HomeMy WebLinkAboutCOW 2026-06-08 Item 4A / 5A - Public Hearing - Resolution on 2027-2032 Transportation Improvement ProgramCity of Tukwila Thomas McLeod, Mayor Marty Wine, City Administrator AGENDA BILL ITEM NO. 4.A. & 5.A. Agenda Item Sponsor Jen Tetatzin, Public Works Director, City Engineer Cyndy Knighton, Senior Program Manager - Transportation Legislative History May 28, 2026 Transportation & Infrastructure Services Committee June 8, 2026 Committee of the Whole June 15, 2026 Regular Meeting Recommended Motion ❑ Discussion Only ❑x Action Requested MOVE TO adopt a resolution adopting the Six -Year Transportation Improvement Program (2027-2032) Resolution for Six -Year Transportation Improvement Program (2027- 2032) EXECUTIVE SUMMARY State law requires cities to approve a resolution adopting the annual update to the Six Year Transportation Improvement Program (TIP) after holding a public hearing. The proposed Six Year TIP for 2027-2032 include 22 new projects related to the 2024 Transportation Element, the 2025 Local Road Safety Plan, and the proposed Transportation Impact Fee updated schedule. Staff is requesting the Committee forward this item to the June 8, 2026 Committee of the Whole Meeting for a Public Hearing. DISCUSSION The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of Washington (RCW) 35.77.010. The TIP is adopted by resolution after a public hearing at the local agency level and incorporated into regional and state TIPs. The TIP is primarily a financial planning document for projects competing for grants. Any project submitted for federal grant funding must be included in the local, regional, and state adopted TIPs. The TIP is a rolling plan showing various funding sources: grants, developer, and local funds. Projects "roll" as funds or stages occur (design report, final design, and construction). Tukwila's Six Year TIP, the Capital Improvement Program (CIP), the Transportation Element, and the Local Road Safety Plan list many of the same transportation -related projects. The TIP typically lists only those transportation -related projects planned within the next six years that are deemed regionally significant or that have grant funding awarded or expected. The attached Draft 2027 - 2032 TIP and was created by modifying the 2026 - 2031 TIP to add or remove projects and adjust project costs. With the current budget cycle beginning and the proposed Transportation Impact Fee schedule being discussed along the same timeline as the TIP update, the draft TIP also includes many more new projects than a typical year. The list of projects is presented in alphabetical order. Prioritization of projects is reflected in the current CIP but new projects added are not prioritized at this point. During the current budget cycle, Council priorities will be established along with budget projections, which will help identify the top priority projects to consider over the next 6 years and beyond. The TIP can be modified at any time throughout the year to rearrange project schedules or the Council can simply wait until next year's annual update to add, remove, or modify projects based on the final biennial budget adopted this year. 4 One o projects were was removed and 22 new projects were added. The majority of new projects added are identified as top priority projects in the Transportation Element and the Local Road Safety Plan. All new projects added to the proposed Transportation Impact Fee schedule are included as they are the majority of the top priority projects in the Transportation Element. The Draft 2027-2032 TIP summary identifies all the new projects and where they originate from, as well as the current projects with the page number of the current CIP. Deleted Southcenter Boulevard Road Diet .................................................................................................................................................................... S 144th Bridge Sidewalks included in their TIP .:........................................................................................................................................................................................................................ Grant was returned, project can be added back in once funding is identified ATTACHMENTS • Draft 2027-2032 TIP Summary • Draft Resolution & 2027-2032 Draft Transportation Improvement Program • Current Adopted 2025-2030 TIP (begins on page 3) * Track changes reflect changes requested at the May 28, 2026 Transportation and Infrastructure Services (TIS) Committee meeting. 