HomeMy WebLinkAboutReg 2026-06-15 Item 7A - Resolution - 2027-2032 Transportation Improvement ProgramCity of Tukwila
Thomas McLeod, Mayor
Marty Wine, City Administrator
AGENDA BILL
ITEM NO.
7.A.
Agenda Item
Sponsor Jen Tetatzin, Public Works Director, City Engineer
Cyndy Knighton, Senior Program Manager - Transportation
Legislative History May 28, 2026 Transportation & Infrastructure Services
Committee
June 8, 2026 Committee of the Whole
June 15, 2026 Regular Meeting
Recommended Motion ❑ Discussion Only ❑x Action Requested
MOVE TO adopt a resolution adopting the Six -Year Transportation
Improvement Program (2027-2032)
Resolution for Six -Year Transportation Improvement Program (2027-
2032)
EXECUTIVE SUMMARY
State law requires cities to approve a resolution adopting the annual update to the Six Year
Transportation Improvement Program (TIP) after holding a public hearing. The proposed Six Year TIP
for 2027-2032 include 22 new projects related to the 2024 Transportation Element, the 2025 Local
Road Safety Plan, and the proposed Transportation Impact Fee updated schedule. Staff is requesting
the Committee forward this item to the June 8, 2026 Committee of the Whole Meeting for a Public
Hearing.
DISCUSSION
The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of
Washington (RCW) 35.77.010. The TIP is adopted by resolution after a public hearing at the local agency level
and incorporated into regional and state TIPs. The TIP is primarily a financial planning document for projects
competing for grants. Any project submitted for federal grant funding must be included in the local, regional,
and state adopted TIPs. The TIP is a rolling plan showing various funding sources: grants, developer, and
local funds. Projects "roll" as funds or stages occur (design report, final design, and construction).
Tukwila's Six Year TIP, the Capital Improvement Program (CIP), the Transportation Element, and the Local
Road Safety Plan list many of the same transportation -related projects. The TIP typically lists only those
transportation -related projects planned within the next six years that are deemed regionally significant or that
have grant funding awarded or expected.
The attached Draft 2027 - 2032 TIP and was created by modifying the 2026 - 2031 TIP to add or remove
projects and adjust project costs. With the current budget cycle beginning and the proposed Transportation
Impact Fee schedule being discussed along the same timeline as the TIP update, the draft TIP also includes
many more new projects than a typical year. The list of projects is presented in alphabetical order. Prioritization
of projects is reflected in the current CIP but new projects added are not prioritized at this point. During the
current budget cycle, Council priorities will be established along with budget projections, which will help identify
the top priority projects to consider over the next 6 years and beyond. The TIP can be modified at any time
throughout the year to rearrange project schedules or the Council can simply wait until next year's annual
update to add, remove, or modify projects based on the final biennial budget adopted this year.
39
One project was removed and 22 new projects were added. The majority of new projects added are
identified as top priority projects in the Transportation Element and the Local Road Safety Plan. All new
projects added to the proposed Transportation Impact Fee schedule are included as they are the majority of
the top priority projects in the Transportation Element. The Draft 2027-2032 TIP summary identifies all the
new projects and where they originate from, as well as the current projects with the page number of the
current CIP.
Deleted
Southcenter Boulevard Road Diet
....................................................................................................................................................................
S 144th Bridge Sidewalks
King County is taking lead and project is
included in their TIP
...........................................................................................................................................................................................................................
Grant was returned, project can be added
back in once funding is identified
ATTACHMENTS (05/28 TIS Committee & 06/08 COW)
• Draft 2027-2032 TIP Summary
• Draft Resolution & 2027-2032 Draft Transportation Improvement Program
• Current Adopted 2025-2030 TIP (begins on page 3)
ATTACHMENTS (06/15 Regular Council)
• Final Resolution for Transportation Improvement Plan
40
Washington.
esol ion No.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2027-
2032), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26, the
City Council of the City of Tukwila has previously adopted a Transportation Improvement
Program and thereafter periodically modified said Transportation Improvement Program
by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six -Year Transportation Improvement Program for the
ensuing six calendar years (2027-2032); and
WHEREAS, on June 8, 2026, a public hearing was held regarding the City's Six -Year
Transportation Improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six -Year Transportation Improvement Program
for the calendar years 2027 to 2032, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the Secretary
of Transportation and the Transportation Improvement Board of the State of Washington
2026 Legislation: 2027-2032 TIP
Version: 04/30/2026
Staff: C. Knighton
Page 1 of 2
41
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Regular Meeting thereof this day of , 2026.
