HomeMy WebLinkAboutReg 2013-08-05 Item 5F - Purchase - 600W Back-Up Generator from Cummins Northwest for $206,619.93 (Surface Water Lift Station #15) COUNCIL AGENDA SYNOPSIS
�IILAki,
�' I:. Initial ITEM NO.
Meetin Date Pre.ared b Ma or,' review Council review
J ir G' 08/05/13 BG• 'Vik
d
0. �� 5F
1 906
ITEM INFORMATION
CAS NUMBER: STAFF SPONSOR: BOB GIBERSON ORIGINAL AGENDA DATE: 8/05/13
AGENDA ITEM TITLE Surface Water Lift Station No. 15
Approve Purchase of Generator from Cummins Northwest
CATEGORY ❑ Discussion ®Motion ❑ Resolution ❑ Ordinance ❑Bid Award ❑Public Hearing ❑ Other
Mtg Date Mtg Date 08/05/13 Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date
SPONSOR ❑ Counci l ❑Mayor ❑HR ❑ DCD ❑Finance ❑ Fire ❑ IT ❑P&R ❑Police ® PW
SPONSOR'S The Surface Water Lift Station No. 15 Project will install electrical upgrades, construct a
SUMMARY modular concrete wall enclosure and then install a City purchased 600KW backup
generator. Cummins Northwest is a listed vendor on the Houston-Galveston Area Council
(H-GAC) purchasing cooperative. Council is being asked to approve the purchase of the
standby generator in the amount of$206,619.93 (including sales tax).
REVIEWED BY ❑ COW Mtg. ❑ CA&P Cmte ❑ F&S Cmte ®Transportation Cmte
❑ Utilities Cmte ❑Arts Comm. ❑Parks Comm. ❑Planning Comm.
DATE: 07/23/13 COMMII l E CHAIR: KATE KRULLER
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMIT nE Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$206,619.93 $558,000.00 $0.00
Fund Source: 412 SURFACE WATER FUND (PAGE 140&136, 2013 CIP)
Comments:
MTG. DATE RECORD OF COUNCIL ACTION
08/05/13
_MTG. DATE ATTACHMENTS
08/05/13 Informational Memorandum dated 07/19/13 (revised after 7/23 TC)
Cummins Northwest, LLC Quotation
Minutes from the Transportation Committee meeting of 07/23/13
41
•
42
44∎14 ILA V
k ' s City of Tukwila
o ti
a . ,, ' o Jim Haggerton, Mayor
"'r, r ?
2 905 INFORMATIONAL MEMORANDUM
TO: Mayor Haggerton
Transportation Committee ti
P 10
FROM: Bob Giberson, Public Works Director
By: Ryan Larson,Senior Program Manager
DATE: July 19, 2013 (revised aft 7/23 TC)
SUBJECT: Surface Water Lift Station No. 15
Project No.91041203
Generator Purchase
ISSUE
Approve purchase of a 600KW generator from Cummins Northwest for the Surface Water Lift Station No. 15.
BACKGROUND
This project will provide a back-up power generator for the Surface Water Lift Station No. 15, which drains
approximately 200 acres of the northern portion of the Tukwila South Development.
The project calls for a contractor to install electrical upgrades to the existing pump station, construct a modular
concrete wall enclosure, and install a City provided 600KW generator(see memo for contractor's bid award).
The City is required to purchase the 600KW generator and provide it to the contractor for installation.
ANALYSIS
Cummins Northwest is a listed vendor on the Houston-Galveston Area Council(H-GAC) purchasing
cooperative. The City of Tukwila has a Council approved purchasing agreement with H-GAC.
Cummins is the staff recommended generator for City facilities and the manufacturer of the majority of the City's
standby generators. Maintenance staff is trained in maintenance and repair of Cummins' generators and are
satisfied with the reliability and serviceability of these units.
BUDGET AND BID SUMMARY(All amounts include sales tax.)
