HomeMy WebLinkAboutRes 1552 - 2005-2010 Transportation Improvement ProgramSection 1. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the
Secretary of Transportation and the Transportation Improvement Board of the State of
Washington.
PASSED BY THE CITY COUNCIL. OF THE CITY OF TUKWILA, WASHINGTON,
at a Regular Meeting thereof this 21st day of June 2004.
o Pm Ha ..y n, Council President
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, ADOPTING A SIX -YEAR TRANSPORTATION
IMPROVEMENT PROGRAM, AND DIRECTING THE SAME TO BE
FILED WITH THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26 as
amended, the City Council of the City of Tukwila has previously adopted a
Transportation Improvement Program and thereafter periodically modified said
Transportation Improvement Program by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs, and based upon
these findings has prepared a Six -Year Transportation Improvement Program for the
ensuing six (6) calendar years (2005- 2010); and
WHEREAS, a public hearing was held on the said Six -Year Transportation
Improvement Program on June 14, 2004;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
ATTEST/ AUTHENTICATED:
J ne E. Cantu, CMG, City Clerk
APPROVED AS FORM BY:
Office of the Ci At{atiey-
TIP 2005 -10 6/17/04
City of Tukwila
Washington
Resolution No. 1552
Filed with the City Clerk: Passed by the City Council:
T
A Washington State Department of Transportation
WI
Tukwila
Co. No.: 17 Co. Name: King Co.
City No.: 1320 MPO /RTPO: PSRC
16 2
19 3
14 6
Project i ecTnt
A. Federal Aid No. B. Bridge No.
C. Project Title
D. Street/Road Name or Number
E. Beginning MP or road Ending MP or road
F. Describe Work to be Done
3
Overlay and Repair Program
Various City Streets
from: to:
Repair, rehabilitate, and overlay City streets as needed in an
annual program.
CBD Transit Center
Central Business District
from:
Construct transit center.
from: Airport Way
Reconstruct bridge.
to:
Pedestrian Safety Program
Various City Streets
from: to:
Boeing Access Rd Bridge Replacement p
0
to: 1 -5
Green River Valley Signal Coordination
c d
0. la t mm m U
n F- co c
E 1 S
N
m
t
a
U
d
4 5 6 7 8
07 S C
G
0
P
S
T
21 P T
W
P
S
12 S
Phase
Start
(mm/dd/yyyy)
9
AL 1/1/2005
Totals
PE 1 1/1/2005
Totals
AL 1 1/1/2005
L
Pave and /or stripe shoulder for walkway and other pedestrian
safety improvements. Totals
14 4 11 S AL 1 1/1/2005
L
Page 1 Six Year Transportation Improvement Program
From 2005 to 2010
Project Costs in thousands of Dotrars Federally Funded
Fund Source Information Expenditure Schedule Projects Only
(Local Agency)
Federal Funding RAN
Federal Federal State 4th Required
Fund Cost by Fund State Local Total 1st 2nd 3rd Thru Envir. Date
Code Phase Code Funds Funds Funds 6th Type (MM/YY)
10 1 11 1 12 13 14 1 15 16 1 17 1 18 1 19 20 21
79501 7950 12501 12501 12501 4200
I I
Hearing Date: 6/14/2004
Amend Date:
Adoption Date:
Resolution No.:
7950 7950 1250 1250 1250 4200
1 101 101 101
10 10 10
4201 4201 701 701 701 210
420 420 70 70 70 210
6001 6001 1001 1001 1001 300
Bridge Program
Various City Streets
from: to:
Perform load ratings and bi- annual inspections as well as
construct necessary repairs and maintenance. Totals 600 600 100 100 100 300
14 5 08002500 09 P 1,000 Ft T PE 1 1/1/2005 1 I 1 1 1 1001 1001 100
Totals 100 100 100
12 S AL 1 1/1/2005 1 1001 1 1 161 1161 1161 CE
L
from: West Valley Corridor to: S 180 St Corridor
Design and construct signal coordination improvements,
monitoring equipment, and control upgrages. Totals 100 16 116 116
Supersedes previous editions
No
No
No
No
No
No
