HomeMy WebLinkAboutCOW 2013-06-10 Item 5A - Resolution - 2014-2019 Transportation Improvement ProgramCOUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Pr oared by _ ,
Ma pr's revie
Council review
06/10/13
BG '0
/'1
CATEGORY a Discussion
06/17/13
BG
►1 Resolution
t
❑ Bid Award
Mtg Date
// Public Hearing
❑ Other
Mtg Date
Mtg Date
Mtg Date 06/17/13
Mtg Date 06/10/13
SPONSOR ❑ Council ❑ Mayor ❑ Adm Svcs ❑ DCD ❑ Finance ❑ Fire ❑ Legal ❑ P&R ❑ Police // PW
SPONSOR'S The Transportation Improvement Program (TIP) is required by RCW to be updated
SUMMARY annually. The TIP is primarily a finanical planning document for projects competing for
grants. A Public Hearing is scheduled on June 10, 2013 for the 2014 - 2019 TIP. After the
Public Hearing, the TIP is adopted by resolution and is then incorporated into the Regional
and State TIPS.
ITEM INFORMATION
ITEM No.
4&
5.A.
CAS NUMBER:
STAFF SPONSOR: BOB GIBERSON
ORIGINAL AGENDA DATE: 6/10/13
AGENDA IIEM TITLE Resolution adopting the Six -Year Transportation
Improvement
Program
2014 - 2019
CATEGORY a Discussion
06/10/13
❑ Motion
Mtg Date
►1 Resolution
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
// Public Hearing
❑ Other
Mtg Date
Mtg Date
Mtg Date 06/17/13
Mtg Date 06/10/13
SPONSOR ❑ Council ❑ Mayor ❑ Adm Svcs ❑ DCD ❑ Finance ❑ Fire ❑ Legal ❑ P&R ❑ Police // PW
SPONSOR'S The Transportation Improvement Program (TIP) is required by RCW to be updated
SUMMARY annually. The TIP is primarily a finanical planning document for projects competing for
grants. A Public Hearing is scheduled on June 10, 2013 for the 2014 - 2019 TIP. After the
Public Hearing, the TIP is adopted by resolution and is then incorporated into the Regional
and State TIPS.
REVIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte
❑ Utilities Cmte ❑ Arts Comm. ❑ Parks
DAI'E: 5/29/13 COMMITTEE
// Transportation
Cmte
Comm. ❑ Planning Comm.
CHAIR: KATE KRULLER
RECOMMENDATIONS:
SPONSOR /ADMIN.
COMMITTEE
Public Works
Unanimous Approval; Forward to Committee of the Whole
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
6/10/13
6/17/13
MTG. DATE
ATTACHMENTS
6/10/13
Informational Memorandum dated 05/24/13
Draft Resolution
Draft 2014 — 2019 TIP Spreadsheet
Current Adopted 2013 — 2018 TIP
Minutes from the Transportation Committee meeting of 05/29/13
6/17/13
1
2
TO:
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
BY: Cyndy Knighton, Senior Engineer
DATE: May 24, 2013
SUBJECT: Resolution for Six -Year Transportation Improvement Program (2014 -2019)
ISSUE
Resolution to adopt the annual update of the Six -Year Transportation Improvement Program for 2014 -2019.
BACKGROUND
The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of Washington
(RCW). The TIP is adopted by resolution after a public hearing at the local agency level and incorporated into regional
and state TIPs. The TIP is primarily a financial planning document for projects competing for grants. Any project submitted
for federal grant funding must be included in the local, regional and state adopted TIPs. The TIP is a rolling plan showing
various funding sources: grants, developer and local funds. Projects "roll" as funds or stages occur (design report, final
design and construction).
Tukwila's TIP and Capital Improvement Program (CIP) list many of the same transportation - related projects. The TIP
generally lists only those transportation - related projects planned within the next six years that are deemed regionally
significant or that have grant funding awarded or expected. The City's CIP lists transportation projects planned in the next
six years and beyond, as well as water, sewer, surface water, and capital facilities projects. The TIP is required to be
adopted by June 30 on an annual basis, while the CIP is prepared during Summer /Fall in conjunction with the City's
budget preparation. Differences between the two may be due to priority changes, funding availability changes, or other
factors which normally occur during the time between adoptions of each document.
ANALYSIS
The attached spreadsheet is the "Draft" 2014 - 2019 TIP and was created by modifying the 2013 - 2018 TIP to add or
remove projects and adjust project costs. No prioritization was assigned and the list of projects is presented in
alphabetical order. Prioritization of projects is reflected in the CIP.
Added: Americans with Disabilities Act (ADA) Improvements (CIP Page 17), BNSF Regional Center Access
(CIP Page 13), Strander Blvd /SW 27th St Phase III (CIP Page 29)
Deleted: Neighborhood Traffic Calming (CIP Page 6)
Modified: Andover Park West (Tukwila Pkwy — Strander Blvd), Boeing Access Rd Bridge Rehabilitation, Interurban
Ave S (S 143rd St - Ft Dent Way), S 133rd St / SR 599 Ramps Intersection, S 144th St (Phase II), S
178th St Realignment, TUC/TOD Pedestrian Improvements, TUC - Transit Center, TUC - Ped /Bike
Bridge, W Valley Hwy / S 156th St
RECOMMENDATION
The Council is being asked to approve the resolution for the 2014 -2019 Six -Year Transportation Improvement Program
and consider this item at the June 10, 2013 Committee of the Whole with a Public Hearing and subsequent June 17, 2013
Regular Meeting.
Attachments: Draft Resolution
2014 — 2019 "Draft" Transportation Improvement Program (TIP) Spreadsheet
Current Adopted 2013 — 2018 TIP
W: \PW Eng \PROJECTS\A- RW & RS Projects \TIP \Info Memo TIP 2014.docx
3
4
FT
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2014-
2019), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26 as
amended, the City Council of the City of Tukwila has previously adopted a
Transportation Improvement Program and thereafter periodically modified said
Transportation Improvement Program by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six -Year Transportation Improvement Program for the
ensuing six calendar years (2014 - 2019); and
WHEREAS, on June 10, 2013, a public hearing was held regarding the City's Six -
Year Transportation Improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A six -year Transportation Improvement Program
for the calendar years 2014 -2019 is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the
Secretary of Transportation and the Transportation Improvement Board of the State of
Washington.
W: \Word Processing- City\Resolutions \TIP 2014 -2019 5 -23 -13
CK:bjs
Page 1 of 2
5
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON,
at a Regular Meeting thereof this day of , 2013.