5 DRAFT 2027 - 2032 TIP SUMMARY Source' or 2025-2030 CIP Sheet PROJECT TITLE Project Costs in Thousands of Dollars Funding Sources Unsecured 2027 2028 2029 2030 2031 2032 TOTAL Federal State/TIB City/Local Grant City* 39 42nd Avenue S Bridge Replacement 600 17,500 17,500 35,600 23,600 17,000 4,500 47 42nd Avenue S Bikeway 295 295 295 30 46th Avenue Safe Routes to School 325 2,070 2,395 1,895 500 1,725 420 New Airport Way Overlay 574 3,424 3,998 3,988 10 49 ADA Improvements 61 61 61 61 61 61 366 54 APE/Minkler Blvd Intersection 375 2,400 2,775 1,900 875 1,900 500 58 APE/Industry Drive Intersection 265 2,400 2,665 2,665 2,400 LRSP Andover Park W (Strander to Tukwila Pkwy) 923 923 923 923 45 Annual Bridge Inspections and Repairs 232 237 242 242 247 247 1,447 1,447 35 Annual Overlay and Repair Program 2,520 2,520 2,720 2,720 3,155 3,155 16,790 16,720 43 Annual Traffic Signal Program 160 160 170 190 190 190 1,060 1,060 38 Boeing Access Road Overlay 3,526 3,526 3,990 TE, TIF Buffered Shared Path on 42nd Ave S Sect. 3 550 550 550 550 57 E Marginal Way S (BAR - S 112th St) 75 75 75 75 TE, LRSP E Marginal Way S (N City Limit to BAR) 6,917 6,917 6,917 6,917 New E Marginal Way S Overlay 685 5,058 5,743 5,743 TE, TIF E Marginal Way S Section 2 Sidewalks 803 803 803 803 LRSP Interurban Avenue S (140th St to S 144th St) 1,484 1,484 1,484 1,484 52 Interurban Avenue S Overlay 356 356 356 TE, LRSP Klickitat Dr (53rd Ave S to Southcenter Pkwy) 582 582 582 582 31 Macadam Road S Complete Streets 300 200 3,100 3,600 3,160 350 3,160 350 TE, TIF Macadam Road S Sect. 1 Sidewalk 992 992 992 992 TE, TIF Minkler Blvd Sect. 2 Sidewalk 1,430 1,430 1,430 1,430 44 Orillia Road S Overlay 1,204 1,204 1,204 TE, TIF S 115th SUE Marginal Way Intersection Impr 2,000 2,000 2,000 2,000 41 S 119th St Pedestrian Bridge Painting 200 200 200 55 S 124th St/50th PI S Reconfiguration 50 1,022 1,072 898 254 59 S 133rd St/SR 599 SB Intersection 550 2,700 3,250 1,620 1,630 1,620 1,630 TE, TIF S 141st St Sect. 1 Sidewalk 510 510 510 510 TE, TIF S 142nd St Sidewalk 541 541 541 541 TE, TIF S 144th St Complete Streets 869 869 869 869 LRSP S 144th St Improvements (Military Rd to TIB) 580 580 580 580 28 S 152nd Street Ped & Bike Improvements 530 4,950 5,480 3,960 1,520 3,960 990 LRSP S 180th St (Sperry Dr to IU Trail) 806 806 806 806 TE, TIF S Norfolk St Bike Facilities 497 497 497 497 37 S Ryan Way 1,275 13,060 14,335 8,850 55,606 8,850 4,231 48 Southcenter Blvd Bike and Ped Xing Upgrades 352 352 352 352 46 Southcenter Blvd Road Diet (with L2S Trail) 135 3,000 3,135 2,400 735 2,400 600 TE, TIF SR 518 EB Off Ramp/Klickitat Drive Improvements 850 850 850 850 TE, TIF Strander Boulevard Sidewalk 467 467 467 467 TE, TIF TIB Sect. 2 Sidewalk (north) 377 377 377 377 TE, TIF TIB Sect. 2 Sidewalk (south) 1,673 1,673 1,673 1,673 - TDM Implementation 52 52 52 52 52 52 312 312 Tukwila and South King County TDM 260 260 130 650 832 208 - South King County Regional TDM 159 159 159 159 636 550 56 LRSP Tukwila Int'I Blvd (S 152nd St to S 144th St) 4,347 4,347 TOTAL 14,491 56,738 37,911 11,769 6,984 10,622 138,515 39,431 42,883 111,853 23,615 34,399 PROJECTS REVISED FROM 2025-2030 TIP New Deleted/Completed: Airport Way Overlay - fully grant funded S 144th Bridge Sidewalks E Marginal Way S Overlay - fully grant funded TE: Transportation Element, TIF: Transportation Impact Fee Schedule, LRSP: Local Road Safety Plan * Unsecured City funding includes all funds necessary outside of the current biennial budget cycle 6 June 2, 2026 NOTE: Changes were made after the May 28, 2026 Transportation and Infrastructure Services (TIS) Committee Meeting. See added page (pg 38 of Exhibit A). A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR TRANSPORTATION IMPROVEMENT PROGRAM (2027- 2032), AND DIRECTING THE SAME TO BE FILED WITH THE STATE SECRETARY OF TRANSPORTATION AND THE TRANSPORTATION IMPROVEMENT BOARD. WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26, the City Council of the City of Tukwila has previously adopted a Transportation Improvement Program and thereafter periodically modified said Transportation Improvement Program by resolution; and WHEREAS, the City Council has reviewed the work accomplished under said program, determined current and future City street and arterial needs and, based upon these findings, has prepared a Six -Year Transportation Improvement Program for the ensuing six calendar years (2027-2032); and WHEREAS, on June 8, 2026, a public hearing was held regarding the City's Six -Year Transportation Improvement Program; NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, HEREBY RESOLVES AS FOLLOWS: Section 1. Program Adopted. A Six -Year Transportation Improvement Program for the calendar years 2027 to 2032, attached hereto as Exhibit A, is hereby adopted. Section 2. Filing of Program. The City Clerk is hereby authorized and directed to file a copy of this resolution, together with the exhibit attached hereto, with the Secretary of Transportation and the Transportation Improvement Board of the State of Washington 2026 Legislation: 2027-2032 TIP Version: 04/30/2026 Staff: C. Knighton Page 1 of 2 7 PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at a Regular Meeting thereof this day of , 2026. ATTEST/AUTHENTICATED: Andy Youn-Barnett, CMC, City Clerk Armen Papyan, Council President APPROVED AS TO FORM BY: Filed with the City Clerk: Passed by the City Council: Resolution Number: Office of the City Attorney Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2027 to 2032 2026 Legislation: 2027-2032 TIP Version: 04/30/2026 Staff: C. Knighton Page 2 of 2 8 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 / 1037(004) TUK-62 42nd Ave S Bridge Replacement 42nd Ave S over the Duwamish River Interurban Ave S to Northern end of bridge Replace the existing 42nd Ave S steel truss bridge. The replacement will require preliminary engineer design, and construction phases. The new structure will meet current road and bridge design standards. The replacement structure configurationtill1111.11 will be two through -lanes, possibly a turn pocket, and include sidewalks. 