INFORMATIONAL MEMORANDUM
Transportation and Infrastructure Services
Jen Tetatzin, Public Works Director
Josh Hopkins, Project Manager
August 11, 2025
Surface Water Fund — Chinook Wind Extension
Project Numbers 92341202
Design Contract with Herrera, Inc. — Amendment No. 1
ISSUE
Approve Amendment #1 to contract 25-045 in the amount of $21,838 with Herrera, Inc. for design services.
BACKGROUND
This project will develop shoreline habitat restoration and connect Tukwila's Duwamish Gardens and King County's Chinook
Wind within recently acquired City property for the Maintenance & Engineering (M&E) Building Project and provide the
`missing trail link' that establishes a continuous trail along the Duwamish River between TIB and East Marginal Way. This
project was identified in the 2013 Duwamish Gardens Opportunities for Expansion Concept Plan, 2019 Public Works Facility
Preferred Master Plan, and the 2021 WRIA 9 Salmon Habitat Plan Update, a Tier 1 project (Duw-7a).
DISCUSSION
This project was taken to approximately 50% design as the shoreline improvements component of the M&E Project, which is
being managed though the mayor's office. In 2024, the city downsized the M&E project due to budget constraints, which
resulted in, among other things, the uncoupling of the shoreline restoration project. This project, known as the Chinook Wind
Extension CIP, is now managed by Public Works staff, and retains the services of Herrera, Inc., the designer of record for the
shoreline work to date.
The original contract scope (post M&E) included two alternatives and a 60% design package. Amendment number 1 adds a
third alternative to develop a hydraulically connected option with Chinook Wind to increase ecological function. If successful,
King County would adopt the project and integrate it into their Mitigation Banking program, the City would continue with the
trail component only. If integration proves to be infeasible or otherwise unsuitable, the design team will shift back to the
original two alternatives and develop the shoreline habitat restoration without integration with Chinook Wind (hydraulically).
The project would continue to be supported by awarded grant funding from KC. The advantage of King County taking over
the project is the County would be responsible for post construction maintenance responsibilities for 10-years. The shoreline
would ultimately be returned to the City after the maintenance period, similar to Chinook Wind.
FISCAL IMPACT
The project's design work under the M&E Project was by $280,000 grant from King County's Open Space and River
Corridors grant program. Surface Water Utility revenue was used for the intermediary contract (25-045) with Herrera for
rescoping and stakeholder coordination with King County. KC OSRC Grant will be used to reimburse Amend. No. 1. Tukwila
has been notified of pending grant awards of $1.6M for further design and construction costs.
Contract Amount Amount Funding Source Amount
Contract 25-045 $99,890.00 Enterprise 412 Surface Water Funds $99,890.00
25-045 Amend. #1 $21,838.00 King County OSRC Grant $21,838.00
Total: $121,825.00 Total: $121,825.00
RECOMMENDATION
Council has been asked to approve Amendment No. 1 to contract 25-045 for $21,838.00 with Herrera Environmental
Consultants, Inc. and consider this item on the Consent Agenda at the September 8th Special Meeting.
Attachments: CIP Sheet - Chinook Wind Extension; Amendment No.1
29
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2025 to 2030
PROJECT: Chinook Wind Extension
Project # 92341202
Project Manager Mike Perfetti Department Surface Water
DESCRIPTION:
JUSTIFICATION:
Following the Public Works Facility Preferred Master Plan (2019) and the Duwamish Gardens Opportunities
for Expansion Concept Plan (2013), this project will develop connecting shoreline habitat and the 'missing
trail link' between Duwamish Gardens and Chinook Wind within recently acquired City property.
This is a Tier 1 project in the WRIA 9 Salmon Recovery Plan, fulfilling a core recovery strategy of restoring,
protecting and enhancing estuary habitat in the Duwamish River. The trail connection has been discussed
in the community for many years and is anticipated to be part of larger, popular shoreline trail.
STATUS: The project is currently at 50% design.
MAINTENANCE IMPACT:
COMMENT:
FINANCIAL (in thousands)
This is a work in progress. The Green Infrastructure Program Proposal is intended, in part, to address
maintenance needs for PW-initiated habitat restoration projects and helping to alleviate pressure on Parks'
given resource constraints. Note that vegetation management maintenance needs decrease over time as
planted vegetation matures. 3 years is considered a rule of thumb for plant establishment.