Generator Bid Results 2013 Budget
Generator Purchase $206,619.93 $200,000.00
Construction Bid (see separate memo) $318,568.35
Project Budget(pg. 140) 315,000.00
2013 Small Drainage Project(pg. 136) 43,000.00
Contingency(10%) 0.00 31,856.84 0.00
Total $206.619.93 $350.425.19 $558.000.00
RECOMMENDATION
The Council is being asked to purchase the Standby Generator in the amount of$206,619.93 for the Surface
Water Lift Station No. 15 Project and consider this item at the August 5, 2013 Regular Consent Agenda.
attachment:Cummins Northwest Quotation
W:\PW Eng\PROJECTS\A-DR Projects\Storm Lift Station No 15 Improvements(91041203)\Design\Info Memo Generator Purchase gl.doc 4 3
•
•
•
•
•
•
•
•
•
}
{
44
Power
4' Generation
Our energy working for ou
Quotation
Cummins Northwest, LLC
811 SW Grady Way
Renton WA 98057 WA 98057 United States
Direct: 425-277-5334
July 17,2013
Project Name: City of Tukwila
Quotation: 2142000000029588
Thank you for your inquiry. We are pleased to quote as follows:
USD
Item Description Qty
Diesel Genset: 60Hz-600kW 50Hz-545kW
Install-US-Stat U.S. EPA, Stationary Emergency Application 1
600DQCA Genset-Diese1,60Hz,600kW 1
A331-2 Duty Rating-Standby Power 1
L090-2 Listing-UL 2200 1
L170-2 EmissionCert,EPA,Tier 2,NSPS CI Stationary Emergency 1
F201-2 Enclosure-Steel,SndAtt,Level 1,Base Mtd,w/ExhSys rated 79 dba @ 23' 1
R002-2 Voltage-277/480,3 Phase,Wye,4 Wire 1
B282-2 Alternator-60Hz,3 Ph,Wye,Extended Range,125/105C 1
H643-2 SET CONTROL-PCC 2100 1
H536-2 Display Language-English 1
H605-2 Display-Control,Graphical 1
KP74-2 Stop Switch-Emergency,Externally Mounted 1
H606-2 Meters-AC Output,Analog 1
K631-2 Relays-Genset Status, User Configured 1
H609-2 Control Mounting-Left Facing 1
A292-2 Heater-Alternator, 120 Volt AC 1
KP79-2 Circuit Breaker Or Entrance Box-Left Side Only 1
KP89-2 CB-1200A,3P,600/690V,UL/IEC,ServEnt,100%UL,Left 1
P175-2 Enclosure Color-Green,Steel Enclosure 1
F208-2 Cooling Air Outlet-Horizontal ,Sound Attenuated 1
H657-2 Distribution Panel-Prewired AC Features 1
F211-2 Louvers-Air Inlet,24VAC Motor Closed,Spring Opened 1
45
KS47-2 Enclosure Lighting-120 VAC 1
C127-2 Separator-Fuel/Water 1
E074-2 Engine Cooling-Radiator, 50C Ambient 1
H389-2 Shutdown-Low Coolant Level 1
H556-2 Coolant Heater-208/240/480V, 40F Minimum Ambient Temp 1
D041-2 Engine Air Cleaner-Normal Duty 1
Genset warranty- Base, Standby 2 years/400 hours, Prime Power 1 year/
L028-2 unlimited hours, Continuous Power 1 year/unlimited hours 1
L050-2 Literature-English 1
A412-2 Packing-Base Mtd Housing 1
CP01-2 Common Parts Listing 1
SPEC-H Product Revision - H 1
Tank with turning vane, starting batteries, battery charger mounted, rated 48
Tank hours at full load, Hazmat decals, IBC engineering cals, 5 gallon spill fill 1
located per departments request.
