HomeMy WebLinkAboutCOW 2025-06-09 Item 4A / 5A - Public Hearing - Resolution Adopting 2026-2031 Transportation Improvement PlanCOUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
Mayor's review
Council review
06/09/25
JR
06/16/25
JR
ITEM INFORMATION
ITEM No.
4.A. &
5.A.
STAFF SPONSOR: CYNDY KNIGHTON
ORIGINAL AGENDA DATE: 06/02/25
AGENDA ITEM TITLE Resolution for Six -Year Transportation Improvement Program (TIP) (2026 - 2031)
CATEGORY ❑ Discussion
Mtg Date
❑ Motion
Mtg Date
0 Resolution
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
1 Public Hearing
❑ Other
Mtg Date
Mtg Date 6/16/25
Mtg Date 6/9/25
SPONSOR ❑Council ❑Mayor ❑HR DCD Finance ❑Fire TS P&R ❑Police 0 PW/ ❑Court
SPONSOR's The TIP is primarily a financial planning document for projects competing for grants and
SUMMARY generally lists only those transportation -related projects planned within the next six years
that are deemed regionally significant or that have grant funding awarded or expected.
Council is being asked to approve the Resolution for the 2026 - 2031 Six -Year
Transportation Improvement Program.
REVIEWED BY
r Trans&Infrastructure ❑ CommunitySvs/Safety ❑ Finance Comm.
❑ LTAC ❑ Arts Comm. ❑ Parks Comm.
DATE: 05/28/2025 COMMITTEE CHAIR: JOVITA
❑ Planning/Economic
Dev.
❑ Planning Comm.
MCCONNELL
RECOMMENDATIONS:
SPONSOR/ADMIN.
CoMMITrEE
Public Works Department
Unanimous Approval; Forward to the Committee of the Whole
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
06/09/25
06/16/25
MTG. DATE
ATTACHMENTS
06/09/25
Informational Memorandum dated 5/23/25
Draft 2026-2031 TIP Summary
Draft Resolution
2026-2031 Draft Transportation Improvement Program
Minutes from the 5/28/25 Transportation and Infrastructure Services Committee Meeting
06/16/25
1
City of Tukwila
Thomas McLeod, Mayor
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Services Committee
FROM: Pete Mayer, Interim Public Works Director
BY: Cyndy Knighton, Senior Program Manager
CC: Mayor McLeod
DATE: May 23, 2025
SUBJECT: Resolution for Six -Year Transportation Improvement Program (2026 - 2031)
ISSUE
Approve a Resolution adopting the annual update of the Six -Year Transportation Improvement Program for
2026 - 2031.
BACKGROUND
The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of
Washington (RCW) 35.77.010. The TIP is adopted by resolution after a public hearing at the local agency
level and incorporated into regional and state TIPs. The TIP is primarily a financial planning document for
projects competing for grants. Any project submitted for federal grant funding must be included in the local,
regional, and state adopted TIPs. The TIP is a rolling plan showing various funding sources: grants,
developer, and local funds. Projects "roll" as funds or stages occur (design report, final design, and
construction).
Tukwila's Six Year TIP, the Capital Improvement Program (CIP), the Transportation Element, and the Local
Road Safety Plan list many of the same transportation -related projects. The TIP generally lists only those
transportation -related projects planned within the next six years that are deemed regionally significant or that
have grant funding awarded or expected.
ANALYSIS
The attached spreadsheet is the "Draft" 2026 - 2031 TIP and was created by modifying the 2025 - 2030 TIP
to add or remove projects and adjust project costs. No prioritization was assigned, and the list of projects is
presented in alphabetical order. Prioritization of projects is reflected in the current CIP. Three projects
were removed. Two new projects were added, all but one fully funded with recently awarded grants.