This grant funded project is being implemented as part of the PW Shops Ph 2 project. There are
expectations by the granting agency that the project will be constructed. It is the middle link of the
Duwamish Gardens/Chinook Wind trail and "blue belt" aquatic restoration corridor.
2025
2026
2027
2028
2029
2030
Beyond
TOTAL
Project Costs
Project Mgmt (Staff Time/Cost)
Design
Construction Mgmt.
Construction
Contingency
$ 10
$ 50
$ 200
$ 1,000
$ 25
$ 10
$ 50
$ 200
$ 1,000
$ 25
Total Project Costs
$ 1,285
$ 1,285
Project Funding
Proposed Grant
Utility Revenues
$ 1,000
$ 285
$ 1,000
$ 285
Total Project Funding
$ 1,285
$ 1,285
30
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Agreement Number:25-045
CONTRACT FOR SERVICES
Amendment #1
Between the City of Tukwila and Herrera Inc.
That portion of Contract No. 25-045 between the City of Tukwila and Herrera Inc. for the project titled
Chinook Wind Extension — Design Services is hereby amended as follows:
Section 2, Scope of Services:
The following language shall be added to the end of the existing Section 2:
In addition, work under this contract shall include reimbursement for services, direct expenses,
and costs associated with the additional contract scope of services as described in Exhibit A-
1 and B-1, attached.
Section 3: Duration of Agreement; Time for Performance:
Section 3 is hereby amended to read as follows:
This Agreement shall be in full force and effect for a period commencing upon execution and
ending December 31, 2025, unless sooner terminated under the provisions hereinafter
specified. Work under this Agreement shall commence upon written notice by the City to the
Consultant to proceed. The Consultant shall perform all services and provide all work product
required pursuant to this Agreement no later than December 31, 2025 unless an extension of
such time is granted in writing by the City.
Section 4, Payment:
Section 4A is hereby amended to read as follows:
Payment for the work provided by the Consultant shall be made as provided on Exhibits "B"
provided that the total amount of payment to the Consultant for that work shall not exceed
$99, 987.00 without express written modification of the Agreement signed by the City.
Payment for the work provided by the Consultant shall be made as provided on Exhibit A-1
and B-1 attached hereto, provided that the total amount of payment to the Consultant for that
work shall not exceed $121, 825.00 without express written modification of the Agreement
signed by the City.
The maximum amount payable under this contract as amended inclusive of all fees and other
costs shall not exceed $121,825.00 without express written modifications of the Agreement
signed by the City.
CA Reviewed May 2020
Page 1 of 2
31
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Agreement Number:25-045
All other provisions of the contract shall remain in full force and effect.
Dated this
CITY OF TUKWILA
day of , 20
Thomas McLeod, Mayor
ATTEST/AUTHENTICATED:
Andy Youn-Barnett, City Clerk
APPROVED AS TO FORM:
Office of the City Attorney
CONTRACTOR:
By:
Printed Name: Theresa M. Wood
Title:
Vice President
32 CA Reviewed May 2020
Page 2 of 2
Al
Science + Planning + Design
On November 13, 2024, Mike Perfetti authorized Herrera Environmental Consultants (Herrera) to prepare
a scope of work and cost estimate to perform engineering design for the City of Tukwila (the City). An
initial scope and budget were agreed to on February 10, 2025. On May 29, 2025, Joshua Hopkins
authorized Herrera to revise the scope and budget based on discussions to date with King County.
Herrera will advance the preliminary Duwamish shoreline restoration design developed for the Tukwila
Public Works Administrative Campus project as a separate project and, in this initial step, evaluate the
feasibility of integrating the design with the King County (the County) Chinook Wind Mitigation project.
The revised project will be referenced as the Chinook Wind Extension Project.
This scope of work includes a discussion of the activities, assumptions, deliverables, and a schedule
associated with this project.
w
s
k
6""'""
II
e�;t
II IIIII � . g e
me
t
Herrera's project manager, Christina Merten, will be responsible for ongoing administration of the
project, including preparing invoices and progress reports, as well as coordination of work efforts with
the designated client point of contact (Josh Hopkins or Mike Perfetti). Herrera's project manager will have
phone and e-mail contact with the City on an as -needed basis.