06/08/26 5/ 11 0.100 DCE Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal ' S Fund Code State Funds Local Funds Total Funds S PE 2027 0 500,000 500,000 S RW 2027 0 0 100,000 100,000 P CN 2028 BR ` 000 0013,000,000 S CN 2028 BR 59•, CIN599,306 MAW 17,000,000 3,900,000 31,499,306 Tota 17,000,000 4,500,000 45,099,306 Expenditure Schedule NOV Phase 1st 2nd 4th 5th & 6th PE 500,000 0 0 0 0 RW 100,000 0 0 0 0 CN 0 17,500,000 17,500,000 0 0 Totals 600,000 17,500,000 17,500,000 0 0 Report Date: June 01, 2026 Page 1 9 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title Hearing D Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID ogc 05 WA-15812 06/08/26 28 C G P S T No W 42nd Avenue S Bikeway 42nd Avenue S 14 Southcenter Blvd to S 150th Street Develop a traffic -calmed bikeway along 42nd Ave S between S 150th St and Southcenter Blvd. On the west side of the street, add striped southbound bike lane between Southcenter Blvd and S 150th St. On the east side of the street, add striped bike lane between Southcenter Blvd and S 151st St. Remove on -street parking to widen the sidewalk on the east side of the street between S 151 st St and S 150th St, creating a shared path; add shared lane markings to the roadway Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federa to Fund Code State Funds Local Funds Total Funds S CN 2027 0 0 295,000 295,000 Total 0 295,000 295,000 Expenditure Schedule Phase 1st 2nd N 4th 5th & 6th CN 295,000 0 0 0 0 Totals 295,000 0 0 0 0 Report Date: June 01, 2026 Page 2 10 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required E. Begin & End Termini F. Project Description G. Structure ID 19 WA-11113 06/08/26 5/ 05 C G P S T 0.370 Yes W 46th Avenue Safe Routes to School 46th Avenue S S 150th Street to S 144th Street Designland construct of curb, Er ancorner r of 46th otke westside o4tith Avenue S, including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised tillIllIllklkk4 crosswalk across S 144th Street with RRFB. Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal S Fund Code State Funds Local Funds Total Funds S PE 2027 i RTS 170,000 80,000 250,000 P RW 2027 0 SRTS 65,000 10,000 75,000 P CN 2028 0 SRTS 1,660,000 410,000 2,070,000 Total + 1,895,000 500,000 2,395,000 Expenditure Schedule Phase 1st 2nd rd 4th 5th & 6th PE 250,000 0 0 0 0 RW 75,000 0 0 0 0 CN 0 2,070,000 0 0 0 Totals 325,000 2,070,000 0 0 0 Report Date: June 01, 2026 Page 3 11 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 TUK-71 Airport Way Overlay Airport Way S Boeing Access Road to North Tukwila City Limit Plane, pavement repair, pave; channelization, and repair of curb and gutter, sidewalk, and guardrail, as necessary. _ 06/08/26 5/ 05 0.380 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun • and Coe State Funds Local Funds Total Funds S PE 2027 NHFP 64,E 0 10,000 574,000 S CN 2028 NHFP 3,424 0 0 3,424,000 Totals . r 1 0 10,000 3,998,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th PE 574,000 0 0 0 0 CN 0 3,424,000 0 0 0 Totals 574,000 3,424,000 0 0 0 Report Date: June 01, 2026 Page 4 12 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 Americans with Disabilities Act (ADA) Improvements Various locations to Design and construct ADA compliant upgrades to City infrastructure in conjunction with a City developed plan. WA-05405 Allir— 06/08/26 41111Ce 5/ 06 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds S ALL 2027 0 366,000 366,000 Totals 0 366,000 366,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 61,000 61,000 1,00 61,000 122,000 Totals 61,000 61,000 1,000 61,000 122,000 Report Date: June 01, 2026 Page 5 13 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 16 Andover Park E/Minkler Blvd Intersection Andover Park E Minkler Blvd to Construct left turn lanes on Andover Park East and reconstruct traffic signal WA-07746 Abb.— 06/08/26 <le 5/ 03 C G O P S TW No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds S PE 2027 0 275,000 275,000 S RW 2027 0 100,000 100,000 P CN 2028 TIB 1,900,000 500,000 2,400,000 Totals w 0 1,900,000 875,000 2,775,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 275,000 0 0 0 0 RW 100,000 0 0 0 0 CN 0 2,400,000 0 0 0 Totals 375,000 2,400,000 0 0 0 Report Date: June 01, 2026 Page 6 14 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 Andover Park East/Industry Dr Intersection Andover Park E Industry Drive to Design and construct traffic signal with Andover Park East left turn lanes and crosswalks.44<( WA-15107 06/08/26 5/ 03 C G P S T W 0.100 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds S PE 2027 0 190,000 190,000 S RW 2027 0 75,000 75,000 P CN 2028 0 0 2,400,000 2,400,000 Totals 0 0 2,665,000 2,665,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 