Added: Deleted
Southcenter Blvd Road Diet Allentown Truck Reroute EIS
S 124th St/50th PI S Reconfiguration Southcenter Blvd/65th Ave S Signal
Keeping South King County Moving w/TDM
FINANCIAL IMPACT
None.
RECOMMENDATION
Council is being asked to approve the Resolution for the 2026 - 2031 Six -Year Transportation Improvement
Program and consider this item at a Public Hearing at the June 9, 2025, Committee of the Whole and
subsequent June 16, 2025, Regular Meeting.
ATTACHMENTS:
• Draft 2026-2031 TIP Summary
• Draft Resolution
• Resolution Exhibit: 2026-2031 Draft Transportation Improvement Program
• Current Adopted 2025-2030 TIP (Res. 2099) (Link Only)
2
DRAFT 2026 - 2031 TIP SUMMARY
2025-2030
CIP Sheet
PROJECT TITLE
Project Costs in Thousands of Dollars
Funding Sources
Unsecured
2026
2027
2028
2029
2030
2031
TOTAL
Federal
State/TIB
City/Local
Grant
City*
39 '42nd
Avenue S Bridge Replacement
1,501
100
20,900
20,900
0
0
43,401
25,000
17,000
1,401
13,000
1,000
47
42nd Avenue S Bikeway
295
0
0
0
0
0
295
295
30
46th Avenue Safe Routes to School
325
2,070
0
0
0
0
2,395
1,895
500
1,895
410
49
ADA Improvements
61
61
61
61
61
61
366
366
305
54
APE/Minkler Blvd Intersection
265
2,400
0
0
0
0
2,665
1,920
745
1,920
493
58
APE/Industry Drive Intersection
180
1,400
0
0
0
0
1,580
1,100
480
1,100
300
45
Annual Bridge Inspections and Repairs
222
232
237
242
245
245
1,423
1,423
1,158
35
Annual Overlay and Repair Program
0
2,520
2,520
2,720
2,860
2,870
13,490
13,490
13,490
43
Annual Traffic Signal Program
130
160
160
170
180
190
990
990
860
38
Boeing Access Road Overlay
564
3,426
0
0
0
0
3,990
3,990
-
57
E Marginal Way S (BAR - S 112th St)
75
0
0
0
0
0
75
75
52
Interurban Avenue S Overlay
669
4,560
0
0
0
0
5,229
4,958
271
271
31
Macadam Road S Complete Streets
0
300
200
3,100
0
0
3,600
3,240
360
3,240
360
44
Orillia Road S Overlay
105
1,204
0
0
0
0
1,309
1,309
-
41
S 119th St Pedestrian Bridge Painting
200
0
0
0
0
0
200
200
55
S 124th St/50th PIS Reconfiguration
275
1,850
0
0
0
0
2,125
1,300
825
1,300
550
59
S 133rd St/SR 599 SB Intersection
0
0
550
2,700
0
0
3,250
1,620
1,630
1,620
1,630
53
S 144th St Bridge Sidewalks
579
2,720
0
0
0
0
3,299
2,500
799
2,000
720
28
S 152nd Street Ped & Bike Improvements
500
3,000
0
0
0
0
3,500
2,500
1,000
2,500
500
37
S Ryan Way
900
12,800
0
0
0
0
13,700
5,300
5,000
3,400
10,300
2,900
South King County Regional TDM
130
0
0
0
0
0
130
116
4
10
48
Southcenter Blvd Bikeway and Ped Xing Upgrades
325
0
0
0
0
0
325
325
46
Southcenter Blvd Road Diet
135
2,755
0
0
0
0
2,890
2,383
507
2,383
372
TDM Implementation
46
47
47
47
46
46
279
279
187
Tukwila and South King County TDM
213
351
351
351
138
1,404
550
832
22
416
11
TOTAL
7,695
41,956
25,026
30,291
3,530
3,412
111,910
43,723
38,794
28,585
41,258
25,319
PROJECTS REVISED FROM 2025-2030 TIP
New
Southcenter Blvd Road Diet
S 124th St/50th PI S Reconfiguration
Deleted/Completed:
Allentown Truck Reroute EIS Project
Southcenter Blvd/65th Ave S Signal
Keeping South King County Moving w/TDM
* Unsecured City funding includes all funds necessary outside of the current biennial budget cycle
Modified
S 152nd Street Ped & Bike Improvements (name change)
W
May 22, 2025
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTIN SIX -YEAR
TRANSPORTATION IMPROVEMENT P - RAM (2026-
2031), AND DIRECTING THE SAME T' - FILED WITH
THE STATE SECRETARY OF TR ' 0 TION AND
THE TRANSPORTATION IMPR• ENT BC). RD.