ATTEST /AUTHENTICATED:
Christy O'Flaherty, MMC, City Clerk Kathy Hougardy, Council President
APPROVED AS TO FORM BY:
Filed with the City Clerk:
Passed by the City Council:
Resolution Number:
Shelley M. Kerslake, City Attorney
Exhibit: City of Tukwila Six -Year Transportation Improvement Program from 2014 to 2019
W:\Word Processing- City\Resoiutions \TIP 2014 -2019 5 -23 -13
CK:bjs
6
Page 2 of 2
DRAFT 2014 - 2019 TIP SUMMARY
FUNDING SOURCES
0
Developer Unsecured
m
F-
a)
Ta-
a7
a
LL
J
0
F-
O)
O
N
ca
O
O N
N
a
ca
N
7 f`
L 0
I- N
C
N
0
O c0
N N
.O
a
N
N
0
N
CL
0 Z
U
co
(°v a
PROJECT TITLE
co o r• o O (O 7 0 0) 0) V N- 0 0 0 00 0( 7 0 0 0 0) (0 0 0 M (f) 0 0 N 0 0 :4
_
N- 0 CO )f) LO 0) N c0 0) 0 0 M 0 V 0 V c0 0 V (O 0 00 r n M V O 0)
co o co N r` t0 0) "a- 00 O M co N t` 0) O N a0 to co r` 0
r 0 N M N N
(00 00 coo 00 00 00 00 00 00
O N 10 (O 0)
c- M
(0 LL) V 0 0 N M O N O 0 (O 0 0 'l)
r- N. 00) U) (0 0)) V 0 0 N M N N c0 0`
r (O 0)
• 0 O O O^
aO O V cO c0
tri r O
co O c0 O co O co
co (00 co ev- 0 U ON a-
m N 0)
W 10 N 0 0 (f) 0 0 0) 0 O r- 0 0 0 O O c_0 V N 0 0 0) 0 0 (O 00 0 (f) 0 0 r-
(O (O O 0 M (0 O N V M 0 (O 0 V 0 0 V (0 0 0 0) N t- 0 M 0) 0
CO O N. O f` O t-- a- W M f` O 0) M N O 00 N co N O (O O r in co c0 (O c0 co c-
O) 0) M O N 0 N M M 7 V N 00
M (f) N 0 (O 0 0 0 0) 0 0 0 0 0 0 0 0 0 V 0 0 0 CO 0 0 0 Y') 0 0 0 0 0.
O t` N M N (O M 0 V' CO 0 0') O (0 0 V O N CO n M :h
Y7 (O M r CO M O 0) N N O N- N N 0 0 0 0 0 CO 0
M N N M M V
(,.) 0 0 0 M 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
O M c0O
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 N
N f0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
CO N. N LO
0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 0 0 0 0 N. 0 NV 0 0 0
CO •et LO N
r 0) M
(O 0 0 0 0 0 0 0 0 n 0 0 0 0 0 00 0. 0 0 0 0 0 0 0 0 0 0) 0 0 '1)
O (O h 0 0 (O 0 N (O 0 M N N 0 0) �
0 N (O (• M (0 (O O
M O 0) N (O
N N 0 0 M M N N N M (c) 7 CO N CO Cr 'Cr ' (0+) N M M OOD M CO N M C0') NI CO
T 2
a
a N. Ti" 7 M * d r.
E O y W c ° o) vi a
0@ m 0 d 0 d � m in 0) o c a c 2
0 a :° m �Q _ 0E m E @m
Q rn E N 0 N r v) d w a) a) o@ a) ! Cj d~ m
_ fn @ cn r ' a) 3 co O a) > N O m E (n C .. Y a) C
U C C O O cu N LL C a C co C >C a L O `O j 3>. Z N m N 2
N >, m Y C d U Q) aa) YO m !n co N •;, . > co !n .O d a a) (0 N d p fn
`m 7 o n y-0 o Q v m in E a3i c `m (O aNi c m E~ (n n
maY ati °) cm`wm mot. ',0.) ��' 3 Ea"N o oa(n� d a) 0Tr;.o
y E y c U a@ m N rn_ m N m aci aci Z=
w > U> .5 in F M in o N LL c O .c co w e a) °° U U m n
Naaa� > m0> Ty a) m�m0_(0 < m ami cammU -2� o a>)= •
c a) °1 c E m a in 0) .c a) 0 0 — >,
@ a) a> a) -- @a @ 7au)zinintin"o a`) Tcn0 m m @ m m @
45000av a a a C C <n a) N N C . 0) M a0 N 00 m O V Y Y Y Y Y Y 07
mm°c)w E2 2zmmUcnUv)cUi)in1- 1-1-F- F- FF-F7-
N M V «) c0 n 00 0.) O N M V 10 (0 c0 0) O N M . (O (0 r 00 CO O N
N N N N N N N N N N M M M M :h
Neighborhood Traffic Calming Program
N
c
a)
E
a)
>
2 -,:-.3.
T
C o
Q _ c
0 2 _ �n m 0
< N N
a i_ a a a E, ro
O y _c a v
CO 7 U N m (/) ix
0 O_ O 0) a 01
• 2 a' - Y m > -.� IX
(n
N O) m 0 U Q C —
Z<0min ¢m =(n
mps Intersection
PROJECTS REVISED FROM 2013 -2018 TIP
F-
w
w
2
rY a-
u_ U
O
w
LI o
N
0 M
o
N
F- z
U Z
W w
M
Occ
Et 0 U
W Valley Hwy / S 156 St
7-
mprovement Program
Six Year Transportation
8
From 2013 to 2018
Agency: Tukwila
d
;
0
z
a
MPO /RTPO:
RW Required
Environmental Type
w
0
0
O
0
Total Length
a
0
Utility Codes
0
0f..
Improvement Type
o
Resolution No.
0
n
r
Amendment
N
Adopted
00
0
N
Hearing
7-
a)
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03766
Andover Park E /Industry Drive Signal
Andover Park E
Industry Drive to
Design and construct a traffic signal and intersection improvements
Priority Number
Functional
co
Class
Total Funds
0
0
0
N
m
0
0
0
Local Funds
0
0
0
n
u�
0
0
0
m
0
State Funds
0
0
State Fund Code
0
Federal Funds
0
0
Federal Fund Code
Phase Start Year (YYYY)
O
N
N
r
a
a
z
0
0)
y
N
a
m
m
0
1
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
1.g
Gt
a
IF:
From 2013 to 2018
Agency: Tukwila
N
0
0
z
}
RW Required
z
Environmental Type
w
0
0
_0
O
Total Length
Utility Codes
Improvement Type
"o
Resolution No.