Up fit Mounting of Spring Isolators 1
Start up Start up &training 2 hours load bank and 2 hour training 1
Up fit Load testing 1
O&M's O&M's 3
Total $188,694.00
City of Tukwila tax rate 9.5% 17,925.93
Grand Total $206,619.93
NOTES:
1. THIS QUOTATION IS SUBJECT TO CUMMINS NORTHWEST, LLC STANDARD TERMS &
CONDITIONS - SEE ATTACHMENT
2. NATURAL GAS AND LP ENGINES ARE FACTORY CERTIFIED TO MEET EPA NEW SOURCE
PERFORMANCE STANDARDS (NSPS) FOR SPARK IGNITED (SI) ENGINE EXHAUST EMISSIONS
REGULATIONS. THE ENGINE(S) ARE NOT FIELD CONVERTIBLE TO OTHER FUEL SOURCES.
EMISSIONS COMPLIANCE FOR THE LIFE OF THESE PRODUCTS IS THE OWNER/OPERATORS
RESPONSIBILITY AS DEFINED BY THE USA EPA.
3. REGARDING SELECTIVE COORDINATION FOR NEC ARTICLE 700 AND 701 LOADS. CUMMINS
GENERATORS ARE EQUIPPED WITH THE MANUFACTURERS RECOMMENDED THERMAL
MAGNETIC CIRCUIT BREAKER. INFORMATION REGARDING THIS DEVICE CAN BE SUPPLIED
UPON REQUEST.THIS QUOTATION IS NOT VALID IF ANY CHANGES TO THIS CIRCUIT
BREAKER(S) IS REQUIRED TO COORDINATE WITH OTHER DEVICES IN THE ELECTRICAL
DISTRIBUTION SYSTEM. IF CHANGES ARE REQUIRED, THE CUSTOMER MUST PROVIDE A
COPY OF THE COORDINATION STUDY LISTING THE MANUFACTURERS PART NUMBER OF THE
DISCONNECT DEVICE TO BE SUPPLIED WITH THE GENERATOR AND A REVISED QUOTATION
46
WILL BE ISSUED.
4. A MAINTENANCE AGREEMENT IS NOT INCLUDED IN THIS QUOTATION, AVAILABLE FOR AN
ADDITIONAL PRICE OF $
Attachment to Quotation
-Exclusions-
Exhaust System: All off-engine piping, hangers,flanges,gaskets, bolts, insulation, and other materials
associated with exhaust system installation unless specifically listed in the preceding
quotation.
Fuel System: All off-engine fuel piping for supply, return,venting,valves,coolers,filters, pumps,fittings,
fuel storage tank&senders, 300 gallons fuel for testing and initial fill of fuel.
Cooling System: Intake louvers, exhaust louvers, air dampers,sheet metal ducting,flex adapters, sound
attenuators/baffles. All off engine piping,flexible connections,secondary loop coolant,
labor to install coolant for remote cooling systems unless specifically listed in the
preceding quotation.
Electrical: All off-engine wiring,field terminations of wiring,and lugs other than those detailed in our
submittal.
Mounting: Generator mounting bolts and anchors.Vibration isolators(if included)for the generator
will be shipped loose for installation at the jobsite by others.
Testing: All electrical testing, including but not limited to NETA, infrared scanning, harmonic
content or other independent agency testing of switchgear,switchboards, protective relays
or any other electrical component unless specifically listed in the preceding quotation.All
environmental testing, including but not limited to EPA, local air quality district or other
unless specifically listed in the preceding quotation. Calculations and Engineering
Services-all electrical coordination studies, arc flash studies,seismic engineering
calculations and seismic anchorage calculations unless specifically included in the
preceding quotation. Programming-all protective relay settings,breaker settings, PLC
programming or other user configurable device programming unless specifically included
in the preceding quotation
Documentation: Unless stated otherwise, electronic submittals and O&M manuals will be provided.
Printed copies are available upon request, additional charges may apply.
Taxes and Permits: Any applicable sales tax, permits, licenses.
Bonds Any bid bond,payment or performance bond,or other type of bond unless specifically
listed in the proposal. Cost for any required bond will be reimbursed to CNW by the
buyer.
All items listed are excluded and will only be supplied by Cummins Northwest, LLC if agreed upon, in writing,by a
sales representative for Cummins Northwest, LLC.
Current factory lead-time is 14-16 weeks after drawing approvals.