WHEREAS, pursuant to the requirements ' , ' Chapters 35.77 and 47.26, the
City Council of the City of Tukwila has previously - •ted a Transportation Improvement
Program and thereafter periodically moa aid portation Improvement Program
by resolution; and
WHEREAS, the City Cou
program, determined curren
these findings, has prepare
ensuing six calendar ye. 20
re mowed the work accomplished under said
Cit 'treet and arterial needs and, based upon
'nsportation Improvement Program for the
31); and
WHEREAS, o . ne 9, 2 a . , blic hearing was held regarding the City's Six -Year
Transportation Imp
NOW, THEREFORE E CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY SOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six -Year Transportation Improvement Program
for the calendar years 2026 to 2031, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the Secretary
of Transportation and the Transportation Improvement Board of the State of Washington
2025 Legislation: 2025-2030 TIP
Version: 03/25/2025
Staff: C. Knighton
4
Page 1 of 2
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Regular Meeting thereof this day of , 2025.
ATTEST/AUTHENTICATED:
Andy Youn-Barnett, CMC, City Clerk Tosh Sharp, Council President
APPROVED AS TO FORM BY:
Filed with thr City Clerk:
Passed b% .iie City Council:
Resoluf ,r, 'umber:
Office of the City Attorney
Exhibit A: City of Tukwila Six -Year Transportation vement Program for 2026 to 2031
2025 Legislation: 2025-2030 TIP
Version: 03/25/2025
Staff: C. Knighton
Page 2 of 2
5
0)
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
/ 1037(004) TUK-62
42nd Ave S Bridge Replacement
42nd Ave S over the Duwamish River
Interurban Ave S to Northern end of bridge
Design and construct a replacement structure for the existing 42nd Ave S Bridg
adjacent to the Tukwila Community Center
06/09/25
06/16/25
11
0.100
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
ode State Funds
Local Funds
Total Funds
S
PE
2026
BR
1,40�
0
100,000
1,500,694
S
RW
2027
0
0
100,000
100,000
P
CN
2027
BR
13,000,000
0
1,000,000
14,000,000
S
CN
2027
BR
10,599,306
A 17,000,000
200,000
27,799,306
Totals
25,000,000
ilk00,000
1,400,000
43,400,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
51
h
PE
1,500,694
0
0
0
0
RW
0
100,000
0
0
0
CN
0
0
20,899,653
20,899,653
0
Totals
1,500,694
100,000
20,899,653
20,899,653
0
Report Date: May 22, 2025
Page 1
Wwasningtan state
A Tr Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
-15812
42nd Avenue S Bikeway
42nd Avenue S
Southcenter Blvd to S 150th Street
Develop a traffic -calmed bikeway along 42nd Ave S between S 150th St and
Southcenter Blvd. On the west side of the street, add striped southbound bike lane
between Southcenter Blvd and S 150th St. On the east side of the street, add striped
bike lane between Southcenter Blvd and S 151st St. Remove on -street parking to
widen the sidewalk on the east side of the street between S 151 st St and S 150th St,
creating a shared path; add shared lane markings to the roadway
06/09/25
06/16/25
28
C G P S T
W
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
Stand Co
to Funds
Local Funds
Total Funds
S
CN
2026
0
Totals
0
0
295,000
295,000
0
295,000
295,000
Expenditure Schedule
)00IrN
0
0
Phase
1st
2nd
3rd
4th
CN
295,000
0
0
0
Totals
295,000
0
0
0
Report Date: May 22, 2025
Page 2
00
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
t
g.
