HomeMy WebLinkAboutReg 2024-11-04 Item 5F - Grant Acceptance - 2 Grants for 42nd Ave S Bridge Final Design and Construction with WA Department of Transportation for $12,000,000 and $17,000,000 (Total $29,000,000)COUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Mayor's review
Council review
11/04/24
JR
ITEM INFORMATION
ITEM No.
5.F.
STAFF SPONSOR: CATRIEN DE BOER
ORIGINAL AGENDA DATE: 11/04/24
AGENDA ITEM TITLE 42nd Ave S Grants — Final Design and Construction Grants
WSDOT Local Bridge Program and Move Ahead Washington Program
CATEGORY ❑ Discussion
Mtg Date
a
Motion
Date 11/04/24
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
Mtg
SPONSOR ❑Council ❑Mayor HR ❑DCD ❑Finance ❑Fire TS P&R ❑Police 11PJV ❑Court
SPONSOR'S In 2021, City staff were notified that we received the full grant award of $12,000,000 from
SUMMARY the Local Bridge Program for the bridge replacement. In 2022, City staff were notified that
we received the full grant award of $17,000,000 from the MAW Program. The City expects
to use these for final design and construction expenses. Council is being asked to accept
two grants to fund final design and construction of the 42nd Ave S Bridge in the amounts of
$12,000,000 and $17,000,000 for a total of $29,000,000.
REVIEWED BY
a Trans&Infrastructure
❑ CommunitySvs/Safety
❑ Arts Comm.
10/28/24
Finance
❑ Parks
Comm. ❑ Planning/Economic Dev.
Comm. ❑ Planning Comm.
CHAIR: ARMEN PAPYAN
LTAC
DATE:
COMMITTEE
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMII°IEE
Public Works Department
Unanimous Approval; Forward to the Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$29,000,000 $0.00 $0.00
Fund Source: GRANT AWARD
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
10/07/24
MTG. DATE
ATTACHMENTS
10/07/24
Informational Memorandum dated 09/20/24
Award letters
Vicinity Maps
Minutes from Transportation and Infrastructure Committee meeting of 10/28/24
(distributed separately)
59
60
City of Tukwila
Thomas McLeod, Mayor
Public Works ❑eportment - Pete Moyer, Interim Director
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Services Committee
FROM: Pete Mayer, Deputy City Administrator/ Interim Public Works Director
BY: Catrien de Boer, Public Works Analyst
CC: Mayor McLeod
DATE: October 25, 2024
SUBJECT: 42"d Ave S Grants — Final Design and Construction Grants
Project No. 91840404
WSDOT Local Bridge Program and Move Ahead Washington Program
ISSUE
Accept two grants for the final design and construction of the 42nd Ave S Bridge: Local Bridge Program
in the amount of $12,000,000 and Move Ahead Washington (MAW) Program in the amount of
$17,000,000 for a total of $29,000,000.
BACKGROUND
In 2019 and 2020, Council authorized staff to submit applications to the Local Bridge Program and the
MAW Program to fund the replacement of the 42nd Ave S Bridge. The 42nd Ave S Bridge is structurally
deficient and is on track to be replaced in the coming years.
DISCUSSION
In 2021, City staff were notified that we received the full grant award of $12,000,000 from the Local
Bridge Program for the bridge replacement. In 2022, City staff were notified that we received the full
grant award of $17,000,000 from the MAW Program.
FISCAL IMPACT
The City was awarded $29,000,000 in grant funding for the complete replacement of 42nd Ave S
Bridge. The City expects to use the Local Bridge Program grant for construction expenses, which
reimburses at 100% (no local city match) if obligated before Sept. 2026. The City expects to use the
MAW Grant for final design and construction, which reimburses at 100% (no local city match).
Project Budget
Local Bridge Program $12,000,000
Move Ahead Washington $17,000,000
Total $29,000,000
RECOMMENDATION
Council is being asked to accept two grants to fund final design and construction of the 42nd Ave S
Bridge in the amounts of $12,000,000 and $17,000,000 and consider this item on the Consent Agenda
at the November 4th Regular Meeting.
Attachments: Award Letters (Local Bridge Program and Move Ahead Washington)
Vicinity Map
61
62
Ti;Washington State
AMR
Department of Transportation
July 15, 2021
Mr. Hari Ponnekanti, P.E.
Interim Public Works Director
City of Tukwila
6300 Southcenter Blvd., Suite 100
Tukwila, Washington 98188
Transportation Building
310 Maple Park Avenue S.E.
P.O. Box 47300
Olympia, WA 98504-7300
360-705-7000
TTY: 1-800-833-6388
www.wsdot.wa.gov
42nd Ave South Bridge
FFY 2021 Local Bridge Program Selections
Federal Funding
Dear Mr. Ponnekanti•
WSDOT is pleased to advise you that the above -mentioned bridge project was recently
selected to receive funding through the Local Bridge Program. The federal funding is
limited to the amount shown below:
42nd Ave South Bridge $12,000,000
Scope: Replacement
NOTE: This project requires a 13.5% local match during the preliminary engineering/design
and right of way phases. Projects that authorize construction by December 2024, are eligible
for 100% federal fundingfor eligible costs. If construction is authorized after December 2024,
13.5% local match is required.
In order to meet state and federal requirements, the following are required:
• Project expenditures incurred before receiving notice from Local Programs of federal
fund authorization are not eligible for reimbursement.