190,000 0 0 0 0 RW 75,000 0 0 0 0 CN 0 2,400,000 0 0 0 Totals 265,000 2,400,000 0 0 0 Report Date: June 01, 2026 Page 7 15 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17047 Andover Park W (Strander to Tukwila Parkway) Andover Park W Strander Boulevard to Tukwila Parkway41111Ce Construct driveway access improvements, provide bus lanes, install RRFB's, and improve signal timing _ 06/08/26 5/ 04 0.390 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2030 0 923,000 923,000 Totals 0 923,000 923,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 923,000 0 Totals 0 0 0 923,000 0 Report Date: June 01, 2026 Page 8 16 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14 Annual Bridge Inspections and Repairs Various City Street to Perform load ratings and bi-annual inspections as well as construct necessary repairs and maintenance WA-03731 Allir— 06/08/26 411111Q 5/ 06 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds S ALL 2027 0 1,447,000 1,447,000 Totals 0 1,447,000 1,447,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 232,000 237,000 242,000 494,000 Totals 232,000 237,000n2,00 2,000 242,000 494,000 Report Date: June 01, 2026 Page 9 17 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 16 WA-03733 Annual Overlay and Repair Program Various City Streets to Repair, rehabilitate, and overlay City streets as needed in an annual program _ 06/08/26<eilligl11(\° 5/ 06 C G O P S TW No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds S ALL 2027 0 16,790,000 16,790,000 Totals 0 16,790,000 16,790,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 2,520,000 2,520,000 0,00 2,720,000 6,310,000 Totals 2,520,000 2,520,000 2 0,000 2,720,000 6,310,000 Report Date: June 01, 2026 Page 10 18 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 Annual Traffic Signal Program Varies to Design and construct traffic signal upgrades and repairs of signals that exceed routine maintenance work;loop replacement, head replacement, and controllers. Replace direct bury cable for existing lighting system.t<( WA-15104 06/08/26 5/ 44 P No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds S ALL 2027 0 1,060,000 1,060,000 Totals 0 1,060,000 1,060,000 Expenditure Schedule1Sr Phase 1st 2nd 3rd 4th 5th & 6th ALL 160,000 160,000 0,000 190,000 380,000 Totals 160,000 160 000 Q 000 190,000 380,000 Report Date: June 01, 2026 Page 11 19 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 1380(005) Boeing Access Road Overlay Boeing Access Road East Marginal Way S to Martin Luther King Jr Way S Grind and overlay roadway, replace concrete overlay of bridge deck over BNSF railway. TUK-68 Air— 06/08/26 41111Ce 5/ 05 0.560 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun • and Coe State Funds Local Funds Total Funds S PE 2027 NHPP 64,E 0 0 564,000 S CN 2027 NHPP 3,426 0 0 3,426,000 Totals r 1 0 0 3,990,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th PE 100,000 0 0 0 0 CN 3,426,000 0 0 0 0 Totals 3,526,000 0 0 0 0 Report Date: June 01, 2026 Page 12 20 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17026 Buffered Shared Path on 42nd Ave S Section 3 42nd Ave S S 150th St to S 144th St Remove parking on one side and widen sidewalk to create shared -use path 06/08/26 411111 5/ 28 No Funding Iiiiik Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Funds Local Funds Total Funds P ALL 2030 0 550,000 550,000 Totals "N 0 550,000 550,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 ellicilliiiir 550,000 0 Totals 0 0 550,000 0 Report Date: June 01, 2026 Page 13 21 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 WA-15109 06/08/26 5/ E Marginal Way S (BAR - S 112 St) E Marginal Way S Boeing Access Road to S 112th St Planning phase to determine project parameters. Goal is to design and construct full street improvements and traffic control. Could include additional lanes and bike lanes tillIlliklkbh4 to support the new Sound Transit Link Light Rail infill station. 03 C G O P S TW 0.270 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal S Fund Code State Funds Local Funds Total Funds P PL 2028 i 0 75,000 75,000 Totals 0 0 75,000 75,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th PL 0 75,000 cc 0 0 0 Totals 0 75,000 0 0 0 Report Date: June 01, 2026 Page 14 22 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 WA-17053 E Marginal Way S (N City Limit to S Boeing Access Rd) Boeing Access Road to Northern City Limit Widen and extend asphalt paving on E Marginal Way S north of S Boeing Access Road. lope facilities d may be desired to bi here, pending BAR I ll stationif eand area redevelopment, could connect to bike facilities on Airport Way if Seattle/Tukwila install, connecting via Norfolk to EMWS If this project moves forward, need to update bike network. tilli, 06/08/26 5/ 04 CPS 1.900 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede St and Code State Funds Local Funds Total Funds P ALL 2032 0 6,917,000 6,917,000 Totals - 0 0 6,917,000 6,917,000 Expenditure Schedule 1. Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 6,917,000 Totals 0 0 0 0 6,917,000 Report Date: June 01, 2026 Page 15 23 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 TUK-70 E Marginal Way S Overlay E Marginal Way S Interurban Avenue S to MP 2.27 Plane, pavement repair, pave, channelization, and repair of curb and gutter and sidewalk, as necessary. _ 06/08/26 41111Ce 5/ 05 0.960 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun • and Coe State Funds Local Funds Total Funds S PE 2027 NHPP .85,E 0 0 685,000 S CN 2028 NHPP 5,058 0 0 5,058,000 Totals r 1 0 0 5,743,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th PE 685,000 0 0 0 0 CN 0 5,058,000 0 0 0 Totals 685,000 5,058,000 0 0 0 Report Date: June 01, 2026 Page 16 24 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17043 E Marginal Way S Section 2 Sidewalk E Marginal Way S Interurban Ave S to S 120th PI Construct sidewalk on both sides of road segment. 06/08/26 411111 5/ 28 0.140 No Funding Iiiiik Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Funds Local Funds Total Funds P ALL 2031 0 803,000 803,000 Totals "N 0 803,000 803,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 ellicilliiiir 0 803,000 Totals 0 0 0 803,000 Report Date: June 01, 2026 Page 17 25 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 WA-17049 Interurban Ave (140th St to S 144th St) Interurban Ave S 140th St to 144th St Construct two landscape medians, install RRFB's, and a new pedestrian crossing 06/08/26 5/ 4111111(1 28 0.270 No Funding Iiiiik Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Funds Local Funds Total Funds P ALL 2031 0 1,484,000 1,484,000 Totals "N 0 1,484,000 1,484,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 eillicW 0 1,484,000 Totals 0 0 0 1,484,000 Report Date: June 01, 2026 Page 18 26 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 / 1391(004) TUK-66 Interurban Avenue S Overlay Interurban Avenue S E Marginal Way S to S 143rd Street Complete pavement repairs, overlay, and curb and gutter repair. 06/08/26 411111 5/ 05 2.250 CE No Funding Iiiiik Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Funds Local Funds Total Funds S CN 2027 NHPP 0 0 4,561,000 Totals 561,0 0 0 4,561,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th CN 356,100 0 ellic"."1111r 0 0 Totals 356,100 0 0 0 Report Date: June 01, 2026 Page 19 27 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17054 Klickitat Dr (53rd Ave S to Southcenter Pkwy) 53rd Ave S to Southcenter Pkwy Multimodal improvements to improve connectivity and accessibility of existing path wayfinding, signage, width improvements, etc. �� 06/08/26 5/ 28 0.410 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2029 0 582,000 582,000 Totals 0 582,000 582,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 2,00 0 0 Totals 0 0 2,000 0 0 Report Date: June 01, 2026 Page 20 28 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17 Macadam Rd S Complete Streets Project Macadam Road S 150th Street to S 144th Street Design and construction of a complete street on Macadam Road. Road widening and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of the roadway. Includes illumination, curb, and storm drainage. WA-11110 06/08/26 5/ t<( 04 0.350 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds P PE 2027 Pe ike Program 350,000 50,000 400,000 P RW 2028 ike Program 10,000 0 10,000 P CN 2029 0 Ped/Bike Program 2,800,000 300,000 3,100,000 Totals 0 3,160,000 350,000 3,510,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 300,000 100,000 0 0 0 RW 0 100,000 0 0 0 CN 0 0 3,100,000 0 0 Totals 300,000 200,000 3,100,000 0 0 Report Date: June 01, 2026 Page 21 29 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17028 06/08/26 5/ 28 0.340 No Macadam Rd S Section 1 Sidewalk 42nd Ave S and Macadam Rd S S 124th St to S 130th St 14 Construct sidewalk on west side of 42nd Ave S from S 124th St to entrance of 42nd Ave S Bridge, construct sidewalk on both sides of 42nd Ave S from entrance of 42nd Ave S Bridge to on bothInterides Ave aSConstruct from both sides of Macadam Rd S from ,‘ S? Interurban Ave S to S 130th St. Funding v Status Phase Phase Start Year (YYYY) Federal Fund Code al State Fund Code State Funds Local Funds Total Funds P ALL 2031 0 0 992,000 992,000 Tot 0 0 992,000 992,000 Expenditure Schedule Phase 1st 2nd N#T 4th 5th & 6th ALL 0 0 0 0 992,000 Totals 0 0 0 0 992,000 Report Date: June 01, 2026 Page 22 30 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 Minkler Blvd Section 2 Sidewalk Minkler Boulevard Andover Park W to Andover Park E Construct sidewalk on both sides of road segment WA-17027 Air- 06/08/26 41111Ce 5/ 28 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2029 0 1,430,000 1,430,000 Totals 0 1,430,000 1,430,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0n0,00 0 0 Totals 0 00,000 0 0 Report Date: June 01, 2026 Page 23 31 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 / 1230(007) Orillia Road South Overlay Ortlia Road S S 200th Street to S 188th Street/WSDOT ROW Complete pavement repairs; overlay; and curb and gutter, sidewalk, and guardrail repair. Make minor improvements to channelization and improve safety near the 188th street intersection. TUK-67 06/08/26 5/ t4<( 05 0.640 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds S CN 