HomeMy WebLinkAboutRes 2148 - 2027-2032 Transportation Improvement ProgramCity of Tukwila
Washington
Resolution No. 2148
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2027-
2032), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26, the
City Council of the City of Tukwila has previously adopted a Transportation Improvement
Program and thereafter periodically modified said Transportation Improvement Program
by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six -Year Transportation Improvement Program for the
ensuing six calendar years (2027-2032); and
WHEREAS, on June 8, 2026, a public hearing was held regarding the City's Six -Year
Transportation Improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six -Year Transportation Improvement Program for
the calendar years 2027 to 2032, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the Secretary
of Transportation and the Transportation Improvement Board of the State of Washington.
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Regular Meeting thereof this 15th day of June, 2026.
ATTEST/AUTHENTICATED:
kA
i nd o -Barnett, CIVIC, City Clerk
A O D AS TO FORM BY:
Office of the City Attorney
Arme Papyan, Council President
Filed with the City Clerk: _
Passed by the City Council
Resolution Number:
06/09/2026
06/15/2026
2148
Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2027 to 2032
2026 Legislation: 2027-2032 TIP
Version: 04/30/2026
Staff: C. Knighton
Page 2 of 2
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
/ 1037(004) TUK-62
06/08/26
06/15/26
2148
11
0.100
DCE
Yes
42nd Ave S Bridge Replacement
42nd Ave S over the Duwamish River
Interurban Ave S to Northern end of bridge
Replace the existing 42nd Ave S steel truss bridge. The replacement will require
preliminary engineer design, and construction phases. The new structure will meet
current road and bridge design standards. The replacement structure configuration
will be two through -lanes, possibly a turn pocket, and include sidewalks.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
500,000
500,000
S
RW
2027
0
0
100,000
100,000
P
CN
2028
BR
13,000,000
0
0
13,000,000
S
CN
2028
BR
10,599,306
MAW
17,000,000
3,900,000
31,499,306
Totalsl
23,599,3061
17,000,000
4,500,0001
45,099,306
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
500,000
0
0
0
0
RW
100,000
0
0
0
0
CN
0
17,500,000
17,500,000
0
0
Totals
600,000
17,500,000
17,500,000
0
0
Resolution 2148 Attachment A Page 1
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-15812
06/08/26
06/15/26
2148
28
C G P S T
No
W
42nd Avenue S Bikeway
42nd Avenue S
Southcenter Blvd to S 150th Street
Develop a traffic -calmed bikeway along 42nd Ave S between S 150th St and
Southcenter Blvd. On the west side of the street, add striped southbound bike lane
between Southcenter Blvd and S 150th St. On the east side of the street, add striped
bike lane between Southcenter Blvd and S 151st St. Remove on -street parking to
widen the sidewalk on the east side of the street between S 151st St and S 150th St,
creating a shared path; add shared lane markings to the roadway
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
0
0
295,000
295,000
Totals
0
0
295,000
295,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
295,000
0
0
0
0
Totals
295,000
0
0
0
0
Resolution 2148 Attachment A Page 2
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
19
WA-11113
06/08/26
06/15/26
2148
05
C G P S T
0.370
Yes
W
46th Avenue Safe Routes to School
46th Avenue S
S 150th Street to S 144th Street
Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S,
including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised
crosswalk across S 144th Street with RRFB.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
SRTS
170,000
80,000
250,000
P
RW
2027
0
SRTS
65,000
10,000
75,000
P
CN
2028
0
SRTS
1,660,000
410,000
2,070,000
Totals
0
1,895,000
500,000