• Please refer to the Local Programs webpage for detailed information, including:
(http://www.wsdot.wa.gov/localprograms/)
✓ Local Agency Guidelines (LAG) manual for the requirements regarding
programming, authorization, reimbursement, etc.;
✓ Projects utilizing federal funds must be included in your current
Transportation Improvement Program (TIP) as a complete programmed
project. Once your TIP amendment is approved, WSDOT will amend the
Statewide Transportation Improvement Program (STIP);
✓ Funding and billing forms;
✓ Quarterly Project Reporting is required to be completed by the end of March,
June, September, and December each year. To access the database you will
need an account name and password. Your account name is Tukwila and
your password is Tukwi785. The password is case sensitive.
• If the project is not actively pursued, or becomes inactive (23 CFR 630), the project
is at risk of being cancelled, funds repaid and reprogrammed.
63
Hari Ponnekanti, P.E.
Interim Public Works Director
City of Tukwila
42nd Ave South Bridge
July 15, 2021
• FHWA requires that all projects are ADA compliant upon completion or the federal
funds must be repaid.
As a reminder, Local Programs requires all agencies to submit monthly progress billings to
ensure timely reimbursement of eligible federal expenditures. Also, it is critical that your
agency adhere to the project schedule previously provided, to ensure the delivery of the local
federal program.
For assistance please contact Mehrdad Moini, your Region Local Programs Engineer, at
206.440.4734.
Sincerely,
57-&-p-hermie-Tax
Stephanie Tax
Interim Director
Local Programs
SJT:sas
cc: Kelly McGourty, Transportation Director, PSRC
Mehrdad Moini, Northwest Region Local Programs Engineer, MS NB82-121
64
WWashington State
AIII Department of Transportation
March 31, 2022
Mr. Hari Ponnekanti, P.E.
Public Works Director
City of Tukwila
6300 Southcenter Blvd., Suite 100
Tukwila, Washington 98188
Transportation Building
310 Maple Park Avenue S.E.
P.O. Box 47300
Olympia, WA 98504-7300
360-705-7000
TTY: 1-800-833-6388
www.wsdot.wa.gov
42nd Avenue Bridge
Move Ahead WA — Capital Projects
2022 Supplemental Transportation Budget
State Funding
Dear Mr. Ponnekanti•
WSDOT is pleased to advise you that the above -mentioned project was selected to receive
funding in the 2022 Supplemental Transportation Budget through the Move Ahead
Washington (MAW) — Capital Projects program. The state funding is limited as shown
below:
42nd Avenue Bridge $17,000,000
2021-23 Available Funding: $17,000,000
Scope: Complete replacement of the existing bridge which is structurally deficient and
functionally obsolete.
In the event the 2021-23 funding is not all reimbursed, WSDOT will request the remaining
funding through the 2023-25 budget development. Until the funding is provided by the
legislature, WSDOT can only reimburse your agency for the approved work completed each
biennium, as reflected above. Therefore, it is critical that the Local Project Report is
updated detailing the project's delivery, so that the funding aligns with the schedule.
In order to meet the state requirements, the following are required:
• Project expenditures incurred before receiving notice from Local Programs of state
fund authorization are not eligible for reimbursement.
• Please refer to the Local Programs webpage for detailed authorization information
including: (https://wsdot.wa.gov/business-wsdot/support-local-programs)
✓ Local Agency Guidelines (LAG) manual for detailed requirements;
✓ Transportation Improvement Program (TIP) and Statewide Transportation
Improvement Program (STIP) amendments, as applicable;
✓ Funding and billing forms;
✓ Local Project Report is required to be completed by the end of June and
December each year. To access the database you will need an account name
and password. Your account name is Tukwila and your password is
Tukwi785. The password is case sensitive.
65
Hari Ponnekanti, PE
City of Tukwila
42nd Avenue Bridge
March 31, 2022
Local Programs encourages all agencies to submit monthly progress billings to ensure
timely reimbursement of eligible expenditures.
For assistance please contact Mehrdad Moini, your Region Local Programs Engineer, at
206.440.4734.
Sincerely,
/6?-i---
Jay Drye, PE
Director
Local Programs
JD:st:ml
cc: Kelly McGourty, Transportation Director, PSRC
Mehrdad Moini, Northwest Region Local Programs Engineer, MS NB82-121
66
White [enter
Mt View
Bunco
Normandy
Park
Tukwila
eaTac
sE Npwp°'r N,
Newcastle
Cougar
Moun rain
Sq
Ms a
East Renton Rd
Highlands
Renton
42nd Avenue S Bridge Replacement Project
Vicinity Map
i
tis
Duwarnish
S 112th 5t
5fi5lb5�
5 160 5t
Tukwila
Community
1-3
Center a
c r4
0
99 er
n
pi ▪ lf▪ l
Riverron
q- 4P
42"d Avenue S
Bridge
Idd
-
w
7-
4.2
Lri
Ln
S JraLO S S
S Leo 5t
5 Ryar1 5E
57 t h AVe 5
59th Ave S
,RtrOrt
Burlington-Northern/Santa Fe Railroad
Intermodal Freight Facility
Anenta
0
s 133 rd 'L
5 140[h St
Access Path
Foster
▪ re5
r Sr
Foster Golf.
Links
64th Ave 5
Skyway
Baker Commodities
67