Washington State Department of Transportation
Ag'cy: Tukwila
Co. No.: 17 Co. Name: King Co
City No.: 1320 MPO /RTPO: PSRC
Project Identification
A. Federal Aid No. B. Bridge No. C L d
r
A o
o_ a C. P roject Title a a J 0
73 o E D. Street/Road Name or Number 9 r .8 Z'
ca
a U 0- z a.1 E. Beginning MP or road Ending MP or road E o
F. Describe Work to be Done
1 2 3 4 5 6 7
14 7 03 P G
Tukwila Intl Blvd (Phase 2) p
P
from: S 116 St to: S 132 St
Construct overlay, curb gutter, sidewalks, illumination, T
drainage, landscaping, and utility undergrounding. W
17 8 03 S 1,650 Ft W
S 144 St (Phase 1) T
S
from: Tukwila Intl Blvd to: Military Road p
Design and construct paving, curb gutter, sidewalks, drainage, G
illumination, and utility undergrounding. C
16 9 12 P W
CBD Traffic Signal Interconnect T
CBD Streets G
from: to: C
Design and install hard wire interconnect system between traffic p
signals in the CBD. S
16 10 01 .P 3,000 Ft W
Southcenter Parkway T
S
from: S 180 St to: S City Limits p
Design and construct widening to 4 lanes and center turn lane G
including curb gutter, sidewalks, drainage, landscaping, and
utility undergreundir
14 11 03 P 4,500 Ft W
Interurban Ave T
S
from: S 143 St to: Ft Dent Way p
Construct paving, curb gutter, drainage, illumination, sidewalk, G
and landscaping. C
16 12 12 P 1,000 Ft W
S 133 St SR 599 Ramps Intersection T
S
from: 500 Ft on each leg to: 500 Ft on each leg G
Design and construct intersection improvements including a new C
traffic signal. p
Project Costs in Thousands of Dollars
Fund Source Information Expenditure Schedule
N
0
L I Federal Funding (Local Agency)
a. Phase Federal Federal State 4th
Ti
d Start Fund Cost by Fund State Local Total
1st 2nd 3rd Thru
(mm/dd /yyyy) Code Phase Code Funds Funds Funds 6th
8 9 I 10 11 12 13 14 15 16 17 18 19
CN 1/1/2005 1 I 36861 42001 14001 9286 43861 49001
Totals 3686 4200 1400 9286 4386 4900
CN 1 1/1/2005 I 1 10161 9391 19551 19551
Totals
PE 1/1/2005
CN 1/1/2006
Totals
CN 1 1/1/2010
Totals
CN 1 1/1/2010
Totals
PE 1/1/2009
CN 1/1/2010
Totals
Page 2
180
1177
1357 374 1731 260 1471
57221 1 1 13741 70961 1
5722
50101
5010
26
274
300
Six Year Transportation Improvement Program
From 2005 to 2010
1016 939 1955 1955
801 260 2601
1 2941 14711 1 1471
I I
I 1 1
Hearing Date: 6/14/2004 Adoption Date:
Amend Date: Resolution No.:
1374 7096
7821 57921
782 5792
4 30
461 3201
50 350
1 1
1 7096
7096
1 5792
5792
30
320
350
Federally Funded
Projects Only
RNV
Required
Envir. Date
Type (MM/YY)
20 21
CE
Supersedes previous editions
No
No
No
No
No
No
Washington State Department of Transportation
WA/
Agency: Tukwila
Co. No.: 17 Co. Name: King Co
City No.: 1320 MPO /RTPO: PSRC
1 2
14 13
16 16
14 17
Project Identification
A. Federal Aid No. B. Bridge No.
C. Project Title
D. Street/Road Name or Number
E. Beginning MP or road Ending MP or road
F. Describe Work to be Done
3
Tukwila Intl Blvd S 116 St
from: SR99 Bridge to: SR599
Design and construct widening on Tukwila Intl Blvd and
intersection improvements at T.I.B. /S 116 St. Totals
16 14 03 P PE 1/1/2008
CN 1/1/2010
East Marginal Way
from: Boeing Access Rd to: S 112 St
Design and construct widening to 3 lanes including curb gutter,
sidewalks, drainage, landscaping, and utility undergrounding. Totals
16 15 12 P 1,000 Ft AL 1 1/1/2007 1
L
Andover Park E Minkler Blvd.
from: 500 Ft each leg to: 500 Ft each leg
Design and construct intersection and traffic signal improvements
and widening for left turn lanes.
S 168 St
from: Southcenter Pkwy to: Andover Park W
Construct new roadway including curb gutter, sidewalk,
drainage, illumination, and landscaping.
