HomeMy WebLinkAboutRes 0596 - Interlocal Agreement - Grant for Preliminary Engineering for Grady Way Bridge
ATTEST:
CITY OF UKWI
WASHINGTON
RESOLUTION NO 596
A RESOLUTION OF THE CITY OF TUKWILA, WASHINGTON,
AUTHORIZING THE MAYOR TO EXECUTE AN INTERLOCAL
AGREEMENT WITH THE CITY OF RENTON TO APPLY FOR
A GRANT TO COVER PRELIMINARY ENGINEERING FOR
GRADY WAY BRIDGE.
WHEREAS, the Grady Way Bridge is the responsibility of both
the City of Tukwila and the City of Renton, and
WHEREAS, concern has been raised over this structure and its
life span, and
WHEREAS, it has been determined that the Grady Way Bridge
is eligible for funding;
NOW, THEREFORE, the City Council of the City of Tukwila,
Washington, does resolve as follows:
The Mayor is hereby authorized to execute an inter
local agreement with the City of Renton to apply
for a grant to cover preliminary engineering for
replacement of the Grady Way Bridge.
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON,
at a regular meeting thereof, this 18th day of July 1977.
Mayor G
COUNCIL ACTION
MEETING I AGENDA
A G R E E M E N T
CAG 060 -77
THIS AGREEMENT, made and entered into this 7 day of (7)(?/nl"9,e'
1977 between the City of Renton and the City of Tukwila, pursuant to the Local
Inter Governmental Cooperation Act.
WHEREAS both the City of Renton and the City of Tukwila are planning to
participate in an Improvement of the SW Grady Way Bridge, involving the
replacement of the existing bridge by a new 2 -lane structure (adapted for
eventual addition of a third and fourth lane), hereinafter called "this
Improvement," as authorized by City of Renton Resolution 112132 dated 22nd day
of August, 1977 and in City of Tukwila Resolution #596 dated 18th day of July
1977, and
WHEREAS the Improvement is located partially within the Cities of Renton
and Tukwila, and
WHEREAS this Improvement is listed in the City of Renton Six Year Urban
Arterial Construction Program and in the City of Tukwila Six Year Urban Arterial
Construction Program, for the period from 1978 to 1983, and
WHEREAS the City of Renton and the City of Tukwila have each included in
their respective 1978 budgets an amount intended to be spent on the design
phases of this Improvement, and
WHEREAS it is considered that this Improvement will be of benefit to the
citizens of both the Cities involved, and
WHEREAS the State Highway Department has advised the City of Renton that
Federal Bridge Replacement Funds are available for authorization to accomplish
the first phase of this project, i.e. Preliminary Engineering including P.S. E.
development, with further funding for construction also potentially being
available dependent upon first phase progress and the status of the Bridge
Replacement Fund, and
WHEREAS the City of Renton and the City of Tukwila recognize that an early
start on the design of this Improvement is necessary in order to comply with
the application procedures for Federal Aid Funds which will be submitted on a
Joint Agency basis,
NOW, THEREFORE, IT IS MUTUALLY AGREED AS FOLLOWS:
I
The City of Renton and the City of Tukwila will work together to develop a
ioijoint pr:
ply
_t to acc:, h this Ir�.pro`:et'ent. All related prospectus sub= teals,
s
abree:aents, contracts and permit applications will be subject to joint review,
approval and signature procedures.
II
The City of Renton will administer the project, but both Cities will
allocate manpower as needed to accomplish each phase on a cooperative basis.
These direct labor costs will be excluded from the expense sharing arrangement
as detailed in Paragraph IV, except that some Construction Engineering costs
may be eligible for inclusion as Federal Aid participation costs.
The Public Works Director of the City of Renton and the Public Works
Director of the City of Tukwila are hereby designated as the representatives
authorized to administer this Agreement. They, in turn, will appoint a Project
Engineer in their respective Public Works Organization to coordinate project
work activities. Every effort will be made to respond to each project related
issue within thirty days of submittal by either City, and any delays longer
than this thirty -day period will be subject to mutual agreement.
III
Development of the project will be in four (4) phases, as follows:
(a) Preparation of a Project Prospectus for Phase One.
(b) Preparation of a "Request for Consulting Engineering Proposal,"
itemizing all data which would be supplied to the Consultant by the Cities
and all work items which would be performed by the Consultant; screening of
Consulting Engineer qualifications and availability to establish a listing of
suitable prospective Consultants, and review of subsequent Proposals as
received from Consultants with eventual selection and awarding of contract to
the Engineering firm which is mutually deemed to be best qualified.
(c) Coordination with Consultant during the Preliminary Design and Final
P.S. E. Phase, followed by joint review and approval of the Design and of
Contract Plans, Specifications and Cost Estimate. (Applicable Environmental
Impact Review action will be taken in conjunction with this phase.)
(d) The Construction Phase of the project will be handled in the following
manner, subject to authorization of Federal Bridge Replacement Funding for
Phase Two construction:
The City of Renton will advertise for bids; both Cities will
jointly review bids and approve the contract award; inspection of
the construction activities will be accomplished through the
ce mated
efforts of the two Gibe?, and the Cir.y of Renton will
rr: the Contractor's payment 5 1"i.,'1 1 a_ for joint' .c
2
Iv
Based on the length of the existing bridge structure located in each
city, the City of Renton will pay 53% and the City of Tukwila will pay 47% of
the incurred expenses which are chargeable to those Local Funds established
by each City to match Federal Funds. Such expenses will include, but will not
be limited to, the anticipated matching ratio of 25% of eligible project costs,
with Federal Bridge Replacement Fund participation being 75%. As an administra-
tion function, the City of Renton will establish budgetary accounts to handle
the various project payments, other than direct labor costs, and will sub-
sequently submit Progress Billings to the City of Tukwila for the 47% pro -rata
reimbursement. The City of Tukwila will pay such Progress Billings within
thirty days of receipt.
v
Each City will arrange for adequate Insurance including coverage for
liability and property damage in connection with this Improvement.
IN WITNESS WHEREOF the parties hereto have set their hands and seals on
the day and year first above written.
CITY OF TUKWILA:
Mayor
ATTEST:
3
CITY OF RENTON:
ATTEST:
/1,
d
Cirk Q//