HomeMy WebLinkAboutTIS 2025-05-28 Item 2G - Resolution - 2025-2030 Transprotation Improvement ProgramCity of Tukwila
Thomas McLeod, Mayor
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Services Committee
FROM: Pete Mayer, Interim Public Works Director
BY: Cyndy Knighton, Senior Program Manager
CC: Mayor McLeod
DATE: May 23, 2025
SUBJECT: Resolution for Six -Year Transportation Improvement Program (2026 - 2031)
ISSUE
Approve a Resolution adopting the annual update of the Six -Year Transportation Improvement Program for
2026 - 2031.
BACKGROUND
The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of
Washington (RCW) 35.77.010. The TIP is adopted by resolution after a public hearing at the local agency
level and incorporated into regional and state TIPs. The TIP is primarily a financial planning document for
projects competing for grants. Any project submitted for federal grant funding must be included in the local,
regional, and state adopted TIPs. The TIP is a rolling plan showing various funding sources: grants,
developer, and local funds. Projects "roll" as funds or stages occur (design report, final design, and
construction).
Tukwila's Six Year TIP, the Capital Improvement Program (CIP), the Transportation Element, and the Local
Road Safety Plan list many of the same transportation -related projects. The TIP generally lists only those
transportation -related projects planned within the next six years that are deemed regionally significant or that
have grant funding awarded or expected.
ANALYSIS
The attached spreadsheet is the "Draft" 2026 - 2031 TIP and was created by modifying the 2025 - 2030 TIP
to add or remove projects and adjust project costs. No prioritization was assigned, and the list of projects is
presented in alphabetical order. Prioritization of projects is reflected in the current CIP. No projects were
removed. Six new projects were added, all but one fully funded with recently awarded grants.
Added: Deleted
Southcenter Blvd Road Diet Allentown Truck Reroute EIS
S 124th St/50th PI S Reconfiguration Southcenter Blvd/65th Ave S Signal
Keeping South King County Moving w/TDM
FINANCIAL IMPACT
None.
RECOMMENDATION
Council is being asked to approve the Resolution for the 2026 - 2031 Six -Year Transportation Improvement
Program and consider this item at a Public Hearing at the June 9, 2025, Committee of the Whole and
subsequent June 16, 2025, Regular Meeting.
ATTACHMENTS:
• Draft Resolution
• Draft 2026-2031 TIP Summary
• 2026-2031 Draft Transportation Improvement Program
• Current Adopted 2025-2030 TIP
53
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTIN SIX -YEAR
TRANSPORTATION IMPROVEMENT P - RAM (2026-
2031), AND DIRECTING THE SAME T' - FILED WITH
THE STATE SECRETARY OF TR ' 0 TION AND
THE TRANSPORTATION IMPR• ENT BC). RD.
WHEREAS, pursuant to the requirements ' , ' Chapters 35.77 and 47.26, the
City Council of the City of Tukwila has previously - •ted a Transportation Improvement
Program and thereafter periodically moa aid portation Improvement Program
by resolution; and
WHEREAS, the City Cou
program, determined curren
these findings, has prepare
ensuing six calendar ye. 20
re mowed the work accomplished under said
Cit 'treet and arterial needs and, based upon
'nsportation Improvement Program for the
31); and
WHEREAS, o . ne 9, 2 a . , blic hearing was held regarding the City's Six -Year
Transportation Imp
NOW, THEREFORE E CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY SOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six -Year Transportation Improvement Program
for the calendar years 2026 to 2031, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the Secretary
of Transportation and the Transportation Improvement Board of the State of Washington
2025 Legislation: 2025-2030 TIP
Version: 03/25/2025
Staff: C. Knighton
Page 1 of 2
54
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Regular Meeting thereof this day of , 2025.