2,395,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
250,000
0
0
0
0
RW
75,000
0
0
0
0
CN
0
2,070,000
0
0
0
Totals
325,000
2,070,000
0
0
0
Resolution 2148 Attachment A Page 3
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
TUK-71
06/08/26
06/15/26
2148
05
0.380
CE
No
Airport Way Overlay
Airport Way
S Boeing Access Road to North Tukwila City Limit
Plane, pavement repair, pave; channelization, and repair of curb and gutter,
sidewalk, and guardrail, as necessary.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
NHFP
564,000
0
10,000
574,000
S
CN
2028
NHFP
3,424,000
0
0
3,424,000
Totals
3,988,000
0
10,000
3,998,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
574,000
0
0
0
0
CN
0
3,424,000
0
0
0
Totals
574,000
3,424,000
0
0
0
Resolution 2148 Attachment A Page 4
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
00
WA-05405
06/08/26
06/15/26
2148
06
No
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
366,000
366,000
Totals
0
0
366,000
366,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
61,000
61,000
61,000
61,000
122,000
Totals
61,000
61,000
61,000
61,000
122,000
Resolution 2148 Attachment A Page 5
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
16
WA-07746
06/08/26
06/15/26
2148
03
C G O P S
No
TW
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
275,000
275,000
S
RW
2027
0
0
100,000
100,000
P
CN
2028
0
TIB
1,900,000
500,000
2,400,000
Totals
0
1,900,000
875,000
2,775,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
275,000
0
0
0
0
RW
100,000
0
0
0
0
CN
0
2,400,000
0
0
0
Totals
375,000
2,400,000
0
0
0
Resolution 2148 Attachment A Page 6
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
04
WA-15107
06/08/26
06/15/26
2148
03
C G P S T
0.100
Yes
W
Andover Park East/industry Dr Intersection
Andover Park E
Industry Drive to
Design and construct traffic signal with Andover Park East left turn lanes and
crosswalks.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
190,000
190,000
S
RW
2027
0
0
75,000
75,000
P
CN
2028
0
0
2,400,000
2,400,000
Totals
0
0
2,665,000
2,665,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
190,000
0
0
0
0
RW
75,000
0
0
0
0
CN
0
2,400,000
0
0
0
Totals
265,000
2,400,000
0
0
0
Resolution 2148 Attachment A Page 7
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17047
06/08/26
06/15/26
2148
04
0.390
No
Andover Park W (Strander to Tukwila Parkway)
Andover Park W
Strander Boulevard to Tukwila Parkway
Construct driveway access improvements, provide bus lanes, install RRFB's, and
improve signal timing
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
923,000
923,000
Totals
0
0
923,000
923,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
923,000
0
Totals
0
0
0
923,000
0
Resolution 2148 Attachment A Page 8
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
3
i
0
o
�
'
i
n
c
m o
'm_
E. Begin & End Termini
c
1<
a
N
F. Project Description G. Structure ID
to
a
m
N
s
m
a
14
WA-03731
06/08/26
06/15/26
2148
06
No
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
1,447,000
1,447,000
Totals
0
0
1,447,000
1,447,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
232,000
237,000
242,000
242,000
494,000
Totals
232,000
237,000
242,000
242,000
494,000
Resolution 2148 Attachment A Page 9
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
16
WA-03733
06/08/26
06/15/26
2148
06
C G O P S
No
TW
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
16,790,000
16,790,000
Totals
0
0
16,790,000
16,790,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
2,520,000
2,520,000
2,720,000
2,720,000
6,310,000
Totals
2,520,000
2,520,000
2,720,000
2,720,000
6,310,000
Resolution 2148 Attachment A Page 10
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
00
WA-15104
06/08/26
06/15/26
2148
44
P
No
Annual Traffic Signal Program
Varies
to
Design and construct traffic signal upgrades and repairs of signals that exceed
routine maintenance work;loop replacement, head replacement, and controllers.