ATTEST/AUTHENTICATED:
Andy Youn-Barnett, CMC, City Clerk Armen Papyan, Council President
APPROVED AS TO FORM BY:
Filed with the City Clerk:
Passed by the City Council:
Resolution Number:
Office of the City Attorney
Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2027 to 2032
2026 Legislation: 2027-2032 TIP
Version: 04/30/2026
Staff: C. Knighton
Page 2 of 2
42
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
/ 1037(004) TUK-62
42nd Ave S Bridge Replacement
42nd Ave S over the Duwamish River
Interurban Ave S to Northern end of bridge
Replace the existing 42nd Ave S steel truss bridge. The replacement will require
preliminary engineer design, and construction phases. The new structure will meet
current road and bridge design standards. The replacement structure configuration
will be two through -lanes, possibly a turn pocket, and include sidewalks.
06/08/26
06/15/26
11
0.100
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
500,000
500,000
S
RW
2027
0
0
100,000
100,000
P
CN
2028
BR
13,000,000
0
0
13,000,000
S
CN
2028
BR
10,599,306
MAW
17,000,000
3,900,000
31,499,306
Totals
23,599,306
17,000,000
4,500,000
45,099,306
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
500,000
0
0
0
0
RW
100,000
0
0
0
0
CN
0
17,500,000
17,500,000
0
0
Totals
600,000
17,500,000
17,500,000
0
0
Report Date: June 01, 2026
Page 1
43
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-15812
42nd Avenue S Bikeway
42nd Avenue S
Southcenter Blvd to S 150th Street
Develop a traffic -calmed bikeway along 42nd Ave S between S 150th St and
Southcenter Blvd. On the west side of the street, add striped southbound bike lane
between Southcenter Blvd and S 150th St. On the east side of the street, add striped
bike lane between Southcenter Blvd and S 151st St. Remove on -street parking to
widen the sidewalk on the east side of the street between S 151 st St and S 150th St,
creating a shared path; add shared lane markings to the roadway
06/08/26
06/15/26
28
C G P S T
W
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
0
0
295,000
295,000
Totals
0
0
295,000
295,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
295,000
0
0
0
0
Totals
295,000
0
0
0
0
Report Date: June 01, 2026
Page 2
44
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA-11113
46th Avenue Safe Routes to School
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
06/08/26
06/15/26
05
C G P S T
W
0.370
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
SRTS
170,000
80,000
250,000
P
RW
2027
0
SRTS
65,000
10,000
75,000
P
CN
2028
0
SRTS
1,660,000
410,000
2,070,000
Totals
0
1,895,000
500,000
2,395,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
250,000
0
0
0
0
RW
75,000
0
0
0
0
CN
0
2,070,000
0
0
0
Totals
325,000
2,070,000
0
0
0
Report Date: June 01, 2026
Page 3
45
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
TUK-71
Airport Way Overlay
Airport Way
S Boeing Access Road to North Tukwila City Limit
Plane, pavement repair, pave; channelization, and repair of curb and gutter,
sidewalk, and guardrail, as necessary.
06/08/26
06/15/26
05
0.380
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
NHFP
564,000
0
10,000
574,000
S
CN
2028
NHFP
3,424,000
0
0
3,424,000
Totals
3,988,000
0
10,000
3,998,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
574,000
0
0
0
0
CN
0
3,424,000
0
0
0
Totals
574,000
3,424,000
0
0
0
Report Date: June 01, 2026
Page 4
46
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA-05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
06/08/26
06/15/26
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
366,000
366,000
Totals
0
0
366,000
366,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
61,000
61,000
61,000
61,000
122,000
Totals
61,000
61,000
61,000
61,000
122,000
Report Date: June 01, 2026
Page 5
47
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA-07746
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
06/08/26
06/15/26
03
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
275,000
275,000
S
RW
2027
0
0
100,000
100,000
P
CN
2028
0
TIB
1,900,000
500,000
2,400,000
Totals
0
1,900,000
875,000
2,775,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
275,000
0
0
0
0
RW
100,000
0
0
0
0
CN
0
2,400,000
0
0
0
Totals
375,000
2,400,000
0
0
0
Report Date: June 01, 2026
Page 6
48
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA-15107
Andover Park East/Industry Dr Intersection
Andover Park E
Industry Drive to
Design and construct traffic signal with Andover Park East left turn lanes and
crosswalks.