Herrera will use an established system of quality assurance/quality control review to ensure high quality
deliverables that comply with the requirements of the scope of work, as well as provide responsive and
technically accurate work product. Work products will be reviewed by technical leads, technical editors,
the project manager, and ultimately by the Principal In Charge and Licensee of Record, Jeff Parsons.
°°• IIr
3
es
• Herrera PM will attend virtual project status update meetings for up to 30 minutes per month.
• Progress reports and invoices.
July 23, 2025
08574_scopeofwork_updatejuly_2025_clean.docx
Page 1 of 4
HERRERA
33
SC PE
S
C
Ir"
2
C
nity
S
Ir"
Ir"
9
Ir"
rn
Herrera will work with the City and the County Mitigation Reserve Program to determine what revisions
to the Chinook Wind Mitigation Site will be allowed by the County and the Interagency Review Team
(IRT) that regulates the Chinook Wind Mitigation Site. Work will include revision of hydraulic models for
the combined sites based on updates to the Shoreline Restoration Design Development level grading
design developed in 2024. It is anticipated that this updated grading plan (Conceptual Grading Option 3)
would be to a 30% design level of detail. Herrera will hold an internal design charette with our
geomorphologists, restoration engineers, landscape architects, and mitigation specialists to refine the
Option 3 design based on modeling results.
Herrera will then meet with the City and County for a design workshop to review modeling results and
recommended refinements. If the workshop results in additional refinements to be made that would
affect model results, Herrera will refine the design and conduct a second model run that incorporates the
new configuration. Herrera will then coordinate an updated design workshop between the City and
County to review all modeling results to date and determine if any additional design refinements are
needed or suggested. If design refinements are identified that would affect model results Herrera will
conduct a third model run to determine potential effects of design refinements. If the design refinements
do not result in changes that need to be modeled, Herrera will run the model on the design option with
the least grading (Option 1 or 2) to determine project results if the Tukwila site is not fully integrated with
the Chinook Wind mitigation area. Up to two meetings each with the Muckleshoot Indian Tribe and
County outside of design charettes to review potential updated shoreline restoration concepts and
modeling results are included.
Herrera will produce a web map to support collaborative review and decision -making as part of this Task.
The web map will be hosted within Herrera's ArcGIS Enterprise environment, and will allow authorized
users from the City, County and Muckleshoot Indian Tribe to explore both existing conditions and up to
two proposed design scenarios for the project area. Each scenario will be represented as a separate set
of data layers, enabling viewers to toggle individual layers on and off to compare elements such as
topography, habitat types, trails and parcel boundaries.
This work will involve coordinating meetings, attending meetings, and documenting action items and key
decisions made during meetings. Meetings will be held between February through October 2025. Based
on discussions and agreements arrived at during meetings, Herrera will meet with the City and County to
determine what constraints may be placed on the overall design and performance standards for the
project that would need to be documented in a Memorandum of Understanding (MOU). Herrera will
then work with the City and County to draft a MOU to document decisions that will influence the design
of the Chinook Wind Extension project going forward. This MOU will be submitted to the City in draft
format by December 31, 2025 for the City to finalize and receive agreement on with the County once IRT
agreement is reached for the revised design.
July 23, 2025
tw08574_scopeofwork_u pdatej u ly_2025_clea n.docx
Page 2 of 4
34
HERRERA
SC PE
Assu iil11
• The City and Herrera staff will attend a virtual project kickoff meeting for up to 2 hours to discuss
project design focus and needs. Herrera project manager and technical staff will attend the
meeting, which will include a landscape architect, restoration engineers, and biologists. (This has
been completed as of the July scope update)
• The County will share with the team the one-dimensional hydraulic model developed to design the
original Chinook Wind Mitigation Site project. (This has been completed as of the June scope
update)
• Topographic information from the Chinook Wind Mitigation Site as -built and the existing Tukwila
shoreline restoration model will be merged into a single topographic surface. (This has been
completed as of the July scope update)
• Hydraulic modeling created for the Tukwila Public Works Administrative Campus will be updated for
existing conditions and up to three alternatives of minor site adjustments based on advancement of
30% design.
• Profile for the proposed alignment for a flow through or high flow flow -through to convey slope
gradient for sediment transport and erosion and supporting cross sections at key transitions to
slope relationship for scour and to also illustrate habitat types based on elevations.
