linkage to Engineer
values plans, etc.) other high availability;
priority Right project
projects at this time
City of Tukwila 2025-26 Budget Development 6
Funding of Capital Projects
Impact Fees
Franchise
fees
Real Estate
Excise Tax
Land Sates
Concurrency
fees
Grants
Solid Waste
Utility Tax
Bonds
(dedicated
revenues)
City of Tukwila 2025-26 Budget Development 7
v
00
6 YEAR CAPITAL
IMPROVEMENT PLAN
City of Tukwila 2025-26 Budget Development
Capital Improvement Program
Select Financial Policies
• Leverage grants, loans or other
external financing options
• Avoid relying on General Fund
support
• Non -transportation capital projects
and improvements should be
funded by operating revenues,
grants or bonds
• Residential streets with safety
issues, high traffic volumes, high
pedestrian activity and poor
roadway conditions prioritized
higher
• REET 1 dedicated to park and open
space land acquisition & arterial
streets; Public Safety Plan debt
service
• REET 2 dedicated to Bridges &
Arterial Streets
• Transportation Impact Fees (TIF) to
support growth
City of Tukwila 2025-26 Budget Development 9
Principles Informing 6 Year CIP
• Pay-as-you-go capital
improvement program
• Maintain what we have
approach
• "Growth pays for growth"
• Prioritize deferred maintenance
and safety needs
• Complete Public Safety Plan -
Address PW Shop facility needs
• Update & pursue ADA
Transition Plan improvements
City of Tukwila 2025-26 Budget Development
10
6 Year CIP Project Type Summary
Arterial Streets (104)
• City Facilities (303)
• Special Projects (000)
• Golf Course (411)
Parks & Trails (301)
fd New Facilties (306)
• Residential Streets (103)
• Sewer (402)
Surface Water (412)
• Water (401)
138 Projects
Gilliam Creek Fish Barrier Removal Project
.4r7
loft, ,Aiaireft;
City of Tukwila 2025-26 Budget Development
11
Project Type Summary
Not Asset -Producing
13%
New Construction/New
Equipment
160/0
Annual Program
16%
ajor Improvement of
Existing Asset
54%
DUWAM1SH PARK I Ste Artotysis4 Cordezt
City of Tukwila 2025-26 Budget Development
12
Project Information & New Features
• Capital Projects Web Pages
City of Tukwila 2025-26 Budget Development
Beverly Park
`i2ath S
Boulevard Park
Southern
Heights
4 aTc Riverton
Park
Evansville Foster
High line
Five Corners
Skyway
[atone -
SeaTac
Riverton
Heights
dth
Tukwila
Fort
Earlington Hill
2 YEAR
CAPITAL IMPROVEMENT
BUDGET
C'ty of Tukwila 2025-26 Budget Development
Factors Impacting 2025-26 CIP
• Significant planning efforts
completed in 2023-24- well
positioned for local, state and
federal grants
• Costing and Sourcing Challenges
• Cost escalation/inflation
• Sourcing lead times for equipment
and materials
• World Cup 2026- preparations &
mitigating construction impacts
on visitors
• No dedicated funding source for
Facilities
• Minimizing impacts on the GF-
less reliance on the GF for capital
and O&M
• Increased cross -departmental
alignment in managing green
infrastructure- integrating
programs and services
City of Tukwila 2025-26 Budget Development 16
Funding Characterization
0.838M, 1
■ Grants
Utilities
Dedicated Revenues/Fund
Balance
■ General Fund Transfer
City of Tukwila 2025-26 Budget Development 17
v
For Every Million Dollars...
KUE
NO-KOMILL
SO.F. PURPOSE S
PE.IVMS SKtikt f,ENTS
Grants
$426,070
Utility Funds
S328,222
5 0 1 8 7 5 1 A
Art. -ANT .GA
Dedicated Revenues General Fund
$235,329 $10,379
*Dedicated Revenues include: Lodging Tax, King County Parks Levy, Transportation Impact Fees, Solid Waste Utility Tax, Real Estate Excise Tax (REET), Impact Fees etc.
City of Tukwila 2025-26 Budget Development 18
Project Type Summary
Arterial Streets (104)
• City Facilities (303)
• Golf Course (411)
„.„. Parks & Trails (301)
New Facilities (306)
Residential Streets (103)
• Sewer (402)
11 Surface Water (412)
• Water (401)
City of Tukwila 2025-26 Budget Development 19
Grant Administration
$34.4M in potential/awarded grants
identified in the next biennium
43% of project costs
City of Tukwila 2025-26 Budget Development 20
Project Highlights
2025-26 Capital Improvement Program
• Ryan Way Infrastructure Improvements
• World Cup Preparations
• PW Shops Phase 2
• Facility Roof Replacements
• 152nd Avenue Improvements
• 42nd Ave Bridge Replacement
• Boeing Access Road Bridge Deck
• Strander Boulevard Extension
• City Hall 16300 Building I TCC
• Park & Trail Master Plans
• FGL Irrigation System Replacement
• Tukwila Pond Improvements
City of Tukwila 2025-26 Budget Development 21
2025-26 CIP Preview- Key Issues & Projects
Issues/Challenges
jit
Addressing Deficiencies & Deferred Maintenance/Backlog
Less reliance on General Fund support for Capital
Advancing ADA Projects & Transition Plan
Lack of Dedicated funding For Capital Facilities
Increased funding for Annual Overlay Program
ARPA Funds Expiring at Year -End
City of Tukwila 2025-26 Budget Development 22