HomeMy WebLinkAboutReg 2012-06-18 Item 6B - Contract Supplement #2 - Water and Sewer Comprehensive Plans with Carollo Engineers for $21,721.50CouNCILAGENDA SYNOPSIS
Initials
Meeting Date Prepared by J Mayor' s
06/11/12 BG
06/18/12 BG
ITEM INFORMATION
STAFF SPONSOR: BOB GIBERSON
ITEM NO.
l review
6. B.
ORIGINAL AGENDA DA'Z'E: 06/11/12
AGENDA ITEM TITLE Water and Sewer Comprehensive Plans
Consultant Supplemental Agreement No. 2 with Carollo Engineers
CATEGORY Discussion Motion Resolution Ordinance Bid Award Public Hearing Other
Mtg Date 06111112 Mtg Date 06118112 Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date
(SPONSOR Council [:]Mayor HR DCD Finance Fire IT P&'R Police PWI
SPONSOR'S Carollo Engineers were hired as the consultant for the Water and Sewer Comprehensive
SUMMARY Plans in 2010. Due to additional requirements on the Water Comprehensive Plan,
Supplement No. 2 with Carollo is required to add to the scope of work. Additional water
funds will come from the Interurban Water Reuse Project with $25,000.00 budgeted.
Council is being asked to approve Supplement No. 2 with Carollo Engineers in the amount
of $21,721.50.
REVIEWED BY COW Mtg. CA &P Cmte F &S Cmte Transportation Cmte
Utilities Cmte Arts Comm. Parks Comm. Planning Comm.
DATE: 05/30/12 COMMITTEE CHAIR: DENNIS ROBERTSON
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works Department
COMMITTEE Unanimous Approval; Forward to Committee of the Whole
COST IMPACT FUND SOURCE
EXPENDITURI7 REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$21,721.50 $328,000.00 $0.00
Fund Source: 401 WATER (PGS 86 90, 2012 CIP)
Comments:
MTG. DATE
06/11/12
06/18/12
RECORD OF COUNCIL ACTION
Forward to next Reaular Meeti-nq
MTG. DATE J ATTACHMENTS
06/11/12 Informational Memorandum dated 05/25/12
Carollo Engineers' Supplement No. 2 to Contract 10 -055
Minutes from the Utilities Committee meeting of 5/30/12
06/18/12 No attachments
91