Replace direct bury cable for existing lighting system.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
0
1,060,000
1,060,000
Totals
0
0
1,060,000
1,060,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
160,000
160,000
170,000
190,000
380,000
Totals
160,000
160,000
170,000
190,000
380,000
Resolution 2148 Attachment A Page 11
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
/ 1380(005) TUK-68
06/08/26
06/15/26
2148
05
0.560
CE
No
Boeing Access Road Overlay
Boeing Access Road
East Marginal Way S to Martin Luther King Jr Way S
Grind and overlay roadway, replace concrete overlay of bridge deck over BNSF
railway.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
NHPP
564,000
0
0
564,000
S
CN
2027
NHPP
3,426,000
0
0
3,426,000
Totals
3,990,000
0
0
3,990,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
100,000
0
0
0
0
CN
3,426,000
0
0
0
0
Totals
3,526,000
0
0
0
0
Resolution 2148 Attachment A Page 12
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17026
06/08/26
06/15/26
2148
28
No
Buffered Shared Path on 42nd Ave S Section 3
42nd Ave S
S 150th St to S 144th St
Remove parking on one side and widen sidewalk to create shared -use path
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
550,000
550,000
Totals
0
0
550,000
550,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
550,000
0
Totals
0
0
0
550,000
0
Resolution 2148 Attachment A Page 13
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
04
WA-15109
06/08/26
06/15/26
2148
03
C G O P S
0.270
Yes
TW
E Marginal Way S (BAR - S 112 St)
E Marginal Way S
Boeing Access Road to S 112th St
Planning phase to determine project parameters. Goal is to design and construct full
street improvements and traffic control. Could include additional lanes and bike lanes
to support the new Sound Transit Link Light Rail infill station.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PL
2028
0
0
75,000
75,000
Totals
0
0
75,000
75,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
0
75,000
0
0
0
Totals
0
75,000
0
0
0
Resolution 2148 Attachment A Page 14
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-17053
06/08/26
06/15/26
2148
04
CPS
1.900
CE
No
E Marginal Way S (N City Limit to S Boeing Access Rd)
Boeing Access Road to Northern City Limit
Widen and extend asphalt paving on E Marginal Way S north of S Boeing Access
Road. Bike facilities may be desired here, pending BAR Infill station and area
redevelopment, could connect to bike facilities on Airport Way if Seattle/Tukwila
install, connecting via Norfolk to EMWS If this project moves forward, need to update
bike network.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2032
0
0
6,917,000
6,917,000
Totals
0
0
6,917,000
6,917,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
6,917,000
Totals
0
0
0
0
6,917,000
Resolution 2148 Attachment A Page 15
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
TUK-70
06/08/26
06/15/26
2148
05
0.960
CE
No
E Marginal Way S Overlay
E Marginal Way S
Interurban Avenue S to MP 2.27
Plane, pavement repair, pave, channelization, and repair of curb and gutter and
sidewalk, as necessary.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
NHPP
685,000
0
0
685,000
S
CN
2028
NHPP
5,058,000
0
0
5,058,000
Totals
5,743,000
0
0
5,743,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
685,000
0
0
0
0
CN
0
5,058,000
0
0
0
Totals
685,000
5,058,000
0
0
0
Resolution 2148 Attachment A Page 16
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17043
06/08/26
06/15/26
2148
28
0.140
No
E Marginal Way S Section 2 Sidewalk
E Marginal Way S
Interurban Ave S to S 120th PI
Construct sidewalk on both sides of road segment.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2031
0
0
803,000
803,000
Totals
0
0
803,000
803,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
803,000
Totals
0
0
0
0
803,000
Resolution 2148 Attachment A Page 17
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-17049
06/08/26
06/15/26
2148
28
0.270
No
Interurban Ave (140th St to S 144th St)
Interurban Ave S
140th St to 144th St
Construct two landscape medians, install RRFB's, and a new pedestrian crossing
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2031
0
0
1,484,000
1,484,000
Totals
0
0
1,484,000