0
n
r
Amendment
N
Adopted
m
Lo
Hearing
N F
a,
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03764
Andover Park E /Minkler Blvd. Intersection
Andover Park E
Minkler Blvd to
Design and construct intersection and traffic signal improvements and widening for
left turn pockets
Priority Number
Functional
o
Class
00
0
O
Total Funds
00
O
O
N
00
0
O
0
Local Funds
0
0
0
N
O
0
0
N
0
0
0
a
n
0
State Funds
0
0
0
State Fund Code
0
Federal Funds
0
0
O
Federal Fund Code
Phase Start Year (YYYY)
M
0
N
o
0
N
CO
0
N
y
r
a
w
a
a
z
0
0
N
a
a
Expenditure Schedule
00
O
N
00
0
N
N
(0
0
0
O
0
M
0
O
0
0
0
N
0
0
O
e
O
m
L
a
a
z
0
Report Date: June 20, 2012
9
mprovement Program
Six Year Transportation
co
ig
c
c
4D
10
From 2013 to 2018
Agency: Tukwila
N
0
z
MPO /RTPO: PSRC
RW Required
z
Environmental Type
w
0
Total Length
0
0
0
O
co
a
0
Utility Codes
0
0i
Improvement Type
0a
Resolution No.
0
N.
Amendment
N
Adopted
F
m
0
Hearing
N
CB
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA- 03760I
Andover Park West Widening
Andover Park West
Strander Blvd to Tukwila Pkwy
Complete widening for center turn pockets and landscape median for access control,
widen sidewalks, upgrade ADA facilities, modify signal operation, upgrade street
lighting, install pedestrian lighting.
Priority Number
Functional
o
Class
a
c
li
O
0
0
of
N
N
C
LL
R
O
F
0
0
0
ei
0
0
0
Local Funds
0
0
0
0
0
0
0
N
State Funds
0
0
0
0
N
e
State Fund Code
0
Federal Funds
0
Federal Fund Code
Phase Start Year (YYYY)
M
O
N
d
L c
a
z
0
0
H
N
m
A
0
1—
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
a
From 2013 to 2018
Agency: Tukwila
c
0
U
a
0
0
z
m
0
}
MPO /RTPO: PSRC
RW Required
z
Environmental Type
Total Length
Utility Codes
Improvement Type
o
Resolution No.
0
r-
r-
Amendment
N
Adopted
E
0
0
N
Hearing
0
CD
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi- annual inspections as well as construct necessary
repairs and maintenance
Priority Number
Functional
-
Class
Total Funds
0
0
0
0
N
N
Local Funds
0
0
0
10
10
0
0
0
n
0
State Funds
0
State Fund Code
0
Federal Funds
0
Federal Fund Code
Phase Start Year (YYYY)
N
L
a
0
N
N
Expenditure Schedule
0
0
v
N
O
0
N
0
O
0
1
N
0
0
0
0
0
0
0
N
0
0
0
0
n
N
N
O
O
N
A
a
J
N
N
O
Report Date: June 20, 2012
11
mprovement Program
Six Year Transportation
O:-
h
m�
r Q
Et
3a
1674
12
From 2013 to 2018
Agency: Tukwila
0
v
Q
z
RW Required
Environmental Type
Total Length
a
0
Utility Codes
o
OF
Improvement Type
o
Resolution No.
0
Amendment
N
Adopted
m
0
N
Hearing
0
co
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
Priority Number
Functional
<c
Class
Total Funds
0
O
0
0
0
0
0
m
M
A
Local Funds
0
0
0
0
0)
0
0
0
0
M
0)
0
State Funds
0
State Fund Code
0
0
a
c
0
LL
70.
9
N
LL
0
Federal Fund Code
Phase Start Year (YYYY)
M
O
N
m
L
a
0
U1
co
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
0
"U)
J 0
z
MPO /RTPO: PSRC
RW Required
z
Environmental Type
Total Length
Utility Codes
a
0
Improvement Type
c
Resolution No.
0
n
n
Amendment
N
Adopted
o
m
0
N
Hearing
7-
m
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03732
Boeing Access Road Bridge Rehabilitation
Boeing Access Road
Airport Way to 1 -5
Reconstruct bridge 08002500
Priority Number
Functional
o
Class
m
0
0
LL
Total Funds
0
O
0
0
0
C')
0
0
O
0
0
0
0
0
0
0
0
N
N
C
LL
A
O
O
J
O
0
0
O
0
0
co
0
0
0
(N
N
N
0
0
0
O
N
N
0
State Funds
O
0
0
State Fund Code
Federal Funds
0
O
O
O
O
O
O
O
Federal Fund Code
cc
m
co
m
Phase Start Year (YYYY)
O
N
0
L
0.
a
cc
Z
0
0
N
a
a
a
Expenditure Schedule
0
0
0
0
L
a
0
O
O
O
M
O
O
O
O
N
O
O
0
N
a
a
Z
U
Report Date: June 20, 2012
13
mprovement Program
Six Year Transportation
1
From 2013 to 2018
14
0
0
a o
N
J
0
MPO /RTPO:
RW Required
z
Environmental Type
w
0
0
0
0
0
r"
0
N
0
m_
9
c
0
Total Length
0
Utility Codes
0
Improvement Type
N
Resolution No.
o
0
O
r
r-
Amendment
Adopted
o
o
0
0
Hearing
N F
o
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA- 03795'
Cascade View Safe Routes to School
S 140th St/33rd Ave S
to
Construct an off - street paved shard use path, sidewalks, and a traffic circle at the
intersection of 33rd Ave S and S 140th Street.
Priority Number
Functional
rn
Class
Report Date: June 20, 2012
N
O
0
o
0
0
n
0
839,0001
0
0
0
r"
0
N
9
c
0
0
0
0
0
LL
o
o
0
0
0
O 5
o
o
0
7
o
0
o
0
u
0
H
0)
N
N
o
o
0
0
0
O
o
0
0
0
co
m
0
C
7
41,
78,
Q)
Phase
LL
ce
1 CN
ALL
Totals)
A
0
0
J
O
O
O
N
O
State Funds
N
7
1,1
State Fund Code
WSDOT
WSDOT
WSDOT
WSDOT
Federal Funds
o
o
0
0
0
Federal Fund Code
0)
0
Phase Start Y
O
N
201
201
O
N
Phase 1
a
RW
CN
ALL
M
Status
a
a
a
o_
0
a
Report Date: June 20, 2012
5th & 0th
O
O
0
839,0001
839,000
r 4th
0
0
0
0
0
3rd
o
o
0
0
0
o
o
0
7
o
0
o
0
u
0
0)
N
N
O
O
0
0
0
m
41,
78,
Q)
Phase
w
a
ce
1 CN
ALL
Totals)
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
N
v
0
O
z
RW Required
z
Environmental Type
0
0
0
0
n
700,0001
w
0
3,350,000
0
co
o
Total Length
0
0
0
0
Utility Codes
0
a
Improvement Type
o
Resolution No.
o
0
0
n
0
N-
Amendment
N
Adopted
Federal Funds
o
0
0
0
N
Hearing
0
m
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03770
East Marginal Way
E Marginal Way
Boeing Access Road to S 112th St
Design and construct widening to 3 lanes including curb & gutter, sidewalks,
drainage, landscaping, and utility undergrounding.