ATTEST/AUTHENTICATED:
Andy Youn-Barnett, CMC, City Clerk Tosh Sharp, Council President
APPROVED AS TO FORM BY:
Filed with thr City Clerk:
Passed b% .iie City Council:
Resoluf ,r, 'umber:
Office of the City Attorney
Exhibit A: City of Tukwila Six -Year Transportation vement Program for 2026 to 2031
2025 Legislation: 2025-2030 TIP
Version: 03/25/2025
Staff: C. Knighton
Page 2 of 2
55
DRAFT 2026 - 2031 TIP SUMMARY
2025-2030
CIP Sheet
PROJECT TITLE
Project Costs in Thousands of Dollars
Funding Sources
Unsecured
2026
2027
2028
2029
2030
2031
TOTAL
Federal
State/TIB
City/Local
Grant
City*
39
42nd Avenue S Bridge Replacement
1,501
100
20,900
20,900
0
0
43,401
25,000
17,000
1,401
13,000
1,000
47
42nd Avenue S Bikeway
295
0
0
0
0
0
295
295
30
46th Avenue Safe Routes to School
325
2,070
0
0
0
0
2,395
1,895
500
1,895
410
49
ADA Improvements
61
61
61
61
61
61
366
366
305
54
APE/Minkler Blvd Intersection
265
2,400
0
0
0
0
2,665
1,920
745
1,920
493
58
APE/Industry Drive Intersection
180
1,400
0
0
0
0
1,580
1,100
480
1,100
300
45
Annual Bridge Inspections and Repairs
222
232
237
242
245
245
1,423
1,423
1,158
35
Annual Overlay and Repair Program
0
2,520
2,520
2,720
2,860
2,870
13,490
13,490
13,490
43
Annual Traffic Signal Program
130
160
160
170
180
190
990
990
860
38
Boeing Access Road Overlay
564
3,426
0
0
0
0
3,990
3,990
-
57
E Marginal Way S (BAR - S 112th St)
75
0
0
0
0
0
75
75
52
Interurban Avenue S Overlay
669
4,560
0
0
0
0
5,229
4,958
271
271
31
Macadam Road S Complete Streets
0
300
200
3,100
0
0
3,600
3,240
360
3,240
360
44
Orillia Road S Overlay
105
1,204
0
0
0
0
1,309
1,309
-
41
S 119th St Pedestrian Bridge Painting
200
0
0
0
0
0
200
200
55
S 124th St/50th PIS Reconfiguration
275
1,850
0
0
0
0
2,125
1,300
825
1,300
550
59
S 133rd St/SR 599 SB Intersection
0
0
550
2,700
0
0
3,250
1,620
1,630
1,620
1,630
53
S 144th St Bridge Sidewalks
579
2,720
0
0
0
0
3,299
2,500
799
2,000
720
28
S 152nd Street Ped & Bike Improvements
500
3,000
0
0
0
0
3,500
2,500
1,000
2,500
500
37
S Ryan Way
900
12,800
0
0
0
0
13,700
5,300
5,000
3,400
10,300
2,900
-
South King County Regional TDM
130
0
0
0
0
0
130
116
4
10
48
Southcenter Blvd Bikeway and Ped Xing Upgrades
325
0
0
0
0
0
325
325
46
Southcenter Blvd Road Diet
135
2,755
0
0
0
0
2,890
2,383
507
2,383
372
-
TDM Implementation
46
47
47
47
46
46
279
279
187
-
Tukwila and South King County TDM
213
351
351
351
138
1,404
550
832
22
416
11
TOTAL
7,695
41,956
25,026
30,291
3,530
3,412
111,910
43,723
38,794
28,585
41,258
25,319
PROJECTS REVISED FROM 2025-2030 TIP
New
Southcenter Blvd Road Diet
S 124th St/50th PI S Reconfiguration
Deleted/Completed:
Allentown Truck Reroute EIS Project
Southcenter Blvd/65th Ave S Signal
Keeping South King County Moving w/TDM
* Unsecured City funding includes all funds necessary outside of the current biennial budget cycle
Modified
S 152nd Street Ped & Bike Improvements (name change)
May 22, 2025
56
ANL
1117, v�rasrlingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
c
Amendment
Resolution No.
