.wq CITY OF TUKWILA Q9- 056(b)
�J .s Council Approval N/A
CONTRACT CHANGE ORDER NO. 2
�`rsoa
DATE: 01 -12 -2010 BUDGET NO.: 401.02.594.343.63.21
PROJECT NO.: 92 -WT06 CONTRACT NO.: 09 -056 C b
PROJECT NAME: Foster Links Reclaimed Water Project
TO: Precision Earthworks, Inc.
You are hereby directed to make the herein described changes to the plans and specifications or do the following described work not
included in the plans and specifications on this contract:
NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued.
Conditions: A. The following change, and work affected thereby, are subject to all contract stipulations and covenants;
B. The rights of the "Owner" are not prejudiced;
C. All claims against the "Owner" which are incidental to or as a consequence of this change are waived; and
D. The Contractor must submit all Field Overhead and Home Office Overhead Rates for approval in advance of all
change orders.
CHANGE:
During the construction, several of the vaults, and other design elements found on the plans prepared by the King County Reclaimed
Water Division were determined to be undersized for the planned water pipe systems. As a result, King County Engineers re- designed
the plans. This necessitated the return of the original vaults and use of larger vaults along with additional materials and labor costs.
After negotiations with Precision Earthworks, Inc., along with review and approval by King County, Change Order No 2 will add
$17,242.26 and 23 calendar days to the contract. The new contract total will be $114,909.60 (without sales tax).
We the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is
approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services
necessary for the work above specified at no additional costs. This change represents a fair, equitable and complete compensation.
ACCEPTED: Date ��J ��v Contractor: Precision Earthworks, Inc.
B <7C Title
Origina Contract (without tax) 94,849.00 APPROVED BY THE CITY OF TUKWILA
Previous Change Orders 2,818.34 Date 7� Y O
This Change Order (without tax) 17.242.26 4 h h
R EV. CONTRACT AMOUNT $114,909.60 By 'l3 rot, G jv Mayor
Additional Calendar Days due to this change: 23 (Twenty- three) calendar days added for an unchanged total of 95 days.
ORIGINAL: City Clerk (1 of 2) cc: Finance Department (wlencumbrance)
Contractor (2 of 2) Construction Inspector
Construction Engineer
file:
O
1i
.1
1908
DATE: 01 -12 -2010 BUDGET NO.: 401.02.594.343.63.21
PROJECT NO.: 92 -WTO6 CONTRACT NO.: 09 -056 OA)
PROJECT NAME: Foster Links Reclaimed Water Project
TO: Precision Earthworks, Inc.
You are hereby directed to make the herein described changes to the plans and specifications or do the following described work
not included in the plans and specifications on this contract:
NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued.
Conditions: A. The following change, and work affected thereby, are subject to all contract stipulations and covenants;
B. The rights of the "Owner" are not prejudiced;
C. All claims against the "Owner" which are incidental to or as a consequence of this change are waived; and
D. The Contractor must submit all Field Overhead and Home Office Overhead Rates for approval in advance of all
change orders.
CHANGE:
This project will allow Foster Golf Links to use King County reclaimed water for irrigation. During the construction of the pond filling
structure, groundwater from the pond was found to be seeping into the underground vault. This was allowing water to fill the vault
and would jeopardize the newly installed equipment making in non functional. To alleviate this, a drain system was added to
relieve flow to a lower elevation nearby.
The work described was required as a result of changed field conditions. This C.O. No. 1 totals $2,818.34. The new contract total
will be 97,667.34 (without sales tax).
We the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is
approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all
services necessary for the work above specified at no additional costs. This change represents a fair, equitable and complete
compensation.
ACCEPTED: Date /ta /io
By
Orig Contract (without tax)
Previous Change Orders
This Change Order (without tax)
REV. CONTRACT AMOUNT
ORIGINAL:
City Clerk (1 of 2)
Contractor (2 of 2)
09 -056 (a)
CITY OF TUKWILA Council Approval N/A
CONTRACT CHANGE ORDER NO. 1
94,849.00
0
2.818.34
97,667.34
Contractor: Precision Earthworks, Inc.
Title a
APPROVED BY THE CITY OF TUKWILA
Date c') OF,,,
TUKWILA
Additional Calendar Days due to this change: 5 (Five) calendar days added for an unchanged total of 95 days.
cc: Finance Department (w /encumbrance)
Construction Inspector
Construction Engineer
file:
5o f C% r6 N t-
Date of Addendum Issue:
Bid Submittal Date:
Bid Opening Date:
ADDENDUM NO. 2
City of Tukwila
Foster Golf Links Reclaimed Water Pipeline Extension
City Project No. 92 -WT06
This Addendum No. 2, containing the following revisions, additions, deletions, and /or
clarifications, is hereby made a part of the Plans and Contract Provisions (Contract Documents)
for the above -named project. Bidders shall take this Addendum into consideration when
preparing and submitting their bids.