Priority Number
STP
Functional
<o
Class
2018
C
a
a
Total Funds
50,0001
0
0
0
0
n
700,0001
3,350,000
Local Funds
50,000
0
0
0
0
700,000
1,130,000
2,050,000
State Funds
o
o
0
0
0
State Fund Code
Federal Funds
o
o
0
0
0
0
0
cn0
1,300,000
Federal Fund Code
STP
Vl
A
O
F
Phase Start Year (YYYY)
2014
2018
2018
2018
Phase
W
a
W
a
7j
o:
CN
Status
<n
d
d
a_
Expenditure Schedule
00
0
O
00
o
co
0
0
M
lh
M
0
L
0
0
0
0
9
tD
0
0
O
0
0
0
0
N
0
0
0
0
0
0
N
O
N
O
O
O
m
a
Lt.!
z
0
W
0
Report Date: June 20, 2012
15
mprovement Program
Six Year Transportation
0
SE
i1;
16
From 2013 to 2018
N
v
0
0
z
}
MPO /RTPO:
RW Required
Environmental Type
w
0
Total Length
Utility Codes
Improvement Type
N
Resolution No.
0
h-
t•••
Amendment
Adopted
N
CO
0
Hearing
N
0
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03783
Greenbelt & Multipurpose Trails
to
Design and construct safe connections to public trails to promoste pedestrian and
bicycle modes of transportation in lieu of motorized vehicles
Priority Number
Functional
o
Class
°
0
0
0
N
Total Funds
0
0
0
N
0
0
0
Local Funds
0
0
0
0
0
0
a
n
0
State Funds
0
0
State Fund Code
0
Federal Funds
0
0
Federal Fund Code
Phase Start Year (YYYY)
M
0
0
W
a
z
0
2
3
5,
m
0
F
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
0
ti
m
0
Z
N
a
c
}
MPO /RTPO: PSRC
RW Required
a�i
Environmental Type
w
0
Total Length
0
u"
0
0
u)
a
0
Utility Codes
O
OF
Improvement Type
o
Resolution No.
0
r
r-
Amendment
Adopted
(V
<o
0
Hearing
N
0)
6
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03771
Interurban Ave S
Interurban Ave S
S 143rd St to Fort Dent Way
Reconstruct street including paving, curb & gutter, drainage, illumination, sidewalk,
and landscaping
Priority Number
Functional
Class
Total Funds
0
0
0
0
0
N-
O
0
0
0
Local Funds
O
O
0
00
O
O
O
00
N
0
c
5
LL
d
A
N
0
0
0
0
0
0
O
0
0
O
0
0
0
State Fund Code
m
1-
0
Federal Funds
0
0
0
0
0
0
0
0
O
0
O
0
0
0
0
Federal Fund Code
a
r
Phase Start Year (YYYY)
a
O
N
d
L
a
a
Z
0
5
rn
a
a
R
0
Expenditure Schedule
0
0
0
O
O
L
O
O
O
0
v
i0
0
O
O
O
O
0
0
O
O
O
0
O
O
O
O
N
y
O
d
L
a
a
Z
0
O
1-
Report Date: June 20, 2012
17
mprovement Program
Six Year Transportation
18
From 2013 to 2018
Agency: Tukwila
m
v
0
0
z
C
MPO /RTPO: PSRC
RW Required
O
z
Environmental Type
w
U
Total Length
Utility Codes
Improvement Type
0
Resolution No.
O
n
Amendment
Adopted
N
0
O
Hearing
N
0
0
O
G. Structure ID
0
M
Macadam Road /S 144th St Intersection
Macadam Road
S 144th Street to
Widen Macadam Road to add a northbound left turn lane
Priority Number
Functional
Class
N.
0
c
'v
0
0
O
O
Total Funds
0
O
O
0
0
0
N
O
O
O
0
0m
O
0
0
O
O
0
N
O
O
State Funds
O
O
O
O
State Fund Code
O
Federal Funds
O
O
O
O
Federal Fund Code
Phase Start Year (YYYY)
cn
0
N
CO
0
N
m
0
N
m
0
N
a
a
U
2
y
N
a
a
a
A
O
F
Expenditure Schedule
O
O
0
O
O
0
O
O
O
0
O
O
O
O
O
N
O
O
O
O
O
O
O
d
N
a
a
z
U
m
1-
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
1�
From 2013 to 2018
Agency: Tukwila
County: King
0
0
.y
J
0
z
MPO /RTPO: PSRC
RW Required
2
Environmental Type
w
0
Total Length
0
0
v
O
1-
Utility Codes
co
a
Improvement Type
o
Resolution No.
O
n
N-
Amendment
N
Adopted
o
0
N
Hearing
0
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03773
Minkler Blvd
Minkler Blvd
Southcenter Pkwy to Andover Park W
Construct widening for 3 lanes including curb & gutter, sidewalk, drainage and
landscaping
Priority Number
Functional
r
Class
0
0
LL
7,7
1-
0
0
0
0
0
m
N
9
0
LL
A
0
0
J
0
O
0
0)
0
0
0
CO
CO
0
State Funds
0
O
State Fund Code
O
Federal Funds
0
Federal Fund Code
Phase Start Year (YYYY)
m
O
0
.0
0.
a
z
0
0
0
w
a
a
0
A
O
Expenditure Schedule
00
0
0
c0
0
00
0
a
0'
0
0
O
0
0
0
O
N
O
O
O
0
O
O
W
a
z
0
CNJ
N
cc
ca
a
Report Date: June 20, 2012
19
mprovement Program
Six Year Transportation
E
20
From 2013 to 2018
Agency: Tukwila
N
z
5
0
}
MPO /RTPO: PSRC
RW Required
z
Environmental Type
Total Length
Utility Codes
Improvement Type
v
Resolution No.