West Valley Hwy S 156 St
Project Costs in 1 housands of bohars
E 1 Fund Source Information
Expenditure Schedule
17 q .I" 13 (Local Agency)
m m al m 1 Federal Funding
E~ i n 9 0- Phase Federal Federal State 4th
E a Start Fund Cost by Fund State Local Total
.o y Funds Funds Funds 1st 2nd 3rd Thru
o (mm/dd/yyyy) Code Phase Code 6th
4 5 6 7 8 9 1 10 1 11 1 12 1 13 1 14 15 16 1 17 1 18 1 19
P PE 1/1/2010 I 100 100 100
04
1,500 Ft P
S
T
W
01 P 2,000 Ft P
T
W
S
12 P 1,500 Ft T
P
Totals
AL
L
1/1/2007
Totals
AL 1 1/1/2009
L
from: Southcenter Blvd to: S 158 St
Construct additional northbound left tum lane at S 156 St for
northbound HOV to northbound 1 -405. Totals
14 18 03 P 2,100 Ft G CN 1 1/1/2005 1
Tukwila Intl Blvd (Phase 3) C
S
from: S 132 St to: S 138 St p
Reconstruct roadway including paving, curb gutter, sidewalks, T
illumination, drainage, and utility undergrounding. W Totals
Page3 Six Year Transportation Improvement Program
From 2005 to 2010
1690
1690
6001
600
39451
I I
Hearing Date: 6/14/2004 Adoption Date:
Amend Date: Resolution No.:
100 100
351 35
2301 1920
265 1955
2001 2001
200 200
7751 775
775 775
1251 7251
35
1 1
I I
125 725
30001 4481 73931 35331 38601
3945 3000 448 7393 3533 3860
2001
100
1920
35 1920
200
4251 350
425 350
725
725
Federally Funded
Projects Only
R/W
Required
Envir. Date
Type (MM/YY)
20 21
Supersedes previous editions
No
No
No
No
No
No
Washington State Department of Transportation
A Tukwila
Co. No.: 17 Co. Name: King Co.
City No.: 1320 MPO /RTPO: PSRC
U
li c
Project identification
A. Federal Aid No. B. Bridge No.
C. Project Title
D. Street/Road Name or Number
E. Beginning MP or road Ending MP or road
F. Describe Work to be Done
1 1 2 3
`oE
0
14 19
from: 1 -405 to: Strander Blvd
Design and construct widening to 7 lanes including curb gutter,
sidewalks, illumination, and drainage. Totals
16 20 04 P 2,000 Ft W AL I 1/1/2009 I
Minkler Blvd T
S
from: Southcenter Pkwy to: Andover Park W p
Consruct widening for 3 lanes inlcuding curb gutter, sidewalk,
drainage, and landscaping.
14 21
16 22
17 23
00 24
West Valley Highway
Tukwila Int'I Blvd. (Phase 4)
from: Boeing Access Rd to: S 116 St
Design and construct widening including paving, curb gutter,
sidewalk, drainage, illumination, landscaping, and utility Totals
undergreundin`. AL 1 1/1/2009
12 P 1,000 Ft W L
Andover Pk E Industry Signal T
S
from: 500 Ft on each leg to: 500 Ft on each leg p
Design and construct a traffic signal and intersection G
improvements. Totals
Nelson Place
CBD Interurban Trail Connector
from: Interurban Trail to: CBD
Design and construct trail from Interurban Trail to CBD.
C
-‘1 e
m, d
o
m U
n l— co 76 z' Phase
g m Start
(mm/dd/yyyy)
4 5 6 7 8 9
05 P 0.5 Mi W AL 1/1/2010
03 P
T
S
P
G
3,500 Ft P
S
W
Totals
PEI 1/1/2010
03 P 600 Ft AL I 1/1/2009 I
L
Totals
Page 4
Project Costs in rhousands of Dollars
Fund Source Information
Federal Funding
Federal
Fund
Code
10
Federal State State Local Total 4th Envir.
Cost by Fund Funds Funds Funds 1st 2nd 3rd Thru Type
Phase Code 6th
11 12 13 I 14 1 15 16 I 17 18 1 19 20 21
5301 501 580 1 580
530
1901
190
Six Year Transportation Improvement Program
From 2005 to 2010
Hearing Date: 6/14/2004 Adoption Date:
Amend Date: Resolution No.:
50 580
4251 4251
Expenditure Schedule
(Local Agency)
425 425 425
1001 1001
100 100
301 2201
30 220
2001 2001
580
425
100
100
220
220
200
from: S 156 St to: S 158 st
Design and construct paving, curb gutter, sidewalks, drainage,
and illumination. Totals 200 200 200
32 P PE 1 1/1/2009 1
1 1 1 1 301 301 1 1 30
30 30 30
Federally Funded
Projects Only
Supersedes previous editions
R/W
Required
Date
(M)WYY)
No
No
No
No
No
No
Washington State Department of Transportation
Ag'cy: Tukwila
Co. No.: 17 Co. Name: King Co.