2027 NHPP 1,204,0 0 0 1,204,000 Totals 1,2 0 0 1,204,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 1,204,000 0 0 0 0 Totals 1,204,000 0 0 0 0 Report Date: June 01, 2026 Page 24 32 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 S 115th SUE Marginal Way Intersection Improvements E Marginal Way 300' South of S 115th St to 300' North of S 115th St Design and construct a new traffic signal, lighting, and pedestrian facilities, including crosswalks and pedestrian push buttons. WA-17025 Allir- 06/08/26 41111Ce 5/ 03 0.000 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2029 0 2,000,000 2,000,000 Totals 0 2,000,000 2,000,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0n0,00 0 0 Totals 0 00,000 0 0 Report Date: June 01, 2026 Page 25 33 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 S 119th St Pedestrian Bridge Painting S 119th Street Bridge West bank Duwamish River to East bank Duwamish River Ongoing maintenance of the S 119th Street Pedestrian Bridge in the Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance needed. WA13494 06/08/26 5/ t4<( 2117 06 0.040 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds S CN 2027 0 200,000 200,000 Totals 0 200,000 200,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 200,000 0 0 0 0 Totals 200,000 0 0 0 0 Report Date: June 01, 2026 Page 26 34 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-16476 S 124th St/50th PIS Reconfiguration S 124th Street 49th Ave S to 51st PI S Reconfigure intersection to remove EB slip lane, new c/g/s on S 124th from 49th to g new paved shoulder oe5tPk, walkway newn south side treatment/rain f 124thetraina connecting to ineold slip walkway on west side of 50th Pk, stormwater treatment/rain garden in old slip w5alkway lane ROW. till1111... 06/08/26 5/ 21 0.140 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal ' S Fund Code State Funds Local Funds Total Funds S PE 2027 TIB 101,000 29,000 130,000 S CN 2028 0 TIB 796,300 225,200 1,021,500 Totals ^ 0 897,300 254,200 1,151,500 1 1 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 50,000 0 0 0 0 CN 0 1,021,500 0 0 0 Totals 50,000 1,021,500 0 0 0 Report Date: June 01, 2026 Page 27 35 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 WA-15108 06/08/26 5/ S 133 St/SR599 Southbound Intersection S 133rd Street SR 599 SB Ramp to Design ad undbot intersection improvements, which could include a new traffic signal or roundabout, lighting, pedestrian facilities, and drainage. tillIllikiklbh4 03 C G O P S TW 0.100 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal S Fund Code State Funds Local Funds Total Funds P PE 2028 A 0 400,000 400,000 P RW 2028 0 0 150,000 150,000 P CN 2029 0 TIB 1,620,000 1,080,000 2,700,000 Total + 1,620,000 1,630,000 3,250,000 Expenditure Schedule Phase 1st 2nd rd 4th 5th & 6th PE 0 400 000 0 0 0 RW 0 150,000 0 0 0 CN 0 0 2,700,000 0 0 Totals 0 550,000 2,700,000 0 0 Report Date: June 01, 2026 Page 28 36 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 07 S 141 st St Section 1 Sidewalk S 141st 37th Ave S to Tukwila International Boulevard Construct sidewalk on both sides of road segment WA-17045 06/08/26 Abb.-<le 5/ 28 0.120 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P PE 2029 0 510,000 510,000 Totals 0 510,000 510,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0n0,00 0 0 Totals0 00,000 0 0 Report Date: June 01, 2026 Page 29 37 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 07 WA-17044 S 142nd St Sidewalk S 142nd St 37th Ave S to Tukwila International Boulevard Construct sidewalk on both sides of road segment _ 06/08/26 41111Ce 5/ 28 0.130 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2029 0 541,000 541,000 Totals 0 541,000 541,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 1,00 0 0 Totals 0 0 1,000 0 0 Report Date: June 01, 2026 Page 30 38 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17041 S 144th St Complete Street 42nd Ave S to 51 st Ave S accommodate on ft lanes, side-2ft bof ter, and 1-10ft two-way cycle track. Construct sidewalk facilities on the south side of the and 1i 1 and-wayremove parking . one side tosidewalk street. 04 C G P S T W 0.500 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal S Fund Code State Funds Local Funds Total Funds P ALL 2030 A 0 869,000 869,000 Totals 0 0 869,000 869,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 cc 0 869,000 0 Totals 0 0 0 869,000 0 Report Date: June 01, 2026 Page 31 39 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17046 S 144th St Improvements (Military to TIB) S 144th St Military Rd S to Tukwila International Boulevard Construct sidewalk improvments, curb and gutter, install RRFB's, and a pedestrian refuge island _ 06/08/26 41111Ce 5/ 28 0.310 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2028 0 580,000 580,000 Totals 0 580,000 580,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 580,000 0 0 Totals 0 580,000 0 0 0 Report Date: June 01, 2026 Page 32 40 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title Hearing D Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required D. Road Name or Number E. Begin & End Termini F. Project