0
n
r
Amendment
Adopted
cc
o
0
N
Hearing
m
co
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03679
Neighborhood Traffic Calming Program
Various city street
to
Program to address neighborhood traffic concerns using striping, signage, roadway
improvements, traffic calming, and education to reduce speeding and improve safety
Priority Number
Functional
�
Class
Total Funds
Local Funds
0
State Funds
0
State Fund Code
0
Federal Funds
0
Federal Fund Code
Phase Start Year (YYYY)
O
N
2
A
H
0
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
c
Y
0
0
0
0
z
0
}
MPO /RTPO: PSRC
RW Required
2
Environmental Type
w
0
0
ZZ
O
Total Length
Utility Codes
Improvement Type
o
Resolution No.
0
1....
Amendment
Adopted
N
r. 0
0
N
Hearing
7
0
0
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03780
Nelsen Place
Nelsen Place
S 156th St to S 158th St
Design and construct paving, curb & gutter, sidewalks, drainage, and illumination
Priority Number
Functional
0
Class
m
0
li
O
0
0
0
N
Total Funds
0
0
0
0
O
0
0
0
0
N
Local Funds
0
0
0
N
0
0
0
W
0
O
O
00
N
0
State Funds
0
O
State Fund Code
O
Federal Funds
O
0
Federal Fund Code
CO
O
N
0)
O
0
0
.0
a
W
z
0
0
0
rn
a
a
Expenditure Schedule
O
0
N
00
0
00
O
0
N
0
0
0
0
13.
0
O
0
N
O
O
O
N
O
O
m
A
a
a
Z
0
0
A
O
Report Date: June 20, 2012
21
mprovement Program
Six Year Transportation
SE
St
a
41)
22
From 2013 to 2018
Agency: Tukwila
c
c
0
N
0
0
z
MPO /RTPO: PSRC
RW Required
z
Environmental Type
w
0
Total Length
0
_)
0
co
a
0
Utility Codes
0
0I_
Improvement Type
o
Resolution No.
0
n
n
Amendment
Adopted
o
m
0
Hearing
N
(0
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin ti End Termini
F. Project Description G. Structure ID
WA -03769
S 133rd St/SR 599 SB Ramps Intersection
S 133rd Street
SR 599 SB Ramps to
Design and construct intersection improvements including a new traffic signal.
Priority Number
Functional
o
Class
0
0
Total Funds
0
0
0
0
0
0
0
0,
0
0
0
0
Local Funds
0
0
0
0
0
0
0
rn
0
State Funds
0
0
0
State Fund Code
0
Federal Funds
0
0
0
0
0
0
0
0
e
Federal Fund Code
71
0
N
m
0
N
ao
0
N
W
a
W
a
Z
0
0
y
5)
a
a
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
0
0
}
MPO /RTPO: PSRC
RW Required
z
Environmental Type
w
0
0
N
O
Total Length
Utility Codes
Improvement Type
N
Resolution No.
0
n
n
Amendment
N
Adopted
0
0
Hearing
N
CD
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03782
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1 -5 between 51st Ave S and 53rd Ave S
Priority Number
Functional
n
Class
0
0
0
0
0
Total Funds
0
0
0
Local Funds
0
0
0
00
0
0
0
0
0
State Funds
0
State Fund Code
0
Federal Funds
0
Federal Fund Code
Phase Start Year (YYYY)
CO
O
m
L
W
a
0
m
to
a
Expenditure Schedule
00
0
O
0
00
0
0
L
v
0
0
0
O
N
O
Y!
O
0
CO
a
a.
A
0
1-
Report Date: June 20, 2012
23
mprovement Program
Six Year Transportation
24
From 2013 to 2018
Agency: Tukwila
c
Y
0
0
N
0
Z
MPO /RTPO: PSRC
RW Required
z°
Environmental Type
w
0
Total Length
0
rn
0
1,818,0001
co
a
68,0001
0
Utility Codes
0
818,000
01_
Improvement Type
o
Resolution No.
00
0
o
o
oo
0
o
0
0
State Funds
Ps
h-
Amendment
0
N
Adopted
a,
0
N
Hearing
0)
m
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03762
S 144th St Phase 2
S 144th Street
42nd Ave S to Tukwila International Blvd
Design and construct paving, curb & gutter, sidewalks, drainage, illumination, and
utility undergrounding. Coordinate with Tukwila Village development. May include on-
street parking and bike lanes
Priority Number
0
Functional
r--
Class
Expenditure Schedule
Report Date: June 20, 2012
Total Funds 1
68,0001
230,0001
40,0001
1,480,0001
1,818,0001
Local Funds
68,0001
230,000
40,000
480,000
818,000
0
0
0
00
0
o
o
oo
0
o
0
State Funds
0
0
State Fund Code
TIB
Federal Funds
0
0
0
0
0
Federal Fund Code
C)
tl
0
01
01
01
N
Phase
Q.
a
ry
CN
C
a
c
li
Status 1
CO
a
a
a
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
c
0
N
v
0
0
z
0)
a
MPO /RTPO: PSRC
RW Required
Y
Environmental Type
w
0
Total Length
0
O
m
O
Utility Codes
a
0
0
Improvement Type
c
Resolution No.
O
N.
N.
Amendment
Adopted
N
m
<o
0
Hearing
N
i
o
m
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03778
S 168th St
S 168th St
Southcenter Pkwy to Andover Park E
Design and construct new roadway including curb & gutter, sidewalk, drainiage,
illumination, on- street parking, landscaping, and underground utilities.
Priority Number
Functional
Class
o
°
O
0
0
N
Total Funds
0
0
0
N
N-
an
v
N
0
c
LL
R
V
O
J
O
0
0
N-
01
O
0
O
O
r
0
0
N
N1
N
O
State Funds
0
0
0
State Fund Code
0
Federal Funds
O
O
0
Federal Fund Code
Phase Start Year (YYYY)
O
O
N
O
O
N
o
O
N
N
a
W
a
z
0
2
m
co
a
a
a
Expenditure Schedule
L
co
N!
r
N
O
L
O
O
0
O
M
0
0
0
O
0
N
O
0
O
N
O
O
O
N
a
a
z
0
N
O
H
Report Date: June 20, 2012
25
mprovement Program
Six Year Transportation
4
41)
26
From 2013 to 2018
Agency: Tukwila
c
Y
c
U
1)
0
0
0
z
0
}
MPO /RTPO: PSRC
RW Required
z
Environmental Type
0
O
a
0
Total Length
Utility Codes
Improvement Type
o
Resolution No.