Improvement Type
C
4
C)
o.
N
Total Length
Environmental Type
RW Required
05
/ 1037(004) TUK-62
42nd Ave S Bridge Replacement
42nd Ave S over the Duwamish River
Interurban Ave S to Northern end of bridge
Design and construct a replacement structure for the existing 42nd Ave S Bridge
adjacent to the Tukwila Community Center Alb,
06/09/25 6/
<e
11
0.100
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code Federal Fundrund
State Funds
Local Funds
Total Funds
S
PE
2026
BR 10,.
0
100,000
1,500,694
S
RW
2027
0
100,000
100,000
P
CN
2027
BR 1' . le
0
1,000,000
14,000,000
S
CN
2027
BR . '•,306
MAW
17,000,000
200,000
27,799,306
Totals 5,0'0
17,000,000
1,400,000
43,400,000
Expenditure Schedule
Phase
1st
2nd
rd
4th
5th & 6th
PE
1,500,694
0
0
0
0
RW
0
100,000
0
0
0
CN
0
0
20,899,653
20,899,653
0
Totals
1,500,694
100,000
20,899,653
20,899,653
0
Report Date: May 22, 2025
Page 1
57
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
y
Amendment
Resolution No.
Improvement Type
c
ot
Total Length
Environmental Type
RW Required
D. Road Name or Number
c
c
C)
E. Begin & End Termini
�.
o.
F. Project Description G. Structure ID
to
N
05
WA-15812
06/09/25 6/
28
C G P S T
No
W
42nd Avenue S Bikeway
42nd Avenue S
<(
Southcenter Blvd to S 150th Street
Develop a traffic -calmed bikeway along 42nd Ave S between S 150th St and
Southcenter Blvd. On the west side of the street, add striped southbound bike lane
between Southcenter Blvd and S 150th St. On the east side of the street, add striped
bike lane between Southcenter Blvd and S 151st St. Remove on -street parking to
widen the sidewalk on the east side of the street between S 151 st St and S 150th St,
creating a shared path; add shared lane markings to the roadway
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federa
a Fund Code
State Funds
Local Funds
Total Funds
S
CN
2026
0
0
295,000
295,000
Total
0
295,000
295,000
Expenditure Schedule
Phase
1st
2nd
rd
4th
5th & 6th
CN
295,000
0
0
0
0
Totals
295,000
0
0
0
0
Report Date: May 22, 2025
Page 2 58
ANL
1117, Viastuneon State
Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
co
�.
to
y
o. c
Amendment
Resolution No.
Improvement Type
c
C)
o.
N
Total Length
Environmental Type
RW Required
19
WA-1111:
46th Avenue Safe Routes to School
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
06/09/25
6/
05
C G P S T
W
0.370
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal
ds
S
Fund Code
State Funds
Local Funds
Total Funds
P
PE
2026
RTS
170,000
80,000
250,000
P
RW
2026
0
SRTS
65,000
10,000
75,000
P
CN
2027
0
SRTS
1,660,000
410,000
2,070,000
Total
1,895,000
500,000
2,395,000
Expenditure Schedule
Phase
1st
2nd
N/1
4th
5th & 6th
PE
250,000
0
0
0
0
RW
75,000
0
0
0
0
CN
0
2,070,000
0
0
0
Totals
325,000
2,070,000
0
0
0
Report Date: May 22, 2025
Page 3 59
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure IDiv
�,
y
c
Amendment
Resolution No.
Improvement Type
c
ot
C)
a
N
Total Length
Environmental Type
RW Required
00
WA-05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan. _
06/09/25 6/
<e
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fund
rund
State Funds
Local Funds
Total Funds
S
ALL
2026
0
600,000
600,000
Totals
0
600,000
600,000
Expenditure Schedule
Phase
1st
2nd
4th
5th & 6th
ALL
61,000
61,000
1,00
61,000
122,000
Totals
61,000
61,000
1,000
61,000
122,000
Report Date: May 22, 2025
Page 4 60
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure IDiv
�,
y
c
Amendment
Resolution No.