Bidders shall acknowledge receipt and acceptance of this Addendum No. 2 in the space
provided on the Proposal Signature Sheet or by signing in the space provided below and
submitting the signed addendum with the bid package. Failure to provide this written
acknowledgement may result in disqualification of the Bidders submittal.
Sincerely,
Bob Giberson, P.E.
City Engineer
BG /MC:Iw
attachments
(P:Prolerls)A WT Proiects192WTOCNTosler Gott Unks Relcaimed Water Pi,eane Extension)
Bidder'
Authorized Official:
Name and Title:
December 15, 2008
Friday, December 19, 2008 9:00 a.m.
Friday, December 19, 2008 10:00 a.m.
NOTICE TO ALL PLANHOLDERS
CONTRACT PLANS
City of Tukwila
Foster Golf Links Reclaimed Water Pipeline Extension
Foster Golf Links Reclaimed Water Pipeline Extension
Plan Sheets
Remove plan sheets C101 and C104. Replace with plan sheets C101 dated 12/15/08 and
C104 dated 12/15/08.
Receipt acknowledged and conditions agreed to this 18th day of December 2008.
Precision Earthworks, Inc.
(Contractor)
(Signature)
Julie Schauss, Vice President
(Print)
Addendum No_2
December 15, 2008
Page 1 of 1
Date of Addendum Issue:
Bid Submittal Date:
Bid Opening Date:
ADDENDUM NO. 1
City of Tukwila
Foster Golf Links Reclaimed Water Pipeline Extension
City Project No. 92 -WTO6
December 12, 2008
Friday, December 19, 2008 9:00 a.m.
Friday, December 19, 2008 10:00 a.m.
NOTICE TO ALL PLANHOLDERS
City of Tukwila
Foster Golf Links Reclaimed Water Pipeline Extension
This Addendum No. 1, containing the following revisions, additions, deletions, and/or
clarifications, is hereby made a part of the Plans and Contract Provisions (Contract Documents)
for the above -named project. Bidders shall take this Addendum into consideration when
preparing and submitting their bids.
Bidders shall acknowledge receipt and acceptance of this Addendum No. 1 in the space
provided on the Proposal Signature Sheet or by signing in the space provided below and
submitting the signed addendum with the bid package. Failure to provide this written
acknowledgement may result in disqualification of the Bidders submittal.
CONTRACT PLANS
Foster Golf Links Reclaimed Water Pipeline Extension
Plan Sheets
Remove plan sheets C101, C102, C103, C104, and C105. Replace with plan sheets C101
dated 12/09/08, C102 dated 12/09/08, C103 dated 12/09/08, C104 dated 12/11108, and C105
dated 12/11/08.
:CONTRACT SREC1F.lCATIONS
Special Provisions 7- 09.3(19A). Pape SP- 47.parac rya ph #4
DELETE "The Contractor shall only be allowed to make those connections to the existing
system (as shown on the Plans) after a successful pressure test has been witnessed by the
Owner's and King County's representative and after a purity test has been satisfactorily
evidenced. The Contractor shall provide all ancillary items to include temporary plugs, caps,
blow -offs, and blocking and otherwise construct the entire proposed facilities up to the point of
connection for the pressure and purity tests."
Special Provisions 7- .09.3(19A), Page SP -47, paragraph #8
DELETE "The Contractor shall maintain service in the existing facilities at each connection until
such time that the connection is actually made. Such connection to the existing facilities shall
Addendum No. 1
December 12, 2008
Page 1 of 3
City of Tukwila
Foster Golf Links Reclaimed Water Pipeline Extension
not be made until such time as the new construction has been tested, chlorinated and flushed
and a continuous safe supply of water is available through the new facilities
Special Provisions 7- 09.3(191A, Page SP-47 prior to the second to last paragraph in this
section
ADD The Contractor shall only be allowed to make those connections to the existing system as
directed by note 2 on drawing C104 and elsewhere on the plans. All new reclaimed water
pipelines shall be pressure tested by the Contractor and pressure testing shall be witnessed by
the Owner's and King County's representative prior to continuing work. All disinfection purity
tests shall be satisfactorily evidenced to the Engineer prior to continuation of work The
Contractor shall provide all ancillary items to include temporary plugs, caps, blow -offs, and
blocking and construct the entire proposed facilities required for pressure and disinfection purity
tests."
Special Provisions 7- 09.3(19)A. Page SP-47. paragraph #10
DELETE "The Contractor shall jet and vactor 300 feet of existing 16" diameter ductile iron pipe
and dispose of the vactured material into existing sanitary sewer manhole located near the
George Long City shops." and REPLACE with "The existing 16" diameter ductile iron pipe shall
be flushed in accordance with Note 2 on drawing C104. The Owner's and King County's
representatives shall witness the flushing of the existing 16" diameter RWR pipeline The
flushing operation will be considered complete after the line has been flushed for a minimum of
30 minutes and the reclaimed water discharged to the sewer is deemed clear by the Owner's
and King County's representatives. If the flushing discharge remains murky and discolored after
3 hours of flushing, the Owner's representative may elect to have the Contractor jet and vactor
300 feet of existing 16" diameter ductile iron pipe and dispose of the vactured material into the
existing sanitary sewer manhole as identified on drawing C101. If jetting and vactoring is
selected, additional pipe excavation and replacement of the thrust block may be required. If the
Owner's representative elects to have the Contractor jet and vactor the existing 16" diameter
ductile iron pipe, the Contractor shall be paid on a time and materials basis for this work."