0
n
n
Amendment
N
Adopted
o
0
0
N
Hearing
o
ro
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03784
S 178th St Realignment
S 178th St
Southcenter Pkwy to W City Limits
Realign S 178th St from current intersection of Southcenter Pkwy /S 180th St to
intersect with Segale Park Dr C and add a new traffic signal at the new intersection.
Priority Number
Functional
o
Class
Total Funds
0
0
0
N
0,
0)
Local Funds
0
0
0
ri
0
0
n
r
ri
State Funds
0
0
0
0,
N
O
0
0
0
0,
N
N
State Fund Code
W
2
O
0
Federal Funds
0
Federal Fund Code
N
R
0
f
O
N
O
r
a
z
0
a
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
c
r
0
d
a
0
0
Z
MPO /RTPO: PSRC
RW Required
z
Environmental Type
w
0
0
0
O
Total Length
Utility Codes
Improvement Type
"o
Resolution No.
O
n
r
Amendment
N
Adopted
to
0
N
Hearing
iTi
O
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03781
S 180th St/Andover Park W Intersection
S 180th Street
Andover Park W to
Widen for north /south left turn pockets
Priority Number
Functional
o
Class
c
LL
0
0
0
0)
cn
Total Funds
0
0
0
0)
O
0
0
O
0
0
0
0
0
0
c)
Local Funds
0
0
0
ui
0
0
0
0
N
0
State Funds
0
0
0
State Fund Code
O
Federal Funds
0
0
0
Federal Fund Code
Phase Start Year (YYYY)
CO
O
N
O
0
N
O
O
N
t
0.
a
z
0
5
A
y
a
a
a
R
0
f
Expenditure Schedule
0
00
L
m
r
un
O
0
0
ID
0
0
0
N
O
L
0
0
0
0
0
0
0
O
N
O
O
O
N
O
O
O
m
N
a
a
cc
z
0
0
N
a)
co
a
Report Date: June 20, 2012
27
mprovement Program
Six Year Transportation
28
From 2013 to 2018
Agency: Tukwila
0>
0
0
0
v o
0
z
MPO /RTPO: PSRC
RW Required
Environmental Type
w
0
Total Length
m
o_
O
Utility Codes
0
0 f.
Improvement Type
0
Resolution No.
0
n
Amendment
N
Adopted
o
ro
m
O
Hearing
N
0)
w
0
O
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03776
Southcenter Blvd Widening
Southcenter Blvd
1 -5 to 61st Ave S
Widen Southcenter Blvd and the 61st Avenue Bridge to add a lane for future traffic
growth.
Priority Number
Functional
v
Class
0
v
0
LL
Total Funds
O
0
O
0
0
1
O
0
O
0
0
O
O
O
0
0
m
0
O
0
O
0
0
O
N
N
0
LL
A
0
0
J
0
0
0
00
O
O
O
00
0
0
0
00
Of
0
0
O
O
0
O
0
N
O
State Funds
O
O
O
State Fund Code
0
Federal Funds
O
0
0
Federal Fund Code
Phase Start Year (YYYY)
0)
O
N
0)
O
N
0)
O
N
a
z
0
a
a
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
ii:
From 2013 to 2018
Agency: Tukwila
MPO /RTPO: PSRC
RW Required
z
Environmental Type
w
0
Total Length
Utility Codes
Improvement Type
N
Resolution No.
0
n-
n-
Amendment
N
Adopted
ro
0
Hearing
N
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03796
Thorndyke Safe Routes to School
S 150th St
Tukwila International Blvd to 42nd Ave S
Construction of roadway improvements including a new sidewalk on the north side of
S 150th St and a new crosswalk in front of Thorndyke Elementary School. Education,
enforcement and encouragement elements are included after the construction as part
of the Safe Routes to Schools program.
Priority Number
Functional
0
Class
m
c
a
0
0
0
O
Ql
Total Funds
0
0
0
0
O
0
N
■
0
Local Funds
0
0
0
N
N
O
0
0
N
0
0
0
0
0)
State Funds
0
0
0
1-
N
State Fund Code
1—
0
0
3
0
0
0
Federal Funds
0
0
Federal Fund Code
Phase Start Year (YYYY)
0
N
0
N
N
r
a
a
z
0
4,
m
N
a
a
N
A
O
H
Expenditure Schedule
0
0
0
0
0
O
0
0
0
0,
0
0
O
0
e
O
O
N
O
O
O
N
N
O
0
N
d
L
a
a
z
0
Report Date: June 20, 2012
29
mprovement Program
Six Year Transportation
30
From 2013 to 2018
Agency: Tukwila
d
}
MPO /RTPO: PSRC
RW Required
2
Environmental Type
Total Length
Utility Codes
Improvement Type
N
Resolution No.
O
N.
Amendment
Adopted
N
C0
0
N
Hearing
0
ro
0
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03775
Traffic Signal Interconnect Program
Various City Streets
to
Design and install hard wire interconnect system between traffic signals and the
Traffic Operations Center
Priority Number
Functional
o
Class
rn
c
a
LL
0
0
O
Total Funds
0
0
0
0
r N
O
0
0
0
0
0
vi
N
9
7
LL
V
O
J
0
0
0
00
C.)
O
0
0
00
LL)
0
0
0
00
0
O
State Funds
O
O
State Fund Code
0
Federal Funds
0
0
O
0
0
0
0
0
N
Federal Fund Code
a
N
Phase Start Year (YYYY)
0
O
0
O
N
m
L
a
a
Z
0
0)
3
01)
a
a
N
R
O
H
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
c
5.
U
d
-o
N
J
0
z
v
}
MPO /RTPO: PSRC
RW Required
2
Environmental Type
w
0
Total Length
0
0
N.
o
Utility Codes
Improvement Type
N
Resolution No.
0
r-
Amendment
N
Adopted
0
Hearing
o N
CO
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03772
TUC/TOD Pedestrian Improvements
Baker Blvd (if extended)
Andover Park W to E City Limits
Design and construct bike and pedestrian connection between the Tukwila Urban
Center and the Commuter Rail Station/TOD area.
Priority Number
Functional
N.
Class
c
u.
0
0
0
Total Funds
Local Funds
O
0
0
O0
C)
O
0
0
00 ■
N
0
0
0
O
u
0
State Funds
0
0
0
State Fund Code
0
Federal Funds
0
0
0
0
0
0
N
O
0
0
0
O
N
Federal Fund Code
W
a
u)
Phase Start Year (YYYY)
O
N
CO
O
N
CO
O
N
N
a
a
ce
z
0
0
0)
y
a.