Improvement Type
C
C)
a
N
Total Length
Environmental Type
RW Required
16
WA-07746
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal _
06/09/25 6/
<e
03
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fundrund
State Funds
Local Funds
Total Funds
S
PE
2026
0
190,000
190,000
S
RW
2026
0
75,000
75,000
P
CN
2027
TIB
1,920,000
493,000
2,413,000
Totals
w 0
1,920,000
758,000
2,678,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
190,000
0
0
0
0
RW
75,000
0
0
0
0
CN
0
2,400,000
0
0
0
Totals
265,000
2,400,000
0
0
0
Report Date: May 22, 2025
Page 5 61
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
co
�.
to
y
o. c
Amendment
Resolution No.
Improvement Type
C
C)
o.
N
Total Length
Environmental Type
RW Required
04
WA-15107 06/09/25 6/
Andover Park East/Industry Dr Intersection
Andover Park E
Industry Drive to
Design and construct traffic signal with Andover Park East left turn lanes and
crosswalks.44<(
03
C G P S T
W
0.100
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code Federal F
Fund Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
180,000
180,000
S
RW
2026
0
70,000
70,000
P
CN
2027
0
TIB
1,100,000
300,000
1,400,000
Totals 0
1,100,000
550,000
1,650,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
110,000
0
0
0
0
RW
70,000
0
0
0
0
CN
0
1,400,000
0
0
0
Totals
180,000
1,400,000
0
0
0
Report Date: May 22, 2025
Page 6 62
ANIL
11171v�rasr�ingti n State
, Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure IDiv
�,
y
c
Amendment
Resolution No.
Improvement Type
c
ot
C)
a
N
Total Length
Environmental Type
RW Required
14
WA-03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance _
06/09/25 6/
<e
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fund
rund
State Funds
Local Funds
Total Funds
S
ALL
2026
0
1,380,000
1,380,000
Totals
0
1,380,000
1,380,000
Expenditure Schedule
Phase
1st
2nd
4th
5th & 6th
ALL
222,000
232,000
7,00
242,000
489,000
Totals
222,000
232,000
7,000
242,000
489,000
Report Date: May 22, 2025
Page 7 63
ANIL
11171v�rasr�ingti n State
, Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure IDiv
�,
y
c
Amendment
Resolution No.
Improvement Type
C
C)
a
N
Total Length
Environmental Type
RW Required
16
WA-03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program _
06/09/25 6/
<e
06
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fund
rund
State Funds
Local Funds
Total Funds
S
ALL
2026
0
16,100,000
16,100, 000
Totals
0
16,100,000
16,100,000
Expenditure Schedule
Phase
1st
2nd
4th
5th & 6th
ALL
0
2,520,000
0,00
2,720,000
5,730,000
Totals
0
2,520,000
2
0,000
2,720,000
5,730,000
Report Date: May 22, 2025
Page 8 64
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
c
�,
y
c
Amendment
Resolution No.
Improvement Type
c
ot
C)
a
N
Total Length
Environmental Type
RW Required
00
WA-15104 06/09/25 6/
Annual Traffic Signal Program
Varies
to
Design and construct traffic signal upgrades and repairs of signals that exceed
routine maintenance work;loop replacement, head replacement, and controllers.
Replace direct bury cable for existing lighting system. t<(
44
P
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal F Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2026
0
1,120,000
1,120, 000
Totals
0
1,120,000
1,120,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
130,000
160,000
0,000
170,000
370,000
Totals
130,000
160,000
0,000
170,000
370,000
Report Date: May 22, 2025
Page 9 65
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
c
Amendment
Resolution No.
Improvement Type
C
,
C)
o.
N
Total Length
Environmental Type
RW Required
03
/ 1380(005) TUK-68 06/09/25 6/
Boeing Access Road Overlay
Boeing Access Road
East Marginal Way S to Martin Luther King Jr Way S
Grind and overlay roadway, replace concrete overlay of bridge deck over BNSF
railway. Alb,<e
05
0.560
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fundrund
State Funds
Local Funds
Total Funds
S
PE
2026
NHPP
.4,.