1,484,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
1,484,000
Tota Is
0
0
0
0
1,484,000
Resolution 2148 Attachment A Page 18
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
/ 1391(004) TUK-66
06/08/26
06/15/26
2148
05
2.250
CE
No
Interurban Avenue S Overlay
Interurban Avenue S
E Marginal Way S to S 143rd Street
Complete pavement repairs, overlay, and curb and gutter repair.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
NHPP
4,561,000
0
0
4,561,000
Totals
4,561,000
0
0
4,561,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
356,100
0
0
0
0
Totals
356,100
0
0
0
0
Resolution 2148 Attachment A Page 19
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
05
WA-17054
06/08/26
06/15/26
2148
28
0.410
CE
No
Klickitat Dr (53rd Ave S to Southcenter Pkwy)
53rd Ave S to Southcenter Pkwy
Multimodal improvements to improve connectivity and accessibility of existing path
wayfinding, signage, width improvements, etc.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
582,000
582,000
Totals
0
0
582,000
582,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
582,000
0
0
Totals
0
0
582,000
0
0
Resolution 2148 Attachment A Page 20
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
17
WA-11110
06/08/26
06/15/26
2148
04
0.350
CE
No
Macadam Rd S Complete Streets Project
Macadam Road
S 150th Street to S 144th Street
Design and construction of a complete street on Macadam Road. Road widening
and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of
the roadway. Includes illumination, curb, and storm drainage.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2027
0
Ped/Bike Program
350,000
50,000
400,000
P
RW
2028
0
Ped/Bike Program
10,000
0
10,000
P
CN
2029
0
Ped/Bike Program
2,800,000
300,000
3,100,000
Totals
0
3,160,000
350,000
3,510,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
300,000
100,000
0
0
0
RW
0
100,000
0
0
0
CN
0
0
3,100,000
0
0
Totals
300,000
200,000
3,100,000
0
0
Resolution 2148 Attachment A Page 21
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17028
06/08/26
06/15/26
2148
28
0.340
No
Macadam Rd S Section 1 Sidewalk
42nd Ave S and Macadam Rd S
S 124th St to S 130th St
Construct sidewalk on west side of
42nd Ave S from S 124th St to entrance
of 42nd Ave S Bridge, construct
sidewalk on both sides of 42nd Ave S
from entrance of 42nd Ave S Bridge to
Interurban Ave S. Construct sidewalk on
both sides of Macadam Rd S from
Interurban Ave S to S 130th St.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2031
0
0
992,000
992,000
Totals
0
0
992,000
992,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
992,000
Totals
0
0
0
0
992,000
Resolution 2148 Attachment A Page 22
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
04
WA-17027
06/08/26
06/15/26
2148
28
No
Minkler Blvd Section 2 Sidewalk
Minkler Boulevard
Andover Park W to Andover Park E
Construct sidewalk on both sides of
road segment
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
1,430,000
1,430,000
Totals
0
0
1,430,000
1,430,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
1,430,000
0
0
Tota Is
0
0
1,430,000
0
0
Resolution 2148 Attachment A Page 23
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
/ 1230(007) TUK-67
06/08/26
06/15/26
2148
05
0.640
CE
No
Orillia Road South Overlay
Orillia Road S
S 200th Street to S 188th Street/WSDOT ROW
Complete pavement repairs; overlay; and curb and gutter, sidewalk, and guardrail
repair. Make minor improvements to channelization and improve safety near the
188th street intersection.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
NHPP
1,204,000
0
0
1,204,000
Totals
1,204,000
0
0
1,204,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
1,204,000
0
0
0
0
Totals
1,204,000
0
0
0
0
Resolution 2148 Attachment A Page 24
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-17025
06/08/26
06/15/26
2148
03
0.000
No
S 115th SUE Marginal Way Intersection Improvements
E Marginal Way
300' South of S 115th St to 300' North of S 115th St
Design and construct a new traffic signal, lighting, and pedestrian facilities, including
crosswalks and pedestrian push buttons.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
2,000,000
2,000,000
Totals
0
0
2,000,000