06/08/26
06/15/26
03
C G P S T
W
0.100
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
190,000
190,000
S
RW
2027
0
0
75,000
75,000
P
CN
2028
0
0
2,400,000
2,400,000
Totals
0
0
2,665,000
2,665,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
190,000
0
0
0
0
RW
75,000
0
0
0
0
CN
0
2,400,000
0
0
0
Totals
265,000
2,400,000
0
0
0
Report Date: June 01, 2026
Page 7
49
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17047
Andover Park W (Strander to Tukwila Parkway)
Andover Park W
Strander Boulevard to Tukwila Parkway
Construct driveway access improvements, provide bus lanes, install RRFB's, and
improve signal timing
06/08/26
06/15/26
04
0.390
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
923,000
923,000
Totals
0
0
923,000
923,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
923,000
0
Totals
0
0
0
923,000
0
Report Date: June 01, 2026
Page 8
50
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA-03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
06/08/26
06/15/26
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
1,447,000
1,447,000
Totals
0
0
1,447,000
1,447,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
232,000
237,000
242,000
242,000
494,000
Totals
232,000
237,000
242,000
242,000
494,000
Report Date: June 01, 2026
Page 9
51
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA-03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/08/26
06/15/26
06
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
16,790,000
16,790,000
Totals
0
0
16,790,000
16,790,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
2,520,000
2,520,000
2,720,000
2,720,000
6,310,000
Totals
2,520,000
2,520,000
2,720,000
2,720,000
6,310,000
Report Date: June 01, 2026
Page 10
52
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA-15104
Annual Traffic Signal Program
Varies
to
Design and construct traffic signal upgrades and repairs of signals that exceed
routine maintenance work;loop replacement, head replacement, and controllers.
Replace direct bury cable for existing lighting system.
06/08/26
06/15/26
44
P
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
1,060,000
1,060,000
Totals
0
0
1,060,000
1,060,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
160,000
160,000
170,000
190,000
380,000
Totals
160,000
160,000
170,000
190,000
380,000
Report Date: June 01, 2026
Page 11
53
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
/ 1380(005) TUK-68
Boeing Access Road Overlay
Boeing Access Road
East Marginal Way S to Martin Luther King Jr Way S
Grind and overlay roadway, replace concrete overlay of bridge deck over BNSF
railway.
06/08/26
06/15/26
05
0.560
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
NHPP
564,000
0
0
564,000
S
CN
2027
NHPP
3,426,000
0
0
3,426,000
Totals
3,990,000
0
0
3,990,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
100,000
0
0
0
0
CN
3,426,000
0
0
0
0
Totals
3,526,000
0
0
0
0
Report Date: June 01, 2026
Page 12
54
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17026
Buffered Shared Path on 42nd Ave S Section 3
42nd Ave S
S 150th St to S 144th St
Remove parking on one side and widen sidewalk to create shared -use path
06/08/26
06/15/26
28
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
550,000
550,000
Totals
0
0
550,000
550,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
550,000
0
Totals
0
0
0
550,000
0
Report Date: June 01, 2026
Page 13
55
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA-15109
E Marginal Way S (BAR - S 112 St)
E Marginal Way S
Boeing Access Road to S 112th St
Planning phase to determine project parameters. Goal is to design and construct full
street improvements and traffic control. Could include additional lanes and bike lanes
to support the new Sound Transit Link Light Rail infill station.
06/08/26
06/15/26
03
C G O P S
TW
0.270
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PL
2028
0
0
75,000
75,000
Totals
0
0
75,000
75,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
0
75,000
0
0
0
Totals
0
75,000
0
0
0
Report Date: June 01, 2026
Page 14
56
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-17053
E Marginal Way S (N City Limit to S Boeing Access Rd)
Boeing Access Road to Northern City Limit
Widen and extend asphalt paving on E Marginal Way S north of S Boeing Access
Road. Bike facilities may be desired here, pending BAR InfiIl station and area
redevelopment, could connect to bike facilities on Airport Way if Seattle/Tukwila
install, connecting via Norfolk to EMWS If this project moves forward, need to update
bike network.