0.
a
A
O
H
Expenditure Schedule
00
0
0
0
L
i0
r
N
O
00
0
0
0
00
0
0
O
0
0
0
0
0
O
0
O
N
O
O
O
O
N
O
O
O
m
N
a
W
a
z
0
N
0
Report Date: June 20, 2012
31
mprovement Program
Six Year Transportation
0;
32
From 2013 to 2018
Agency: Tukwila
v
.y
0
z
RW Required
z
Environmental Type
w
0
0
O
O
Total Length
co
Utility Codes
a
0
Improvement Type
o
Resolution No.
0
Amendment
N
Adopted
o
m
0
N
Hearing
0
m
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03774
Tukwila International Blvd (Phase 4)
Tukwila International Blvd
Boeing Access Road to S 116th St
Design and construct widening including paving, curb & gutter, sidewalk, drainage,
lillumination, landscaping, and utility undergrounding.
Priority Number
Functional
Class
0
0
0
Total Funds
O
0
0
N
M
0
0
0
m
N
Local Funds
0
0
O
r
N
0
0
0
N
CO
0
0
O
0
State Funds
0
0
0
0
0
0
ri
0
0
0
0
0
N
ei
State Fund Code
0
H
0
Federal Funds
0
0
Federal Fund Code
Phase Start Year (YYYY)
O
O
5)
O
N
a.
a
a
z
0
c0
N
a
a
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
MPO /RTPO: PSRC
RW Required
z
Environmental Type
w
0
0
0
v
O
Total Length
Utility Codes
a
Improvement Type
c
Resolution No.
0
1-
n
Amendment
N
Adopted
10
0
Hearing
N
10
ro
0
A. PIN /Project No. 8. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03777
Tukwila International Blvd /S 116th St/SR 599 On -ramp
Tukwila International Blvd
S 116th St/SR 599 On -ramp to
Design and construct southbound left turn lane, pedestrian signalization and lighting
Priority Number
Functional
Class
Of
0
0
U.
Total Funds
0
0
0
vi
N
N
O
0
0
uS
O
Local Funds
O
State Funds
O
O
0
N
O
O
0
N
State Fund Code
1-
0
Federal Funds
0
0
O
Federal Fund Code
a
1-
Phase Start Year (YYYY)
CO
O
N
O
O
N
m
t
a
a
Z
0
a
a
R
0
Expenditure Schedule
00
(.6
N
N
L
to
ob
r
00
co
V
O
L
v
O
O
0
M
0
O
O
0
N
O
O
O
N
O
O
m
a
a
Z
0
A
0
Report Date: June 20, 2012
33
mprovement Program
Six Year Transportation
n�n
n4
P45
st
la
�jt 6
is
4D
34
From 2013 to 2018
Agency: Tukwila
rn
c
c
0
0
.y
z
MPO /RTPO: PSRC
RW Required
z
Environmental Type
w
0
Total Length
Utility Codes
Improvement Type
N
Resolution No.
0
r-
n
Amendment
Adopted
N
co
0
Hearing
—"0...5
0
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03798
Tukwila Manufacturing Industrial Center "Street Smart" Non - motorized Project
Various City Streets
to
1. Planning study of non - motorized improvement options along Boeing Access Road,
to provide safe bicycle and pedestrian travel alternatives. 2. PE & CN of bike facilities
on E Marginal Way S between Boeing Access Road and SR 599. 3. PE & CN of bike
lanes and shared use path on Airport Way from Boeing Access Road /E Marginal
Way S to the northern City limit.
Priority Number
Functional
O.
Class
c
7
LL
0
0
Total Funds
0
0
0
0
CO
0
m
M
0
Local Funds
0
0
0
0
0
State Funds
0
0
0
0
0
0
N
State Fund Code
H
0
0
0
Federal Funds
0
0
0
0
CO
0
(e
M
n
Federal Fund Code
a
0
U
Phase Start Year (YYYY)
0
N
M
0
N
•
a.
a
a
a
0
to
Q_
0
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
c
c
U
m
v
5
O
N
Y
MPO /RTPO: PSRC
RW Required
m
Environmental Type
w
0
Total Length
co
a
0
Utility Codes
O
0i
Improvement Type
N
Resolution No.
O
r
n
Amendment
N
Adopted
E
0
0
N
Hearing
�-
0
m
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03734
Tukwila Urban Center - Transit Center
Andover Park W
Strander Blvd to Tukwila Pkwy
Design and construct a transit center
Priority Number
Functional
o
Class
Total Funds
o
o
0
N
0
0
0
0
N
h
9 o
C
0
LL
A
O
0
J
o
0
0
0)
0
0
1
State Funds
0
0
O
0
ci
0
0
O
I
M
r
ri
State Fund Code
Federal Funds
0
0
0
0
0
0
0
O
0
O
a
Federal Fund Code
Phase Start Year (YYYY)
M
O
N
m
a.
a
Z
0
0
3
Expenditure Schedule
0
t
.0
0
a
0
0
a
M
0
O
O
N
Z
0
m
F
Report Date: June 20, 2012
35
mprovement Program
Six Year Transportation
c
t
41)
36
From 2013 to 2018
Agency: Tukwila
d
a
0
z
v
}
0)
Y c 0
5
c d
� H
0 6
O
2
RW Required
m
Environmental Type
w
0
0
V
co
o
Total Length
Utility Codes
Improvement Type
N
Resolution No.
0
N.
N.
Amendment
N
Adopted
o
CO
0
N
Hearing
i
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
/1320(002) TUK -50
Tukwila Urban Center Pedestrian /Bicycle Bridge over Green River
New bridge over the Green River, approximately between Baker Blvd (if extended)
and Longacres Way (if extended)
Near Riverside office complex to Best Western hotel 15901 WVHwy
Design and preliminary engineering of a new pedestrian /bicycle bridge across the
Green River, connecting the Tukwila Urban Center 'core' to the Sounder Commuter
Rail /Amtrak Station and surrounding neighborhood of transit- oriented development.
Priority Number
Functional
o
Class
°
rn
0)
LL
M
O
Total Funds
O
0
O
O
O
0
O
0
0
Local Funds
0
0
0
M
N
0
O
O
m
N
N
0
0
0
r
to
N
O
State Funds
0
0
0
0
0
00
0
State Fund Code
0
0
M
00
0
Federal Funds
0
0
0
0
0
0
N
N
Federal Fund Code
0
0
0
Phase Start Year (YYYY)
C)
0
0
N
0,
0
N
m
L
a
a
z
0
co
a
a
N
A
O
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
SE
.6t
From 2013 to 2018
Agency: Tukwila
c
c
5
N
0
z
MPO /RTPO: PSRC
RW Required
z
Environmental Type
Total Length
Utility Codes
Improvement Type
N
Resolution No.