-Terms and Conditions-
• This offer and quotation incorporates and is contingent upon acceptance of the terms and conditions in the
standard Sales Order of Cummins Northwest, LLC. Purchase Orders or other documents with terms and
conditions that are inconsistent with the CNW standard Sales Order will not be accepted unless agreed to in
writing by an officer of Cummins Northwest, LLC.
• Prices are valid for 30 days
• If included in the quotation, all on-site startup,testing and training assumes weekdays, during standard
47
CNW business hours.Additional charges may be added for work requested to be done on overtime,
weekends,and holidays.
• F.O.B.factory,freight allowed to first destination,off-loading is not included
• Factory direct shipments require credit approval prior to shipment
• Terms are C.O.D.,or 30 days upon approval of credit
• Equipment held for longer than 30 days may be charged a monthly storage fee
• Cancellation charges are 25%minimum after release of order
Submitted by
(94#10sa"-
Dennis Tarr , Electric Power Generation Sales
dennis.tarr@Cummins.com
Mobile: 206-450-2383
Fax: 425-235-8202
48
lJ��iLA-,1
�' �M City of Tukwila
y
���, �oi' Transportation Committee
TRANSPORTATION COMMITTEE-Meeting Minutes
July 23, 2013—5:15 p.m. —Conference Room #1
PRESENT
Councilmembers: Kate Kruller, Chair; Dennis Robertson,Joe Duffle
Staff: Bob Giberson, Frank Iriarte, Ryan Larson, Robin Tischmak, Pat Brodin, Jack Pace, Gail
Labanara,Maggi Lubov, David Cline, Laurel Humphrey
Guest: Roger Baker, resident
CALL TO ORDER: Committee Chair Kruller called the meeting to order at 5:15 p.m.
I. PRESENTATIONS
No presentations.
II. BUSINESS AGENDA
A. Surface Water Lift Station No. 15 —Bid Award
Staff is seeking Council approval to award a bid to Gary Harper Construction, Inc. in the amount of
$318,568.35, for the construction of the Surface Water Lift Station No. 15 project. This project will
provide a backup generator for this station, which drains approximately 200 acres of the northern
portion of the Tukwila South Development. Gary Harper Construction is the low bidder and has
successfully completed a similar project for the City. $36,000 unused dollars will be transferred
from the 2013 Small Drainage Program to cover a project budget shortage. UNANIMOUS
APPROVAL. FORWARD TO AUGUST 5 REGULAR CONSENT AGENDA.
B. Surface Water Lift Station No. 15—Purchase of Backup Generator
ff is il approval of the purchase a generator in amount of
$206Sta ,619.93 from seeking CCouncummins Northwest, LLC for the Surface of Water 600KW Lift Station the No. 15 project
„4(
described in item A above. Cummins is the manufacturer of the majority of the City's standby
f generators and maintenance staff are satisfied with the reliability and serviceability of the units.
UNANIMOUS APPROVAL.FORWARD TO AUGUST 5 REGULAR CONSENT AGENDA.
C. 42nd Ave S/Allentown Roadside Barrier Warrant Analysis
Staff presented and discussed the draft roadside barrier warrant analysis for 42nd Avenue South in
Allentown that was prepared by KPG, Inc. Several areas of the river bank along 42nd Avenue
South and South 115th Street are being recommended for guardrail or barrier installation and/or
upgrades and modifications. Most of the areas analyzed in the report would benefit from beam
guardrail type 31. Existing concrete barriers are recommended to be removed and replaced due to
being unrestrained, their proximity to the edge of pavement, and erosion under the base. The total
project cost estimate for all recommendations is $366,480. The report also included short-term
safety improvement recommendations, which are not figured into the total cost. Committee
members asked clarifying questions about definitions and barrier types.
The committee packet includes a draft CIP sheet that reflects staff's proposal to spread the cost and
the construction over the next six years to minimize the impact to the Residential Street Fund (103
Fund). Committee members requested that staff prepare a proposal that would reflect a
compressed schedule allowing construction to be completed sooner but having more immediate
financial impact.
49