2,000,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
2,000,000
0
0
Totals
0
0
2,000,000
0
0
Resolution 2148 Attachment A Page 25
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
00
WA13494
06/08/26
06/15/26
2148
06
0.040
No
S 119th St Pedestrian Bridge Painting
S 119th Street Bridge
West bank Duwamish River to East bank Duwamish River
Ongoing maintenance of the S 119th Street Pedestrian Bridge in the
Allentown/Duwamish neighborhoods. Painting of bridge is outstanding maintenance
needed.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
0
0
200,000
200,000
Totals
0
0
200,000
200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
200,000
0
0
0
0
Totals
200,000
0
0
0
0
Resolution 2148 Attachment A Page 26
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-16476
06/08/26
06/15/26
2148
21
0.140
No
S 124th St/50th PI S Reconfiguration
S 124th Street
49th Ave S to 51 st PI S
Reconfigure intersection to remove EB slip lane, new c/g/s on S 124th from 49th to
51st, new paved shoulder walkway on south side of 124th connecting to existing
walkway on west side of 50th Pk, new stormwater treatment/rain garden in old slip
Zane ROW.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
TIB
101,000
29,000
130,000
S
CN
2028
0
TIB
796,300
225,200
1,021,500
Totals
0
897,300
254,200
1,151,500
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
50,000
0
0
0
0
CN
0
1,021,500
0
0
0
Totals
50,000
1,021,500
0
0
0
Resolution 2148 Attachment A Page 27
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-15108
06/08/26
06/15/26
2148
03
C G O P S
0.100
Yes
TW
S 133 St/SR599 Southbound Intersection
S 133rd Street
SR 599 SB Ramp to
Design and construct intersection improvements, which could include a new traffic
signal or a roundabout,
lighting, pedestrian facilities, and drainage.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2028
0
0
400,000
400,000
P
RW
2028
0
0
150,000
150,000
P
CN
2029
0
TIB
1,620,000
1,080,000
2,700,000
Totals
0
1,620,000
1,630,000
3,250,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
400,000
0
0
0
RW
0
150,000
0
0
0
CN
0
0
2,700,000
0
0
Totals
0
550,000
2,700,000
0
0
Resolution 2148 Attachment A Page 28
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
07
WA-17045
06/08/26
06/15/26
2148
28
0.120
No
S 141st St Section 1 Sidewalk
S 141st
37th Ave S to Tukwila International Boulevard
Construct sidewalk on both sides of
road segment
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2029
0
0
510,000
510,000
Totals
0
0
510,000
510,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
510,000
0
0
Totals
0
0
510,000
0
0
Resolution 2148 Attachment A Page 29
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
07
WA-17044
06/08/26
06/15/26
2148
28
0.130
No
S 142nd St Sidewalk
S 142nd St
37th Ave S to Tukwila International Boulevard
Construct sidewalk on both sides of
road segment
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
541,000
541,000
Totals
0
0
541,000
541,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
541,000
0
0
Totals
0
0
541,000
0
0
Resolution 2148 Attachment A Page 30
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17041
06/08/26
06/15/26
2148
04
C G P S T
0.500
CE
No
W
S 144th St Complete Street
42nd Ave S to 51 st Ave S
Restripe and remove parking on one side to accommodate 2-1 Oft lanes, 1-2ft buffer,
and 1-10ft two-way cycle track. Construct sidewalk facilities on the south side of the
street.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
869,000
869,000
Totals
0
0
869,000
869,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
869,000
0
Totals
0
0
0
869,000
0
Resolution 2148 Attachment A Page 31
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17046
06/08/26
06/15/26
2148
28
0.310
No
S 144th St Improvements (Military to TIB)
S 144th St
Military Rd S to Tukwila International Boulevard
Construct sidewalk improvments, curb and gutter, install RRFB's, and a pedestrian
refuge island
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2028
0
0
580,000
580,000
Totals
0
0
580,000
580,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
580,000
0
0
0
Totals
0
580,000
0
0
0
Resolution 2148 Attachment A Page 32
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
19
WA-11112
06/08/26