06/08/26
06/15/26
04
C P S
1.900
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2032
0
0
6,917,000
6,917,000
Totals
0
0
6,917,000
6,917,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
6,917,000
Totals
0
0
0
0
6,917,000
Report Date: June 01, 2026
Page 15
57
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
TUK-70
E Marginal Way S Overlay
E Marginal Way S
Interurban Avenue S to MP 2.27
Plane, pavement repair, pave, channelization, and repair of curb and gutter and
sidewalk, as necessary.
06/08/26
06/15/26
05
0.960
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
NHPP
685,000
0
0
685,000
S
CN
2028
NHPP
5,058,000
0
0
5,058,000
Totals
5,743,000
0
0
5,743,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
685,000
0
0
0
0
CN
0
5,058,000
0
0
0
Totals
685,000
5,058,000
0
0
0
Report Date: June 01, 2026
Page 16
58
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17043
E Marginal Way S Section 2 Sidewalk
E Marginal Way S
Interurban Ave S to S 120th PI
Construct sidewalk on both sides of road segment.
06/08/26
06/15/26
28
0.140
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2031
0
0
803,000
803,000
Totals
0
0
803,000
803,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
803,000
Totals
0
0
0
0
803,000
Report Date: June 01, 2026
Page 17
59
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-17049
Interurban Ave (140th St to S 144th St)
Interurban Ave S
140th St to 144th St
Construct two landscape medians, install RRFB's, and a new pedestrian crossing
06/08/26
06/15/26
28
0.270
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2031
0
0
1,484,000
1,484,000
Totals
0
0
1,484,000
1,484,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
1,484,000
Totals
0
0
0
0
1,484,000
Report Date: June 01, 2026
Page 18
60
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
/ 1391(004) TUK-66
Interurban Avenue S Overlay
Interurban Avenue S
E Marginal Way S to S 143rd Street
Complete pavement repairs, overlay, and curb and gutter repair.
06/08/26
06/15/26
05
2.250
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
NHPP
4,561,000
0
0
4,561,000
Totals
4,561,000
0
0
4,561,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
356,100
0
0
0
0
Totals
356,100
0
0
0
0
Report Date: June 01, 2026
Page 19
61
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17054
Klickitat Dr (53rd Ave S to Southcenter Pkwy)
53rd Ave S to Southcenter Pkwy
Multimodal improvements to improve connectivity and accessibility of existing path
wayfinding, signage, width improvements, etc.
06/08/26
06/15/26
28
0.410
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
582,000
582,000
Totals
0
0
582,000
582,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
582,000
0
0
Totals
0
0
582,000
0
0
Report Date: June 01, 2026
Page 20
62
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA-11110
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
06/08/26
06/15/26
04
0.350
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2027
0
Ped/Bike Program
350,000
50,000
400,000
P
RW
2028
0
Ped/Bike Program
10,000
0
10,000
P
CN
2029
0
Ped/Bike Program
2,800,000
300,000
3,100,000
Totals
0
3,160,000
350,000
3,510,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
300,000
100,000
0
0
0
RW
0
100,000
0
0
0
CN
0
0
3,100,000
0
0
Totals
300,000
200,000
3,100,000
0
0
Report Date: June 01, 2026
Page 21
63
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17028
Macadam Rd S Section 1 Sidewalk
42nd Ave S and Macadam Rd S
S 124th St to S 130th St
Construct sidewalk on west side of
42nd Ave S from S 124th St to entrance
of 42nd Ave S Bridge, construct
sidewalk on both sides of 42nd Ave S
from entrance of 42nd Ave S Bridge to
Interurban Ave S. Construct sidewalk on
both sides of Macadam Rd S from
Interurban Ave S to S 130th St.
06/08/26
06/15/26
28
0.340
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2031
0
0
992,000
992,000
Totals
0
0
992,000
992,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
992,000
Totals
0
0
0
0
992,000
Report Date: June 01, 2026
Page 22
64
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA-17027
Minkler Blvd Section 2 Sidewalk
Minkler Boulevard
Andover Park W to Andover Park E
Construct sidewalk on both sides of
road segment
06/08/26
06/15/26
28
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
1,430,000
1,430,000
Totals
0
0
1,430,000
1,430,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
1,430,000
0
0
Totals
0
0
1,430,000
0
0
Report Date: June 01, 2026
Page 23
65
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
/ 1230(007) TUK-67
Orillia Road South Overlay
Orillia Road S
S 200th Street to S 188th Street/WSDOT ROW
Complete pavement repairs; overlay; and curb and gutter, sidewalk, and guardrail
repair. Make minor improvements to channelization and improve safety near the
188th street intersection.