City No.: 1320 MPO /RTPO: PSRC
1 2
16 25
17 26 03 P 1000 P
S 144 St (Phase 2) Feet T
W
from: 42nd Ave S to: Tukwila Intl Blvd g
Design and construct paving, curb gutter, sidewalks, drainage, G
illumination, and utility undergrounding. C
16 27 03 P 1.1 W
Southcenter Blvd. Miles S
T
from: 1 to: Tukwila Intl Blvd. C
Improve roadway to a three -lane urban arterial with medians, turn G
lanes, curbs, gutters, sidewalks, street lighting, and drainage.
16 28
14 29
17 30
Project Identirication
A. Federal Aid No. B. Bridge No.
C. Project Title
D. Street/Road Name or Number
E. Beginning MP or road Ending MP or road
F. Describe Work to be Done
3
Klickitat SC Pkwy /1-5 Access Revision
from: 1 -5 Off Ramp to: S 168 St
Design and construct safety and capacity improvements.
Andover Park West
from: Tukwila Parkway to: Strander Blvd.
Complete widening for center left turn lane.
SC Blvd. 61st Ave S Bridge Widening
from: 1 -5 to: 62nd Ave S
Widen Southcenter Blvd. and the 61st Ave S Bridge to add a lane
for future traffic growth.
S 144th St Bridge Sidewalks
from: 51st Ave S to: 53rd Ave S
Widen existing sidewalks on bridge over 1 -5 between 51st Ave S
and 53rd Ave S.
N
m 0
N
h h C
mm m 0 c
0
n1 h Ii Z a Phase
E 1- w Start
2 (mm/dd/yyyy)
4 5 6 7 8
05 P 1,500 Ft W PE 1/1/2005
T
S
P
G
Totals
PE 1/1/2006
CN 1/1/2007
Totals
PE 1/1/2007
CN 1/1/2008
9
Totals
05 P C PE 1/1/2006 1
G
P
S
T
W Totals
04 P 0.5 C PE 1 1/1/2007 1
Miles G
P
S
T
W Totals
05 P 0.25 C PEI 1/1/2005
Miles G
P
S
T
W Totals
Grand Totals fo
Project hosts in 1 housands of boliars
Fund Source Information
Federal Funding
Federal Federal State
Fund Cost by Fund
Code Phase Code
10
11 12
Page5 Six Year Transportation Improvement Program
From 2005 to 2010
State Local Total
Funds Funds Funds
13
Hearing Date: 6/14/2004
Amend Date:
Expenditure Schedule
(Local Agency)
4th
1st 2nd 3rd Thru
6th
14 1 15 16 1 17 1 18
5001 500 3001 2001
500 500 300 200
1 1501 1001 250 1 2501
1 8401 5601 14001 1 1 1400
990 660 1650 250 1400
1 1501 150 1 1 150
1 16001 16001 1 1
1750 1750
1 1001 1001 1 1001
100 100
1001 100
100 100 100
251 251 251
25 25 25
100
Adoption Date:
Resolution No.:
1 1 1001
150 1600
1600
Federally Funded
Projects Only
Envir.
Type
19 20 21
Supersedes previous editions
R/W
Required
Date
(MM/YY)
No
No
No
No
No
No
AFFIDAVIT OF MAILING
I
laws of the State of Washington that on JAlP�QI
stamped and addressed envelope directed to
certify under penalty of perjury under the
2004, I deposited in the mail of the United States of America a properly
Douglas MacDonald, WSDOT Secretary
Omar Mehyar, W S T I P Region Manager
PSRC Information Center "Doris"
dzii-
&L
Said addressed envelope, mailed from 6200 Southcenter Boulevard,
Tukwila, Washington, contained Resolution 1552 attachments relative to
the annual Six -Year Transportation Improvement Program, from the
City of Tukwila
DATED this 23 day of UDC) 2004
Bob Baker, CMC,
Deputy City Clerk