06/15/26
2148
05
C G O P S
0.300
CE
Yes
TW
S 152nd Street Pedestrian and Bike Improvements
S 152nd Street
Tukwila International Blvd to 42nd Avenue S
Install curb, gutter, sidewalks on S 152nd Street, including widening pavement and
construction of a buffer between the roadway and sidewalk on the south side.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
300,000
300,000
S
RW
2027
0
0
230,000
230,000
P
CN
2028
0
TIB
3,960,000
990,000
4,950,000
Totals
0
3,960,000
1,520,000
5,480,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
300,000
0
0
0
0
RW
230,000
0
0
0
0
CN
0
4,950,000
0
0
0
Totals
530,000
4,950,000
0
0
0
Resolution 2148 Attachment A Page 33
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
04
WA-17048
06/08/26
06/15/26
2148
28
0.280
No
S 180th St (Sperry Drive to Interurban Trail)
S 180th St
Sperry Drive to Interurban Trail
Construct shared use path on the north side and stall no turn on red phasing at
180th and Sperry Dr.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
806,000
806,000
Totals
0
0
806,000
806,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
806,000
0
Totals
0
0
0
806,000
0
Resolution 2148 Attachment A Page 34
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17021
06/08/26
06/15/26
2148
28
P S T W
0.140
CE
No
S Norfolk St Bike Facilities
S Norfolk Street
E Marginal Way S to East city limit
Add bike facilities on S Norfolk St
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
497,000
497,000
Totals
0
0
497,000
497,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
497,000
0
0
Totals
0
0
497,000
0
0
Resolution 2148 Attachment A Page 35
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
04
WA-15829
06/08/26
06/15/26
2148
06
C G P S T
0.500
No
W
S Ryan Way
SR 900 to 51 st Ave S
Resurface and rechannel S Ryan Way to improve failing pavement and improve
safety. Add pedestrian and bicycle facilities where appropriate. Signalize intersection
with 47th Avenue S to accommodate future growth and improve safety.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
1,275,000
1,275,000
P
RW
2028
0
TIB
200,000
100,000
300,000
P
CN
2028
0
TIB
8,650,000
4,131,000
12,781,000
Totals
0
8,850,000
5,506,000
14,356,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
1,275,000
0
0
0
0
RW
0
300,000
0
0
0
CN
0
12,760,000
0
0
0
Totals
1,275,000
13,060,000
0
0
0
Resolution 2148 Attachment A Page 36
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
04
WA-15813
06/08/26
06/15/26
2148
28
C G P S T
No
W
Southcenter Blvd Bikeway and Pedestrian Crossing Upgrades
Southcenter Boulevard
International Boulevard to 42nd Avenue S
Improve the existing bike lanes and crosswalks on Southcenter Blvd within a half -
mile of Tukwila International Boulevard Station (TIBS). Re-channelize to 11 ft
general purpose lanes to accommodate separated bike lanes. Tighten intersection
with 40th Ave S to shorten crossing distance. Add bike channelization and upgrade
to high -visibility crosswalk markings at Southcenter Blvd/TIBS station entrance and
Southcenter Blvd/42nd Ave S intersections.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2027
0
0
325,000
325,000
Totals
0
0
325,000
325,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
325,000
0
0
0
0
Totals
325,000
0
0
0
0
Resolution 2148 Attachment A Page 37
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-17128
06/08/26
06/15/26
2148
21
DCE
No
Southcenter Blvd Road Diet (with Lake to Sound Regional Trail)
Southcenter Boulevard
S 66th Ave to 53rd Ave S
As part of the King County led Lake to Sound Regional Trail F1 Phase, narrow
Southcenter Blvd from 5 lanes to 3 lanes between approx. 62nd Ave S and 66th Ave
S. Reconfigure signal operations at 66th Ave S to include dual WB left turn lanes and
a single WB thru lane. All lanes will generally shift to the south of the existing ROW
to allow for construction of the Lake to Sound trail and trail buffering.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2027
0
0
135,000
135,000
P
CN
2029
0
TIB
2,400,000
600,000
3,000,000
Totals
0
2,400,000
735,000
3,135,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
135,000
0
0
0
0
CN
0
0
3,000,000
0
0
Totals
135,000
0
3,000,000
0
0
Resolution 2148 Attachment A Page 38