06/08/26
06/15/26
05
0.640
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
NHPP
1,204,000
0
0
1,204,000
Totals
1,204,000
0
0
1,204,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
1,204,000
0
0
0
0
Totals
1,204,000
0
0
0
0
Report Date: June 01, 2026
Page 24
66
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-17025
S 115th SUE Marginal Way Intersection Improvements
E Marginal Way
300' South of S 115th St to 300' North of S 115th St
Design and construct a new traffic signal, lighting, and pedestrian facilities, including
crosswalks and pedestrian push buttons.
06/08/26
06/15/26
03
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
2,000,000
2,000,000
Totals
0
0
2,000,000
2,000,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
2,000,000
0
0
Totals
0
0
2,000,000
0
0
Report Date: June 01, 2026
Page 25
67
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA13494
S 119th St Pedestrian Bridge Painting
S 119th Street Bridge
West bank Duwamish River to East bank Duwamish River
Ongoing maintenance of the S 119th Street Pedestrian Bridge in the
Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance
needed.
06/08/26
06/15/26
2117
06
0.040
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
0
0
200,000
200,000
Totals
0
0
200,000
200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
200,000
0
0
0
0
Totals
200,000
0
0
0
0
Report Date: June 01, 2026
Page 26
68
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-16476
S 124th St/50th PI S Reconfiguration
S 124th Street
49th Ave S to 51st PI S
Reconfigure intersection to remove EB slip lane, new c/g/s on S 124th from 49th to
51 st, new paved shoulder walkway on south side of 124th connecting to existing
walkway on west side of 50th Pk, new stormwater treatment/rain garden in old slip
lane ROW.
06/08/26
06/15/26
21
0.140
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
TIB
101,000
29,000
130,000
S
CN
2028
0
TIB
796,300
225,200
1,021,500
Totals
0
897,300
254,200
1,151,500
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
50,000
0
0
0
0
CN
0
1,021,500
0
0
0
Totals
50,000
1,021,500
0
0
0
Report Date: June 01, 2026
Page 27
69
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-15108
S 133 St/SR599 Southbound Intersection
S 133rd Street
SR 599 SB Ramp to
Design and construct intersection improvements, which could include a new traffic
signal or a roundabout,
lighting, pedestrian facilities, and drainage.
06/08/26
06/15/26
03
C G O P S
TW
0.100
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2028
0
0
400,000
400,000
P
RW
2028
0
0
150,000
150,000
P
CN
2029
0
TIB
1,620,000
1,080,000
2,700,000
Totals
0
1,620,000
1,630,000
3,250,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
400,000
0
0
0
RW
0
150,000
0
0
0
CN
0
0
2,700,000
0
0
Totals
0
550,000
2,700,000
0
0
Report Date: June 01, 2026
Page 28
70
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
07
WA-17045
S 141 st St Section 1 Sidewalk
S 141st
37th Ave S to Tukwila International Boulevard
Construct sidewalk on both sides of
road segment
06/08/26
06/15/26
28
0.120
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2029
0
0
510,000
510,000
Totals
0
0
510,000
510,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
510,000
0
0
Totals
0
0
510,000
0
0
Report Date: June 01, 2026
Page 29
71
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
07
WA-17044
S 142nd St Sidewalk
S 142nd St
37th Ave S to Tukwila International Boulevard
Construct sidewalk on both sides of
road segment
06/08/26
06/15/26
28
0.130
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
541,000
541,000
Totals
0
0
541,000
541,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
541,000
0
0
Totals
0
0
541,000
0
0
Report Date: June 01, 2026
Page 30
72
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17041
S 144th St Complete Street
42nd Ave S to 51 st Ave S
Restripe and remove parking on one side to accommodate 2-10ft lanes, 1-2ft buffer,
and 1-10ft two-way cycle track. Construct sidewalk facilities on the south side of the
street.
04
C G P S T
W
0.500
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
869,000
869,000
Totals
0
0
869,000
869,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
869,000
0
Totals
0
0
0
869,000
0
Report Date: June 01, 2026
Page 31
73
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17046
S 144th St Improvements (Military to TIB)
S 144th St
Military Rd S to Tukwila International Boulevard
Construct sidewalk improvments, curb and gutter, install RRFB's, and a pedestrian
refuge island
06/08/26
06/15/26
28
0.310
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2028
0
0
580,000
580,000
Totals
0
0
580,000
580,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
580,000
0
0
0
Totals
0
580,000
0
0
0
Report Date: June 01, 2026
Page 32
74
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA-11112
S 152nd Street Pedestrian and Bike Improvements
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Install curb, gutter, sidewalks on S 152nd Street, including widening pavement and
construction of a buffer between the roadway and sidewalk on the south side.
