Laserfiche WebLink
Exhibit A - Scope of Work <br />Riverton Creek Flapgate Removal Project <br />City of Tukwila <br />April 03, 2017 <br />Otak Project No. 32740 <br />Introduction and Background <br />Tukwila has adopted policies to identify and restore habitat and ecological function along the <br />Duwamish River where restoration can succeed with existing conditions and adjacent uses. The <br />removal of flapgates and perched culverts at the outlet of Riverton Creek is a key opportunity to <br />remove a fish barrier and re -open a historical stream outfall and restore rearing and migrating habitat <br />adjacent to the Duwamish. <br />For this project, the City is requesting Otak to finalize the design of the Riverton Creek Flap Gate <br />Removal improvements initiated by a previous consultant working for the City. This will include <br />taking the 75- percent design to final design and preparing construction documents, updating <br />environmental assessment reports and technical supporting documents, and providing technical <br />support to obtain permits. This project may also include construction support services. <br />Based on our discussions with the City, the project will be accomplished in two phases — Phase 1 - <br />Intake Review and Charter Meeting, Phase 2 - Permitting and Final Design. If construction support <br />or other supplemental services are requested, a supplement will be submitted to add Phase 3 <br />services. This scope of work describes activities within the first two phases — initially with broad <br />terms, and then with specific tasks for each phase. <br />Phase I— Intake Review and Charter Meeting <br />The first step we will take is performing a detailed review of the 75- percent design including all <br />reports and supporting documentation made available by the City. This review will include a field <br />visit to assess the existing conditions and note any discrepancies from the data and descriptions <br />from the 75- percent design which was performed from 2009 -2011. The Intake Review will also <br />include development of a simple Permitting Strategy Plan that identifies all regulatory requirements <br />and design criteria for various agencies so that permitability of all project elements can be <br />confirmed. After the Intake Review, we will facilitate a project Charter Meeting with Tukwila to <br />assess how project challenges have been addressed as part of the completed existing design (75- <br />percent level) and what will need to be addressed by the Otak team. <br />After the Charter Meeting has been completed, but prior to completion of Phase 1, Otak will review <br />the scope of work for Phase 2 and, if required and authorized by the City, make any adjustments in <br />the scope, schedule and budget for City review and contract processing. Upon completion of Phase <br />23 <br />