Special Provisions 7- 09.3(24U. Page SP-49
DELETE "No connection shall be made between the existing distribution system and the
pipelines not disinfected, unless they are connected with a Washington State Department of
Health approved air gap." and REPLACE with "No connection shall be made between the
existing distribution system. and the pipelines not disinfected, except as directed by Note 2 on
drawing C104."
Special Provisions 7- 09.3(24)N. Page SP-49. second paragraph
DELETE "Sections of pipe to be disinfected shall first be flushed to remove any solids or
contaminated material that may have become lodged in the pipe. If no hydrant is installed at the
end of the main, then a tap shall be provided, which is large enough to develop a velocity of at
least 3 feet per second (fps) in the main. Taps required by the contractor for temporary or
permanent release of air, chlorination or flushing purposes shall be provided by the contractor
as part of the construction of reclaimed water mains at no cost to the Owner and King County."
and REPLACED with "Sections of pipe to be disinfected shall first be flushed to remove any
solids or contaminated material that may have become lodged in the pipe. Refer to Drawing
C104, Note 2 for the sequencing of new pipe flushing and disinfection. Taps and temporary pipe
restraints required by the Contractor for temporary or permanent release of air, chlorination or
flushing purposes shall be provided by the Contractor as part of the construction of reclaimed
water mains at no cost to the Owner and King County."
Addendum No 1
December 12, 2008
Page 2 of 3
City of Tukwila
Foster Golf Links Reclaimed Water Pipeline Extension
ALL OTHER REQUIREMENTS OF THE CONTRACT DOCUMENTS REMAIN IN EFFECT.
All bidders shall acknowledge receipt and acceptance of this Addendum No. 1 in the
space provided on the Proposal Signature Sheet or by signing in the space provided
below and submitting the signed addendum with the bid package. Failure to acknowledge
receipt of this Addendum No. 1 may be considered as an irregularity in the Bid Proposal and the
City reserves the right to determine whether the bid will be disqualified.
Sincerely,
Bob Giberson, P.
City Engineer
BG/MC:Iw
attachments
(P:PfclectsU—WT Proniels s 2 WT66iFoster Golf Links Relcalmed Wales Pipeline Ede
Receipt acknowledged and conditions agreed to this 18th day of December 2008.
Bidder: Precision Earthworks, Inc.
(Contractor)
Authorized Official:
Name and Title:
(Signature)
Julie Schauss, Vice President
(Print)
Addendum No 1
December 12, 200E
Page 3 of 3
AGREEMENT FORM
CONTRACT NO. 09 -056
Council Approval 2/2/09
THIS AGREEMENT is made and entered into on this ��day of W4 20_Q!5, by and between
the City of Tukwila, Washington "Owner and Precision Earthworks, Inc. "Contractor Now,
therefore the parties agree as follows:
1. Project. Contractor shall complete all work and furnish all labor, tools, materials, and
equipment for the project entitled "Foster Links Reclaimed Water Pipeline Extension Project" Project No.
92 -WT06, including all changes to the Work and force account work, in accordance with the Contract
Documents, as described in Section 1 -04.2 of the Supplemental General Requirements.
2. Payments. Owner shall pay Contractor at the unit and lump sum prices, and by force
account as specified in the Proposal according to the Contract Documents as to time, manner, and condition
of payment. The payments to Contractor include the costs for all labor, tools, materials and equipment for the
Work.
3. Completion Date. Contract time shall commence upon Owner's Notice to Proceed date.
The Work under this Agreement shall be completed within the time specified in the Proposal. If the Work
under this Agreement is not completed within the time specified, as detailed in the Contract Documents,
Contractor shall pay liquidated damages and all engineering inspection and supervision costs to Owner as
specified in the Proposal.
4. Attorney's Fees. In the event litigation is commenced to enforce this Agreement, the
prevailing party shall be entitled to recover its costs, including reasonable attorney's and expert witness fees.
5. Disclaimer. No liability of Contractor shall attach to Owner by reason of entering into this
Agreement, except as expressly provided in this Agreement.
6. Counterparts. This Agreement is executed in two (2) identical counterparts, by the parties,
each of which shall for all purposes be deemed an original.
CITY OF TUKWILA, WASHINGTON Precision Earthworks, Inc.
(Owner) (Contractor)
By:
Ocd►►�c.arClr�yor
Title: Vice President
Attest: y1 Attest:
This lfb dayof nVollat, 20p el_ This 93 day of 201
CJJ&� rbl.
City Clerk
Approved as to Form: tractor's License No.
PRECIEI179PG
ity orn� i
Address for giving notices: Address for giving notices:
3816 South Road
Mukilteo WA 98275