06/08/26
06/15/26
05
C G O P S
TW
0.300
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
300,000
300,000
S
RW
2027
0
0
230,000
230,000
P
CN
2028
0
TIB
3,960,000
990,000
4,950,000
Totals
0
3,960,000
1,520,000
5,480,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
300,000
0
0
0
0
RW
230,000
0
0
0
0
CN
0
4,950,000
0
0
0
Totals
530,000
4,950,000
0
0
0
Report Date: June 01, 2026
Page 33
75
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA-17048
S 180th St (Sperry Drive to Interurban Trail)
S 180th St
Sperry Drive to Interurban Trail
Construct shared use path on the north side and stall no turn on red phasing at
180th and Sperry Dr.
06/08/26
06/15/26
28
0.280
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
806,000
806,000
Totals
0
0
806,000
806,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
806,000
0
Totals
0
0
0
806,000
0
Report Date: June 01, 2026
Page 34
76
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17021
S Norfolk St Bike Facilities
S Norfolk Street
E Marginal Way S to East city limit
Add bike facilities on S Norfolk St
06/08/26
06/15/26
28
P S T W
0.140
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
497,000
497,000
Totals
0
0
497,000
497,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
497,000
0
0
Totals
0
0
497,000
0
0
Report Date: June 01, 2026
Page 35
77
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA-15829
S Ryan Way
SR 900 to 51 st Ave S
Resurface and rechannel S Ryan Way to improve failing pavement and improve
safety. Add pedestrian and bicycle facilities where appropriate. Signalize intersection
with 47th Avenue S to accommodate future growth and improve safety.
06/08/26
06/15/26
06
C G P S T
W
0.500
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
1,275,000
1,275,000
P
RW
2028
0
TIB
200,000
100,000
300,000
P
CN
2028
0
TIB
8,650,000
4,131,000
12,781,000
Totals
0
8,850,000
5,506,000
14,356,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
1,275,000
0
0
0
0
RW
0
300,000
0
0
0
CN
0
12,760,000
0
0
0
Totals
1,275,000
13,060,000
0
0
0
Report Date: June 01, 2026
Page 36
78
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA-15813
Southcenter Blvd Bikeway and Pedestrian Crossing Upgrades
Southcenter Boulevard
International Boulevard to 42nd Avenue S
Improve the existing bike lanes and crosswalks on Southcenter Blvd within a half -
mile of Tukwila International Boulevard Station (TIBS). Re-channelize to 11 ft
general purpose lanes to accommodate separated bike lanes. Tighten intersection
with 40th Ave S to shorten crossing distance. Add bike channelization and upgrade
to high -visibility crosswalk markings at Southcenter Blvd/TIBS station entrance and
Southcenter Blvd/42nd Ave S intersections.
06/08/26
06/15/26
28
C G P S T
W
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
0
0
325,000
325,000
Totals
0
0
325,000
325,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
325,000
0
0
0
0
Totals
325,000
0
0
0
0
Report Date: June 01, 2026
Page 37
79
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-17128
Southcenter Blvd Road Diet (with Lake to Sound Regional Trail)
Southcenter Boulevard
S 66th Ave to 53rd Ave S
As part of the King County led Lake to Sound Regional Trail F1 Phase, narrow
Southcenter Blvd from 5 lanes to 3 lanes between approx. 62nd Ave S and 66th Ave
S. Reconfigure signal operations at 66th Ave S to include dual WB left turn lanes and
a single WB thru lane. All lanes will generally shift to the south of the existing ROW
to allow for construction of the Lake to Sound trail and trail buffering.
06/08/26
06/15/26
21
DCE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
135,000
135,000
P
CN
2029
0
TIB
2,400,000
600,000
3,000,000
Totals
0
2,400,000
735,000
3,135,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
135,000
0
0
0
0
CN
0
0
3,000,000
0
0
Totals
135,000
0
3,000,000
0
0
Report Date: June 01, 2026
Page 38
80
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
05
WA-17022
SR 518 EB Off-ramp/Klickitat Dr Intersection Improvements
Klickitat Drive
51 st Ave S to Klickitat Drive
Design and construct a new traffic signal, lighting, and pedestrian facilities including
crosswalks and pedestrian push buttons.