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
D. Road Name or Number
c
a
3
0
�
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
O5
WA-17022
06/08/26
06/15/26
2148
03
P S W
0.020
CE
No
SR 518 EB Off-ramp/Klickitat Dr Intersection Improvements
Klickitat Drive
51st Ave S to Klickitat Drive
Design and construct a new traffic signal, lighting, and pedestrian facilities including
crosswalks and pedestrian push buttons.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
850,000
850,000
Totals
0
0
850,000
850,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
850,000
0
Totals
0
0
0
850,000
0
Resolution 2148 Attachment A Page 39
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
04
WA-17029
06/08/26
06/15/26
2148
28
0.200
No
Strander Blvd Sidewalk
Strander Blvd and SW 27th St
Christensen Rd to Interurban Trail
Construct sidewalk on south side of
Strander Blvd from Christensen Rd to W
Valley Hwy. Construct sidewalk on both
sides of Strander Blvd from W Valley
Hwy to east boundary of Tukwila city
limits
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
467,000
467,000
Totals
0
0
467,000
467,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
467,000
0
0
Totals
0
0
467,000
0
0
Resolution 2148 Attachment A Page 40
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-17039
06/08/26
06/15/26
2148
28
C G P S T
0.260
CE
No
W
TIB Section 2 Sidewalk (North)
Tukwila International Blvd
S 112th Ave to SR99
Construct sidewalk on east side of Tukwila International Blvd from S 112th St to the
HW 99 Exit Ramp.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
377,200
377,200
Totals
0
0
377,200
377,200
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
377,200
0
0
Totals
0
0
377,200
0
0
Resolution 2148 Attachment A Page 41
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-17040
06/08/26
06/15/26
2148
28
C G P S T
0.440
CE
No
W
TIB Section 2 Sidewalk (South)
SR 99 to 12400 Block
Construct sidewalk on both sides of Tukwila International Blvd from the HW 99 Exit
Ramp to 12400 Block.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2029
0
0
1,672,800
1,672,800
Totals
0
0
1,672,800
1,672,800
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
1,672,800
0
0
Tota Is
0
0
1,672,800
0
0
Resolution 2148 Attachment A Page 42
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
00
WA-13491
06/08/26
06/15/26
2148
44
0.000
No
Transportation Demand Management Implementation
to
Provision of TDM services to Commute Trip Reduction -affected employment sites.
Facilitate employer reporting and records associated with biennial CTR survey.
Engage CTR employment sites with opportunities for improvement and remain
connected via technical meetings with other CTR jurisdictional representatives.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2027
0
WSDOT
103,200
0
103,200
P
ALL
2028
0
WSDOT
258,000
0
258,000
Totals
0
361,200
0
361,200
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
51,600
51,600
51,600
51,600
103,200
Totals
51,600
51,600
51,600
51,600
103,200
Resolution 2148 Attachment A Page 43
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
3
i
0
o
�
'
i
n
c
m o
'm_
E. Begin & End Termini
c
1<
a
N
F. Project Description G. Structure ID
to
a
m
N
s
m
a
00
WA-17063
06/08/26
06/15/26
2148
18
No
Tukwila and South King County TDM
to
Provide TDM services to help people use sustainable transportation options that
increase access to opportunity, and reduce drive -alone travel and traffic congestion
in Tukwila and South King County.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2027
0
OTHER
832,000
208,000
1,040,000
Totals
0
832,000
208,000
1,040,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
260,000
260,000
130,000
0
0
Totals
260,000
260,000
130,000
0
0
Resolution 2148 Attachment A Page 44
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
=
y
3
°_
3
°—'
n»
c
B
D. Road Name or Number
c
a
3
i
0
o
�
i
n
c
m o
E. Begin & End Termini
3
1<
a
'
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
00
TUK-69
06/08/26
06/15/26
2148
24
0.000
CE
No
Tukwila and South King County TDM
Tukwila and South King County
N/A to N/A
This project will provide TDM programming and services to help people access