DescriptionG. Structure ID ogc 19 WA-11112 06/08/26 05 C G O P S 0.300 CE Yes TW S 152nd Street Pedestrian and Bike Improvements S 152nd Street Tukwila International Blvd to 42nd Avenue S Install curb, gutter, sidewalks on S 152nd Street, including widening pavement and construction of a buffer between the roadway and sidewalk on the south side.44<( Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds S PE 2027 0 300,000 300,000 S RW 2027 0 230,000 230,000 P CN 2028 0 TIB 3,960,000 990,000 4,950,000 Totals 0 3,960,000 1,520,000 5,480,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 300,000 0 0 0 0 RW 230,000 0 0 0 0 CN 0 4,950,000 0 0 0 Totals 530,000 4,950,000 0 0 0 Report Date: June 01, 2026 Page 33 41 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 WA-17048 S 180th St (Sperry Drive to Interurban Trail) S 180th St Sperry Drive to Interurban Trail Construct shared use path on the north side and stall no turn on red phasing at 180th and Sperry Dr. _ 06/08/26 411111Q 5/ 28 0.280 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2030 0 806,000 806,000 Totals 0 806,000 806,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 806,000 0 Totals 0 0 0 806,000 0 Report Date: June 01, 2026 Page 34 42 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 WA-17021 S Norfolk St Bike Facilities S Norfolk Street E Marginal Way S to East city limit Add bike facilities on S Norfolk St 06/08/26 411111 5/ 28 P S T W 0.140 CE No Funding Iiiiik Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Funds Local Funds Total Funds P ALL 2029 0 497,000 497,000 Totals "N 0 497,000 497,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 elliNc.111111111r 0 0 Totals 0 0 0 0 Report Date: June 01, 2026 Page 35 43 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 WA-15829 06/08/26 5/ S Ryan Way SR 900 to 51 st Ave S failing pavement aand improve and rechannel S Ryan Way to improveappropriate. Rsafety. safety. Add pedestrian and bicycle facilities where appropriate. Signalize intersection tillIllikklki4 with 47th Avenue S to accommodate future growth and improve safety. 06 C G P S T W 0.500 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal S Fund Code State Funds Local Funds Total Funds S PE 2027 A 0 1,275,000 1,275,000 P RW 2028 0 TIB 200,000 100,000 300,000 P CN 2028 0 TIB 8,650,000 4,131,000 12,781,000 Total + 8,850,000 5,506,000 14,356,000 Expenditure Schedule Phase 1st 2nd rd 4th 5th & 6th PE 1,275,000 0 0 0 0 RW 0 300,000 0 0 0 CN 0 12,760,000 0 0 0 Totals 1,275,000 13,060,000 0 0 0 Report Date: June 01, 2026 Page 36 44 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 WA-15813 Southcenter Blvd Bikeway and Pedestrian Crossing Upgrades Southcenter Boulevard International Boulevard to 42nd Avenue S Improve the existing bike lanes and crosswalks on Southcenter Blvd within a half - mile of Tukwila International Boulevard Station (TIBS). Re-channelize to 11 ft general purpose lanes to accommodate separated bike lanes. Tighten intersection with 40th Ave S to shorten crossing distance. Add bike channelization and upgrade to high -visibility crosswalk markings at Southcenter Blvd/TIBS station entrance and Southcenter Blvd/42nd Ave S intersections. 06/08/26 5/ 14 28 C G P S T W No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federa to Fund Code State Funds Local Funds Total Funds S CN 2027 0 0 325,000 325,000 Total 0 325,000 325,000 Expenditure Schedule Phase 1st 2nd N 4th 5th & 6th CN 325,000 0 0 0 0 Totals 325,000 0 0 0 0 Report Date: June 01, 2026 Page 37 45 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 Added after 05/28/26 Special TIS Committee Meeting N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 WA-17128 Southcenter Blvd Road Diet (with Lake to Sound Regional Trail) Southcenter Boulevard S 66th Ave to 53rd Ave S As part of the King County led Lake to Sound Regional Trail F1 Phase, narrow Blvd from 5 lanes to 3 lanes between approx.lude62nAve S and 66th Ave S. Reconfigure S. Reconfigure signal operations at 66th Ave S to include dual WB left turn lanes and a single WB thru lane. All lanes will generally shift to the south of the existing ROW to allow for construction of the Lake to Sound trail and trail buffering. 06/08/26 5/ 14 21 DCE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede St and Code State Funds Local Funds Total Funds S PE 2027 0 135,000 135,000 P CN 2029 0 TIB 2,400,000 600,000 3,000,000 Totals 0 2,400,000 735,000 3,135,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 135,000 0 0 0 0 CN 0 0 3,000,000 0 0 Totals 135,000 0 3,000,000 0 0 Report Date: June 01, 2026 Page 38 46 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 05 SR 518 EB Off-ramp/Klickitat Dr Intersection Improvements Klickitat Drive 51 st Ave S to Klickitat Drive Design and construct a new traffic signal, lighting, and pedestrian facilities including crosswalks and pedestrian push buttons. WA-17022 Allir— 06/08/26 411111Q 5/ 03 P S W 0.020 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2030 0 850,000 850,000 Totals 0 850,000 850,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 850,000 0 Totals 0 0 0 850,000 0 Report Date: June 