0
0
564,000
S
CN
2027
NHPP
3,426,►
0
0
3,426,000
Totals
, . 1 1
0
0
3,990,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
564,000
0
0
0
0
CN
0
3,426,000
0
0
0
Totals
564,000
3,426,000
0
0
0
Report Date: May 22, 2025
Page10 66
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
co
�.
to
y
o. c
Amendment
Resolution No.
Improvement Type
c
C)
o.
N
Total Length
Environmental Type
RW Required
04
WA-15109 06/09/25 6/
E Marginal Way S (BAR - S 112 St)
E Marginal Way S
Boeing Access Road to S 112th St
Planning phase to determine project parameters. Goal is to design and construct full
street improvements and traffic control. Could include additional lanes and bike lanes
tillillibilin.<(
to support the new Sound Transit Link Light Rail infill station.
03
C G O P S
TW
0.270
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal
ds
S
Fund Code
State Funds
Local Funds
Total Funds
S
PL
2026
0
75,000
75,000
Totals
0
0
75,000
75,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
75,000
0
0
0
0
Totals
75,000
0
0
0
0
Report Date: May 22, 2025
Page11 67
ANL
1117, v�rasr�ingti n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
iv
�,a
Amendment
Resolution No.
Improvement Type
C
4
C)
N
Total Length
Environmental Type
RW Required
03
/ 1391(004) TUK-66
Interurban Avenue S Overlay
Interurban Avenue S
E Marginal Way S to S 143rd Street
Complete pavement repairs, overlay, and curb and gutter repair.
06/09/25
<I
c1:
016,1/11
05
2.250
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
tate
State Funds
Local Funds
Total Funds
S
PE
2026
NHPP
0
0
668,386
S
CN
2027
NHPP
,288,E
0
271,386
4,560,000
Totals
4,95
0
271,386
5,228,386
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
668,386
0
0
0
0
CN
0
4,560,000
0
0
0
Totals
668,386
4,560,000
0
0
0
Report Date: May 22, 2025
Page12 68
ANL
1117, ViastungIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
y
o
Amendment
Resolution No.
Improvement Type
c
ot
C)
o.
N
Total Length
Environmental Type
RW Required
17
WA-1111(
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
06/10/24
7/
2099
04
0.350
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code Federal F
Fund Code
State Funds
Local Funds
Total Funds
P
PE
2027
Pe ike Program
350,000
50,000
400,000
P
RW
2028
ike Program
90,000
10,000
100,000
P
CN
2029
0
Ped/Bike Program
2,800,000
300,000
3,100,000
Totals 0
3,240,000
360,000
3,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
300,000
100,000
0
0
RW
0
0
100,000
0
0
CN
0
0
0
3,100,000
0
Totals
0
300,000
200,000
3,100,000
0
Report Date: May 22, 2025
Page 13 69
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
c
Amendment
Resolution No.
Improvement Type
C
,
C)
o.
N
Total Length
Environmental Type
RW Required
03
/ 1230(007) TUK-67
Orillia Road South Overlay
Orillia Road S
S 188th Street to S 204th Street
Complete pavement repairs; overlay; and curb and gutter, sidewalk, and guardrail
repair.
06/09/25 6/
<e
05
0.750
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fundrund
State Funds
Local Funds
Total Funds
S
PE
2026
NHPP
1 ,.
0
0
105,000
S
CN
2026
NHPP
1,204,►
0
0
1,204,000
Totals
, . • 1
0
0
1,309,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
105,000
0
0
0
0
CN
0
1,224,000
0
0
0
Totals
105,000
1,224,000
0
0
0
Report Date: May 22, 2025
Page 14 70
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
c
Amendment
Resolution No.
Improvement Type
c
ot
C)
o.