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
-1111:
46th Avenue Safe Routes to School
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
06/09/25
06/16/25
05
C G P S T
W
0.370
Yes
Funding '
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
F Code
State Funds
Local Funds
Total Funds
P
PE
2026
0
S
170,000
80,000
250,000
P
RW
2026
0
TS
65,000
10,000
75,000
P
CN
2027
0
RT
1,660,000
410,000
2,070,000
Totals
0
�95,000
500,000
2,395,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5
th
PE
250,000
0
0
0
0
RW
75,000
0
0
0
0
CN
0
2,070,000
0
0
0
Totals
325,000
2,070,000
0
0
0
Report Date: May 22, 2025
Page 3
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
-05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjuncts
with a City developed plan.
06/09/25
06/16/25
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
ode
State Funds
Local Funds
Total Funds
S
ALL
2026
.
0
600,000
600,000
Totals
0
0
600,000
600,000
Expenditure Schedule
�441‘
.10
Phase
1st
2nd
3rd
5t
th
ALL
61,000
61,000
61,000
61,000
122,000
Totals
61,000
61,000
61,000
61,000
000
Report Date: May 22, 2025
Page 4
CO
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
-07746
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
06/09/25
06/16/25
03
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
le
ode
State Funds
Local Funds
Total Funds
S
PE
2026
.
0
190,000
190,000
S
RW
2026
0
0
75,000
75,000
P
CN
2027
0
IB
1,920,000
493,000
2,413,000
Totals
0
1,920,000
758,000
2,678,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th &
PE
190,000
0
0
0
RW
75,000
0
0
0
0
CN
0
2,400,000
0
0
0
Totals
265,000
2,400,000
0
0
0
Report Date: May 22, 2025
Page 5
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
-15107
Andover Park East/Industry Dr Intersection
Andover Park E
Industry Drive to
Design and construct traffic signal with Andover Park East left turn lanes and
crosswalks.
06/09/25
_
06/16/25
03
C G P S T
W
0.100
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fun
to F Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
0
180,000
180,000
S
RW
2026
0
0
70,000
70,000
P
CN
2027
0
IB
1,100,000
300,000
1,400,000
Totals
0
1,100,000
550,000
1,650,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th
PE
110,000
0
0
0
0
RW
70,000
0
0
0
0
CN
0
1,400,000
0
0
0
Totals
180,000
1,400,000
0
0
0
Report Date: May 22, 2025
Page 6
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
-03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
06/09/25
06/16/25
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
ode
State Funds
Local Funds
Total Funds
S
ALL
2026
.
0
1,380,000
1,380,000
Totals
0
0
1,380,000
1,380,000
Expenditure Schedule
Phase
1st
2nd
3rd
4tN1‘
5t th
ALL
222,000
232,000
237,000
242,000 489,000
Totals
222,000
232,000
237,000
242,000 000
Report Date: May 22, 2025
Page 7
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
-03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/09/25
06/16/25
06
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
ode
State Funds
Local Funds
Total Funds
S
ALL
2026
.
0
16,100,000
16,100,000
Totals
0
0
16,100,000
16,100,000
Expenditure Schedule
�441‘
.10
Phase
1st
2nd
3rd
505
ALL
0
2,520,000
2,520,000
2,720,000
730,000
Totals
0
2,520,000
2,520,000
2,720,000
000
Report Date: May 22, 2025
Page 8
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
-15104
Annual Traffic Signal Program
Varies
to
Design and construct traffic signal upgrades and repairs of signals that exceed
routine maintenance work;loop replacement, head replacement, and controllers.