sustainable transportation options that reduce drive -alone travel and traffic
congestion in Tukwila and South King County. Tukwila's TDM Program reaches
people regionally at employment centers, community hubs, multifamily housing
complexes, and educational institutions.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PL
2027
CMAQ
550,000
WSDOT
85,838
0
635,838
Totals
550,000
85,838
0
635,838
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PL
158,959
158,959
158,960
158,960
0
Totals
158,959
158,959
158,960
158,960
0
Resolution 2148 Attachment A Page 45
Washnoun e Six Year Transportation Improvement Program
From 2027 to 2032
Agency: Tukwila
County: King
MPO/RTPO: PSRC Y Inside N Outside
m
3
'<
T
G
m
A. PIN/Project No. B. STIP ID
3
0
3
3
3
Z
C. Project Title
y
3
°_
3
n»
c
D. Road Name or Number
=
c
a
3
0
�
°—'
n
m o
B
E. Begin & End Termini
3
i
1<
o
a
'
i
c
N 'm_
F. Project Description G. Structure ID
to
a
c
m
N
s
m
a
03
WA-17042
06/08/26
06/15/26
2148
04
C P S W
0.530
CE
No
Tukwila International Boulevard (S 152nd St to S 144th St)
S 152nd St to S 144th St
Construct landscape median, refine corridor access, roadway diet, and multimodal
lanes.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2030
0
0
4,347,000
4,347,000
Totals
0
0
4,347,000
4,347,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
4,347,000
0
Totals
0
0
0
4,347,000
0
Federal Funds State Funds Local Funds Total Funds
Grand Totals for Tukwila 43,635,306 142,961,338 66,509,200 153,105,844
Resolution 2148 Attachment A Page 46
From:
Jennifer Marshall
To:
amarklev(a)Dsrc.ora
Cc:
Anna Lieck; Andy Youn-Barnett; Cvndv Knighton; Adam Cox
Subject:
Tukwila - Transportation Improvement Program 2027-2032
Date:
Wednesday, June 24, 2026 5:38:06 PM
Attachments:
imaae001.Dna
imaae003.Dna
June 24, 2026
TO: PUGET SOUND REGIONAL COUNCIL
RE: CITY OF TUKWILA 2027-2032 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to the city of Tukwila Resolution #2148 passed June 16, 2026 adopting the
Transportation Improvement Program for 2027-2032.
IRes 2148- 2027-2032 T r ire m. rt f iii in III m m r m m ir�f Ill rya .r m
Regards,
)ennifer Marshall, CMC/CPRO
Acting City Clerk I Office of the City Clerk
6200 Southcenter Blvd I Tukwila WA 98188
Phone: 206 433-7189
NOTICE: ALL emails and attachments sentto and from the City of Tukwila are public records
and may be subjectto disclosure pursuant to the Public Records Act (Chapter 42.56 RCW).
From: Jennifer Marshall
To: areaa(a)tib.wa.aov
Cc: Anna Lieck; Andy Youn-Barnett; Cvndv Knighton; Adam Cox
Subject: Tukwila - Transportation Improvement Program 2027-2032
Date: Wednesday, June 24, 2026 5:38:08 PM
Attachments: imaae001.Dna
imaae003.Dna
June 24, 2026
TO: TRANSPORTATION IMPROVEMENT BOARD
RE: CITY OF TUKWILA 2027-2032 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to the city of Tukwila Resolution #2148 passed June 16, 2026 adopting the
Transportation Improvement Program for 2027-2032.
IRes 2148- 2027-2032 T r ire m. rt f iii in III m m r m m ir�f Ill rya .r m
Regards,
)ennifer Marshall, CMC/CPRO
Acting City Clerk I Office of the City Clerk
6200 Southcenter Blvd I Tukwila WA 98188
Phone: 206 433-7189
NOTICE: ALL emails and attachments sentto and from the City of Tukwila are public records
and may be subjectto disclosure pursuant to the Public Records Act (Chapter 42.56 RCW).
From:Jennifer Marshall
To:julie.meredith@wsdot.wa.gov
Cc:Anna Lieck; Adam Cox; Cyndy Knighton
Subject:Tukwila - Transportation Improvement Program 2027-2032
Date:Thursday, June 25, 2026 8:36:54 AM
Attachments:image001.png
image002.png
June 25, 2026
TO: WASHINGTON STATE DEPARTMENT OF TRANSPORTATION
RE: CITY OF TUKWILA 2027-2032 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to the city of Tukwila Resolution #2148 passed June 16, 2026 adopting
the Transportation Improvement Program for 2027-2032.
Res 2148 - 2027-2032 Transportation Improvement Program
Regards,
Jennifer Marshall, CMC/CPRO
Acting City Clerk | Office of the City Clerk
6200 Southcenter Blvd | Tukwila WA 98188
Phone: 206 433-7189
NOTICE: All emails and attachments sent to and from the City of Tukwila are public records
and may be subject to disclosure pursuant to the Public Records Act (Chapter 42.56 RCW).