N
Total Length
Environmental Type
RW Required
00
WA13494 06/09/25 6/
S 119th St Pedestrian Bridge Painting
S 119th Street Bridge
West bank Duwamish River to East bank Duwamish River
Ongoing maintenance of the S 119th Street Pedestrian Bridge in the
Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance
needed. t<(
06
0.040
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal F Fund Code
State Funds
Local Funds
Total Funds
P
CN
2026
0
200,000
200,000
Totals
0
200,000
200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
200,000
0
0
0
0
Totals
200,000
0
0
0
0
Report Date: May 22, 2025
Page 15 71
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
c
Amendment
Resolution No.
Improvement Type
c
ot
C)
o.
N
Total Length
Environmental Type
RW Required
05
WA-16476
S 124th St/50th PI S Reconfiguration
S 124th Street
49th Ave S to 51 st PI S
Reconfigure intersection to remove EB slip lane, new c/g/s on S 124th from 49th to
51st, new paved shoulder walkway on south side of 124th connecting to existing
walkway on west side of 50th Pk, new stormwater treatment/rain garden in old slip tIIIIIIIIIIhk.4—
lane ROW.
06/09/25 6/
21
0.140
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal ' ds
S
Fund Code
State Funds
Local Funds
Total Funds
S
PE
2026
i
0
275,000
275,000
P
CN
2027
0
TIB
1,300,000
550,000
1,850,000
Totals
AIIIIII 0
1,300,000
825,000
2,125,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
275,000
0
0
0
0
CN
0
1,850,000
0
0
0
Totals
275,000
1,850,000
0
0
0
Report Date: May 22, 2025
Page16 72
ANL
1117, v�rasr�ingIi n state
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
co
�.
to
y
o. c
Amendment
Resolution No.
Improvement Type
c
C)
o.
N
Total Length
Environmental Type
RW Required
03
WA-15108
S 133 St/SR599 Southbound Intersection
S 133rd Street
SR 599 SB Ramp to
Design and construct intersection improvements, which could include a new traffic
signal or a roundabout,
lighting, pedestrian facilities, and drainage. tillirli
06/09/25
6/
03
C G O P S
TW
0.100
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal
ds
S
Fund Code
State Funds
Local Funds
Total Funds
P
PE
2028
)
0
400,000
400,000
P
RW
2028
0
0
150,000
150,000
P
CN
2029
0
TIB
1,620,000
1,080,000
2,700,000
Total
1,620,000
1,630,000
3,250,000
Expenditure Schedule
Phase
lst
2nd
N/14th
5th & 6thPE000,000
0
0
RW
0
0
150,000
0
0
CN
0
0
0
2,700,000
0
Totals
0
0
550,000
2,700,000
0
Report Date: May 22, 2025
Page17 73
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
�.
to
y
o. c
Amendment
Resolution No.
Improvement Type
c
ot
C)
o.
N
Total Length
Environmental Type
RW Required
05
TUK-65
S 144th Street Bridge Sidewalks
S 144th Street Bridge
51 st Ave S to 53rd Ave S
The project entails replacing approximately 320 feet of raised bridge deck on the S
144th street bridge with 6-foot-wide sidewalks, which will be separated from the
traffic lanes by a crash tested barrier and a pedestrian railing. Sharrows will also beIIIIIIIIIIhk.4—
added to the traffic lanes for bicycle traffic.
06/09/25 6/
28
0.060
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal ' ds
S
Fund Code
State Funds
Local Funds
Total Funds
S
PE
2026
STBG(UL)
500 i
0
79,000
579,000
P
CN
2027
SRTS
.,000
0
720,000
2,720,000
Totals
AIIIIII , 000
0
799,000
3,299,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
579,000
0
0
0
0
CN
0
2,720,000
0
0
0
Totals
579,000
2,720,000
0
0
0
Report Date: May 22, 2025
Page18 74
ANL
1117, v�rasr�ingIi n state
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No.
C. Project Title
D. Road Name or Number
E. Begin & End Terminisv
Project Description
B. STIP ID
G. Structure ID
�,
Amendment
Resolution No.
Improvement Type
c
C)
aF.