Replace direct bury cable for existing lighting system.
06/09/25
_
06/16/25
44
P
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fun
to F
Code
State Funds
Local Funds
Total Funds
S
ALL
2026
0
0
1,120,000
1,120,000
Totals
0
0
1,120, 000
1,120, 000
Expenditure Schedule
Phase
1st
2nd
3rd
5th
ALL
130,000
160,000
160,000
170,000
0,000
Totals
130,000
160,000
160,000
170,000
0
Report Date: May 22, 2025
Page 9
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
/ 1380(005) TUK-68
Boeing Access Road Overlay
Boeing Access Road
East Marginal Way S to Martin Luther King Jr Way S
Grind and overlay roadway, replace concrete overlay of bridge deck over BNSF
railway.
06/09/25
06/16/25
05
0.560
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
ode
State Funds
Local Funds
Total Funds
S
PE
2026
NHPP
56• ..
0
0
564,000
S
CN
2027
NHPP
3,426,000
0
0
3,426,000
Totals
3,990,000
0
0
3,990,000
Expenditure Schedule
Phase
1st
2nd
3rd
4
5th &
PE
564,000
0
0
0
0
CN
0
3,426,000
0
0
Totals
564,000
3,426,000
0
0
0
Report Date: May 22, 2025
Page 10
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
-15109
E Marginal Way S (BAR - S 112 St)
E Marginal Way S
Boeing Access Road to S 112th St
Planning phase to determine project parameters. Goal is to design and construct I
street improvements and traffic control. Could include additional lanes and bike lanes
to support the new Sound Transit Link Light Rail infill station.
06/09/25
06/16/25
03
C G O P S
TW
0.270
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
F
Code
State Funds
Local Funds
Total Funds
S
PL
2026
0
0
75,000
75,000
Totals
0
0
75,000
75,000
Expenditure Schedule
N
Phase
1st
2nd
3rd
4t
5th &
PL
75,000
0
0
0
0
Totals
75,000
0
0
0
Report Date: May 22, 2025
Page 11
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
/ 1391(004) TUK-66
Interurban Avenue S Overlay
Interurban Avenue S
E Marginal Way S to S 143rd Street
Complete pavement repairs, overlay, and curb and gutter repair.
06/09/25
06/16/25
05
2.250
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
ode
State Funds
Local Funds
Total Funds
S
PE
2026
NHPP
..
0
0
668,386
S
CN
2027
NHPP
4,288,.14
0
271,386
4,560,000
Totals
4,957,000
0
271,386
5,228,386
Expenditure Schedule
Phase
1st
2nd
3rd
5th
11*
0
0
PE
668,386
0
0
CN
0
4,560,000
0
0
0
Totals
668,386
4,560,000
0
0
0
Report Date: May 22, 2025
Page 12
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
co
g.
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
-1111(
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widenin
and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides o
the roadway. Includes illumination, curb, and storm drainage.
06/10/24
_
06/17/24
2099
04
0.350
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fun
to F
Code
State Funds
Local Funds
Total Funds
P
PE
2027
0
Pe
rogram
350,000
50,000
400,000
P
RW
2028
0
Ped/
Progra
90,000
10,000
100,000
P
CN
2029
0
Pe
e Pr
2,800,000
300,000
3,100,000
Totals
0
£240,000
360,000
3,600,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th
PE
0
300,000
100,000
0
0
RW
0
0
100,000
0
0
CN
0
0
0
3,100,000
0
Totals
0
300,000
200,000
3,100,000
0
Report Date: May 22, 2025
Page 13
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
/ 1230(007) TUK-67
Orillia Road South Overlay
Orillia Road S
S 188th Street to S 204th Street
Complete pavement repairs; overlay; and curb and gutter, sidewalk, and guardr
repair.