06/08/26
06/15/26
03
P S W
0.020
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
850,000
850,000
Totals
0
0
850,000
850,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
850,000
0
Totals
0
0
0
850,000
0
Report Date: June 01, 2026
Page 39
81
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
04
WA-17029
Strander Blvd Sidewalk
Strander Blvd and SW 27th St
Christensen Rd to Interurban Trail
Construct sidewalk on south side of
Strander Blvd from Christensen Rd to W
Valley Hwy. Construct sidewalk on both
sides of Strander Blvd from W Valley
Hwy to east boundary of Tukwila city
limits
06/08/26
06/15/26
28
0.200
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
467,000
467,000
Totals
0
0
467,000
467,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
467,000
0
0
Totals
0
0
467,000
0
0
Report Date: June 01, 2026
Page 40
82
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-17039
TIB Section 2 Sidewalk (North)
Tukwila International Blvd
S 112th Ave to SR99
Construct sidewalk on east side of Tukwila International Blvd from S 112th St to the
HW 99 Exit Ramp.
28
C G P S T
W
0.260
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
377,200
377,200
Totals
0
0
377,200
377,200
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
377,200
0
0
Totals
0
0
377,200
0
0
Report Date: June 01, 2026
Page 41
83
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-17040
TIB Section 2 Sidewalk (South)
SR 99 to 12400 Block
Construct sidewalk on both sides of Tukwila International Blvd from the HW 99 Exit
Ramp to 12400 Block.
28
C G P S T
W
0.440
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
1,672,800
1,672,800
Totals
0
0
1,672,800
1,672,800
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
1,672,800
0
0
Totals
0
0
1,672,800
0
0
Report Date: June 01, 2026
Page 42
84
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA-13491
Transportation Demand Management Implementation
to
Provision of TDM services to Commute Trip Reduction -affected employment sites.
Facilitate employer reporting and records associated with biennial CTR survey.
Engage CTR employment sites with opportunities for improvement and remain
connected via technical meetings with other CTR jurisdictional representatives.
06/08/26
06/15/26
44
0.000
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
WSDOT
103,200
0
103,200
P
ALL
2028
0
WSDOT
258,000
0
258,000
Totals
0
361,200
0
361,200
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
51,600
51,600
51,600
51,600
103,200
Totals
51,600
51,600
51,600
51,600
103,200
Report Date: June 01, 2026
Page 43
85
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA-17063
Tukwila and South King County TDM
to
Provide TDM services to help people use sustainable transportation options that
increase access to opportunity, and reduce drive -alone travel and traffic congestion
in Tukwila and South King County.
06/08/26
06/15/26
18
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2027
0
OTHER
832,000
208,000
1,040,000
Totals
0
832,000
208,000
1,040,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
260,000
260,000
130,000
0
0
Totals
260,000
260,000
130,000
0
0
Report Date: June 01, 2026
Page 44
86
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
TUK-69
Tukwila and South King County TDM
Tukwila and South King County
N/A to N/A
This project will provide TDM programming and services to help people access
sustainable transportation options that reduce drive -alone travel and traffic
congestion in Tukwila and South King County. Tukwila's TDM Program reaches
people regionally at employment centers, community hubs, multifamily housing
complexes, and educational institutions.
06/08/26
06/15/26
24
0.000
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2027
CMAQ
550,000
WSDOT
85,838
0
635,838
Totals
550,000
85,838
0
635,838
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
158,959
158,959
158,960
158,960
0
Totals
158,959
158,959
158,960
158,960
0
Report Date: June 01, 2026
Page 45
87
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2027 to 2032
N Outside
Functional
Class
Priority Number
A. PIN/Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
Hearing
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
03
WA-17042
Tukwila International Boulevard (S 152nd St to S 144th St)
S 152nd St to S 144th St
Construct landscape median, refine corridor access, roadway diet, and multimodal
lanes.
04
C P S W
0.530
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
4,347,000
4,347,000
Totals
0
0
4,347,000
4,347,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
4,347,000
0
Totals
0
0
0
4,347,000
0
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
43,635,306
42,961,338
66,509,200
153,105,844
Report Date: June 01, 2026
Page 46
88