N19
Total Length
Environmental Type
RW Required
S 152nd Street Pedestrian and Bike Improvements
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Install curb, gutter, shared use path and sidewalks on S 152nd Street, including
widening pavement and construction of a buffer between the roadway and sidewalk
on the south side.
WA-1111 06/09/25
till1/11111...<(4C
05
C G O P S
TW
0.300
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal
ds
S
Fund Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
274,000
274,000
S
RW
2026
0
0
200,000
200,000
P
CN
2027
0
TIB
2,500,000
500,000
3,000,000
Total
2,500,000
974,000
3,474,000
Expenditure Schedule
Phase
1st
2nd
N/1
4th
5th & 6th
PE
270,000
0
0
0
0
RW
230,000
0
0
0
0
CN
0
3,000,000
0
0
0
Totals
500,000
3,000,000
0
0
0
Report Date: May 22, 2025
Page19 75
ANL
1117, v�rasr�ingIi n state
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title D. Road Name or Number
Begin & End Termini
Project Description G. Structure ID
iv
�,aF.
Amendment
Resolution No.
Improvement Type
c
C)E.
N04
Total Length
Environmental Type
RW Required
WA-15829 06/09/25tIIIINkh\.<(:Ca3>
S Ryan Way
S R 900 to 51 st Ave S
Resurface and rechannel S Ryan Way to improve failing pavement and improve
safety. Add pedestrian and bicycle facilities where appropriate. Signalize intersection
with 47th Avenue S to accommodate future growth and improve safety.
06
C G P S T
W
0.500
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal
ds
S
Fund Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
500,000
500,000
P
PE
2026
SRTS
00
0
0
100,000
P
RW
2026
SRTS
000
0
100,000
300,000
P
CN
2027
SRTS
,00
TIB
5,000,000
2,800,000
12,800,000
Tota
300,000
5,000,000
3,400,000
13,700,000
Expenditure Schedule
N,
Phase
1st
2nd
4th
5th & 6th
PE
600,000
0
0
0
0
RW
300,000
0
0
0
0
CN
0
12,800,000
0
0
0
Totals
900,000
12,800,000
0
0
0
Report Date: May 22, 2025
Page 20 76
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
=
�.
to
y
c
Amendment
Resolution No.
Improvement Type
c
ot
C)
o.
N
Total Length
Environmental Type
RW Required
00
TUK-64
South King County TDM
South King County
N/A to N/A
This project will provide TDM programming and services at selected activity centers
in Tukwila and partnering South King County jurisdictions. Activity centers include
community hubs, commercial areas, business parks, multifamily housing complexes,
and educational institutions. For example, places such as Tukwila International
Boulevard District, Southcenter, and Sea-Tac Airport. By providing transportation
resources and incentives, the project will encourage people to choose sustainable
transportation options that reduce drive -alone travel and traffic congestion in South
King County. TDM services will be provided to residents, commuters, and visitors,
targeting those willing and able to try sustainable modes of transportation. The
program will work in partnership with partner agencies, nonprofits, employers, and
community organizations.
06/09/25 6/
<(
24
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal
ds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2026
CMAQ
449,567
OTHER
20,164
50,000
519,731
Totals
449,567
20,164
50,000
519,731
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
129,933
0
0
0
0
Totals
129,933
0
0
0
0
Report Date: May 22, 2025
Page 21 77
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
Amendment
Resolution No.
Improvement Type
c
ot
C)E.
o.
N04
Total Length
Environmental Type
RW Required
WA-15813
Southcenter Blvd Bikeway and Pedestrian Crossing Upgrades
Southcenter Boulevard
International Boulevard to 42nd Avenue S
Improve the existing bike lanes and crosswalks on Southcenter Blvd within a half -
mile of Tukwila International Boulevard Station (TIBS). Re-channelize to 11 ft general
purpose lanes to accommodate separated (tuff curb and post) bike lanes. Tighten
intersection with 40th Ave S to shorten crossing distance. Add bike channelization
and upgrade to high -visibility crosswalk markings at Southcenter Blvd/TIBS station
entrance and Southcenter Blvd/42nd Ave S intersections.
