2019 to 2024
<br />PROJECT: Strander Blvd Extension Phase 3 Project No. 98610403
<br />DESCRIPTION:
<br />Design and construct arterial improvements for a new roadway extending Strander Blvd/SW 27th St
<br />from West Valley Highway to Oaksdale Ave in the City of Renton.
<br />JUSTIFICATION: East/west capacity between 1-405 and S 180 St is needed to serve Tukwila and Renton access.
<br />Project segregated into three phases. Phase I extended Stander Blvd/SW 27th St from Oaksdale Ave to
<br />STATUS: Naches Ave SW. Phase II constructed a 2 lane road from Naches to the Sounder Train's Tukwila Longacres
<br />Station's parking lot. Paid Renton $1m for Phase I & II. Phase III will construct the undercrossing of the
<br />UPRR and complete the 4 lane roadway from West Valley Hwy in Tukwila to Naches Ave SW in Renton.
<br />MAINT. IMPACT: New street.
<br />Project partners include the City of Renton, Boeing, WSDOT, FMSIB, Sound Transit, Metro, Amtrak, and
<br />COMMENT: BNSF and UP Railroads. Funds in 2015-16 are for updated cost estimates and grant applications.
<br />STP (PSRC), FAST Lane, and TIGER grants were submitted in 2016.
<br />FINANCIAL Through Estimated
<br />(in $000's)
<br />2015 2016 2017
<br />2018
<br />2019
<br />2020
<br />2021
<br />2022
<br />BEYOND TOTAL
<br />EXPENSES
<br />Design
<br />58
<br />301
<br />341
<br />2,500
<br />1,659
<br />4,859
<br />Land (R/W)
<br />104
<br />1,860
<br />1,964
<br />Wetland Mitigation
<br />500
<br />50
<br />550
<br />Const. Mgmt.
<br />1,015
<br />1,951
<br />2,966
<br />Construction
<br />21,000
<br />23,524
<br />44,524
<br />TOTAL EXPENSES
<br />162
<br />301
<br />341
<br />2,500
<br />3,619
<br />22,515
<br />25,525
<br />0
<br />0
<br />54,863
<br />FUND SOURCES
<br />Awarded STP Grant
<br />255
<br />1,000
<br />2,637
<br />3,892
<br />Awarded Fastlane Grant
<br />2,500
<br />2,500
<br />5,000
<br />Awarded FMSIB Grant
<br />2,500
<br />2,500
<br />5,000
<br />State/Fed Appropriation
<br />250
<br />250
<br />500
<br />Proposed State TIB Grant
<br />5,000
<br />5,000
<br />10,000
<br />KC Metro
<br />500
<br />500
<br />1,000
<br />Sound Transit
<br />500
<br />500
<br />1,000
<br />PSRC Grant
<br />4,760
<br />4,760
<br />City of Renton Funds
<br />1,000
<br />1,000
<br />UPRR Funds
<br />1,000
<br />1,000
<br />2,000
<br />BNSF Funds
<br />1,000
<br />1,000
<br />2,000
<br />City Mitigation impact Fees
<br />1,000
<br />1,000
<br />2,000
<br />Other State Discretionary Funds
<br />5,000
<br />5,000
<br />10,000
<br />City Oper. Revenue 162
<br />301
<br />86
<br />1,500
<br />882
<br />(2,495)
<br />6,275
<br />0
<br />0
<br />6,711
<br />TOTAL SOURCES 162
<br />301
<br />341
<br />2,500
<br />3,519
<br />22,515
<br />25,525
<br />0
<br />0
<br />54,863
<br />2019 - 2024 Capital Improvement Program