O
n
r-
Amendment
N
Adopted
o
FE,
0
N
Hearing
E
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03761
Walk & Roll Plan (Nonmotorized Transportation Plan
Various City Streets
to
Select, design, and construct non - motorized projects including bike lanes, sidewalks
and trails
Priority Number
Functional
r-
Class
0
0
0
0
Total Funds
0
O
0
0
0
0
0
O
State Funds
0
State Fund Code
0
Federal Funds
0
Federal Fund Code
Phase Start Year (YYYY)
O
N
0
r
a
a
5
m
y
a
N
A
O
F
Expenditure Schedule
0
0
0
O
0
0
0
0
0
v
�n
0
C
N
0
0
N
0
m
CO
r
0.
a
a
0
Report Date: June 20, 2012
37
mprovement Program
Six Year Transportation
1F
38
From 2013 to 2018
Agency: Tukwila
c
Y
C
0 7
m
0
z
MPO /RTPO: PSRC
RW Required
z°
Environmental Type
w
0
0
0
N
0
Total Length
Utility Codes
Improvement Type
o
Resolution No.
0
i,
Amendment
N
Adopted
o
ro
0
Hearing
N
CD
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
WA -03779
West Valley Highway
SR 181/West Valley Highway
1 -405 to Strander Blvd
Design and costruct widening to 7 lanes including curb & gutter, sidewalks,
illumination, drainage, and traffic control
Priority Number
Functional
Class
0
0
0
Total Funds
0
0
0
0
0
0
0
n
CD
0
0
0
Local Funds
0
0
0
0
In
0
0
0
M
d
0
State Funds
0
0
State Fund Code
0
Federal Funds
0
0
Federal Fund Code
Phase Start Year (YYYY)
o
0
N
CO
0
N
a
z
0
a
EL
3,
m
0
Expenditure Schedule
Report Date: June 20, 2012
mprovement Program
Six Year Transportation
From 2013 to 2018
Agency: Tukwila
0
O
Z
MPO /RTPO: PSRC
RW Required
!
}
Environmental Type
w
0
Total Length
Utility Codes
a
0
Improvement Type
o
Resolution No.
0
N.
1-
Amendment
N
Adopted
m
0
N
Hearing
10
0
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin 8 End Termini
F. Project Description G. Structure ID
WA -03765
West Valley Highway /S 156th St
SR181/West Valley Highway
Southcenler Blvd to S 158th St
Construct additional northbound left turn lanes at S 156th Street for northbound HOV
to northbound 1 -405
Priority Number
Functional
v
Class
0
0
0
Total Funds
O
0
0
0 Lo
0
0
0
CO
0
O
O
0
0
0
0
00
10
O
00
0
O
00
O
0
m
0
0
State Funds
0
0
O
State Fund Code
0
Federal Funds
0
0
0
0
0
0
0
0
0
3
Federal Fund Code
O
U
Phase Start Year (YYYY)
m
O
N
O
O
N
C1
L
o.
a
a
U Z
m
0
m
m
0.
a
N
A
O
F
Expenditure Schedule
00
0
N
t
0
L
N
00
N
0
O
0
0
0
0
9
P7
0
0
O
c
O
O
O
W
a
Z
U
A
F
Total Funds
Local Funds
State Funds
Federal Funds
Grand Totals for Tukwila
Report Date: June 20, 2012
39
40
TRANSPORTATION COMMITTEE - Meeting Minutes
May 29, 2013 — 5:15 p.m. — Conference Room #1
City of Tukwila
Transportation Committee
PRESENT
Councilmembers: Kate Kruller, Chair; Joe Duffie and Dennis Robertson
Staff: Bob Giberson, Frank Iriarte, Robin Tischmak, Cyndy Knighton, Laurel Humphrey, Kimberly Matej
CALL TO ORDER: Committee Chair Kruller called the meeting to order at 5:15 p.m.
I. PRESENTATIONS - No presentations.
II. BUSINESS AGENDA
A. Resolution for Six -Year Transportation Improvement Program (2014 -2019)
Staff is seeking Council adoption via resolution of the 2014 -2019 Six -Year Transportation
Improvement Program (TIP), as required by the Revised Code of Washington (RCW). The TIP is a
financial planning tool that lists transportation- related projects planned within the next six years that are
regionally significant or that have grant funding potential. This annual update to the TIP is generally
modified to reflect the City's Capital Improvement Program (CIP), since the two are updated at
different times. Differences between the two plans may be due to priority changes, funding availability,
or other factors. The memo in the agenda packet clearly outlines the project additions, deletion, and
modifications, and staff distributed the finalized 2014 -2019 TIP that will be attached to the resolution.
Councilmembers and staff discussed the feasibility of approving the TIP and the CIP on the same
annual cycle in an effort to reduce discrepancies. Currently, the CIP is finished by the end of each year,
and the TIP must be approved by June 30. Staff will look into aligning these schedules and return with
a recommendation at a later date. UNANIMOUS APPROVAL. FORWARD TO JUNE 10 COW
FOR DISCUSSION.
III. SOUTH COUNTY AREA TRANSPORTATION BOARD (SCATBd )
The April 16, 2013 meeting summary was included in the agenda packet, along with the May 21 agenda.
Highlights mentioned by Committee Chair Kruller included the May 21 vote to issue a letter of support for
Substitute House Bill 1954, the update on the I- 405 /SR 167 Corridor Project, and the 2012 Statewide
VOWS Panel Transportation Survey. The Board discussed tolling and carpool requirements in other areas
of the country, and indiciated there may be a future movement to require three or more car occupants for
carpool lane access. INFORMATION ONLY.
IV. MISCELLANEOUS
Councilmember Robertson requested an update on the South 178th Realignment Project. Staff indicated that
Segale Properties is now working under an approved grading plan, and that clearing activities have begun.
Negotiations with Puget Sound Energy and the Highline Water District are ongoing.
Councilmember Robertson shared a concern about the safety of schoolchildren walking on 42 °d Avenue
South and wondered if any short-term safety solutions could be implemented. Staff mentioned galvanized
steel pedestrian rails as one possibility and will look into it.
Councilmember Duffie expressed ongoing concern about aggressive bicyclists on bike trails that intersect
with roadways (such as the Green River Tail crossing with South 116th Street), as well as pedestrian safety
issues along 531d Avenue South.
41