01, 2026 Page 39 47 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 04 Strander Blvd Sidewalk Strander Blvd and SW 27th St Christensen Rd to Interurban Trail Construct sidewalk on south side of Strander Blvd from Christensen Rd to W Valley Hwy. Construct sidewalk on both sides of Strander Blvd from W Valley Hwy to east boundary of Tukwila city limits WA-17029 06/08/26 5/ ....mh.. 11>4.11111(( 28 0.200 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede unds Fund Code State Funds Local Funds Total Funds P ALL 2029 0 0 467,000 467,000 Totals 0 0 467,000 467,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 467,000 0 0 Totals 0 0 467,000 0 0 Report Date: June 01, 2026 Page 40 48 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 TIB Section 2 Sidewalk (North) Tukwila International Blvd S 112th Ave to SR99 Construct sidewalk on east side of Tukwila International Blvd from S 112th St to the HW 99 Exit Ramp. WA-17039 44<( 28 C G P S T W 0.260 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds P ALL 2029 0 377,200 377,200 Totals 0 377,200 377,200 Expenditure Schedule 14 Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 7,200 0 0 Totals 0 0 7,200 0 0 Report Date: June 01, 2026 Page 41 49 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 TIB Section 2 Sidewalk (South) SR 99 to 12400 Block Construct sidewalk on both sides of Tukwila International Blvd from the HW 99 Exit Ramp to 12400 Block. WA-17040 44<( 28 C G P S T W 0.440 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds P ALL 2029 0 1,672,800 1,672,800 Totals 0 1,672,800 1,672,800 Expenditure Schedule 14 Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 1 2,800 0 0 Totals 0 0 2,800 0 0 Report Date: June 01, 2026 Page 42 50 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 WA-13491 Transportation Demand Management Implementation to Provision of TDM services to Commute Trip Reduction -affected employment sites. Facilitateageemployer ymrepent g and records ppassociatednites with biennial andTR survey. Engage CTR employment sites with opportunities for improvement and remain connected via technical meetings with other CTR jurisdictional representatives. tilliblli. 06/08/26 5/ 44 0.000 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal ' S Fund Code State Funds Local Funds Total Funds S ALL 2027 SDOT 103,200 0 103,200 P ALL 2028 0 WSDOT 258,000 0 258,000 Totals ^ 0 361,200 0 361,200 1 1 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 51,600 51,600 51,600 51,600 103,200 Totals 51,600 51,600 51,600 51,600 103,200 Report Date: June 01, 2026 Page 43 51 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing D o- 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 Tukwila and South King County TDM to Provide TDM services to help people use sustainable transportation options that increase access to opportunity, and reduce drive -alone travel and traffic congestion in Tukwila and South King County.t<( WA-17063 06/08/26 5/ 18 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F Fund Code State Funds Local Funds Total Funds S PL 2027 THER 832,000 208,000 1,040,000 Totals 832,000 208,000 1,040,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PL 260,000 260,000 0,000 0 0 Totals 260,000 260,000 0,000 0 0 Report Date: June 01, 2026 Page 44 52 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID Hearing D o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 TUK-69 Tukwila and South King County TDM Tukwila and South King County N/A to N/A This project will provide TDM programming and services to help people access reduce drive -alone a travel andr traffic congestion intTukwilaSouthhs King congestion Tukwila and King County. Tukwila's TDM Program reaches people regionally at employment centers, community hubs, multifamily housing complexes, and educational institutions. 06/08/26 5/ 14 24 0.000 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Fede St and Code State Funds Local Funds Total Funds S PL 2027 CMAQ •• WSDOT 85,838 0 635,838 Totals - 0,000 85,838 0 635,838 Expenditure Schedule 1. Phase 1st 2nd 3rd 4th 5th & 6th PL 158,959 158,959 58,960 158,960 0 Totals 158,959 158,959 158,960 158,960 0 Report Date: June 01, 2026 Page 45 53 Agency: Tukwila County: King MPO/RTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2027 to 2032 N Outside Functional Class Priority Number A. PIN/Project No. C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description B. STIP ID G. Structure ID Hearing o 0 Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 03 Tukwila International Boulevard (S 152nd St to S 144th St) S 152nd St to S 144th St Construct landscape median, refine corridor access, roadway diet, and multimodal lanes. WA-17042 1.— 41111Ce 04 C P S W 0.530 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun and Coe State Funds Local Funds Total Funds P ALL 2030 0 4,347,000 4,347,000 Totals 0 4,347,000 4,347,000 Expenditure Schedule Phase 1st 2nd 4th 5th & 6th ALL 0 0 4,347,000 0 Totals 0 0 0 4,347,000 0 nds State Funds Local Funds Total Funds Grand Totals for Tukwila 43,635,306 42,961,338 66,509,200 153,105,844 Report Date: June 01, 2026 Page 46 54