• The model software to be used will be HEC-RAS 2D.
• No new topographic survey will be required.
• The design concept and modeling does not evaluate or consider sea level rise or other projected
climate changes.
• Coordination does not include coordination or meetings with the Federal Emergency Management
Agency (FEMA) or Conditional Letter of Map Revision (CLOMR) regarding revisions to design and
hydraulic model results.
• CLOMR/LOMR assistance will be limited to providing planning level cost estimates for obtaining
CLOMR/LOMR based on model results described elsewhere in this SOW.
• Herrera will coordinate, attend, and provide documentation of action items and key decisions made
during meetings for up to eight virtual meetings, including design charettes and workshops, with
the County, the City, the IRT, and/or the Muckleshoot Indian Tribe for up to 2 hours each.
• Herrera will host a web map for the duration of this Task that will allow for up to three external
read-only Iogins allowing City, County, and Muckleshoot Indian Tribe to access a read-only web
map. Web map will allow users to export information but will not allow for editing. Web map will be
designed for ease of use and visual comparison, but not for mor advance tools such as swiping or
commenting functionality.
•
July 23, 2025
tw08574_scopeofwork_u pdatej u ly_2025_clea n.docx
Page 3 of 4
HERRERA
35
SC
PE F
• King County will provide the City a summary of the potential effects on mitigation credits based on
revised habitat types and areas for the combined sites.
• King County will provide Herrera site monitoring data or summaries that have been conducted to
date at the Chinook Wind site to inform design refinements.
• Task does not cover any permit applications or revisions to applications.
°°• IIr
3
es
• ArcGIS Enterprise environment Web Map hosted through December 2025 with up to three external
read-only logins.
• Draft (MS Word version) and Final (PDF version) meeting action items and key decisions within 2
weeks of meetings, design charettes, or workshops.
• Draft (MS Word version) and Final (PDF version) technical memo summarizing hydraulic modeling
results based on 30% grading design update agreed to during meetings with the City, IRT and
Muckleshoot Indian Tribe.
• Draft (MS Word version) and Final (PDF version) technical memo describing mitigation options and
potential mitigation habitat value (in summary table format) for work on the City -owned property
and any proposed changes to Chinook Wind Mitigation Site habitat types, including visuals for IRT
presentation support.
• Draft (MS Word version) of MOU between the City and the County documenting decisions captured
in meeting minutes.
July 23, 2025
tw08574_scopeofwork_u pdatej u ly_2025_clea n.docx
Page 4 of 4
36
HERRERA
HERRERA
Cos Estimate for
Herrera Project No.
7/23/2025
Herrera Labor based on:
Chinook Wind Extension Project
24-08574-000
Burdened Labor Rates
chechde
Task No.
Task Start
Task End D
Project
Management
2
2
KC MRP
Coordination
2025
2026
B1
Merten, Christina
Parsons, Jeff
Van Orden, Emma
Forester, Kate
Rapoza, Danielle
Crickmore, Ian David
Fox, Michelle
Marshall, Eric
Webber, Michael
Dendall, Tamara
Nichols, Allison
Lux, Gretchen
Holtz, Liza (Mary)
Trolio, Nicole
Siegel, Andrew
Scientist VII
Engineer VI
Engineer IL
Landscape Architect VI
Scientist III
GIS Analyst V
Administrative Coordinator III
CAD Designer V
Project Accountant III
Engineer I
Engineer III
Scientist V
Landscape Designer II
Marketing Specialist IV
GIS Analyst III
$316.87
$305.33
$163.24
$254.78
$154.17
$203.24
$130.27
$189.17
$148.66
$127.08
$177.05
$257.49
$136.88
$163.07
$162.63
23
4
4
4
4
2
1
4
15
1
1
Total Hours per Task
Subtotal Labor
Subtotal Herrera Labor
Grand Subtotal
Grand Total
68
$15,430
$15,430
$15,430
54
51
110
43
66
4
12 13
30 34
15
40 41
6
16
77
55
114
47
70
6
7
17
68 72
16 16
27 27
543 611
$106,394 $121,825
$106,394 $121,825
$106,394 $121,825
$121,825
Note: Herrera adjusts labor rates annually in January unless contract specifies otherwise.