06/09/25
06/16/25
05
0.750
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fu
ode
State Funds
Local Funds
Total Funds
S
PE
2026
NHPP
10 ..
0
0
105,000
S
CN
2026
NHPP
1,204,000
0
0
1,204,000
Totals
1,309,000
0
0
1,309,000
Expenditure Schedule
Phase
1st
2nd
3rd
4
5th &
PE
105,000
0
0
0
0
CN
0
1,224, 000
0
0
Totals
105,000
1,224,000
0
0
0
Report Date: May 22, 2025
Page 14
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
co
g.
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
13494
S 119th St Pedestrian Bridge Painting
S 119th Street Bridge
West bank Duwamish River to East bank Duwamish River
Ongoing maintenance of the S 119th Street Pedestrian Bridge in the
Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance
needed.
06/09/25
_
06/16/25
06
0.040
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Fun
to F
Code
State Funds
Local Funds
Total Funds
P
CN
2026
0
0
200,000
200,000
Totals
0
0
200,000
200,000
Expenditure Schedule
Phase
1st
2nd
3rd
Sth
CN
200,000
0
0
0iii
Totals
200,000
0
0
0
0
Report Date: May 22, 2025
Page 15
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
-16476
S 124th St/50th PI S Reconfiguration
S 124th Street
49th Ave S to 51 st PI S
Reconfigure intersection to remove EB slip lane, new c/g/s on S 124th from 49th
51 st, new paved shoulder walkway on south side of 124th connecting to existing
walkway on west side of 50th Pk, new stormwater treatment/rain garden in old slip
lane ROW.
06/09/25
06/16/25
21
0.140
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
0
275,000
275,000
P
CN
2027
0
IB
1,300,000
550,000
1,850,000
Totals
0
1300,000
825,000
2,125,000
Expenditure Schedule
lN)i
0
0
Phase
1st
2nd
3rd
4th
PE
275,000
0
0
0
CN
0
1,850,000
0
0
Totals
275,000
1,850,000
0
0
Report Date: May 22, 2025
Page 16
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
-15108
S 133 St/SR599 Southbound Intersection
S 133rd Street
SR 599 SB Ramp to
Design and construct intersection improvements, which could include a new traffic
signal a roundabout,
lighting,, peddestrianian facilities, and drainage.
06/09/25
06/16/25
03
C G O P S
TW
0.100
Yes
Funding '
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
F
Code
State Funds
Local Funds
Total Funds
P
PE
2028
0
0
400,000
400,000
P
RW
2028
0
0
150,000
150,000
P
CN
2029
0
TIB
1,620,000
1,080,000
2,700,000
Totals
0
�20,000
1,630,000
3,250,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5
th
PE
0
0
400,000
0
0
RW
0
0
150,000
0
0
CN
0
0
0
2,700,000
0
Totals
0
0
550,000
2,700,000
0
Report Date: May 22, 2025
Page 17
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
TUK-65
S 144th Street Bridge Sidewalks
S 144th Street Bridge
51st Ave S to 53rd Ave S
The project entails replacing approximately 320 feet of raised bridge deck on the
144th street bridge with 6-foot-wide sidewalks, which will be separated from the
traffic lanes by a crash tested barrier and a pedestrian railing. Sharrows will also be
added to the traffic lanes for bicycle traffic.
06/09/25
06/16/25
28
0.060
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
Code State Funds
Local Funds
Total Funds
S
PE
2026
STBG(UL)
500,000
0
79,000
579,000
P
CN
2027
SRTS
2,000,000
0
720,000
2,720,000
Totals
2,500,000
0
799,000
3,299,000
Expenditure Schedule
j0
Phase
1st
2nd
3rd
4th
PE
579,000
0
0
0CN
0
2,720,000
0
0
Totals579,0002,720,0000
00
Report Date: May 22, 2025
Page 18
Wwasningtan state
A Tr Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
t
g.
