HomeMy WebLinkAboutUtilities 2012-10-23 Item 2C - Contract Supplement #3 - Water and Sewer Comprehensive Plan with Carollo EngineersCit of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM TO: Mayor Haggerton Utilities Committee FROM: Bob Giberson Public Works Director BY: Mike Cusick, PE, Senior Engineer DATE: October 19, 2012 SUBJECT: Water and Sewer Comprehensive Plans Project No. 91040101, Contract No. 10 -055 Supplemental Agreement No. 3 ISSUE Approve Supplemental Agreement No. 3 with Carollo Engineers to revise the Comprehensive Water Plan. BACKGROUND In 2010 the City contracted with Carollo Engineers to update the Water Comprehensive Plan. DISCUSSION For the 2005 Comprehensive Water Plan, the Washington State Department of Health (DOH) required no additional storage of water in lieu of the existing 2 million gallon reservoir and multiple taps off Seattle pipelines. In 2009, DOH guidelines were revised to require standby storage of water at 200 gallons per equivalent residential unit (ERU). With the 2009 DOH storage guidelines, the existing Tukwila 2 million gallon reservoir is now undersized for the current population of the city. With the projected 2030 population growth model provided by the Tukwila Department of Community Development (DCD), the condition worsens. Initially, Carollo Engineers used the 2010 -2030 population data study from Puget Sound Regional Council (PSRC), as provided by DCD, to determine the required reservoir size to meet the revised requirements from DOH. Using the PSRC 2030 population model, the City of Tukwila would be required to construct a new reservoir to bring the City's total water storage to 7.1 million gallons with a design and construction cost for the proposed reservoir at over $5.5 million dollars. This cost estimate does not include the cost of land acquisition for the reservoir and a necessary pump station. The total cost of the project could be over $10 million dollars for the reservoir, pump station, and land. With the high cost of the required water reservoir and other water CIP improvements, Public Works questioned DCD on the projected 2030 population growth model for the City. It was agreed that the 2030 PSRC model used for population forecasting overstates projected growth within the City. For the Comprehensive Water Plan, DCD agreed to cut the projected growth in half by changing the time period from 2010 -2030 to 2010 -2040. With a reduced population growth, the total reservoir requirement of 7.1 million gallons can be reduced to 4 to 5 million gallons of total storage. The reduction in reservoir size results in savings to the City of several million dollars in costs to the Water Fund. Carollo Engineers additional work will modify the Water Comprehensive Plan. The supplement will focus on updating the revised growth projections with the new 2012 data 39 Info Memo Page 2 Carollo Engineers Supplement No. 3 developed by DCD. The reduced growth projections will be used to calculate new average and maximum day water demand for future planning scenarios. The new demand will be updated in the supply analysis, hydraulic modeling analysis, and storage analysis. The system will be evaluated to determine the deficiencies and proposed improvements needed with the new demand in each service area. It is anticipated that this will also modify the proposed improvements in the CIP and this new data will modify most sections of the Water Comp Plan. FINANCIAL IMPACT Supplemental Agreement No. 3 will increase the consultant's scope of work for Task 300 Planning Considerations for $16,250.00. Funding for the additional work will come from the Interurban Water Reuse Project, page 86 of the 2012 CIP at $25,000.00 and Andover Park West Water Line Project for $16,000.00, which will now be constructed in 2013. EXPENDITURES Original contract Supplement No. 1 Supplement No. 2 Supplement No. 3 Total $291,000.00 12, 662.00 21,721.50 16.250.00 $341,633.50 Fundina Budaet Water Comp Plan $160,000.00 Sewer Comp Plan 143,000.00 Interurban Water Reuse 25,000.00 APE Water Line 16.000.00 E, M RECOMMENDATION Approve Supplemental Agreement No. 3 to Contract No. 10 -055 with Carollo Engineers for $16,250.00 to update population growth projects for the Comprehensive Water Plan and consider this item at the November 13, 2012 Committee of the Whole and subsequent November 19, 2012 Regular Meeting. Attachment: Supplemental Agreement No. 3 WAPW EngTROJECT9k WT Pm*tslWater Comprehensive Plan -Water (91040101)ilnio Memo Carrollo Sup 10-16-12.dm 40 SUPPLEMENTAL AGREEMENT NUMBER 3 to C THIS SUPPLEMENTAL AGREEMENT is entered into between the City of Tukwila, Washington, herein -after referred to as "the City," and Carollo Engineers hereinafter referred to as "the Consultant in consideration of the mutual benefits, terms, and conditions hereinafter specified. The City desires to supplement the agreement entered into with the Consultant and executed on, May 19, 2010, and identified as Agreement No. 10 -055. All provisions in the basic agreement remain in effect except as expressly modified by this supplement. The changes to the agreement are described as follows: 1. Scope of Services, for Supplemental Agreement #3 to the Comprehensive Sewer and Water Plans (Plans) for the City of Tukwila. The purpose of this supplement is to add: The following work effort is a modification to the Comprehensive Plan (Plan) for the City of Tukwila. The update will be focused on updating the revised growth projections with the new 2012 data developed by the Planning Department. The growth projections will be used to calculate new average and maximum day water demand for the future planning scenarios. Tile new demand will be updated in the supply analysis, hydraulic modeling analysis and the storage analysis. The system will be evaluated to determine the deficiencies and proposed improvements needed with the new demand in each service area. It is anticipated that this will also modify the proposed improvements in the CIP. This new data will modify most sections of the Plan. 2. Deliverables, Carollo will prepare a revised Executive Summary and Chapters 2, 3, 5, 6, 7 that summarizes the new future demand, analysis and recommended improvements. 3. Time for Performance, is amended to change the number of calendar days for completion of the work to read an additional 90 days for a total of 1,070 days. 4. Payment, shall be amended as follows: Payment for the work provided by the Consultant as part of this supplement shall be made for an additional $16,250.00. The total amount for the Consultant for this contact shall not exceed $341,633.50 without express written modification of the Agreement signed by the City. DATED this day of 2012. CITY OF TUKWILA Jim Haggerton, Mayor CONSULTANT By: Lara Kammereck, Associate Vice President 41