06/09/25
<(4C2-
28
C G P S T
W
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federa
a Fund Code
State Funds
Local Funds
Total Funds
S
CN
2026
0
0
325,000
325,000
Total
0
325,000
325,000
Expenditure Schedule
Phase
1st
2nd
rd
4th
5th & 6th
CN
325,000
0
0
0
0
Totals
325,000
0
0
0
0
Report Date: May 22, 2025
Page 22 78
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
co
�.
to
y
o. c
Amendment
Resolution No.
Improvement Type
c
C)
o.
N
Total Length
Environmental Type
RW Required
03
WA-16478
Southcenter Blvd Road Diet (with Lake to Sound Regional Trail)
Southcenter Boulevard
S 66th Ave to 53rd Ave S
As part of the King County led Lake to Sound Regional Trail F1 Phase, narrow
Southcenter Blvd from 5 lanes to 3 lanes between approx. 62nd Ave S and 66th Ave
S. Reconfigure signal operations at 66th Ave S to include dual WB left turn lanes and
a single WB thru lane. All lanes will generally shift to the south of the existing ROW
to allow for construction of the Lake to Sound trail and trail buffering.
......m....._ li,
06/09/25
6/
28
C G O P S
TW
0.930
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Fed
unds
a and Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
0
135,000
135,000
P
CN
2027
0
OTHER
2,383,000
372,000
2,755,000
Tot
2,383,000
507,000
2,890,000
Expenditure ScheduleNI
Phase
1st
2nd
4th
5th & 6th
PE
135,000
0
0
0
0
CN
0
2,755,000
0
0
0
Totals
135,000
2,755,000
0
0
0
Report Date: May 22, 2025
Page 23 79
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
Amendment
Resolution No.
Improvement Type
c
ot
C)E.
o.
N00
Total Length
Environmental Type
RW Required
WA-13491
Transportation Demand Management Implementation
to
Provision of TDM services to Commute Trip Reduction -affected employment sites.
Facilitate employer reporting and records associated with biennial CTR survey.
Engage CTR employment sites with opportunities for improvement and remain
connected via technical meetings with other CTR jurisdictional representatives.
06/tIIIIIIIIIIhm<#16r\cL
44
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal '
ds
S
Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2026
i
SDOT
93,300
0
93,300
P
ALL
2027
0
WSDOT
186,600
0
186,600
Totals
4.111
0
279,900
0
279,900
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
46,650
46,650
46,650
46,650
4,665,093,300
Totals
46,650
46,650
46,650
46,650
4,665,093,300
Report Date: May 22, 2025
Page 24 80
ANL
1117, v�rasr�ingIi n State
Department ot Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
c
�.
to
y
c
Amendment
Resolution No.
Improvement Type
c
ot
C)
o.
N
Total Length
Environmental Type
RW Required
00
TUK-69
Tukwila and South King County TDM
Tukwila and South King County
N/A to N/A
This project will provide TDM programming and services to help people access
sustainable transportation options that reduce drive -alone travel and traffic
congestion in Tukwila and South King County. Tukwila's TDM Program reaches
people regionally at employment centers, community hubs, multifamily housing
complexes, and educational institutions.
06/09/25
6/
24
0.000
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Fede
unds
St Fund Code
State Funds
Local Funds
Total Funds
S
PL
2026
WSDOT
416,000
10,700
426,700
S
PL
2027
CMAQ
0,000
0
0
550,000
P
PL
2028
0
WSDOT
416,000
10,700
426,700
Tot
550,010
832,000
21,400
1,403,400
Expenditure Schedule
Phase
1st
2nd
Ne
4th
5th & 6th
ALL
213,350
350,850
350,850
350,850
137,500
Totals
213,350
350,850
350,850
350,850
137,500
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
44,055,567
39,090,064
32,140,786
115,286,417
Report Date: May 22, 2025
Page 25 81