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
-1111;
S 152nd Street Pedestrian and Bike Improvements
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Install curb, gutter, shared use path and sidewalks on S 152nd Street, including
widening pavement and construction of a buffer between the roadway and sidewalk
on the south side.
06/09/25
06/16/25
05
C G O P S
TW
0.300
Yes
Funding '
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
F
Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
0
274,000
274,000
S
RW
2026
0
0
200,000
200,000
P
CN
2027
0
TIB
2,500,000
500,000
3,000,000
Totals
0
ri00,000
974,000
3,474,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5
th
PE
270,000
0
0
0
0
RW
230,000
0
0
0
0
CN
0
3,000,000
0
0
0
Totals
500,000
3,000,000
0
0
0
Report Date: May 22, 2025
Page 19
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
-15829
S Ryan Way
SR 900 to 51st Ave S
Resurface and rechannel S Ryan Way to improve failing pavement and improve
safety. Add pedestrian and bicycle facilities where appropriate. Signalize intersection
with 47th Avenue S to accommodate future growth and improve safety.
06/09/25
06/16/25
06
C G P S T
W
0.500
No
Funding '
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
F
Code
State Funds
Local Funds
Total Funds
S
PE
2026
0
0
500,000
500,000
P
PE
2026
SRTS
100,000
0
0
100,000
P
RW
2026
SRTS
200,000
0
100,000
300,000
P
CN
2027
SRTS
5,000,000
00,000
2,800,000
12,800,000
Totals
5,300,000
000
3,400,000
13,700,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
& 6th
PE
600,000
0
0
0
0
RW
300,000
0
0
0
0
CN
0
12,800,000
0
0
0
Totals
900,000
12,800,000
0
0
0
Report Date: May 22, 2025
Page 20
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
TUK-64 06/09/25
South King County TDM
South King County
N/A to N/A
This project will provide TDM programming and services at selected activity cen
in Tukwila and partnering South King County jurisdictions. Activity centers include
community hubs, commercial areas, business parks, multifamily housing complexes,
and educational institutions. For example, places such as Tukwila International
Boulevard District, Southcenter, and Sea-Tac Airport. By providing transportation
resources and incentives, the project will encourage people to choose sustainable
transportation options that reduce drive -alone travel and traffic congestion in South
King County. TDM services will be provided to residents, commuters, and visitors,
targeting those willing and able to try sustainable modes of transportation. The
1111(lict
program will work in partnership with partner agencies, nonprofits, employers, and
community organizations.
06/16/25
A'
24
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State F d Code
StatLocal Funds
Total Funds
S
PL
2026
CMAQ
449,567
OTHER
4 50,000
)J*IIIIIL
519,731
Totals
449,567
0, 50,000
519,731
Expenditure Schedule
ih
Phase
1st
2nd
3rd
4th
& 6th
PL
129,933
0
0
0
0
Totals
129,933
0
0
0
0
Report Date: May 22, 2025
Page 21
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
-15813
Southcenter Blvd Bikeway and Pedestrian Crossing Upgrades
Southcenter Boulevard
International Boulevard to 42nd Avenue S
Improve the existing bike lanes and crosswalks on Southcenter Blvd within a half -
mile of Tukwila International Boulevard Station (TIBS). Re-channelize to 11 ft general
purposeslanes accommodate separatedrten f curb and .post)dd bike lanes. Tighten
intersection with 40th Ave S to shorten crossing distance. Add bike channelization
and upgrade to high -visibility crosswalk markings at Southcenter Blvd/TIBS station
entrance and Southcenter Blvd/42nd Ave S intersections.
06/09/25
06/16/25
28
C G P S T
W
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
Stand Co
to Funds
Local Funds
Total Funds
S
CN
2026
0
Totals
0
0
325,000
325,000
0
325,000
325,000
Expenditure Schedule
)00IrN
0
0
Phase
1st
2nd
3rd
4th
CN
325,000
0
0
0
Totals
325,000
0
0
0
Report Date: May 22, 2025
Page 22
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
-16478
Southcenter Blvd Road Diet (with Lake to Sound Regional Trail)
Southcenter Boulevard
S 66th Ave to 53rd Ave S
As part of the King County led Lake to Sound Regional Trail F1 Phase, narrow
Southcenter Blvd from 5 lanes to 3 lanes between approx. 62nd Ave S and 66th Ave
S. Reconfigure signal operations at 66th Ave S to include dual WB left turn lanes and
a single WB thru lane. All lanes will generally shift to the south of the existing ROW
to allow for construction of the Lake to Sound trail and trail buffering.
06/09/25
06/16/25
28
C G O P S
TW
0.930
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
Stat d Cod
tate Funds
Local Funds
Total Funds
S
PE
2026
0
0
135,000
135,000
P
CN
2027
0
T
372,000
2,755,000
Totals
0
%8k3,000
3,000
507,000
2,890,000
Expenditure Schedule
Phase
1st
2nd
3rd
4thdN
e
PE
135,000
0
0
0
0
CN
0
2,755,000
0
0
0
Totals
135,000
2,755,000
0
0
0
Report Date: May 22, 2025
Page 23
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
-13491
Transportation Demand Management Implementation
to
Provision of TDM services to Commute Trip Reduction -affected employment sit
Facilitate employer reporting and records associated with biennial CTR survey.
Engage CTR employment sites with opportunities for improvement and remain
connected via technical meetings with other CTR jurisdictional representatives.
06/09/25
06/16/25
44
0.000
No
Funding
Nislo
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds Code State Funds
Local Funds
Total Funds
S
ALL
2026
OT 93,300
0
93,300
P
ALL
2027
0
DOT 186,600
0
186,600
Totals
0
279,900
0
279,900
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th
ALL
46,650
46,650
46,650
46,650
, 65,09 ,
Totals
46,650
46,650
46,650
46,650
4,665,093,300
Report Date: May 22, 2025
Page 24
wasningtan state
Departmental Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2026 to 2031
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
TUK-69
Tukwila and South King County TDM
Tukwila and South King County
N/A to N/A
This project will provide TDM programming and services to help people access
sustainable transportation options that reduce drive -alone travel and traffic
in alyaTukwila and South nt King Conty. Tukwila's TDM l Program roushes
people regionally
people regionally at employment centers, community hubs, multifamily housing
ing
complexes, and educational institutions.
06/09/25
06/16/25
24
0.000
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
Sta
d Code
State Funds
Local Funds
Total Funds
S
PL
2026
0
DOT
416,000
10,700
426,700
S
PL
2027
CMAQ
550,000
0
0
550,000
P
PL
2028
0
416,000
10,700
426,700
Totals
550,000
000
21,400
1,403,400
Expenditure Schedule
Phase
1st
2nd
3rd
4th
6th
ALL
213,350
350,850
350,850
350,850
137,500
Totals
213,350
350,850
350,850
350,850
137,500
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
44,055,567
39,090,064
32,140,786
115,286,417
Report Date: May 22, 2025
Page 25
Transportation & Infrastructure Services Committee Minutes May 28, 2025
F. Grant Award: Gilliam Creek Fish Barrier Removal and Habitat Enhancement
Staff is seeking approval to accept a Recreation and Conservation Office Brian Abbot Fish
Barrier Removal Board award in the amount of $300,000 for preliminary design of the project.
Committee Recommendation
Majority approval. Forward to June 2, 2025 Regular Meeting Consent Agenda.
G. Resolution: Annual Six -Year Transportation Improvement Program
*Staff is seeking approval of the annual resolution adopting the TIP for 2026-2031.
Committee Recommendation
Majority approval. Forward to June 9, 2025 Committee of the Whole
The meeting adjourned at 6:35 p.m.
IfVf
Committee Chair Approval
Minutes by LH
31